You are on page 1of 2

FOREMAN

PROJECT DESCRIPTION:
-2 LAMPS CONTROLLED IN THREE DIFFERENT LOCATIONS USING TWO 3-WAY
SWITCH & ONE 4-WAY SWITCH
-1 LAMP CONTROLLED BY SPST SWITCH

SCHEMATIC DIAGRAM:

LEGENDS:
KS- PLANCA , UB- UTILITY BOX , JB- JUNCTION BOX, ST- SOCKET

PROJECT: ₱ 6,000.00 PROJECT = ₱ 6,000.00


Need to finish in 2 days: LABOR & MATERIALS = ₱ 3,965.00
₱ 2,035.00
Electrician Salary = ₱ 400.00 x 2 = ₱ 800.00
Helper Salary = ₱ 250.00 x 2 = ₱ 500.00
Materials = ₱ 2,665.00
TOTAL: ₱ 3,965.00

BILL OF MATERIALS
QTY DESCRIPTION UNIT COST TOTAL COST
1 PLANCA(KNIFE SWITCH) ₱ 950.00 ₱ 950.00
3 INCANDESCENT LAMP ₱ 60.00 ₱ 180.00
2 3-WAY SWITCH ₱ 100.00 ₱ 200.00
1 4-WAY SWITCH ₱ 110.00 ₱ 110.00
1 SPST SWITCH ₱ 50.00 ₱ 50.00
20m AWG #14 THHN WIRE ₱ 30.00 ₱ 600.00
4 JUNCTION BOX ₱ 60.00 ₱ 240.00
3 SOCKET ₱ 45.00 ₱ 135.00
4 UTILITY BOX ₱ 50.00 ₱ 200.00

TOTAL: ₱ 2,665.00
FOREMAN:
ELECTRICIAN:
HELPER:
HELPER
My specific assignment for this installation project is a helper. As a helper, my primary
job function is to help electrician in installing and maintaining electrical and power system and
perform other duties as may direct.
Before the activity, I properly wear my Personal Protective Equipment (PPE) for our
safety such as:
Hard-hat to protect my head;
Gloves to protect my hands;
Safety shoes to protect my feet;
Goggles to protect my eyes;
Mask to protect my nose and mouth from dust particles and
Apron and Tools Holster.

All construction materials and equipment needed during installation were already
prepared as per guidance from our foreman and electrician.

These are the construction materials and equipment used during the installation:
QTY UNIT DESCRIPTION
3 pcs Incandescent lamp 50w/220v
2 pcs 3-way switch
1 pcs 4-way switch
1 pcs SPST switch
20 mtrs AWG #14 THHN wire
4 pcs Junction box
3 pcs Socket
4 pcs Utility box
2 mtrs PVC Pipe ½”
20 pcs PVC Clip ½”
20 pcs PVC Connector ½”
2 set Electrical Tape
2 pcs Fuse 15A
1 pcs Knife Switch Assembly
TOOLS AND EQUIPMENTS:
Multi Tester Philips Screw Driver Screw Driver
Side Cutter Plier Hammer Hack Saw
Plier/Long Nose Knife Electrical Drill

After the installation, I cleaned the area and removed/disposed all unnecessary things
or items. I also cleaned the tools and equipment and arranged it and put it all side the tool box
and make it sure that all equipment and materials are accounted for.
FOREMAN:
ELECTRICIAN:
HELPER: