Objectives

Participants know the flow of Radio Network Optimization

Participants know the key parts of the stages of radio network

Optimization

Participants make the radio network Optimization be more standard and

controllable

Page 2 www.DigiTrainee.com Company Confidential


RNP&O Service

There are four phases during network lifecycle: Pre-Bidding, Bidding,


Implementation, Maintenance.
The RNP&O services are present throughout the network lifecycle,
divided by four parts: Scheme Traction, Radio Network Planning
(including Nominal Planning, Site Selection, Detail Planning), Radio
Networking Optimization (including Initial Tuning, Network Performance
Improvement), On-going

Page 3 www.DigiTrainee.com Company Confidential


Initial Tuning Proceduer
Equipment Installation

Software
Debugging Acceptance Test
Parameter Checking

Single Site Verification

Test and Analysis (DT)

RF Trouble Shooting

Test for Comparisaon


(For Swap)
Initial Tuning
Report

Engineering Implementation Maintenance

Key Points : How to find the solution quality problem and push it.
The Initial tuning must be finished before the network come to commercial use
Page 4 www.DigiTrainee.com Company Confidential
Initial Tuning Procedure

Single site verification, the first phase of network optimization, involves


function verification at each new site.
Single site verification aimsAttention:
to ensure that each site is properly installed
PM should
and that parameters are lounch a spot
correctly check to the
configured.
sites by 5%.
Alarm data dan cells status should be
collected before the drive test.
It is necessary to check the software
version
Enginerring Parameter
Hardware and installation issue.
XXX Site Verification Table
Table
Antenna issue SSV Report
Data Configuration Input
Alarm Messages Engpar Table
Testing Instruments Problem Tracing Table

Key Points : How to find the solution for engginering quality problem and push it

Page 5 www.DigiTrainee.com Company Confidential


Network Performance Improvement (NPI)
Initial
Tuning
Customer Complaint Resolve Acceptance
Test
RF Optimization

Interfenece test and analysis

Neihgbour cell Planning

RF Parameter Optimization

VIP User Annalysis

KPI Analysis

Network Performance ATP

Implementation Maintenance

Key Points : The Manner and contents ATP : Test by cluster, test the whole network.

Page 6 www.DigiTrainee.com Company Confidential


Network Performance Improvement (NPI)

To Adjust the Engineering parameters and system parameters to meet


the coverage requirements and control the interference.

Engpar Table Eng Parameter Tuning Scheme :


DT Data Eng Par Table
Alaram data/ cells status
Traffic statistic data
Problems tracing table
Cov target range DT and Traffic statistic comparison
Hardware and Para Configuration report after optimization

Page 7 www.DigiTrainee.com Company Confidential


Page 8 www.DigiTrainee.com Company Confidential
End of Section

Page 9 www.DigiTrainee.com Company Confidential

You might also like