MATERIALS UNIT QUANTITY COST/UNIT TOTAL COST

ITEM I. (OWNER SUPPLIED)


I.A. FOOTING
a.1 CEMENT bgs 116 225 26,100.00
a.2 SAND cu. m. 7 300 2,100.00
a.3 GRAVEL cu. m. 26 300 7,800.00
a.4 16mm dia. X 6m RSB Le 88 225 19,800.00
a.5 #16 TIEWIRE kgs. 12 70 840.00
I.B. COLUMNS
b.1 CEMENT bgs 61 225 13,725.00
b.2 SAND cu. m. 3.375 300 1,012.50
b.3 GRAVEL cu. m. 6.75 300 2,025.00
b.4 20mm dia. X 6m RSB Le 87 320 27,840.00
b.5 10mm dia. X 6m RSB Le 84 130 10,920.00
b.6 12mm dia. X 6m RSB Le 32 180 5,760.00
b.7 #16 TIEWIRE kgs. 46 70 3,220.00
I.C. BEAMS/LINTEL BEAM
c.1 Cement bgs. 108 225 24,300.00
c.2 Sand cu.m. 6 300 1,800.00
c.3 Gravel cu.m. 12 300 3,600.00
c.4 25mm dia. X 6m Le 35 580 20,300.00
c.5 20mm dia. X 6m Le 105 320 33,600.00
c.6 12mm dia. X 6m RSB Le 209 180 37,620.00
c.7 #16 G.I. Tiewire kgs. 82 70 5,740.00
I.D. WALL FOOTING
d.1 CEMENT bgs 41 225 9,225.00
d.2 SAND cu. m. 2.3 300 690.00
d.3 GRAVEL cu. m. 4.81 300 1,443.00
d.4 16mm dia. X 6m RSB Le 60 225 13,500.00
d.5 12mm dia. X 6m RSB Le 64 180 11,520.00
d.6 #16 TIEWIRE kgs. 20.55 70 1,438.50
I.E. CHB WALL
e.1 6" CHB pcs. 3162 15 47,430.00
e.2 CEMENT bgs. 652 225 146,700.00
e.3 SAND cu.m. 48 300 14,400.00
e.4 12mm dia. X 6m RSB Le 215 180 38,700.00
e.5 #16 TIEWIRE kgs. 13.5 70 945.00
e.6 Skimcoat bgs. 16 430 6,880.00
e.7 Latex-Flat (white) gals. 11 490 5,390.00
e.8 #100 Sand Paper pcs. 20 9 180.00
e.9 #220 Sand Paper pcs. 30 10 300.00
e.10 Latex Semi-gloss gals. 11 605 6,655.00
e.11 #9 Roller brush pcs. 10 77 770.00
e.12 #4 Baby Roller brush pcs. 15 45 675.00
e.13 #3 Paint brush pcs. 12 18 216.00
e.14 #9 Paint Tray pcs. 15 48
e.15 Acrytex Primer gals. 10 2981
e.16 Acrytex Reducer gals. 25 385
e.17 Masonry Neutralizer gals. 13 130
e.18 Acrytex Cast gals. 10 439
e.19 Acrytex Flat gals. 10 3025
I.F. ROOF FRAMING
f.1 5mm x 2" Angle bar Le 27 1130
f.2 5mm x 1 1/2" Angle bar Le 10 904
f.3 2mm thk. X 2" x 4" C-Purlins Le 48 720
f.4 10mm dia. X 6m RSB Le 50 130
f.5 Epoxy Primer gals. 2 1240
f.6 Epoxy Reducer gals. 2 560
I.G. TINSMITHRY
g.1 0.6mm thk. Hi-rib type corrugated longspan roof ln-m 102 200
g.2 4' x 50m Double skin insulation foam roll 2 2300
g.3 #16 G.I. Tiewire kgs. 10 70
g.4 Rugby bot. 20 34
I.H. CEILING WORKS
h.1 19mm x 50mm x 0.4m x 5m MetalFurring Le 100 123
h.2 12mm x 38mm x 1mm x 5m Carrying Channel Le 82 145
h.3 W-clip pcs. 500 6
h.4 3/16" Blind rivets box 5 635
h.5 4.5mm thk. X 1.22m x 2.44m Hardieflex sht. 35 498
h.6 Mesh Tape pcs. 20 92
h.7 1 1/2" Ficem Screw pcs. 1000 1
h.8 Latex Flat (white) gals. 5 490
h.9 Latex Semi-gloss gals. 5 605
h.10 #9 Roller brush pcs. 10 77
h.11 #4 Baby Roller brush pcs. 8 45
h.12 #3 Paint brush pcs. 8 18
h.13 #9 paint Tray pcs. 5 48
h.14 2" Masking Tape pcs. 6 30
h.15 1" Masking Tape pcs. 6 15
I.I. CONCRETE FLOORING
i.1 CEMENT bgs. 262 225
i.2 SAND cu.m. 14.5 300
i.3 GRAVEL cu.m. 29 300
i.4 12mm dia. X 6m RSB Le 630 110
i.5 #16 TIEWIRE kgs. 105 70
i.6 Polyethylene sheet roll 5 2100
I.J. FORMWORKS
j.1 2" X 2" COCO pcs. 120 68
j.2 2" x 3" COCO pcs. 120 102
j.3 4" C.W.N. kgs. 50 80
j.4 3" C.W.N. kgs. 50 80
j.5 1 1/2 C.W.N. kgs. 25 80
j.6 2" C.W.N. kgs. 30 80
j.7 3/8" thk. Plywood sht. 15 600
TOTAL MATERIAL COST (TMC)
MISCELLANEOUS ITEMS (Doors, Metal Louver windows, Concrete Epoxy, Chemical Anchors)
ELECTRICAL (LUMPSUM)
EXCAVATION AND BACKFILL (LUMPSUM)
TOTAL PROJECT COST