Introduction
“Bangalore has the potential to become the No. 1 City in India
and an internationally prominent metropolis. To make this possible
, we need to adopt a new urban planning model, upgrade our
infrastructure , improve the social facilities and create a better
environment for good quality of life. In other words, we must re-
invent Bangalore.”

Challenge is to ensure that growth flows into a spatial plan, else it


results in chaos and encroachment and inability for municipal
services to plan their investments in capacity expansion and new
coverage.
Planning has been identified as THE major issue facing our city –
as far back as 1997 as the two quotes from a report by the
Committee on Urban Management of Bangalore city, 1997.

“Planning is by far the most important tool for coping with the
increasing demands made by the growth of city on Housing,
infrastructure and amenities. In the absence of proper planning,
the city experiences infrastructural inadequacies and degeneration
and the authorities are driven to finding ‘ad-hoc’ solutions and
crisis management from time to time in respect of many of cities
requirements, to meet which advance action has not been taken”

“Planning is important for raising public confidence and morale.


Furthermore, planning helps to smoothen the relationship between
the elected representatives and the officials in charge of city.
Residents of the city routinely – and quite rightly 0 blame the
‘absence of planning’ or ‘poor planning’ for everything from
congestion on roads to poor sanitation and water supply.”
DEMOGRAPHIC PROFILE

POPULATION PLAN ESTIMATES - IN LAKHS

AREA 1996 2011 2021

BMA 51.00 76 90.00

BMR 71.62 109.36 130.00

Present Estimates: 2021

™BMA: 103 lakh as per Revised Master Plan


™6 LPA’s: 47 lakhs
™APZ-1: 10 lakhs
™Total BMR: 160.00 lakhs
VARIOUS PLANNING AREAS WITHIN BMR

Areas within BMR Area in Sq.Kms.


BDA 1219.50
BMICAPA 426.24
RCUDA 63.06
Anekal LPA 402.30
Nelamangala LPA 735.00
Magadi LPA 501.52
Hoskote LPA 535.00
Kanakapura LPA 412.78
BIAAPA 792.00
APZ-I (excluding RCUDA & BMICAPA) 462.50
All IZ’s in BMR 2455.00
TOTAL BMR 8005.00

IMPORTANT INFORMATION OF ALL IMP’S


(Area in Hectares)
Name of the LPA LPA Area in Conurbation area as
Sq.Kms per provisional

ANEKAL 402.3 21,547.00

NELAMANGALA 735.00 7,046.00


HOSKOTE 535.00 14,713.00

MAGADI 501.52 10,307.00


KANAKAPURA 412.78 10,182.00
BIAPPA 792.00 12,636.00
Working Groups

‰ Kickoff meeting held on 10th September, 2008

¾ Immediate / Priority Objectives to be completed in six months;


¾ Medium / Long Term Objectives to be completed 12 months or
above;

Plans have to be submitted by all the following participating agencies.


Agency Name Action Report Progress
Status
BBMP Commissioner Received No action

BDA Commissioner Received No action

BMTC MD Received No action

KSRTC MD Not Received Submission by 18-


10-08
BTP DCP Received No action

BWSSB Chairperson Received No action

Housing & Slum Principal Not Received No deadline given


Clearing board Secretary
Namma Metro MD Not Received No deadline given

High Speed Rail Link MD Not Received 2-3 weeks

BESCOM MD Received No action


Road, Traffic Management & Transportation

Planning / Governance / Strategic

Immediate / Priority Objectives - by December 2008

Objectives Progress

Strengthen BMLTA and make it responsible for The draft Bill is under finalization
Transportation Planning for BMR. DULT to prepare
a draft Bill, defining structure, scope, function and
mandate of the BMLTA – due within 15 days

Commission CTTS Agreed


Examine all Laws, Acts and prepare comprehensive Dr. Ravindra would prepare a
list of Legislative amendments table for the same
Complete review of all Mega/Medium The draft Bill is under finalization
Transportation projects and finalize blue print with
BMLTA
Financing / Investment plan of Bangalore
Metropolitan regional projects.

Land Acquisition/substitution from Railway/ Defence The Hon’ble Chief Minister has
Ministry agreed to take up all such issues
directly with the respective Ministry
and informed all departments to
submit details to get the clearances.

Immediate / Priority Objectives - by January 2008

Objectives Progress
Review 1st Draft of Structure Plan

Review 1st Draft of CTTS


Road, Traffic Management & Transportation

Infrastructure Projects – Repairs / Capacity Expansion /


Addition
Immediate / Priority Objectives - by December 2008

Objectives Progress
Bruhath Bangalore Mahanagara Palike (BBMP)
All road humps on main roads are to be removed by 30th
September 2008

Road Widening
‰ Race Course Road
‰ Bellary Road
‰ Sarjapura Main Road
‰ Nagarabhavi Main Road
‰ Madiwala Village Panchayath Road
‰ Byrasandra Road from Hosur Road to Jayanagar T
Block
‰ Bull Temple Road
‰ Sevashram Road
‰ Shampura Main Road
‰ Tannery Road
ITBT Roads work
‰ Indiranagar 100 Ft Road
‰ Koramangala 80 Ft Road
‰ Kaggadassapura Main Road
‰ ST bed
35 Bus bays

Model Ward to be developed. Identified of this model The model ward to be undertaken in 4
ward to be done wards and the theme to be jointly
developed by all the civic agencies with
Principal Secretary to coordinate the
effort. Details to be submitted within the
next 15 days.

Bangalore Development Authority (BDA)


‰ All road humps on main roads are to be removed by
30th September 2008

Construction of Grade separator


‰ Agara and Ibulr junction (two flyover)
‰ Magadi Road and Chord Road Ready for inauguration by Nov/Dec
08
Road, Traffic Management & Transportation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Bangalore Development Authority (BDA)
Construction of ORR connecting

‰ Mysore Road to Magadi Road

Grade separator – Foundation stone / Ground braking ceremony


‰ HSR layout junction
‰ Bellundar junction
‰ Devarabeesanahalli junction
‰ Kadubeesanahalli
‰ Mahadevapura junction
‰ Kalyannagar junction
‰ Hennur junction
‰ Veeranapalya junction

Construction of 8 lane peripheral ring road - Foundation stone/ Ground braking


ceremony
‰ BOT pattern

Bangalore Traffic Police (BTP)

‰ 80 Traffic Surveillance Camera


‰ Factual Actuated Signals
‰ Signboards - 1000

Bangalore Metropolitan Transport Corporation (BMTC)

‰ New buses – 100


Namma Metro

‰ BMRCL should present alternate BMRCL to give the alternative plan in


Traffic Management Plan in particular close consultation with BMTC, KSSIDC &
for the underground section (Majestic IG, Traffic.
etc) to the Task Force for each stage
starting October 2008 to November
2008
Road, Traffic Management & Transportation

Infrastructure Projects – Repairs / Capacity Expansion /


Addition
Immediate / Priority Objectives - by March 2009

Objectives Progress
Bruhath Bangalore Mahanagara Palike (BBMP)

Road Widening
‰ Palace Road
‰ Hosur Road
230 High Raised Pedestrian crossing

Precast segmental box Underpass

‰ At Maharani’s college

Construction
‰ Flyover at Yeshwanthpura circle
‰ ROB on Wheelers Road near ITC
‰ Pedestrian Subway at City Market
‰ Pedestrian Subway at Vijayanagar Bus
stand
‰ Underpass at 21st Main near Forum Mall
‰ Underpass near Garuda Mall
‰ Underpass at 46th Cross near Ragi Gudda
Temple
Bangalore Development Authority (BDA)
‰ BDA to meet the project cost of ORR from
out of its own resources. Ground breaking
ceremony – Jan 2009

Namma Metro
‰ BMRCL to circulate a note on the
possibilities of commercial exploitation in the
stations and along the corridor to the Task
force.
‰ After Mid term review – BMRCL to furnish
the final financing structure to Task Force.
Road, Traffic Management & Transportation

Immediate / Priority Objectives - by March 2009

Objectives Progress
High Speed Rail Link
‰ Viability gap proposal presentation to GOK
for final decision
Bangalore Metropolitan Transport Corporation (BMTC)
The work is entrusted to the land
‰ Traffic Transit and Transportation
Army. Committee has insisted
Management would be completed by 1st BMTC to complete the work on
January, 2009. time.

Bangalore Traffic Police (BTP)


‰ Need to empower officers to collect fines – Principal Secretary has agreed
proposal to authorize ASI sent to Govt for to clear this proposal
approval
‰ 380 Vehicle Actuated Signals
‰ 5 Enforcement Camera 20 VMS
‰ 20000 Signboards
‰ TMC building construction
‰ TMC Technology
‰ 50 junction improvement
‰ 5 interceptors for enforcement
Road, Traffic Management & Transportation

Infrastructure Projects – Repairs / Capacity Expansion /


Addition
Medium Term Objectives - April 2009 - 2012

Objectives Progress
Bruhath Bangalore Mahanagara Palike (BBMP)
Sky Walks with escalator
‰ Hosur Lasker Road,
‰ Airport Road
‰ Kamaraja Road
‰ Residency Road (DBOT basis)
‰ Raja Ram Mohan Roy Road
‰ Richmond Road
‰ Race Course Road
‰ Commissionerate Road (DBOT basis)

Road Widening

‰ Hosur Lasker Road


‰ Sheshadri Road
‰ Kasthuraba Road
Construction of Underpass

‰ Hennur Main Road


‰ Tagore circle & KR Road
‰ Nagavara Junction
Construction of bridge over storm water drain
‰ Galli Anjaneya Road

Signal free movement


‰ along Hosur Road from Silk Board to
Vellara junction
Multilevel Car Parking under Swiss Challenge method

‰ Four truck terminals


‰ Doddaballapura
‰ Nelamangala
‰ Hoskote & Devanahalli
Road, Traffic Management & Transportation

Medium Term Objectives - April 2009 - 2012

Objectives Progress
Bangalore Development Authority (BDA)
Make ORR 100% Signal free - February 2010
‰ ORR to be completely signal free
and a plan for implementation
over the next 18 months.
Construction of ORR
‰ Connecting Mysore Road to
Magadi Road including underpass
at Bangalore Mysore Railway line

Grade separator – Completion


‰ HSR layout junction
‰ Bellundar junction
‰ Devarabeesanahalli junction
‰ Kadubeesanahalli
‰ Mahadevapura junction
‰ Kalyannagar junction
‰ Hennur junction
‰ Veeranapalya junction

Construction of Grade separator and ORR junction


‰ Magadi Road
Water & Sanitation
Road, Traffic Management & Transportation

Planning / Governance / Strategic

Immediate / Priority Objectives - by December 2008

Objectives Progress
‰ Financing plan for BWSSB Meeting has been scheduled on
16th October, 2008. The out come
will be discussed in the next
meeting however the draft plan
will be prepared for the
subsequent meeting.
‰ Jurisdiction of BWSSB to be extended
to Metropolitan Region.

The Committee is schedule to meet


‰ Dual Water Pipeline Policy to be
shortly and finalize the proposal in
finalized consultation with other members of
the committee.
‰ Rain Water Harvesting Legislation Draft cabinet note has been prepared
and sent to Principal Secretary UD.
Principal Secretary UD informed the
Chair that the note has been sent to
Law and Parliamentary to vet the
Draft law amendment.
‰ Ground Water Regulation Legislation

‰ Lake Policy to be finalized After detailed deliberation on the various


issues that emerged in forming a
workable policy for Lakes, the committee
felt that the Heads of BBMP, BDA, BMA,
BMARD, Irrigation Department, Forest
Department and Revenue Department
must meet and discuss and prepare a
comprehensive policy framework to
protect and preserve the lakes. Principal
Secretary UD to chair the meeting. The
Minister for BWSSB mentioned that
BWSSB would be interested in utilizing
the water from the lakes and not involved
in the policy decision of the committee
Water & Sanitation
Infrastructure Projects – Repairs / Capacity Expansion /
Addition
Immediate / Priority Objectives - by December 2008

Objectives Progress
Providing Cauvery water to the former CMC wards
‰ Ward No. 23 & 24 of the erstwhile Yelahanka CMC (3500 house holds).

‰ Ward No. 7, 11 & 13 of the erstwhile Dasarahalli CMC (4000 house


holds)
‰ Ward No. 4 & 15 (P) of the erstwhile Byatarayanapura CMC (2000
house holds)
‰ Ward No. 25, 26 & 32 of the erstwhile Dasarahalli CMC (4000 house
holds)
‰ Ward No. 4, 5, 6 & 16 of the erstwhile Rajarajeshwarinagara CMC
(6000 house holds)
‰ Ward No. 1 to 7 of the erstwhile Kengeri CMC (1200 house holds)

‰ Ward No.11,19 & 26 to 31 of the erstwhile Bommanahalli CMC (7000


house holds)
‰ Ward No. 26, 28 to 31 of the erstwhile Rajarajeshwarinagara CMC
(4300 house holds)
Procurement of Combination Machines and setting up of R.W.H. Theme Park
‰ Procurement of 15 Nos. of 6,000 litres capacity Combination Machines (to
carry 3,000 litres of water or 3,000 litres of sewage) to be mounted on
suitable chassis to be supplied by the Board
‰ Rain Water Harvesting Theme Park at Jayanagar
‰ Rain Water Harvesting to Cauvery Bhavan, ‘D’ Block
Setting up of R. W. H. Theme Park

‰ Rain Water Harvesting Theme Park at Jayanagar


‰ Amendment to Board Resolution to make Rain Water Harvesting
Compulsory
‰ Project to introduce 24 x 7 Water Supply
Providing water supply network, feeder mains & sewerage net work in the former C.M.C. Areas
‰ Providing Water Supply distribution network in Bommanahalli CMC
under GBWASP2.50 Km of 250/200mm dia pipeline in ward no. 3,5 &
65.0 Km of 100mm dia pipeline in Banneraghatta road
‰ Providing Water Supply distribution network in Dasarahalli CMC under
GBWASP · 2.75 Km of 100 mm dia in National Highway portion ·1.10Km
of 200/300/450mm dia pipeline National Highway

‰ Providing Water Supply distribution network in KR Puram CMC under


GBWASP · 0.50Km of 150mm dia inside Railway Local shed area

‰ Providing Water Supply distribution network in Mahadevapura CMC


Under GBWASP · 2.40Km of 150mm dia along Railway track near Hoodi
level Crossing to Sonnamangala
Water & Sanitation
Immediate / Priority Objectives - by December 2008

Objectives Progress
Providing water supply network, feeder mains & sewerage net work in the
former C.M.C. Areas
‰ Providing Water Supply distribution network in
Bommanahalli CMC under GBWASP2.50 Km of
250/200mm dia pipeline in ward no. 3,5 & 65.0 Km of
100mm dia pipeline in Banneraghatta road
‰ Providing Water Supply distribution network in
Dasarahalli CMC under GBWASP · 2.75 Km of 100 mm
dia in National Highway portion 1.10Km of
200/300/450mm dia pipeline National Highway
·
‰ Providing Water Supply distribution network in KR
Puram CMC under GBWASP 0.50Km of 150mm dia
inside Railway Local shed area
‰ Providing Water Supply distribution network in
Mahadevapura CMC Under GBWASP · 2.40Km of
150mm dia along Railway track near Hoodi level
Crossing to Sonnamangala.
Providing Feeder Mains under GBWASP
‰ Hegganahalli GLR to Kammagondanahalli - 8.50 Km
ranging from 1100 to 600mm dia pipeline – crossing of
NH road by trench less method is under progress
[Hegganahalli, Srigandanagar, Rajagopalanagara,
Ganapathinagar Dugalamma L/O Parvathinagara,
Laxmidevinagar, Jallahalli Road.]
‰ Kothanur dinne GLR to Hulimavu – 1.40Km of
1200mm dia to 1000m pipeline, [Hulimavu,
Bannerghatta Road, MICO L/O]
‰ Nayanappanahalli to Viratanagar – 2.50Km of 1000 to
600mm pipeline is under progress. 400mt rock cutting
is under progress. [IIMB back side, Belekallahalli]
‰ Nayanappanahalli to Begur tank - 2.20Km of 600mm
dia pipeline, 200 mts. rock portion is under progress
[Nayanappanahalli,Kodichikkanahalli,
Devrachikkanahalli, Hogasandra]
‰ Providing Under ground drainage facilities to erstwhile
R.R.Nagar CMC area (Zone 5B)
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
‰ GKVK GLR to Nagavara – 12.50Km of pipeline dia ranging
from 1200mm to 800mm. 40m length Railway crossing and
180m crossing of NH4 crossing by trench less method under
progress.[Vidyaranyapura, Sahakaranagar, CanaraBank
L/O, Byatarayanapura, Kodigehalli, Dasarakhalli Nagavara]

‰ Providing Under ground drainage facilities to erstwhile


Byatarayanpura CMC area -(Zone 2A)
‰ Providing Sewerage System to erstwhile Byatarayanpura
CMC are Zone 2C)
‰ Providing Under ground drainage facilities to erstwhile
Mahadevpura CMC area (Zone 3B)
‰ Providing Under ground drainage facilities to erstwhile
K.R.Puram CMC area (Zone 3E)
‰ Providing Under ground drainage facilities to erstwhile
Bommanahalli CMC area (Zone 4B)
‰ Providing Under ground drainage facilities to erstwhile
Bommanahalli CMC area (Zone 4C)
‰ Providing Under ground drainage facilities to erstwhile
Bommanahalli CMC area (Zone 4D)
‰ Providing Under ground drainage facilities to erstwhile
Dasarahalli CMC area (Zone 7A)
‰ Providing Under ground drainage facilities to erstwhile
Dasarahalli CMC area ( Zone 7C)
‰ Providing Under ground drainage facilities to erstwhile
R.R.Nagar CMC area (Zone 5B)
Providing water supply network, feeder mains & sewerage net work in the former C.M.C. Areas

‰ Providing Water Supply distribution network in


Bommanahalli CMC under GBWASP2.50 Km of
250/200mm dia pipeline in ward no. 3,5 & 65.0 Km of
100mm dia pipeline in Banneraghatta road
‰ Providing Water Supply distribution network in Dasarahalli
CMC under GBWASP · 2.75 Km of 100 mm dia in National
Highway portion ·1.10Km of 200/300/450mm dia pipeline
National Highway
‰ Providing Water Supply distribution network in KR Puram
CMC under GBWASP · 0.50Km of 150mm dia inside
Railway Local shed area
‰ Providing Water Supply distribution network in
Mahadevapura CMC Under GBWASP · 2.40Km of 150mm
dia along Railway track near Hoodi level Crossing to
Sonnamangala.
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Providing Feeder Mains under GBWASP
‰ Hegganahalli GLR to Kammagondanahalli - 8.50
Km ranging from 1100 to 600mm dia pipeline –
crossing of NH road by trench less method is under
progress [Hegganahalli, Srigandanagar,
Rajagopalanagara, Ganapathinagar Dugalamma L/O
Parvathinagara, Laxmidevinagar, Jallahalli Road.]
‰ Kothanur dinne GLR to Hulimavu – 1.40Km of
1200mm dia to 1000m pipeline, [Hulimavu,
Bannerghatta Road, MICO L/O]
‰ Nayanappanahalli to Viratanagar – 2.50Km of 1000
to 600mm pipeline is under progress. 400mt rock
cutting is under progress. [IIMB back side,
Belekallahalli]
‰ Nayanappanahalli to Begur tank - 2.20Km of
600mm dia pipeline, 200 mts. rock portion is under
progress [Nayanappanahalli,Kodichikkanahalli,
Devrachikkanahalli, Hogasandra]
‰ GKVK GLR to Nagavara – 12.50Km of pipeline dia
ranging from 1200mm to 800mm. 40m length
Railway crossing and 180m crossing of NH4
crossing by trench less method under
progress.[Vidyaranyapura, Sahakaranagar,
CanaraBank L/O, Byatarayanapura, Kodigehalli,
Dasarakhalli Nagavara]
‰ Providing Under ground drainage facilities to
erstwhile Byatarayanpura CMC area -(Zone 2A)
‰ Providing Sewerage System to erstwhile
Byatarayanpura CMC are Zone 2C)
‰ Providing Under ground drainage facilities to
erstwhile Mahadevpura CMC area (Zone 3B)
‰ Providing Under ground drainage facilities to
erstwhile K.R.Puram CMC area (Zone 3E)
‰ Providing Under ground drainage facilities to
erstwhile Bommanahalli CMC area (Zone 4B)
‰ Providing Under ground drainage facilities to
erstwhile Bommanahalli CMC area (Zone 4C)
‰ Providing Under ground drainage facilities to
erstwhile Bommanahalli CMC area (Zone 4D)
‰ Providing Under ground drainage facilities to
erstwhile Dasarahalli CMC area (Zone 7A)
‰ Providing Under ground drainage facilities to
erstwhile Dasarahalli CMC area ( Zone 7C)
‰ Providing Under ground drainage facilities to
erstwhile R.R.Nagar CMC area (Zone 5B)
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Replacement of major leaking lines
‰ 600 mm dia CI pipeline by MS pipeline from
Kamakshipalya Tank bund to KHB Bus stop
along Magadi road
‰ 600 mm dia CI pipeline by MS pipeline at
Tumkur road at 4 places
‰ 27” dia CI /PSC pipeline by MS pipeline at
Rajkumar road Rajajinagar at 3 locations
‰ 400 mm dia CI pipeline by 450 mm dia MS
pipeline from Sirsi circle to 9 ML, GLR along
Binny Mill road
‰ 600 mm dia PSC pipeline by MS pipeline from
Hama Sagara Hotel to Havanur circle in
Basaveshwranagar
‰ 600 mm dia CI pipeline by MS pipeline from
th
Beggars colony upto 5 block GLR Nagarabhavi
‰ 600 mm dia pipeline by MS pipeline at Bellary
road to Side Palace Compound.
‰ 300 mm dia CI pipeline by MS pipeline at
Sanjayangar main road
th
‰ 300 mm dia CI pipeline by MS pipeline at 5
main Ganganahalli
‰ 200 mm dia CI pipeline at Bellary road near
HMT Bhavan
‰ 300 mm dia CI pipeline at BEL road
‰ 600 mm dia PSC/ CI pipeline by MS pipeline
from Millers road along Bore Bank road upto
Pottery town
‰ 675 mm dia PSC / CI pipeline by 700 mm dia
MS pipeline Manipal Centre upto Aero Engine
along Ulsoor main road & Old Madras road upto
GLR
‰ 600 mm dia pipeline by MS pipeline from
Benneganahally bridge upto ITPL along White
Field
‰ 300 mm dia CI pipeline by MS pipeline 100’ ring
th
road 17 main Koramangala from St Johns
college to 50’ road signal
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Replacement of major leaking lines
‰ 300 mm dia CI pipeline by MS pipeline 100’ ring
th
road 17 main Koramangala from St Johns college
to 50’ road signal
‰ 300 mm dia Sarjapura road from St John signal to
Kuduremukh colony
st
‰ 450 mm dia pipeline by MS pipeline from 1 main
th
Koramangala & Sarjapur road upto 17 main
Koramangala along service road
th
‰ 450 mm dia PSC pipeline by MS pipeline at 46
th th
cross from 5 block Jayanagar to 9 block
Jayanagar
‰ 450 mm dia PSC pipeline by MS pipeline at
Someswaranagar main road
‰ 300 mm dia CI pipeline by MS pipeline at Housr
road from NIMHANS to VIGNANA Hospital

‰ 450 mm dia PSC pipe line by MS pipeline at BTS


road, Opposite to PWD Quarters

‰ 450 mm dia PSC/CI pipeline by MS pipeline from


D’souza circle up to ISRO along Victoria Road &
Old Air port road
‰ 600 mm dia PSC pipeline by MS pipeline at 100’
nd
ring road BTM 2 stage
th
‰ 300 mm dia CI pipeline by DI pipeline at 46 cross
th
from Field office to 24 main under J.P Nagar
th
‰ 200 mm dia PVC pipeline by DI pipeline at 14
cross, JP Nagar II phase
‰ 300 mm dia pipeline @ Kastuabangar
Chamarajpet
‰ Replacing 675 mm dia PSC /CI pipeline with MS at
th
30 main, Banashankari II Stage
‰ 600 mm dia PSC/CI line by MS pipeline from
Balabrooie gate to Mount Carmel College along
Palace road
‰ 27’ PSC line by MS pipeline running along
Rajbhavan road & Cubbon road,
‰ 600mm dia water supply line by MS pipeline along
Millers road.
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Replacement of major leaking lines
‰ 600 dia wate600 mm dia water supply feeder line
in Bellary Main road from Pafrom Palace road to
Giriyas Centre
‰ 600 mm dia MS line in place of leaking 600 mm
nd
dia PSC line (2 Stage line) from Southend
Circle up to Dwarakanath Bhavan KR Road
‰ Replacement of 450 mm dia CI line by MS line at
the junction of Victoria Road & Cambell Road in
front of Life Style upto Toyota Showroom
‰ Shifting of water and sanitary lines due to road
widening, construction of under passes, metro
etc
‰ Shifting of 300 mm dia NP3 Class S & S RCC
pipeline at Bellary road at CBI road junction to
th
Sanjaynagar road cross & 5 main road
th
Ganganagar to 5 main road
‰ Shifting of 100 & 150 mm dia CI line Ananda Rao
fly over to KR circle
‰ Shifting of 450 mm dia MS & 200, 150, 100 mm
dia water supply lines in lieu of existing water
supply lines at RC college junction along Race
course road
‰ Shifting of 100mm, 200 mm dia DI water supply
lines in lieu of existing water supply lines at RC
college junction along Race course road
‰ Shifting of 100mm, 150 mm, 200mm, 450 mm dia
DI water supply lines at Ananda Rao circle to
Basaveshwara circle
‰ Shifting of 600 mm dia MS water supply line in
lieu of existing water supply lines at RC college
upto Maharanis college circle
‰ Shifting of 600 mm dia MS water supply line in
lieu of existing water supply lines from Maharanis
college circle to Old central jail.
‰ Shifting of existing water supply line by 450 mm
dia MS water supply line at Palace road and
Sheshadri road junction in lieu of existing water
supply lines
Water & Sanitation

Immediate / Priority Objectives - by December 2008

Objectives Progress
Shifting of water and sanitary lines due to road widening, construction of under passes,
metro etc
‰ Shifting of existing water supply line by 450 mm
dia MS water supply line at Palace road in lieu of
existing water supply lines
‰ Shifting of existing water supply line by 250 mm
dia MS water supply line in lieu of existing water
supply lines at RC college to Maharanis college
circle
‰ Shifting of 100 mm, 150 mm & 200 mm dia water
supply pipelines at Sheshadri road
‰ Shifting of 200 mm & 100 mm dia water supply
lines to the foot path of 80 ft. Road on either
sides of footpath from IIPM to Kalavathi Kalyana
Mantapa junction
‰ Shifting of 225 mm dia SW pipe line to the
footpath of 80ft Road on either sides of footpath
from IIPM to Kalavathi Kalyana Mantapa

Major improvement works


‰ Providing water supply facilities to Begur Village
Ward No. 11 Bommanahalli
‰ Providing & laying and linking of 300 mm dia
Feeder Main line on CBI Road, in Ganga Nagar
area coming under R.T. Nagar S/stn.,
‰ Providing 300 mm dia & 225 mm dia SW line in
Austin Town
Rehabilitation of trunk sewers in K&C Valley
To convey the sewage to the K & C Valley STP and to avoid the flow into the SWD, which
leads to Bellandur tank the following works proposed
‰ Replacement of 900/1200mm dia by 1800mm dia
th
sewerline at 14 Main HSR for a length of 180
RMT
‰ Replacement of 900/1200mm dia by 1800mm dia
sewerline at Agaram for a length of 85 RMT
‰ Replacement of 900/1200 by 1800mm dia
sewerline across the HSR Ring Road by
Trenchless for a length of 50 RMT
‰ Replacement of 900/1200mm dia by 1800mm dia
sewerline for a length of 215 RMT at Cambridge
Layout, Indiranagar
‰ Work of realignment of 900mm dia RCC sewer
line at Gangadhara Chetty Road near Ulsoor Lake
for a length of 200 RMT
Water & Sanitation
Immediate / Priority Objectives - by December 2008

Objectives Progress
Rehabilitation of trunk sewers in K&C Valley
To convey the sewage to the K & C Valley STP and to avoid the flow into the SWD, which
leads to Bellandur tank the following works proposed
‰ Work of rehabilitation of 1800 / 2000 mm dia
outfall sewer line at Challaghatta Village for a
length of 50 RMT

‰ Providing and laying 450/600/800mm dia sewer


from Magrat Road to Infant Jesus Church along
Victoria Road for a length of 2000 RMT

Rehabilitation of trunk sewers in V Valley

‰ Work of RCC wet well at Kempambudhi Lake for


segregation of sewage in SWD to avoid
ingression into the Kempambudhi Lake

Integrated water Management (Reuse of Lake Water), Environment action


plan works & CWSS Stage – IV, phase - II
‰ Vrishabhavathi Valley -180 MLD/105
MLD/135 MLD

Lakes
‰ Bellandur - 60 MLD

‰ Nagavara 30 MLD

‰ Kalkere/ Raja Canal 20 MLD

‰ Kengeri - 30 MLD- Rs.100.00 Crores


K.R.Puram - 20 MLD
‰ K&C Valley - Varthur - 300 MLD- Rs.900.00
Crores Koralur - 50 MLD
‰ Jakkur, Begur, Puttenahalli (JP Nagar),
Madavara, Doddabommasandra,
Voderahalli, Hulimavu, Dorkere etc.
Water & Sanitation

Infrastructure Projects – Repairs / Capacity Expansion /


Addition
Immediate / Priority Objectives - by March 2009

Objectives Progress
Providing Cauvery water to the former CMC wards
‰ Commissioning of Cauvery water supply to ward
No. 1, 2 & 18 of the erstwhile K. R. Puram CMC
(2600 house holds)
Procurement of Combination Machines and setting up of R.W.H. Theme Park
‰ Procurement of 15 Nos. of 6,000 litres capacity
Combination Machines (to carry 3,000 litres of
water or 3,000 litres of sewage) to be mounted
on suitable chassis to be supplied by the Board
‰ Rain Water Harvesting Theme Park at
Jayanagar
‰ Rain Water Harvesting to Cauvery Bhavan, ‘D’
Block
Setting up of R. W. H. Theme Park
‰ Project to introduce 24 x 7 Water Supply
Replacement of major leaking lines
‰ 600 mm dia CI pipeline by MS pipeline from
Kamakshipalya Tank bund to KHB Bus stop
along Magadi road
‰ 600 mm dia CI pipeline by MS pipeline at
Tumkur road at 4 places
‰ 27” dia CI /PSC pipeline by MS pipeline at
Rajkumar road Rajajinagar at 3 locations
‰ 400 mm dia CI pipeline by 450 mm dia MS
pipeline from Sirsi circle to 9 ML, GLR along
Binny Mill road
‰ 600 mm dia PSC pipeline by MS pipeline from
Hama Sagara Hotel to Havanur circle in
Basaveshwranagar
‰ 600 mm dia CI pipeline by MS pipeline from
th
Beggars colony upto 5 block GLR
Nagarabhavi
‰ 600 mm dia pipeline by MS pipeline at Bellary
road to Side Palace Compound.
‰ 300 mm dia CI pipeline by MS pipeline at
Sanjayangar main road
th
‰ 300 mm dia CI pipeline by MS pipeline at 5
main Ganganahalli
‰ 200 mm dia CI pipeline at Bellary road near
HMT Bhavan
‰ 300 mm dia CI pipeline at BEL road
Water & Sanitation
Immediate / Priority Objectives - by March 2009

Objectives Progress
Replacement of major leaking lines
‰ 600 mm dia PSC/ CI pipeline by MS pipeline from Millers road
along Bore Bank road upto Pottery town
‰ 675 mm dia PSC / CI pipeline by 700 mm dia MS pipeline
Manipal Centre upto Aero Engine along Ulsoor main road & Old
Madras road upto GLR
‰ 600 mm dia pipeline by MS pipeline from Benneganahally
bridge upto ITPL along White Field
th
‰ 300 mm dia CI pipeline by MS pipeline 100’ ring road 17 main
Koramangala from St Johns college to 50’ road signal
‰ 300 mm dia Sarjapura road from St John signal to Kuduremukh
colony
st
‰ 450 mm dia pipeline by MS pipeline from 1 main Koramangala
th
& Sarjapur road upto 17 main Koramangala along service road
th th
‰ 450 mm dia PSC pipeline by MS pipeline at 46 cross from 5
th
block Jayanagar to 9 block Jayanagar
‰ 450 mm dia PSC pipeline by MS pipeline at Someswaranagar
main road
‰ 300 mm dia CI pipeline by MS pipeline at Housr road from
NIMHANS to VIGNANA Hospital
‰ 450 mm dia PSC pipe line by MS pipeline at BTS road,
Opposite to PWD Quarters
‰ 450 mm dia PSC/CI pipeline by MS pipeline from D’souza circle
up to ISRO along Victoria Road & Old Air port road
‰ 600 mm dia PSC pipeline by MS pipeline at 100’ ring road BTM
nd
2 stage.
th
‰ 300 mm dia CI pipeline by DI pipeline at 46 cross from Field
th
office to 24 main under J.P Nagar.
th
‰ 200 mm dia PVC pipeline by DI pipeline at 14 cross, JP Nagar
II phase.
‰ 300 mm dia pipeline @ Kastuabangar Chamarajpet.
th
‰ Replacing 675 mm dia PSC /CI pipeline with MS at 30 main,
Banashankari II Stage.
‰ 600 mm dia PSC/CI line by MS pipeline from Balabrooie gate to
Mount Carmel College along Palace road.
‰ 27’ PSC line by MS pipeline running along Rajbhavan road &
Cubbon road
‰ 600mm dia water supply line by MS pipeline along Millers road

‰ 600 dia wate600 mm dia water supply feeder line in Bellary


Main road from Pafrom Palace road to Giriyas Centre
‰ 600 mm dia MS line in place of leaking 600 mm dia PSC line
nd
(2 Stage line) from Southend Circle up to Dwarakanath
Bhavan KR Road
‰ Replacement of 450 mm dia CI line by MS line at the junction of
Victoria Road & Cambell Road in front of Life Style upto Toyota
Showroom
Water & Sanitation
Immediate / Priority Objectives - by March 2009

Objectives Progress
Shifting of water and sanitary lines due to road widening, construction of under
passes, metro etc
‰ Shifting of 600 mm dia MS water supply line in
lieu of existing water supply lines from
Maharanis college circle to Old central jail.
‰ Shifting of existing water supply line by 450 mm
dia MS water supply line at Palace road and
Sheshadri road junction in lieu of existing water
supply lines.
‰ Shifting of existing water supply line by 450
mm dia MS water supply line at Palace road in
lieu of existing water supply lines.
‰ Shifting of existing water supply line by 250
mm dia MS water supply line in lieu of existing
water supply lines at RC college to Maharanis
college circle
‰ Shifting of 200 mm & 100 mm dia water supply
lines to the foot path of 80 ft. Road on either
sides of footpath from IIPM to Kalavathi
Kalyana Mantapa junction.
Rehabilitation of trunk sewers in K&C Valley
To convey the sewage to the K & C Valley STP and to avoid the flow into the SWD, which
leads to Bellandur tank the following works proposed
‰ Work of 1200mm dia by 1800mm dia sewerline
at Central Silk Board for a length of 35 RMT
‰ Replacement of 900/1200mm dia by 1800mm
dia sewerline at Indiranagar for a length of 30
RMT.
‰ Replacement of 900/1200mm dia by 1600mm
dia sewerline for a length of 30 RMT at
Adharsha Theater
‰ Replacement of 300/450/600mm dia by 600mm
dia sewerline for a length of 700 RMT from
Jaraganahali lake to 100 feet Ring Road
‰ Replacement of 900/1200mm dia by 1800mm
dia sewerline for a length of 170 RMT from
Shastrinagar up to Cambridge Layout
Public taps
‰ Removal of public taps
Replacement of old water meters
‰ There are 5,40,000 house service connections
in the city. All these connections are provided
with water meters. As a policy matter it is
decided to replace the working water meters for
more than 7 years period at the Board’s cost to
i ll i
Water & Sanitation
Immediate / Priority Objectives - by March 2009

Objectives Progress
Works to be completed in the former C.M.C. Areas for providing water supply network, feeder
mains & sewerage net
‰ Hoodi GLR to ITPL main road – 2.0 Km of 800mm
dia pipeline. 1.0Km is balance, permission awaited
from PWD. [Hoodi road, ITPL road.]
‰ Hoodi Jn to Hope farm Jn – 1.9Km of 700 to
600mm dia 1.90Km pipeline is pending, BDA
permission is awaited. [Hope farm surroundings]
‰ ORR at Bangalore University to Kengeri – 2.51Km
of 1000 to 600mm dia pipeline, 1.65Km of
1000mm, 0.25Km of 900mm dia, 0.16Km of
800mm dia and 0.96m of 600mm dia are balance.
BDA permission is awaited.[Ullala,
Mariyappanapalya, Basaveswara L/O,
Doddabasthi, Kengeri
‰ Providing Under ground drainage facilities to the
area under erstwhile Kengeri TMC - Amount put to
tender Rs. 2553.00 Lakhs
‰ Providing Under ground drainage facilities to the
area under erstwhile Yelahanka CMC – Amount
put to tender Rs. 2030.00 Lakhs
Providing Cauvery water to former CMC wards
‰ Commissioning of Cauvery water supply to Ward No. 9
& 10 of the erstwhile Bommanahalli CMC (5000 house
holds);
‰ Commissioning of Cauvery water supply to Ward No.
9,10,14,15,16 of erstwhile of Dasarahalli CMC (4500
house holds);
‰ Commissioning of Cauvery water supply to Ward No. 22
& 24 of erstwhile of Dasarahalli CMC (2000 house
holds);

Sinking of Bore wells in former CMC areas


‰ Installation of 100 Sodium hypochlorite equipments
Replacement of major leaking lines

‰ 200 mm dia pipeline by DI pipeline at Shakambarinagar,


Kanakapura road.
th
‰ 450mm dia MS water supply line at 46 Cross,
Jayanagar.
Shifting of pipelines in view of Road widening
‰ 450 mm dia , 300 mm dia NP3 RCC pipeline in place of
existing 450 mm dia SW line (shifting ) and 225 mm dia
SW line from SWD to RON INN all along the proposed
Ring road.
th
‰ 400 mm dia RCC NP3 sewer line along 6 cross from
th th
6 main to 4 main in SR Nagara and linking it to the
existing 600 mm dia RCC sub main
Water & Sanitation

Immediate / Priority Objectives - by March 2009


Objectives Progress
Shifting of pipelines in view of Road widening
rd th
‰ 9” dia UGDF to BDA L/o 3 block, 6 block and Income Tax
layout Ravi GYM Nagarabhavi.
‰ 300 mm dia SW sanitary pipeline inplace of 150 mm dia & 175
mm dia pipeline from Thimmiah road along Narayana Pillai
street upto Nala road.
‰ 300 mm dia SW sanitary pipeline inplace of 150 mm dia & 175
mm dia pipeline from Thimmiah road along Mackhan road upto
Nala road.
th
‰ 9” dia SW line from 80 cross to 82 cross near CWSS pipeline
th th st
road, 58 cross to 66 cross, 1 stage Kumarswamy L/o.6” dia
nd th
SW line Kumaraswamy L/o 6” dia by 9” dia SW line at 2 & 4
nd
main Kumarswamy L/o, 2 stage.
‰ water supply lines which are passing through UGD manholes
adjacent to UGD manholes of water supply at Byrappa block,
th
14 cross, Shastrinagar
‰ 225 mm dia SW line inplace of 6” dia SW line and
st nd nd
reconstruction of damaged manholes at 1 & 2 cross and 2
rd rd st th
main 3 cross, 3 main 1 cross 6 main Ashwathakatte main
road Kasthribanagar and providing 260 mm dia HDPE storm
th th
water drain at 8 and 10 main Kasthribanagar Chamarajpet.
‰ 6” dia 9” dia SW line at Vinobha Badavane Nagendra block S/s.
‰ 300 mm dia NP3 class S & S RCC line in storm water drain
nd
below the flyover across Airport road, HAL 2 stage Domlur
S/s.
‰ Water supply & UGD facilities to Kakatheya nagar, Naidu
Layout.
Replacement of corroded pipelines
‰ 100 mm dia DI line inplace of corroded 80 mm dia corroded CI
th th
pipe line at Dr. Rajkumar road, 10 C, D, E, F & G road and 75
th th
A B C crosses and 14 A & B cross 6 block, Rajajinagar.
‰ 100 mm dia DI line in place of corroded 80 mm dia corroded CI
th th th
PVC pipeline at 10 , 12 & 13 main & cross roads
K.P.Agrahara.
th th th
‰ 100 mm dia DI pipeline at 3” dia corroded CI line in 6 , 7 , 8 ,
th th th
11 A , 15 crosses and part of 4 main SR nagar ward No.77
‰ 100 mm dia DI pipeline inplace of 3” dia corroded CI line in II III,
VI, VII main SR Nagar ward No. 77
Rehabilitation of trunk sewers in V - Valley
‰ Providing 450mm dia line at Food Corporation of India Layout,
Vijayanagar for a length of 450 RMT to convey the sewage to V.
Valley STP and to avoid flow in SWD.
‰ Providing 450mm dia line at Hampinagar, RPC Layout for a
length of 490 RMT to convey the sewage to V. Valley STP
‰ Providing 450mm dia line at Dhobighat at Kempambudhi Lake
for a length of 450 RMT to convey the sewage to V. Valley STP
‰ Work of 900/1200mm dia line to convey the sewage generated
from upstream area of Nayandanahalli lake for a length of 1700
RMT to avoid ingression of sewage into Nayandanahalli Lake
Water & Sanitation

Immediate / Priority Objectives - by March 2009

Objectives Progress
Rehabilitation of trunk sewers in K&C – Valley

‰ Providing and laying 1200mm dia NP4 class sewer


across JC Road near Cargo Tarpaulin complex by
trenchless technology for a length of 80 RMT to
convey the sewage to K & C Valley STP.

‰ Providing and laying 1200mm dia RCC sewer to


link to existing 900mm dia sewer across HSR Ring
Road by the side of Agaram Lake for a length of 20
RMT to convey the sewage to K & C Valley STP

‰ Providing and laying 450mm dia NP3 class sewer


line by shifting existing damaged 400mm dia sewer
running below the building to along the road at
Siddapura of Someshwaranagar, Wilson Garden for
a length of 450 RMT to convey the sewage to K & C
Valley STP
‰ Providng and laying 900mm dia NP3 class RCC
sewer line by shifting existing damaged NP2 class
900mm Dia sewer running below the buildings
along Diwakar Hospital, J.P. Nagar for a length of
206 RMT to convey the sewage to K & C Valley
STP
‰ Providing and laying 450mm dia submain via
Hutchins road from Devis Road to Pottery Road for
a length of 380 RMT to convey the sewage to K & C
Valley STP
Rehabilitation of trunk sewers in Hebbal Valley

‰ Providing and laying 450mm dia submain at MLA


Layout, Ganganagar for a length of 513 RMT to
convey sewage to Hebbal Valley STP.
‰ Providing and laying 450mm dia sub-main
Krishnappa Layout to Sanjayanagar for a length of
500 RMT to convey sewage to Hebbal Valley STP.

‰ Providing and laying 450mm dia submain at


Kariyannanapalya for a length of 350 RMT to
convey sewage to Hebbal Valley STP.
‰ Extension of 450mm dia submain in 80 feet Road
Sanjayanagar for a length of 500 RMT to convey
sewage to Hebbal Valley STP.
‰ Providing and laying 450mm dia submain from
Ambedkar Medical College to Devarajeevanahalli
Main Road for a length of 2800 RMT to convey
sewage from BBMP area to Hebbal Valley STP.
Water & Sanitation

Immediate / Priority Objectives - by March 2009

Objectives Progress
Integrated water Management (Reuse of Lake Water), Environment action
plan works & CWSS Stage – IV, phase - II

‰ Vrishabhavathi Valley -180 MLD/105


MLD/135 MLD
Lakes
‰ Bellandur - 60 MLD
‰ Nagavara 30 MLD
‰ Kalkere/ Raja Canal 20 MLD
‰ Kengeri - 30 MLD- Rs.100.00 Crores
K.R.Puram - 20 MLD
‰ K&C Valley - Varthur - 300 MLD- Rs.900.00
Crores Koralur - 50 MLD
‰ Jakkur, Begur, Puttenahalli (JP Nagar),
Madavara, Doddabommasandra,
Voderahalli, Hulimavu, Dorkere etc.
Water & Sanitation

Infrastructure Projects – Repairs / Capacity Expansion /


Addition
Medium Term Objectives - April 2009 -2012

Objectives Progres
‰ Providing Cauvery water to the former
CMC wards

‰ Procurement of Combination Machines


and setting up of R.W.H. Theme Park

‰ Procurement of combination machines

‰ Setting up of R. W. H. Theme Park

‰ Providing water supply network, feeder


mains & sewerage net work in the former
C.M.C. Areas

‰ Replacement of major leaking lines

‰ Shifting of water and sanitary lines due to


road widening, construction of under
passes, metro etc.

‰ Major improvement works

‰ Replacement of corroded pipelines

‰ Rehabilitation of trunk sewers in K&C


Valley

‰ Rehabilitation of trunk sewers for abating


sewage flow into K&C Valley

‰ Model ward – BBMP ward No. 100


(Sanjaynagar) selected to make it as
Model ward for water supply & sanitary
system

‰ Construction of New GLRs in BBMP area

‰ Sinking of Bore wells in the former CMC


areas

‰ Rehabilitation of trunk sewers in V Valley

‰ Rehabilitation of trunk sewers in K&C


Valley

‰ Rehabilitation of trunk sewers in Hebbal


Valley

‰ Integrated Water Management (Reuse of


lake water), Environment action plan works
Water & Sanitation

Medium Term Objectives - April 2009 -2012

Objectives Progress
Procurement of Combination Machines

‰ Procurement of 45 Nos. of 6,000 litres capacity Combination


Machines (to carry 3,000 litres of water or 3,000 litres of
sewage) to be mounted on suitable chassis to be supplied
by the Board
Major improvement works
‰ Providing under ground drainage facilities to Peenya Ward
No. 11 of Dasarahalli

Replacement of Corroded pipelines


‰ Replacement of corroded pipes in Bharathinagar area.

‰ Replacing 110 mm dia PVC line by 100 mm dia DI pipe to


avoid contamination at Austin Town.
Rehabilitation of trunk sewers for abating sewage flow into K&C Valley:
‰ Providing 1200 mm dia NP 3 class sewer inplace of
existing 900 mm sewer from Krishnappa Garden to Silk
Board at Madivala
‰ Providing and laying 600 mm dia NP 3 class from Akkipet
circle to Super Talkies, Cotton pet including pipe laying by
trenchless technology of 100 Rmt
‰ Replacing existing 450 mm dia NP 2 class pipe at
Puttenahalli from Sharada Layout to Ganesha Temple by
600 mm dia NP 3 class RCC pipe due to existing invert
levels and sewage entry in to Jaraganhalli lake
‰ Providing 1200 mm dia NP 3 class sewer by replacing the
existing 900 mm dia NP2 class sewer in order to avoid
over loading of the existing sewer in J P Nagar from
Manthri Apartments to Ranka Apartments on Bannerghatta
road
‰ Replacing existing 450 mm dia NP 2 class pipe at
Taverekere by 450 mm dia NP 3 class RCC pipe due to
the crown corrosion of the existing pipeline
‰ Providing and laying 600 mm sewer from Agaram to
Agaram Pump house to convey the sewage generated in
HSR layout
‰ Providing 50 MLD pumping station to pump the sewage
generated in Koramangala and ST Bed areas and entering
in to Bellandur lake by intercepting the SWD to K & C
Valley STP including providing Civil, Mechanical, Electrical
equipment and rising main
‰ Strengthening of the existing 1500 mm dia NP 2 class
existing sewer at ISRO layout after the detail conditional
assessment of the existing pipeline
‰ Providing and laying 900 mm dia NP 3 class inplace of
existing 600 mm dia NP 2 class pipe in SWD from
Wheelers Road to Gandhi gram Pottery town through
Water & Sanitation

Medium Term Objectives - April 2009 -2012

Objectives Progress
Model Ward
‰ BBMP ward No. 100 (Sanjayanagar) has been selected
to make it as Model ward for water supply & sanitary
system. In the first instance it is proposed to lay feeder
main, identification and regularization of unauthorized
water supply connection and laying of sanitary lines in
lieu of Old / Silted smaller dia sanitary lines.

Construction of New GLRs in BBMP area


‰ Ten ground level reservoirs at an approximate cost of
Rs. 50.00 Crores has been proposed for construction
at various locations of BBMP area. Tenders are invited
for the same with the last date for requisition of E-
Tender forms upto 10.11.2008 and submission on
12.11.2008
Replacement of major leaking lines
‰ 600 mm dia pipeline by MS pipeline from Mekri circle
upto CJF
‰ 400 mm dia CI pipeline by MS pipeline inside
Defence Bellary road
Shifting of pipelines in view of Road widening
‰ Shifting 700 mm dia MS pipeline from HGR S/s upto
Guard street / Cubbon road junction along Infantry
road.
‰ Shifting of 600 mm dia MS water supply line feeding
to Halasur
‰ Shifting of 250 mm dia MS water supply line from 4
MG reservoir at HGR
‰ Shifting of 200 mm dia MS water supply outlet line
from OHT across Sankey road
‰ Shifting of 300 mm dia MS water supply inlet line
OHT across Sankey road
‰ Shifting of 600 mm dia MS water supply line feeding
to Indiranagar
‰ Shifting of 100 mm dia MS water supply line

‰ Shifting 700 mm dia MS water supply line in Indira


Gandhi musical fountain premises and linking it to
675 mm PSC line along Sankey road
‰ Shifting of 450 mm, 150 mm & 100 mm dia water
th th
supply pipelines at 24 main, 15 cross, J. P.
th
‰ Nagara
Shifting of 9” & 12” dia UGD pipelines at 24 main,
th
15 cross, J. P. Nagara
‰ Shifting of 450 mm, 300 mm, 250 mm and 100 mm
water supply pipelines and valves at Kadirenahalli
and Ring road junction.
‰ Shifting of 9” dia UGD pipeline at Kadirenahalli and
Ring road junction.
Water & Sanitation

Medium Term Objectives - April 2009 -2012

Objectives Progress
Shifting of pipelines in view of Road widening
‰ Shifting of 600 mm, 450 mm, 300mm, 150 mm & 100 mm
dia water supply pipelines and valves at Checkpost of
Hosur road (Sarjapura road) infront of Koramangala S/s.

‰ Shifting of 150 mm, 100 mm dia DI water supply line at


Hosur road HP petrol bunk to Bharat Petrol bunk

‰ Shifting of 9” dia SW line with 12” dia RCC line at Hosur


road main road HP petrol bunk to Bharat Petrol bunk

‰ Shifting of 300 mm dia SW line from Shooly circle to


Adugodi police station along Luskar road

‰ Shifting of different dia of MS/CI/DI water supply line from


Shoolay circle to opp NDRI all along Laskar Hosur road

‰ Shifting of 4” dia, 6”dia, 12” dia, 18” dia & 24” dia CI line by
MS line for widening of Hosur road

‰ Shifting of 457 mm dia MS feeder main in place of existing


450 mm dia CI/ PSC line from Chandra layout Reservoir up
to Bangalore University gate via Mysore road

Major improvement works


‰ 100 mm dia DI line in place of damaged 110 mm dia PVC
line at MCT slum attached to Sanjayanagar slum.

‰ 12” dia SW line from Siddanna lane to Avenue road junction


along Nagarthrpet main road
‰ 250 mm dia feeder main from Ramakrishna Ashrama to
Kempegowda main road along Hayavadana road ,
Syndicate bank circle to improve W/S to Bhavaninagar.
‰ 300 mm dia SW sanitary pipe line inplace of 6” dia SW P/L
th
along road way & B.No.18 street, Shivajinagar.

‰ 450 mm dia RCC NP3 class sanitary from murugon pillai


street along Nala road linking it to the existing 600 mm dia
line at Armstrong road .
‰ 450 mm dia NP3 class S & S RCC pipeline at
Cholanayakanahalli from Hospital at sub main.

‰ 80 mm dia PVC providing and laying 100 mm dia & 150 mm


dia DI pipe at Old Byappanahalli, Jeevanahalli park area &
surrounding areas.
nd
‰ 300 mm dia water supply line from 2 cross to 100’ road
Ejipura main road to improve water supply to Ejipura area.

st
‰ 300 mm dia SW line from J K.Pura main road to 1 main
Vinayakanagar
Water & Sanitation

Medium Term Objectives - April 2009 -2012

Objectives Progress
Integrated water Management (Reuse of Lake Water), Environment action
plan works & CWSS Stage – IV, phase – II
‰ Vrishabhavathi Valley -180 MLD/105
MLD/135 MLD
Lakes
‰ Bellandur - 60 MLD

‰ Nagavara 30 MLD

‰ Kalkere/ Raja Canal 20 MLD


‰ Kengeri - 30 MLD- Rs.100.00 Crores
K.R.Puram - 20 MLD
‰ K&C Valley - Varthur - 300 MLD- Rs.900.00
Crores Koralur - 50 MLD
‰ Jakkur, Begur, Puttenahalli (JP Nagar),
Madavara, Doddabommasandra, Voderahalli,
Hulimavu, Dorkere etc.
Thank
You