Project Title: Parcel 3.

09 WADI CB Ref: MS/002


Client Ref:
Erection Method Statement Page: 3 of 18

REV: 00

Date: 30th May 2012

1.0 PURPOSE

The purpose of this method statement is to describe in detail the safe system of work to be employed in the
erection of the Parcel 3.09 WADI Build in the King Abdullah Financial District located in Riyadh, Saudi Arabia.

NB: Whilst every attempt has been made to ensure this document is as comprehensive as possible at the time
of writing, it should be noted that the methods and procedures employed will be under constant review and
may be revised where necessary to maintain efficient and safe systems of work at all times.

2.0 SCOPE

Cleveland Bridge scope of work includes the following:


ƒ Delivery of plant and materials.
ƒ Installation of temporary works (where required).
ƒ Offloading the steelwork
ƒ Erection of all structural steelwork
ƒ Assembly of the trusses

3.0 REFERENCES

All works are to be carried out in accordance with the following documentation:
ƒ Cleveland Bridge Company Management System
ƒ Cleveland Bridge drawings
ƒ Cleveland Bridge method statement, sketches and appendices
ƒ The client’s specification as detailed in section 3.1

3.1 SPECIFICATION

This Method Statement has been produced with reference to the following documents:

Specification:

• National Structural Steelwork Specification NSSS – 5th Edition: CE Marking Version

Erection Method Statement


C0999 – Parcel 3.09 WADI
Cleveland Bridge