You are on page 1of 1

[WEEKLY

SIMOP COORDINATION MEETING]

No. Activity PIC Status Due Date


1 Integrated schedule for Alur Siwah cluster to be updated Rossy & Open 31st March
incorporating schedule input from EPC-1, 2 & Drilling Heyder 2018
nd
2 Engineering of all discipline from wellhead to production JEC Open 2 April 2018
manifold will be executed by JEC
3 Section 1 of flowline and instrument tubing will be installed JEC Open 2nd April 2018
inside the concrete trenched and will be constructed by JEC
4 Prior to execute any SIMOP in Alur Siwah cluster, CTR requested Gatot & Open 2nd April 2018
to submit SIMOP Execution Plan as specific as actual work plan Aulia
as per CPY supplied SIMOP Management Plan
5 There is confirmed that Alur Siwah will be divided by 2 zone and INFO Open NA
3 section area, as per following drawing:

Project
Muster Point
Production
manifold

Section 3
(outside 50 mtr radius)
ZONE A
(Medco PTW without Drilling Authorization)

Section 2
(inside 50 mtr radius)

Section 1

ZONE B

(Medco PTW with Drilling Authorization)

6 To separate boundary working area between zone A & zone B, Andri Open 30th April
HSE is requested to install the soft barricade tape at site Hapsari 2018
7 EPC-1 & 2 CTR shall submit the list of personnel name to register Gatot & Open 02nd April
to HSE ARAS for Rig HSE & H2S induction Aulia 2018
nd
8 CPY instrument engineer confirmed that there will be installed Gatot, Open 2 April 2018
the additional 2 points of ESD push button where will be Meiriansyah
installed at the rig floor and Drilling COMAN cabin. For the cable & Wisnu
of push button at drilling COMAN will be routed from the panel
house at cooler area by crossing road to the perimeter fence
behind drilling office.
9 Electrical power for additional ESD is needed either by Gatot Open 2nd April 2018
permanent power source from CPP or by placing temporary
genset in cooler area by JEC
10 HSE requirement for SIMOP in AS will need to be fulfilled prior Andri Open 2nd April 2018
to start the construction activities, please refer to approved Task Hapsari
Risk Assessment
11 Next SIMOP meeting will be held on next Monday, 2nd April 2018 Naufal/Dedi Open 2nd April 2018

You might also like