FLOW CHART FOR WORK COMMENCEMENT

Mode of Commencement Driven by date One LTP


of Work specified in yes for entire yes
LTP ? LOT? Work will commence
on10 sites at the same day

no

no

Separate LTP for each Plant. Work


Commencement will be effective from the
Commencement of work effective from site date of issuance of LTP for each site.
handover to contractor:
Work Commencement will be effective from the
date of site handover to contractor.
FLOW CHART FOR WORK COMMENCEMENT

Work completed in 180 days yes No Liquidated Damages

no

Liquidated Damages

Liquidated
Damages on Liquidated Damages charged at the rate of
cummulative yes 1% of the total lot price per week of delay
price of a lot? upto a maximum of 10% of the total
contract price

no

Liquidated Damages charged for each


remaining site individually at the rate of 1%
of the contract (Individual site) price per
week of delay upto a maximum of 10% of
contract price for individual site.