TORRES TRADING
6553 E. RAMOS STREET MAKATI CITY
CONTACT NUMBER: 09173234989/09207709901
EMAIL; adtorrestrading@yahoo.com

March 13, 2018

Attention: Architect Benny June Nacion


Subject: Ground Level Demolition Of Old House Located At Fernando St>
Paco Manila

Dear Sir,
I would like to formalize a bid proposal for the Ground level Demolition Of Old House
located at Fernando St. Paco Manila . Please find the details of our offer as follow

DEMOLITION COST -------------------------------------------- Php 340,000.00


Less Recovery Items ------------------------------------------ Php 200,000.00
Total Payable To Be Contractor = Php 140,000.00
excavation not included

TERMS OF PAYMENT:
1. 30% down payment of total demolition cost upon mobilization to the demolition site .
2. Remaining balance of 70% upon completion of the project .

SCOPE OF WORK:
1. Demolition of whole structure to the ground level. should expose natural grade line
2. Use of equipment’s or machineries to speed up demolition procedure with the help of manual
man power.
3. Clearing and hauling of all debris and garbage’s to its appropriate dumping site except soil.

CONDITIONS:
1. All salvageable items (wood, concrete, steel, glass, lighting fixtures, wiring, tiles, and all other
salvageable items inside the structure, will be for the account of the demolition contractor.
2. Insurance, wages and coverage of all workers that will undergo the demolition services for the
account of the contractor.
3. All government permits necessary for the demolition of the said structure, are for the account
of the contractor.
4. Project duration is thirty (30) working days upon issuance of demolition permit.
target date should be 14-21 days only with
excavation

Should you have any questions/clarifications on the above matter, please feel free to contact us
and we will be more than willing to serve you.
Thank you very much for giving us this opportunity to offer our services and we hope to have a
long lasting business relationship with your prestigious company.

TOTAL BREAKDOWN

Hauling of Debris ------------------------------------------ Php 90,000.00


Rental Backhoe ---------------------------------------------- Php 50,000.00
Labor Expenses ---------------------------------------------- Php 80,000.00
Cutting Tools Expenses ---------------------------------- Php 15,000.00
Demolition Permit ------------------------------------------ Php 75,000.00
Expenses ------------------------------------------------------- Php 30,000.00
Total Breakdown -------------------------------------------- Php 340,000.00

Your’s Truly,

ANTONIO DORIO TORRES


Proprietor
Hi, Arch Benny

A pleasant day to you.

Thank you for taking my call earlier. As discussed over the phone, attached is ADTorres' revised
proposal for the demolition of the house. The scope are as follows:

1. Processing of demolition permit


2. Demolition of house (scrap sales shall be under the ownership of the demolition contractor)
3. Clearing and hauling of debris (up to ground zero - floor slab will be left)

As mentioned, the reason why their initial proposal was high ( inclusive of 2m depth excavation) is
that they will be outsourcing the excavation services to a specialty contractor and will be filing for
an excavation permit. Since ADTorres specialty is demolition and not excavation, I suggest you
consider to award the excavation to your gencon as part of their scope of works or consider hiring
a excavation trade contractor directly to save cost. By packaging the excavation works with the
general civil works contractor, you will be in a better position to haggle costs as they will also be
considering the other scope of works assigned to them when they submit their proposed
discounted prices. If you go with the latter proposal which is awarding the excavation directly to
an excavation trade contractor, the demolition contractor's overhead and mark up costs will be
eliminated thus you will be only charged by the excavation contractor's actual cost. excavation should be
included to advance soil
Feel free to call my attention for any clarification or questions regarding the proposal.testing