Register Ref: RA09 Page: 2 of 4

TASK SPECIFIC HEALTH & SAFETY RISK ASSESSMENTS FOR METHOD STATEMENTS
Revision No: 00 Date:

Operation / Activity: Working At Height Last Review by: Date:

Personnel / Property at Risk Erectors, Welders, Platers, Labourers Prep by: Date:

Site to be applied App’d by: Date:

Handrails and toe boards provided on shake-out


platforms.
All operatives to read and understand Method Statement.
Safety awareness of operatives maintained through
weekly TBT’s.

Suspension Trauma as a 2 3 6 If suspended from a harness the rescue to take no longer 0 3 0


than 15 – 20 minutes.
results of being suspended in
a harness A pre assembled kit, such as a Gotcha to be available on
site.

Severity (S): 1-minor 1st aid, 2-Minor hospital referral, 3-RIDDOR (over 3 day), 4-Major injury, 5-fatality
Likelihood (L): 0 - Very Remote, 1 - Remote, 2 - Occasional, 3- Probable, 4 – Frequent
Hazard Rating S x L (0-3 = Low, work can 4-7 = Medium, Work needs additional controls, 8 or more = High, Work shall not commence)
commence,
NG / 0430 /RA