A. CONCRETING
1. Concrete hollow block
a. # 4 1,100 pcs. ( 9.00 ) P 9,900.00
b. # 6 1,050 pcs. ( 13.00 ) P 13,650.00
2. Plastering
a. Cement 35 bags ( 225.00 ) P 7,875.00
b. Sand 3.5 cu.mts ( 1,200.00/cu.mt.) P 4,200.00
3. Mortaring
a. Cement 150 bags ( 225.00 ) P 33,750.00
b. Sand 10 cu.mts ( 1,200.00/cu.mt.) P 12,000.00
4. Topping
a. Cement 15 bags ( 225.00 ) P 3,375.00
b. Sand 2 cu.mts ( 1,200.00/cu.mt.) P 2,400.00
5. C.H.B. Laying
a. 168.84 sq.mts. ( 100.00 ) P 16,039.80
6. PLASTERING / TOPPING
a. 423.44 sq.mts, ( 90.00 ) P 38,109.60
C. CEILING
1. 30 pcs. 12mm x 1.22m x 2.44m Moisture Resistant Gypsum Board
( 550.00 ) p 16,500.00
2. 50 pcs.Ga. 26 x 2 x 16 ft. furring channel
( 100.00 ) P 5,000.00
3. 14 pcs. Ga. 26 x 1 x 16 ft carrying channel
( 100.00 ) P 1,400.00
4. 120 pcs. Ga. 26 W CLIP ( 20.00 ) P 2,400.00
5. 35 pcs. Ga.26 1 x 1 x 8 ft wall angle
( 80.00 ) P 2,800.00
6. CEILING WORKS 85.76sq.mts ( 120.00 ) P 10,291.20
( 2,800.00 ) P 22,400.00
E. TILES
1. 980 pcs. 300mm x 300mm floor tiles
( 25.00/pc ) P 24,500.00
2. 2,150 pcs. 300m x 300mm wall tiles
( 21.00/pc ) P 45,150.00
3. Tile Adhesive ( ABC TILE ADHESIVE )
40 Bags ( 250.00 ) P 10,000.00
4. Tile Grout
25 Bags ( 60.00 ) P 1,500.00
5. TILING WORKS
TOTAL P 494,404.10
.