PURCHASE ORDER Date: August 5, 2017

PO NO# 2015-1050-001

Reverie Power & Automation VENDOR Heaven Construction and WORK TO: PGCB 132kV GIS Substation
Engineering Ltd. : Engineering Sreerampur, Dhamrai
260/B, Tejgaon, I/A 5/4 Monipurpara, Shangsad Avenue Dhaka
Dhaka-1208 Tejgaon, Dhaka
Contact: Md. Ariful Hoque Shuhan Phone: 9138488
Phone 01712225056 Email: heavenandco07@gmail.com
Email: shuhan@reverie-bd.com

ITEM
DESCRIPTION UNIT NO. UNIT UNIT PRICE LINE TOTAL
NO.
Compact Earth Filling

The Compaction of Earth Filling is 98%


1 13,58,000 CuFt 10.00 1,35,80,000.00
Earthfilling Quantity to be measured after the
completion of compaction
2 Rent For Crawler Bulldozer 3 Months 2,00,000.00 6,00,000.00

Total(BDT One Crore Forty One Lac and Eighty Thousand Only) 141,80,000.00

1. For the rent of the Crawler Bulldozer, 2 Lac Taka Advanced


would be provided. Requested to submit invoice for the
advanced payment.
2. For the rent of the Crawler Bulldozer, Payment would be
done each month for maximum 3 months. Vendor must
finish the earth filling job within 60 days. If the Crawler is
required for more than 3 months due to the latency of the
vendor, vendor would carry every cost of the crawler until
the filling and compaction is achieved.
3. Until compaction and final measurement, BDT 1000 would be
paid for each truck regardless of its measurement.
4. Minimum invoice amount would be BDT 5,00,000 Lac
5. For each week, at least 1200 Nos. of truck of soil should be
filled in the field. In case of the slow filling rate, employer
may impose liquidity damage if PGCB/SIEMENS make
liquidity damage to them.
6. This Purchase order is valid for 8 months. In any case, the
unit price of the items would not change within this time.
7. All the local issues would be taken care by the vendor.
8. The employer would provide the water supply for the soil
compaction.