You are on page 1of 16

wor

Energy Reports 2 (2016) 8998

Contents lists available at ScienceDirect

EnergyReports
journal homepage: www.elsevier.com/locate/egyr

Design and assessment of solar PV plant for girls hostel (GARGI) of


MNIT University, Jaipur city: A case study
Rahul Khatri
Guest Faculty, Centre for Energy & Environment, Malaviya National Institute of Technology, Jaipur, India

articl MNIT University Jaipur city was analyzed. A solar PV plant was
designed with its financial and environmental assessment
e considering recent market prices. All the aspects related to a
solar PV plant were considered for financial feasibility of PV
Article history: plant near this location. The different financial parameters
Received 4 which affect the financial feasibility of PV plant were considered
December 2015 i.e. discount rate, effective discount rate, rate of escalation of
Received in electricity cost, salvage value of the plant etc. The
revised form
environmental aspect related with the energy generated with
12 April 2016
PV plant i.e. reduction in carbon emission and carbon credits
Accepted 9
May 2016
earned was also considered. Result obtained with the
Available assessment of the proposed plant with different discount rate
online 24 May and current rate of inflation shows that the max IRR 6.85% and
2016 NPV of $1,430,834 was obtained with a discount rate of 8% and
an inflation rate of 7.23% when no land cost considered and if
land cost was considered the maximum IRR was 1.96% and NPV
Keywords:
PV plant
of $630,833. Minimum discounted payback of the plant will be
Financial 13.4 years if inflation was considered.
assessment 2016 Published by Elsevier Ltd.
Payback period This is an open
& carbon credits access
article
abstrac under
the CC
t BY-NC-
ND
In this paper license
designing and (http:/
assessment of /creati
a solar PV vecom
plant for mons.
meeting the org/lic
energy enses/
demand of by-nc-
girls hostel at nd/4.0
/).

1. Introduction available throughout the year must be


utilized to its maximum. At the same
In current era the use of time as the efficiency of the solar
renewable technology for energy systems is low a real time financial
generation is growing at a faster rate. analysis must be done to identify the
Considering the low stock of conditions in which it will be most
conventional fuels and consistent economical. The use of energy for the
price rise the use of solar energy at production and installation of the
places where solar radiations are renewable system must be taken into
90 R. Khatri / Energy Reports 2 (2016) 8998

account to calculate their energy land required for it and its economic
payback time. This paper present a analysis is proposed. This paper cover all
complete analysis and assessment of the preferences addressed by the (Soni
a PV plant for Gargi Hostel for girls at and Gakkhar, 2014) in their paper i.e.
MNIT Jaipur which comprises of 406 Costs, Payback period as an economical
rooms and can have at least same parameter, location and CUF as a
amount of girls residing at a time in technical parameter and type of cell and
hostel. The idea of developing performance ratio as PV parameters.
environmentally friendly PV plants Nomenclature
was discussed (Chena et al., 2012) and
MNIT Malaviya National Institute of Technology
suggests that huge green energy
PV Photovoltaic NPV
source generated from the sun, PV
Net Present Value
industry will gain the best opportunity
to grow up. We should grasp the kWp Kilowatt peak
opportunity to build the most suitable (EPBT), Energy Payback Time
environmental friendly PV power (LCCE) Life Cycle Conversion Efficiency
plant. Considering this as an EPF Electricity Production Factor
opportunity to propose a clean source Ah Ampere-hour
of energy for complete energy V Voltage
demand of the girls hostel, a solar PV DOD Depth-of-Discharge
plant design and its assessment has MPPT Maximum Power Point Tracking
been carried out. CUF Capacity Utilization Factor
GHG Green House Gas
Em Energy for Materials
E-mail address: rahulkhatri2311@gmail.com.
Emf Energy for manufacture PV system
http://dx.doi.org/10.1016/j.egyr.2016.05.002 Et Energy for Transport
The study carried out for photovoltaic Ei Energy for Installation
systems size optimization techniques Emg Energy for Management
suggests that optimization of PV system Eg Annual Electricity Generation
is strongly depends on meteorological Esol Solar Energy
variables such as solar energy, ambient
Ls Life of Plant
temperature and wind speed (Khatib et
Cu Cost per unit of Electricity
al., 2013) so it becomes important to
CRF Capital Recovery factor i
have a detailed analysis at various
Discount Rate
locations for accurate results. This paper
will identify the designing and i Effective Discount Rate j
assessment issues and will allow Inflation Rate
developing energy strategies for the e Escalation Rate of Electricity
areas similar to that of the study. A case Sharma and Tiwari (2013) provides an
study on Gambia (Sowe et al., 2014) inclusive comparative life cycle
evaluate the feasibility between assessment of on-field PV system dealing
crystalline Si (c-Si) and thin film (CdTe) on an existing setup. Energy metrics
modules on the basis of NPV and IRR. (energy payback time, electricity
Based on technical and economic production factor and life cycle
assessments of the c-Si and CdTe PV conversion efficiency) of hybrid
power plants, the CdTe PV power plant photovoltaic (PV) modules have been
presented the reasonable technology for analyzed and presented for the
rural electrification in The Gambia. composite climate of New Delhi, India
Similar case study (Messinaa et al., 2014) (Tiwari et al., 2009). A review has been
having two 2.4 kWp grid-connected PV done to estimate the environmental
systems installed at different locations impacts of different solar PV based
i.e. Tepic and Temixco-Morelos electricity generation systems using life
concluded that the Temixco-Morelos PV cycle assessment technique (Sherwani et
system supplied nearly 90% of electrical al., 2010). A study on the life cycle
energy need for the house and identifies assessment of PV systems (Kannan et al.,
grid-connected PV in the urban and 2006) used EPBT as an indicator for
suburban areas or stand-alone PV primary energy use, life cycle cost
systems for the remote agricultural analysis are performed for a distributed
communities in Mexico is both feasible, 2.7 kWp grid-connected monocrystalline
and should form part of the national solar PV system operating in Singapore
sustainable policies. and concludes that GHG emission from
In this paper a 336 kW p on site solar electricity generation from the solar PV
PV power plant was designed with the system is less than one-fourth that from

2352-4847/ 2016 Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
R. Khatri / Energy Reports 2 (2016) 8998 91

an oil-fired steam turbine plant and one- 3.1. Panel generation factor (How to
half that from a gas-fired combined cycle Design Solar PV System)
plant, it shows great impact on the
environment. Panel Generation Factor is a key
The methodology adapted was based element in designing a solar PV plant
on the literature survey and the process which gives for every Wp capacity in
flow of the paper is shown in the Fig. 1. the panel we can expect to get an
This paper provides design and analysis average of Wh/day and it is different
of a 336 kWp SPV plant with different in each site location, for Jaipur city
parameters associated with real time considering 5.30 kWh/m2;
market prices and future escalation of
Panel Generation Factor
the prices. This paper analyzes feasibility
Daily Solar
study for the plant near the site location
Radiation
with its energy metrics i.e. Energy
Payback Time (EPBT), Life Cycle =
Conversion Efficiency (LCCE) etc. A
satellite image of the hostel location with Standard Test conditions Irradiance
its sunpath is shown in Figs. 2 and 3 for PVpanels
which shows the availability of the land
near the site.
. (1)
2. Energy demand of the hostel
3.2. Energy required from PV modules
A detailed survey of each room of (How to Design Solar PV System)
hostel and sections of the hostel was
carried out to identify the amount of Energy required from PV modules
load connected to it. Tables 15 provides will be daily energy demand of the
the complete details of the different hostel and compensation for the
equipments their wattage and hours of system losses which is generally taken
operation (on the basis of survey) (How as 30%, therefore the total energy
to Design Solar PV System). Total energy required will be
that needed to be supplied by the solar Energy required
PV system is estimated as 1368 kWh/day.
= (Energy Demand System Losses
Table 1 Compensation Factor)
No. of rooms in hostel.
Floor = 1368 1.3 = 1778.4 kWh/day. (2)
Ground
First 3.3. Watt Peak rating for PV modules
Second (How to Design Solar PV System)
Third
Fourth
Total Watt peak rating for PV
Fifth
Total modules is calculated to identify
system sizing which depends on the
energy required from modules and
3. Solar photovoltaic power plant
designing panel generation factor
Watt Peak rating for PV Modules
Design of solar photovoltaic power
Energy required from PV modules
plant consists of PV modules sizing,
1780
inverter sizing, battery sizing and
module circuit design. For designing = =
solar PV plant geographical details = 336 kWp. (3)
and weather data of the site is Panel Generation Factor 5.30
required. Table 6 and Fig. 4 provides a
monthly average radiation data for 3.4. PV modules (How to Design Solar PV
the Jaipur city which is located at System)
26.9260N, 75.8235E in Rajasthan
state of India (Synergy Enviro A nearby supplier of PV module
Engineers). Fig. 5 provides the was identified for a realistic analysis
location of Jaipur city in Rajasthan and and availability of the modules, Ajit
its global daily radiation data. Solar with PV module model of ASPL
V-60 was considered in this analysis.
This module was selected as the
92 R. Khatri / Energy Reports 2 (2016) 8998

supplier is local and agreed on the selected module and Table 7(ii)
mentioned cast i.e. 0.62$ per W. Table provides the modified efficiency
7(i) gives full specifications of the

Table 2
Energy required in rooms.
S.No. Name of equipment Nos. Rating (W) Hours of operation Energy required (kWh)
1. Tube light 01 40 12 0.48
2. Fan 01 60 18 1.08
3. Laptop 01 60 6 0.36
4. Server (LAN port) 01 15 6 0.09
5. Mobile charger 01 5 2 0.01
One room 2.02
For 406 rooms 820.12

Table 3
Energy required per floor other than rooms.
S.No. Component Nos. Electrical equipment Total wattage (W)
Hours of operation Total (kWh)

Type Quantity Rating (W)


1. Stairs 4 CFL 4 15 240 12 2.88
2. Bathroom 8 CFL 10 15 1200 12 14.40
3. Lobby CFL 84*2 15 2520 12 30.24
4. Water cooler 2 2 1550 3100 4 12.40
For one floor 59.92
For five floors 299.60

Table Energy
4 required for miscellaneous.
S.No. Component Quantity Electrical equipment Total wattage (W)
Hours of operation Total (kWh)
Name Quantity Rating (W)

1. Mess 01 Tube lights 39 40 1 560 4 2.88


Fans 27 60 1 620 9 14.58
Water cooler 01 1550 1 550 12 18.60
2. Common room 02 Tube lights 12 40 960 12 11.52
Fans 08 60 960 18 17.28
3. Laundry room 01 Washing machine 06 4300 25 800 2 51.60
Dryer 06 5.6 25 800 2 51.60
R. Khatri / Energy Reports 2 (2016) 8998 93

Fig. 1. Process flow for design and assessment of the PV plant.

Fig. 2. Satellite view of Gargi Hostel MNIT Jaipur.


94 R. Khatri / Energy Reports 2 (2016) 8998

Fig. 3. Sun path on Sep-22 at Gargi Hostel using


SunCalc.
of cell, based on temperature variations on the location; Depth of Discharge =
the total no of modules required for the proposed plant 40%
depends on the peak rating of the modules. Battery Capacity = 175
Total Watt Peak Rating Ah
No. of modules required =
Battery Efficiency =
90%
PV module Peak Rated
Output Life of a Battery = 4
years

1460 Modules.
(4)
Battery sizing (How to Design Solar PV System)
Designing an onsite power plant always requires a
Table 6
storage medium and in case of PV plant batteries is the
Solar
most common storage medium, in present case as it is an radiation
educational institute it is very important to have storage data for
medium importantly for exam days. The battery should be Jaipur
(26.9260
large enough to store sufficient energy to operate the
N,
appliances at night and cloudy days. MNIT is located in 75.8235
Jaipur city with minimum power cut periods therefore E)
single day of autonomy is enough for the hostel (Synergy
requirements. ).
Month Average (kWh/m2)

Table 5 Jan 4.19


Total energy required per day. Feb 5.00
S.No. Component Total energy required per day (kWh) Mar 6.09
Apr 7.08
1. Rooms 820.12
May 7.23
2. Floors components 299.60 Jun 6.64
3. Miscellaneous 247.56 Jul 5.15
Total 1367.28 Aug 4.81
Battery Sep 5.42
Oct 5.00
Specificat
Nov 4.27
ons: Dec 3.68
Annual Average 5.3 (kWh/m2/day)
Nominal Voltage = 48 V
R. Khatri / Energy Reports 2 (2016) 8998 95
April 38 13 0.053061 0.1515
may 41 16 0.065306 0.1496
June 40 15 0.061224 0.1502
July 35 10 0.040816 0.1535
Aug 33 8 0.032653 0.1548
Sept 35 10 0.040816 0.1535
Oct 34 9 0.036735 0.1541
Nov 30 5 0.020408 0.1567
Dec 25 0 0 0.16
Average 0.1550

Table 8
Life cycle and environmental assessment of the plant.
S.No. Parameters Value
1 EPBT (energy payback time) 8.24 yr
2 Electricity production factor 0.12
3 Capacity utilization factor 0.152
Fig. 4. Monthly solar radiations variations in Jaipur city
(Synergy). 4 Life cycle conversion efficiency 0.072
5 Total embodied energy of the plant 1516.59 kWh/m2
6 CO2 emission from embodied energy 5794 tonnes Of CO2
Table 7(i) 7 Yearly CO2 mitigation 702.5 tonnes Of CO2
PV module specifications (Ajit Solar ASPL V-60) ASPL Product 8 Net CO2 mitigation 15 281 tonnes Of CO2
Information. 9 Carbon credits earned $10,300
a
Module type ASPL V60
3.5. Inverter rating
Peak power output watt (Wp) 230
(How to Design Solar
Current at peak power output amp (Imax) 7.77
PV System)
Voltage at peak power output volt (Vmax) 29.60
Short circuit current amp (Isc) 8.28
Open circuit voltage volt (Voc) 37.10 Size of the inverter
Dimensions (mm) required
1665 * 995 * 50 for the plant
Cell efficiency 16% depends upon the
Power tolerance 3%
a
peak watts
Electrical specifications mentioned above are at standard test
conditions of 100 mW/sq cm. AM 1.5 and at 25 C cell temperature and requirement. The
are within normal production tolerance of 10%. peak requirement of
the hostel is 336 kW p.
The inverter must be
Batter Capacity Required (Ah) large enough to
(Total Wh required) Days of Autonomy handle the total
= amount of watts peak
requirement. The
(5) inverter size should
Nominal Battery Voltage (1 DOD) Battery
be 25%30% bigger
Efficiency than total watts
Batter Capacity Required (Ah) requirement; The
inverter size = 336
. 1.3 = 450 kW.
Cost effective
No. of Batteries required: Solectria PVI 82 kW
The total no. of batteries required depends on the Grid Tied Inverter 480
capacity of each battery, in present analysis; Trojan VAC PVI-82 kW
J185E-AC 12V Deep Cycle (Solectria) inverter
Battery costing $205.5 is used (atbatt.com); costing $36 306 was
selected for the
Battery system with 82 kW
Capacity Required No. of Batteries rated Power and max
= open circuit voltage
Single Battery Capacity of 600 VDC, integrated
with PV Maximum
Power Point Tracking
= = 302 Batteries.
(MPPT).
Table 7(ii)
According to the
Modified cell efficiency based on temperature variation (Dubey et al., 2013). rated power of the
Month Average temperature TTref (TTref) Efficiency inverter
( the no. of
Jan 23 2 0.00816 0.1613 inverters required is:
Feb 26 1 0.004082 0.1593
Mar 32 7 0.028571 0.1554
96 R. Khatri / Energy Reports 2 (2016) 8998

Inverter Size 450 4.1. Energy payback


No. of inverters = = = 6. time of the plant
(7)
Rated Power of an Inverter 82 Energy payback
time is defined as
3.6. Module circuit (How to Design Solar PV System) How long does a PV
system have to
The module circuit means the no. of modules to be operate to recover
connected in series i.e. the size of an array and voltage the energy that went
input to the inverter and total no. of arrays in the solar into making the
field. system and it is
Size of an array depends on the inverter maximum Voc given by;
and Voc of the module used.
Maximum Open Circuit Voltage of (Em + Emf +
Inverter Et + Ei +
Size of an array = Emg)

Open Circuit Voltage of each PV


Module (10)

= = 16 Modules.
Maximum voltage input to the inverter where;

(Maximum Voltage from a Module No. of Modules in E m: Primary


Series) energy demand to
produce materials
= (29.6 16) = 474 V
comprising PV
Total No. of Arrays in the solar field will be system.
No. of Modules 1460 Emf : Primary
= = = 91 Arrays. energy demand to
(9) manufacture PV
system. Et:

Fig. 5. Global daily radiation in Rajasthan.


4. Life cycle assessment of the PV plant Primary energy
demand to
The assessment of any renewable system includes the transport
amount of energy consumed by the system components materials used
for their materials; manufacturing transportation i.e. during the life
embodied energy of the system amount of energy cycle.
generated by the plant, its energy payback time (EPBT) its Ei: Primary energy
life cycle conversion efficiency (LCCE) and capacity demand to install
utilization factor (CUF). Table 8 provides the complete the system.
details of the life cycle assessment of the proposed plant.
R. Khatri / Energy Reports 2 (2016) 8998 97

Emg: Primary energy demand for end-of-life


management.
Eg: Annual electricity generation in primary energy
terms.

The value for the total energy consumed in materials,


manufacturing, transport, installation and management
for each m2 area of the module was proposed by Tiwari et
al. (2009).
(Em + Emf + Et + Ei + Emg) = 1516.59 kWh/m2 of module,
therefore;

Total Embodied
Energy is = 2418
1516.59 = 3667 MWh
(Eg) = 1368
(325)# =
444.6
MWh/year
.
# No. of Clear
Sunny days in
Jaipur (Pandey et
al., 2012),

Energy Payback Time


(EPBT)
Total
Embodied
Energy of
Modules
=

Annual
Electricity
Generated from
Plant

= = 8.24
years. (12)

4.2. Electricity
production factor
(EPF)

It is defined as
Total area of modules
the ratio of the
= No. of Modules Length Width of Modules annual energy
output to the input
= 1460 1.665 0.995 = 2418 m2 energy and it
predicts the overall
98 R. Khatri / Energy Reports 2 (2016) 8998

performance of the PV module. EPF is reciprocal of CO2 Emissions =


EPBT. Thus (Eem 1.58) =

Eg 444.6 3667 103
EPF = = = 0.12.
1.58
(13)
(Emg + Emgf + Et + Ei + Emg) 3667 = 5794 tonnes of CO2.
(16)

4.3. Capacity utilization factor (CUF) 5.2. CO2 mitigation

Capacity Utilization Factor (CUF) is the ratio of The CO2


actual energy generated by SPV plant over the year to mitigation is the
the equivalent energy output at its rated capacity over amount of CO2
the yearly period. The energy generation for SPV emission reduction
project depends on solar radiation & number of clear by generating the
sunny days energy from the
Annual Energy Generated for each kW peak PV plant that
capacity would otherwise
released by the
CUF =
8760 hours thermal power
444600 plant in case of
336
= India.
= 0.152. (14)
8760 Yearly CO2

mitigation = Eg
4.4. Life cycle conversion efficiency (LCCE)
1.58 = 444.6
It is the net energy productivity of the PV system with 103 1.58
respect to the solar input (radiation) over the life time of = 702.5 tonnes of
the PV system, CO2. (17)

Eg
5.3. Net CO2
Ls Eem mitigation
LCCE =
Net CO2
Esol Ls mitigation for the
proposed PV
power plant will be
.
the difference
(15)
between the CO2
emission and CO2
5. Estimating Greenhouse Gas Emissions Reduction,
mitigation over its
Mitigation and Carbon Credit
entire life i.e. 30 yr.
Photovoltaic is a clean source of energy requiring Net CO2 Mitigation = (Yearly CO2 Mitigation Ls)
no fuel and no GHG emissions during its service
periods. India is highly dependent on the coal based (CO2 Emissions )
thermal power plants for electricity generation and the = (702.5 30) 5794
average CO2 emission is 0.98 kg of CO2 per kWh. = 15 281 tonnes of CO2. (18)
5.4. Carbon credits
5.1. CO2 emissions
Carbon Credits
CO2 emission from the embodied energy of the PV are awarded
plant includes the emissions in manufacturing, against reduction
materials etc. The average CO 2 emission for electricity in greenhouse
generation and considering other embodied emissions gases emissions
from coal based thermal power plant is 0.98 kg of CO2 CO2 etc. Carbon
per kWh (Sharma and Tiwari, 2013). If the transmission credits can be
and distribution losses and, for Indian conditions are traded in the
taken, the average CO2 per kWh can be taken as 1.58 international
kg. market at their
R. Khatri / Energy Reports 2 (2016) 8998 99

current market price. One carbon credit is earned iv. Miscellaneous


against reduction in one tonne of CO 2 emissions {Operation and
(tCO2e). In present work the net CO 2 mitigation is 15 Maintenance cost,
281 tCO2e. Installation Cost,
The current market price of one carbon credit is $0.67/ Electrical Items
tCO2e (Certified), Rakhi Sharma et al. used $31/tCO 2e (Cables etc.),
which is nearly 50 times more than the current Packing and
exchange rate. Freight}.

Carbon Credits ($) = 15 281 0.67 = $10,300


6.1. Cost of modules
Yearly Earnings from carbon Credits : $350
#
$ Ajit Solar ASPL V-
1 60 module is
. considered in the
4 designing of the
8 plant. The global
/ module cost is
e decreasing every day,
. the market trends
shows that currently
it is around $0.62 per
6. Financial assessment of the plant
Wp in India (Global PV
Renewable energy technologies have enjoyed a Module Pricing).
period of rapid growth in recent years. They will have
to become price competitive to sustain their growth. Total module cost =
For the financial assessment of the plant the realistic 336 103 0.62 =
values or the current market prices of the components $208,320. (20)
associated with the project must be taken, most of the
studies for the financial assessment does not include
the real market prices, Chandel et al. (2014) uses 6.2. Cost of inverters
modules that cost $530 for 215 W Pmax
Inverter is an
Table 9 electronic device
Cost break-up for solar PV plant. which is able to
S.No. Particular Cost ($)
convert a DC potential
1 Module cost normally derived
2 Batteries cost from solar panels or
3 Inverters cost battery into a
4 Miscellaneous cost
5 Land cost
stepped-up AC
Total cost without land cost potential which may
Total cost with land cost be quite comparable
1,698,333
which is highly unrealistic in current market. This study to the voltage that is
uses the current market prices of the components for a found in domestic AC
real time financial analysis. Table 9 gives details of the outlets. Solectria PVI
cost breakup for the proposed plant. Table 10 gives a 82 kW Grid Tied
complete list of parameters used for the financial Inverter 480 VAC PVI-
assessment of the plant and Table 11 gives complete 82 kW (Solectria) was
details of the result obtained from the financial considered for this
assessment of the plant. system.
The project cost includes
Cost of One Inverter =
i. Cost $36 300
of Total Cost of Inverters
Modules. = $36 300 6 =
ii. Cost of $217,800. (21)
Batteries.
iii. Cost 6.3. Cost of batteries
of
Inverters. Batteries store
energy being
produced by a given
100 R. Khatri / Energy Reports 2 (2016) 8998

generating source, and when this source is unavailable layout and their
this energy can be used by the load. The inclusion of arrangements.
storage in any energy generating system will increase the Number of PV
availability of the energy. Trojan J185E-AC 12 V Deep Cycle modules required
Battery costing $205.5 (atbatt.com) was used. The battery 1460; the arrays can
life was considered as five years as there will be no be arranged as 7
frequent use of batteries and annual maintenance arrays in a row and 13
contract will improve the life of the battery. The such rows. So the
replacement cost was considered after every five years area required will be
considering the applicable discount rate
Dimension of one PV
module = 1.665 m
Cost of (4 12 V) Battery with Rack
0.995 m
= ($205.5 4 + $150 4) = $1422
No of Modules
Total Cost of Batteries = $1422 302 = $429,444.
Table 10
Parameters for economic assessment.
S.No. Particular Value
1 Discount rate i 8%, 10%, 12%
2 Inflation rate j 7.23% (July-2014)
3 Effective discount ratea i* 0.7%, 2.6%, 4.5%
4 Price of unit energy $/kWh 0.13
5 Escalation in price of unit energy e 2%
6 Cost of land $ 166.67/m2
7 Rs to $ Rs 60/$
a
Effective discount rate .

Table 11 Financial analysis of the SPV


plant.
Considering 2% escalation in price/kWh
With land cost NPV ($) IRR Discounted payback period Simple payback period (yr)

Discount rate@ 8% Negative 4.92% NEVER


@ 10% Negative 6.65% NEVER 27.35
@ 12% Negative 8.32% NEVER

Effective discount rate (i)


Discount rate@ 8% = 0.7% 630,833 1.96% 23.6 yr
@ 10% = 2.6% 21,167 0.08% 29.3 yr 27.35
@ 12% = 4.5% Negative 1.74% NEVER
Without land cost

Discount rate@ 8% Negative 0.38% NEVER


@ 10% Negative 2.18% NEVER 14.47
@ 12% Negative 3.93% NEVER

Effective discount rate (i)


Discount rate@ 8% = 0.7% 1,430,834 6.85% 13.4 yr
@ 10% = 2.6% 821,167 4.87% 15.16 yr 14.47
@ 12% = 4.5% 412,834 2.96% 18.19 yr

6.4. Miscellaneous cost connected in series =


16
Miscellaneous cost including Operation and
Width of an array =
Maintenance cost, Installation Cost, Electrical Items
(Cables etc.), Packing and Freight, it comes out to be 0.995 16 = 16 m2
nearly $0.13/Wp (Chandel et al., 2014), thus total
miscellaneous cost of the proposed plant will be

Miscellaneous cost = 0.13 336 103 = $43,680.


Width of the solar
6.5. Land required
field = No. of array in
Financial assessment includes the land cost of the site row 16
therefore two cases were taken while assessment i.e. = 7 16 = 112 m
once land cost was considered and in second case land (24)
cost was not considered. If land cost is to be considered
No. of rows in solar
for the plant the area required for plant must be
field = 13
calculated. The area of the plant depends on the modules
R. Khatri / Energy Reports 2 (2016) 8998 101

Assuming Ground Cover Ratio of the plant 12 0.124 Negative


System Effective i CRF NPV * CRF $/kWh
as 0.5, the pitch distance between
0.7 0.037 630,833 0.0525
consecutive array will be 2.6 0.048 21 167 0.0023
With land cost
= 1.665 2 = 3.4 m 4.5 0.061 Negative

Total length of the solar field 0.7 0.037 1,430,834 0.12


Without land cost 2.6 0.048 821,167 0.089
= (3.4 12) + 1.665 m (Either for first or last row ) = 4.5 0.061 412,834 0.057
43 m the consumption
So total area required for the plant is = 112 43 = 4816 of fossil fuels but it
m2. (25) can be a
continuous source
6.6. Cost of land
of energy for
The MNIT university is located near Jaipur airport in critical areas like
Malaviya Nagar where the current price of the land is hostel of
universities where
$166.67/m2 near to the proposed site, the total
uninterrupted
investment required to
supply is
acquire the land will be = 166.66 4816 = $802,635. demanded. As this
is a case study it
6.7. Cost per unit of electricity (Cu) will imply on the
places like
Cost of energy is the price at which electricity must Rajasthan or an
be generated from a specific source to break even over area with
the lifetime of the project. It is an economic abundant solar
assessment of the cost of the energygenerating system energy available
including all the costs over its lifetime: initial for nearly whole
investment, operations and is very useful in calculating year. In this paper
the costs of generation from different sources. the efforts have
The cost of energy is calculated using capital been made to
recovery factor, NPV net present value and annual identify the
energy generated from the system. Table 12 gives requirements of
values of Cu at different discount rates, with and the plant for
without land cost. continuous supply
of energy to the
Annualized uniform cost
hostel and its
The Cu = feasibility was
Annual energy identified with its
generated where; Annualized environmental and
uniform cost = NPV CRF financial
assessment. This
NPV = Net present value will be useful for
i (1 + i )n energy planning
and developing

CRF = Capital Recovery factor = (1 + i )n new strategies for
PV
1, implementation.
Reduction in
i = discount rate, n = life of plant. CO2 emissions from
the energy
7. Results generated with
solar energy which
The analysis of a solar PV plant designed for a girls could be otherwise
hostel is carried out. The PV technology is not used only generated with
for reducing highly polluting
coal based thermal
Table 12
power plant was
Cost per unit of electricity (Cu).
System Discounts rate (i) CRF NPV * CRF also analyzed. For
a precise
8 0.088 Negative
With land cost 10 0.106 Negative assessment the
12 0.124 Negative embodied energy
8 0.088 Negative
of the plant is also
Without land cost 10 0.106 Negative taken into account,
102 R. Khatri / Energy Reports 2 (2016) 8998

which was used to analyze the energy payback time of Tabl


e 13
the plant i.e. 8.24 years with a capacity utilization Assessment of the proposed
factor of 0.152. The PV technology used can also earn PV plant.
carbon credits from reduction in CO 2 emissions and in $0.13/kWh and
the present case the proposed plant is capable of current rate of
earning nearly 15 281 Carbon credits which worth inflation of the
$10,300, however the recent market prices are very country i.e. 7.23% is
low for the carbon credits still a real value is used in also considered as an
this paper. important factor for
The peak capacity required for meeting the energy the financial viability
demand of the hostel is 336 kW p which require an area of the project; the
of nearly 4816 m2, as discussed abundant land is inflation is a variable
available inside institute campus the land cost must parameter so the
not be a factor in its financial assessment but this assessment was done
paper proposes an analysis for the location not only for with and without
the site therefore two cases with and without land cost inflation, the inflation
are considered so that the effect of land cost on the is analyzed with the
financial viability of the project could be identified. term effective
discount rate. The
results obtained from
the financial
assessment of the
plant are shown in
table where the
simple payback
period for the plant
without considering
land cost is 14.47
years which increases
to 27.35 years if land
cost is considered.
With effective
discount rate the
minimum discounted
payback is 13.4 years
without considering
land cost and 23.6
years if cost of land is
considered. The
maximum IRR with
effective discount
rate is 6.85% without
land cost. Cost of
energy Cu is the price
at which electricity
must be generated
from a specific source
to break even over
the lifetime of the
project, the
maximum Cu resulted

S.No Particular Value


1 Capacity of the plant 336 kWp
2 Life of the plant 30 yr
The effect of the
3 Area required for the plant 4816 m2
other financial 4 Cost of plant without land cost $898,333
parameters like the 5 Cost of plant with land cost $1,698,333
rate of escalation of 6 Savings from total energy generated in life time (13 338 MWh)@ Rs 0.13/kWh $1,778,334
energy with 2% which 7 Savings from carbon credits earned (15 281)@ $0.67/Credit $10,300
8 Salvage value of the plant @ 15% of total Initial cost $113,334
is currently available 9 Simple payback period with land cost 27.35 yr
@ 10 Simple payback period without land cost 14.47 yr
11 Minimum discounted payback with land cost & effective discount rate 23.6 yr
12 Minimum discounted payback without land cost & effective discount rate 13.4 yr
13 Maximum IRR with land cost 4.92%
14 Maximum IRR without land cost 0.38%
15 Maximum IRR with land cost & effective discount rate 1.96%
16 Maximum IRR without land cost & effective discount rate 6.85%
R. Khatri / Energy Reports 2 (2016) 8998 103

in this paper is $0.12/kWh. Table 13 shows complete market/ certified-


emission-reductions-
details associated with the proposed plant. futures#!/2014/09/26
This case study brings a complete analysis of a (09.26.14) online.
proposed PV plant for girls hostel and the possible future Chandel, Mevin, Agrawal,
G.D., AnujMathur,
scope of this study will be the practical implementation SanjayMathur, 2014.
which will help in developing a sustainable environment Technoeconomic
analysis of solar
and improving policies for the better use of solar energy. photovoltaic power
plant for garment zone
of Jaipur city. Case Stud.
8. Conclusion Therm. Eng. 2, 17.
Chena, Nuofu, Zhang, Xiulan,
This paper has attempted an assessment of a Solar PV Baia, Yiming, Zhang,
Han, 2012.
plant for girls hostel of MNIT University in Jaipur city and Environmental friendly
examines its financial viability with parameters associated PV power plant. Energy
Procedia 16, 3237.
and real time market prices. The findings of the presented Dubey, Swapnil, Narotam
study are concluded as: Sarvaiya, Jatin, Seshadri,
Bharat, 2013.
The 336 kWp system designed for the hostel requires Temperature dependent
photovoltaic (PV)
1460 modules of 230 Wp with an array containing 16 efficiency and its effect
modules each, the plant requires an area of 4816 m 2 on PV production in the
worlda review. Energy
this can cost about nearly the same as the capital cost
Procedia 33, 311321.
of the plant. Global PV Module Pricing,
greentechmedia.
The EPBT of the plant comes out to be 8.24 years with http://www.greentech
a life cycle conversion efficiency of 0.072. The capacity media.com/
utilization factor of the proposed plant is nearly 0.152. articles/read/global-pv-
prices-will-increase-
The carbon credits that can be earned from the plant nine-percent-in-2014
was results as 15 281 tCO2e which worth of $10,300 at (accessed 09.25.14)
online.
a price of $0.67/Credit which is very low but a real time Government, Rajasthan Solar
price from European Energy Exchange on 26/09/2014 Energy, Bureau of
was considered. Investment Promotion in
Rajasthan.
For the financial assessment of the plant an 2% http://investrajasthan.c
escalation every year in energy cost was considered om/solar-energy.cms
(accessed 09.22.14)
and a real time inflation rate of 7.23% (July-2014) online.
(Inflation India) in India was considered which resulted How to Design Solar PV
System, Leonics.
in high impact on the financial viability of the proposed
http://www.leonics.com
plant, for the discount rate of 8% and effective discount /support/article2_
rate of 0.7% the IRR is nearly three times if the land 12j/articles2_12j_en.ph
cost is not considered i.e. 6.85% and 1.96% p (accessed 09.24.14)
online.
respectively. Inflation Indiacurrent
The result shows that even in areas where solar energy is Indian inflation,
abundantly available the effect of the real time market inflation.eu.
http://www.inflation.eu
prices could affect the financial viability of the project and / inflation-
its energy saving potential. The life of the plant, the rates/india/inflation-
india.aspx, online.
current discount rate, inflation rate and escalation in
Kannan, R., Leong, K.C.,
energy cost must be considered for detailed analysis of Osman, R., Ho, H.K.,
the plant. In the current market scenario with low cost of Tso, C.P., 2006. Life
cycle assessment
renewable technology the role of other financial study of solar PV
parameters affects the financial viability of the project systems: An
therefore it is necessary to analyze all the parameters example of a
2.7kWp distributed
carefully before installing a PV plant especially in areas solar PV system in
where land cost is a considerable parameter. This paper Singapore. Sol.
can be utilized to identify shortcomings in the energy Energy 80, 555563.
Khatib, Tamer, Mohamed,
policies and strategies for the countries or states trying to Azah, Sopian, K., 2013.
reduce their GHG emissions and making this technology A review of photovoltaic
systems size
more attractive and financially viable.
optimization
techniques. Renewable
References Sustainable Energy Rev.
22, 454465.
ASPL Product Information, Ajit Solar. Messinaa, Sarah, Paz
http://www.ajitsolar.com/products.html (accessed 09.25.14) online. Hernndez Rosales,
atbatt.com. Trojan J185E-AC 12V Deep Cycle Battery. http://www.atbatt. I., Saldaa Durn,
com/trojan-j185e-ac-12v-deep-cycle-battery.asp?cr_brand=Trojan&cr_ Claudia E., Jess
product=J185E-AC (accessed 09.25.14) online. Quiones, J., Nair,
Certifiedx Emission Reduction Futures, European Energy Exchange. https:// P.K., 2014.
www.eex.com/en/market-data/emission-allowances/derivatives- Comparative study
104 R. Khatri / Energy Reports 2 (2016) 8998
of system performance of two 2.4 kW grid-connected PV
installations in Tepic-Nayarit and Temixco-Morelos in Mxico.
Energy Procedia 57, 161167.
Pandey, Shreemat, Shanker Singh, Vijai, Pal Gangwar, Naresh,
Vijayvergia, M.M., 2012. Determinants of success for promoting
solar energy in Rajasthan, India. Renewable Sustainable Energy Rev.
16, 35933598.
Sharma, Rakhi, Tiwari, G.N., 2013. Life cycle assessment of stand-alone
photovoltaic (SAPV) system under on-field conditions of New Delhi,
India. Energy Policy 63, 272282.
Sherwani, A.F., Usmani, J.A., Varun, , 2010. Life cycle assessment of solar PV
based electricity generation systems: A review. Renewable Sustainable
Energy Rev.
14, 540544.
Solectria PVI 82 kW Grid Tied Inverter 480 VAC PVI-82 kW, pvpower.com.
http: //www.pvpower.com/solectriapvi82kwinverter82kw.aspx
(accessed 09.26.14) online.
Soni, M.S., Gakkhar, Nikhil, 2014. Techno-economic parametric assessment
of solar power. Renewable Sustainable Energy Rev. 40, 326334.
Sowe, Samba, Ketjoy, Nipon, Thanarak, Prapita, Suriwong, Tawat, 2014.
Technical and economic viability assessment of PV power plants for
rural electrification in the gambia. Energy Procedia 389398.
SunCalc, SunCalc.
(http://suncalc.net/#/26.8647,75.8147,17/2014.09.22/10:49)
(accessed 9.22.14) online.
Synergy Enviro Engineers,
http://www.synergyenviron.com/tools/solar_insolation. asp?loc=Jaipur
%2CRajasthan%2CIndia, online.
Tiwari, Arvind, Barnwal, P., Sandhu, G.S., Sodha, M.S., 2009. Energy
metrics analysis of hybridphotovoltaic (PV) modules. Appl. Energy
86, 26152625.

You might also like