CJ20N Create project/WBS/Network/Acitivity/activity element- Composite

Project profile defaults the org structure/reqmt grouping


Planning Method - Free planning, bottoms up(dates from lower WBS is copied to head
WBS), top down,

Network Profile:

Workcentre category 6

Purchase Req grouping category


Bill of material transer CN33
create project specific BOM CS71

Production Scheduling Profile:


Auto batch creation
Batch classfication value assignment: forground/background
Impact of yied on Material reservation:

Template Creation
-> Standard WBS (Cj91) Normal - CJ01
-> Standard Network (CN01) Normal - CN21
-> Standard Milestone (CN11) - Normal -

Create project normal:CJ06

CN52 - Component overview


CN53N - Milestone overview