Professional Documents
Culture Documents
TR-RWH 01 1
Water in
from Filter basin
rooftop
Thin Mortar
shell fillet
cover
Overflow
with U-
Tamana bend
handpump
Ground
Floating level
offtake
Low level
inlet
TR-RWH 01 2
Downpipe
Filter basin
(serves as an
access hatch)
Ferrocement
Cover
Low-cost
handpump
Render
Brick
parapet
Ferrocement
with Concrete
waterproof ring beam
cement liner
TR-RWH 01 3
Introduction
Tanks for rainwater storage come in many shapes and sizes. The main distinction
between tank types are size, shape, material and whether they are sited above or
below ground.
Some of the relative merits and drawbacks of above and below ground tanks are listed
in Table 1 below.
The partially below ground (PBG) tank incorporates the merits of both above and
below ground tanks in one simple, low-cost design. The PBG tank takes advantage of
the support given by the soil, to do away with the need for a structural component
below ground level. At the same time protection is given against contamination by
surface runoff and damage by vehicles.
TR-RWH 01 4
To date (November 2000), about 20 of these tanks have been built in SW Uganda
using render linings, often without the chicken mesh. The reports from the field have
been good, and feedback suggests that the tanks are easy to construct by masons with
some training, at a reasonable cost. A training course for masons was held Kyera
Farm, Mbarara, Uganda in June 2000 and 8 local masons were trained in the art of
constructing the PBG tank. The instructions given here for manufacturing the tank
were developed for this training course.
WARNING: The PBG tank is suitable for construction where the soil conditions are
stable e.g. in the lateritic soils of East Africa. If there is any doubt about the stability
of the soil, then seek further advice. Working in soils that are unstable can be very
dangerous, even fatal.
Instructions are given in a step-by-step guide and these should be followed carefully,
especially the tips relating to curing and quality of workmanship. It is worth bearing
in mind, however, that materials availability varies from place to place, and so where
a given material is not available, a substitute can usually be found and the necessary
amendments made.
The instructions given below are for the construction of the PBG tank without the
cover or handpump (although the cost of the cover is included in Table 2).
Instructions for the manufacture of the cover and the handpump are given is
separate documents TR-RWH 04 and TR-RWH 09 respectively.
Neither is any detail given for sizing the tank in terms of demand and supply. This
information can be found in many RWH texts or on the DTU Web Page at
http://www.eng.warwick.ac.uk/DTU/rainwaterharvesting/index.html
TR-RWH 01 5
Materials
The following are the materials required for a 10.8 cubic metre, ferrocement lined
tank.
Table 2 - Materials requirement for the 10.8 cubic metre ferrocement lined PBG tank
Item Tank component
Ground Ring Excav- Parapet Parapet - Internal Internal Cover Placing Totals
leveling beam ation wall external render render- cover
and ring render - first second
excav'n coat coat
Cement (OPC) - kg 30 50 25 100 200 50 10 465
Sand - kg 60 300 125 300 600 150 50 1585
Aggregate (<50mm) kg 120 120
Bricks (angled) - no 300 300
Chicken wire (0.9m wide) - m 24 24
Staples - kg 1 1
Waterproof agent - kg 4 4
6mm rebar - m 20 20
8mm rebar - m 20 20
Coffee tray mesh - (0.9 wide) 4.8 4.8
-m
Binding wire - kg 1 1
Basin for filter 1 1
Labour (skilled) - days 0.25 1 2 2 2.5 1 0.5 9.25
Labour (unskilled) - days 1 0.5 10 2 2 2.5 1 0.25 19.25
TR-RWH 01 6
Instructions for manufacture
1. Finding a suitable site
1.1. The first step is to find a suitable site for the tank. Some pointers for what
constitutes a good site are given below:
Close enough to the dwelling to avoid long lengths of guttering and
downpipe (some suggest siting the tank mid way along the length of a
building to reduce gutter size this is fine if water from one side of the
building only will be fed into the tank)
Reasonably flat where possible otherwise the ground will have to be
levelled before marking out
Away from areas where surface water will gather (i.e. depressions)
Away from trees the roots of trees can be problematic
Away from areas where animals will wander or else the tank should be
fenced off
Not so close to the dwelling that the foundations of the dwelling are
undermined
Somewhere convenient for extracting water e.g. close to the kitchen area
1.2. The ground should be suitable for digging and for siting such a tank. There
should be no large stones, bed rock or sheet rock close to the surface, and one
should be sure that the groundwater table in the area is several meters below
the bottom of the tank. This information can often be gleaned from locals
who may have tried digging wells, sinking boreholes or digging garbage pits.
Figure 2 - Showing the cleared ground and the markings in place for the ring
beam
2.2. The nominal diameter of the tank is given as 2m. All the sizes given in these
instructions are for a tank of 2m nominal diameter. The actual internal
diameter is slightly less than this.
TR-RWH 01 7
2.3. The actual volume of the tank is dependant, therefore, upon the depth of the
tank. Table 2 below shows the volume of the tank for a number of given
depths (the depth is total depth from the top of the parapet wall, which is
1.0m high).
3.3. Make a concrete mix of 1:2:4 (cement : sand : aggregate), using the quantities
shown in Table 5. Be sure the concrete is well mixed and then place the mix
into the trench being sure that any air voids are removed by vibrating the
concrete with a stick. Remember that wet concrete mixes will have lower
final strength, so keep the mix workable but not too wet.
TR-RWH 01 8
Table 5 - Quantity of material required for the ring beam
Approximate quantity
required
Material Kg
Aggregate (<50mm) 120
Sand (clean, graded) 60
Cement (Ordinary Portland) 30
Water (clean) Enough to make the mix
workable
3.4. The ring beam should be covered and cured for 7 days before any further
work is carried out (keep the concrete wet during the curing period). Keep the
beam covered with polythene during this time and wet the concrete at least
twice a day.
Radius 0.95m
Radius 1.10m
4.2. As a rough estimate of the time and manpower required to dig the hole, use
the figure of 1 person-day per cubic metre of excavation.
4.3. The bottom of the hole is shaped like a hemisphere or an inverted dome. This
shape is easily dug with a shovel. A rod can be placed centrally in the ground
and a piece of string used as a guide if there is any difficulty.
TR-RWH 01 9
Figure 5 Excavation of the tank
Figure 7a Showing the mould used for Figure 7b - The bricks with profiled ends
casting the bricks used for the parapet
wall
TR-RWH 01 10
5.2. The number of bricks required depends on the actual brick size, but assuming
the dimensions are as given above, then 24 bricks per course will be required.
For a height of 1.0m this will be a total of 240 to 270 bricks (10 or 11 courses
depending on thickness of mortar used). This represents 6m2 of brickwork.
5.3. Bricks should be laid with a mortar mix of 1:6. When placing the final course
of bricks two small gaps should be left, one for handpump pipe, which will be
placed later, and the other for the overflow pipe. This should also be cast into
the wall at this stage.
5.4. The overflow trap (see Figure 9) allows overflow water to escape from the
tank while preventing mosquitoes from entering the tank. The U-trap is filled
with water and so mosquitoes cannot pass. A mosquito mesh also prevents
mosquitoes entering the overflow pipe. The trap is made from 50mm (or
similar) plastic pipe. If the U-trap is not used then mosquito mesh should be
fitted over the end of the overflow pipe. The tank owner should be advised to
replace this if damaged or removed.
5.5. When complete, the parapet wall can be externally rendered. This is not
essential but makes the tank look better.
250mm
7.5o
angled
brick ends
100m
225mm
a/ b/
Figure 8 - a/ where bricks are cast and fired specially for tank construction, they can
be cast with a slight angle at each end. To minimise the amount of mortar used the
bricks should be cast with an angle of 7.5o on each end of the brick b/ showing actual
dimensions of brick cast for tank construction
TR-RWH 01 11
5.6. Material requirement for wall
5.7. Allow 2 skilled person-days and 2 unskilled person-days for building and
rendering the parapet wall.
6.2. It is very important to achieve a waterproof lining for the tank. As mentioned
earlier, one of the drawbacks of an underground tank is that it is difficult to
TR-RWH 01 12
detect leaks. We, therefore, need to be sure that the tank is well lined and will
not leak under normal usage. Good workmanship here is essential.
A thin coat (~ 1cm) of 3:1 cement render is applied evenly to the wall of
the tank. When the render has started to set (after about 30 minutes), score
the render lightly to provide a key for the next layer.
This first coat is allowed to cure for 2 days. The top of the tank should be
covered with a plastic sheet during this time and the walls regularly and
liberally sprinkled with water.
A layer of 1 chicken wire mesh is then applied to the render. This mesh is
fixed to the render using galvanised fencing staples. Care should be taken
to lay the mesh as flat as possible onto the render.
When the chicken wire is in place the second coat of render can be
applied. This is again a 1:3 mix, but includes a waterproofing agent, which
is added during the mixing. Any proprietary waterproofing agent can be
used and the manufacturer's instructions followed regarding the quantity to
be added. The second coat of render should be applied in a similar fashion
to the first about 1cm in thickness (although it may be thicker in places
to cover the chicken mesh). This second coat of render should be cured for
7 days as described above.
The gap around the overflow pipe should be sealed using a waterproof
mortar. This is done before the cover is fitted.
Scaffolding or ladders should be used when rendering the walls of the tank.
See Figure 12
TR-RWH 01 13
Material requirement for render:
Table 7 Quantity of material required for the ferrocement lining (1:3 mix
approx. 21m2)
Approximate quantity required
Material kg
Sand (clean, graded) 600
Cement (Ordinary Portland) 200
Water (clean) Enough to make the mix workable
TR-RWH 01 14
Figure 13 - The tank with cover in place
8.2. The cover is easily lifted into place by 4 6 people. It weighs in the region of
200kg and the lifting height is 1m. Care should be taken when lifting the
cover and proper safety precautions should be observed.
8.3. The cover will be mortared into place. A 2cm thick mortar is placed on top of
the parapet wall and the cover is placed onto the mortar. The mortar is
smoothed to seal the cover onto the wall. The mortar is also smoothed on the
inside of the wall / cover joint to form a continuous waterproof lining.
9. The filter is part of the cover. When the cover is manufactured, a plastic basin is
used to form the access opening. This basin is then left in place, filled with coarse
gravel and covered with a fine cloth. The cloth filters out any coarse debris and
should cleaned when dirty and replaced when damaged. It is easy to monitor the
condition of the cloth as it is in clear view on top of the tank. The owner of the
tank should be made aware of this.
Figure 14 - Showing two types of handpump (DTU and Tamana), filter basin and
externally rendered parapet wall, on this demonstration tank at Kyera Farm, Mbarara,
Uganda. The guttering has not yet been fitted.
TR-RWH 01 15
10. Guttering and pipework
10.1. The guttering and downpipe are not specified. This is due to the wide
variation in the styles available. This is left to the discretion of the installer.
11. Maintenance. The maintenance of the tank is quite simple. The following steps
should be followed:
The tank should be cleaned annually - at the end of the dry season, the tank
should be emptied and any debris in the bottom of the tank removed.
The filter should monitored to make sure that it does not become blocked. If
the cloth becomes damaged it should be replaced.
The overflow should be covered with mosquito mesh at all times.
The tank and associated guttering and pipework should be kept in good
general repair. Any damage or faults should be rectified as soon as possible.
The maintenance of the pump is discussed in TR-RWH 09.
TR-RWH 01 16