CALCULO DE LA FORMULA POLINOMICA

CREACION DEL CENTRO COMUNAL COMERCIAL EN EL SECTOR SUTIL, DISTRITO


OBRA:
DE RECUAY , PROVINCIA DE RECUAY - ANCASH

COSTOS PRIVADOS = S/. 279,635.62

AGRUPAMIENTO PRELIMINAR

DESCRIPCION IND. UNIF. MONTO % % INCD.


MANO DE OBRA
Mano de Obra Inc.
47 S/. 41,066.28 14.686%
Leyes Sociales
Total S/. 41,066.28 14.686%

MATERIALES
Agregados 5 S/. 11,912.59 4.260%
Cemento 21 S/. 21,941.96 7.847%
Ladrillo 17 S/. 15,639.06 5.593%
Acero 3 S/. 63,372.28 22.662%
Madera para Carp. Nac. 43 S/. 50,834.80 18.179%
Total S/. 163,700.69 58.541%

MAQ. EQUIPO,
HERRAMIENTOS Y
FLETE.
Maq. Nacional 48 S/. 7,612.46 2.722%
Herramientas 37 S/. 1,427.35 0.510%
Flete 26 S/. 25,198.02 9.011%
Total S/. 34,237.83 12.244%

INDICE GENERAL DE
PRECIOS AL 39
CONSUMIDOR
Gastos Generales 39.00 S/. 23,900.48 8.547%
Utilidades 39.00 S/. 16,730.34 5.983%
S/. 40,630.82 14.530%
Total S/. 279,635.62 100.00%

FORMACION DE MONOMIOS

MONOMIO AGRUPAMIENTO I.U. % INC. SIMBOLO FACTOR


Agregados 5 7.277%
Cemento 21 13.404%
Agregados, Cemento y Ladrillo 17 9.553% T 0.585
Ladrillo
Acero 3 38.712%
Madera para Carp. Nac. 43 31.054%
Flete 26 73.60%
Equipo y Materiales EM 0.122
Maq. Equipo y H. 48 26.40%
Gastos Generales
Gastos Generales 39 100.00% GG 0.145
Utilidades
Mano de Obra Inc.
Jornales 47 100.00% J 0.147
Leyes Sociales

Coeficiente de Incidencia 1.000

K= 0.585 Tr/GTo + 0.122 EMr/EMo + 0.145 GGr/GGc + 0.147 Jr/Jo