A comprehensive study of wheelchair scaffolding


construction technology (package will), not to be missed!
The
2017-09-07 390,000 Realm Construction Technology

Fastener type steel pipe bracket is our construction process, the template bracket to choose
the most form. Today we would like to introduce the wheel buckle bracket, wheel-type support
mold is in the fastener-type steel pipe support model on the basis of vertical and horizontal
horizontal pole and pole connection method to disk and plug self-locking form, so Can greatly
improve the efficiency of supporting the frame, in the civil construction has been a very good
application and greatly promote.

First, the characteristics of wheeled scaffolding construction technology

1, wheel buckle bracket structure design reasonable and clever, with good mechanical
properties;

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 1/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

2, safe and reliable, no moving parts, management, transportation, storage convenience, long
service life;
3, component standardization, modularization, erection and demolition fast and easy;
4, easy to use, can improve the construction efficiency and reduce labor intensity
5, you can waste the short steel pipe processing, turning waste into treasure, saving materials,
in line with the requirements of green construction.

Second, the wheel claw scaffolding construction conditions

1, according to the structure of the project, the level of high, to determine the length of pole
and bar (model), etc., and in accordance with the requirements of the material turnover to

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 2/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

purchase or lease enough erection materials.


2, the scene has a sufficient number of ordinary steel pipe and fasteners, in order to set up
scissors and other components.
3, the support surface to have sufficient strength, and there are good contact with the pole, in
order to facilitate the transmission of force.
4, the floor line has been completed.
5, the pole erection position has been calibrated.
6, has been done supporting the mold construction program and audited, approved by the
workers and carried out targeted technology to the end.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 3/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

Third, the wheel claw scaffolding construction process

The wheeled scaffolding is a support system consisting of a steel pipe with a roulette, a steel
pipe with a plug, and an adjustable jack and so on. Erection process basically with the fastener
scaffolding, but the pole and the bar are fixed, the connection between the pole and the bar is
also less active fastener fixed this link.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 4/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

1, the process

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 5/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

2, erection of materials approach


According to the structure of the project and the high requirements of custom or lease the
corresponding length (model) of the pole and cross bar. In the selection of time to consider
two factors: applicability and turnover use. The main models are: LG-240 (length 2.4m), LG-180
(length 1.8m), LG-120 (length 1.2m) 3 kinds. The models of the bar are HG-30 (length 0.3m),
HG-60 (length 0.6m), HG-90 (length 0.9m) and HG-120 (length 1.2m). Long bar generally use
LG-240, according to the different layers can choose other models, short bar generally use HG-
90 and HG-120.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 6/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

3, positioning line
After the completion of the concrete pouring strength of 1.2MPa or more, such as the pole
erected on the foundation by the foundation treatment to reach a certain strength, according
to the construction axis size of the control line, the establishment of control network, cited
elevation control line, according to the measured Of the control line to determine the location
of the beam and column, and marked the erection position.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 7/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

4, laying the mat or place the base


In order to expand the bearing area at the bottom of the pole to ensure that the load bearing
surface uniform force, to lay the bottom of the pole and put the base.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 8/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 9/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

5, set up pole, cross bar


Wheel claw scaffolding of the shorter components, the general pole and bar erection of a
person can operate to complete. When erecting, place the pole on the pre-placed mat, and
then insert the bar's plug into the roulette of the pole and the other end into another roulette.
The length of the pole is directly inserted into the pole at the end of the pole Φ58mm × 4mm
× 200mm casing, to ensure that the upper and lower pole of the docking, the effective
transmission of stress.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 10/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 11/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

6, set the scissors support


After the bar and the bar are laid on the requirements, the vertical scissors shall be provided on
the four sides of the frame body and the middle row of the four rows of stands. More than 4m
of the template bracket, both ends and the middle of every four rows of pole from the top to
start down every 2 steps to set a horizontal scissors support. Four angle angle bracing. Facade
Scissors Stopped by conventional practice.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 12/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 13/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

7, connecting, reinforcement plate base body


After the support frame is erected to form a stable force body, the connection of the bottom
frame body and the bottom frame body and the pole rod is adopted in the form of adjustable
jacking.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 14/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 15/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

8, laying the roof plywood


When the bottom of the sub-keel (wood Leng) and the main keel (double steel) by the
elevation control line (elevation can be adjusted through the adjustable top care) after
installation, you can install the top of the bamboo plywood. When installing the top plate
template, use a nail to secure it with the bottom of the board and ensure that the template is
securely installed, flat and patchy.

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 16/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 17/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

9, check the acceptance


(1), support mold is strictly in accordance with the program implementation, construction
measures are reasonable. Is the connection between the pole and the bar secure?
(2), after the completion of the template correction flatness and floor elevation.

10, pouring roof concrete


After the installation of the template and the reinforcement of the bar, the pouring roof
concrete, pouring the concrete in the roof when pouring, and found that the timely elimination
of hidden dangers.

11, support mold removal


Branch mold removal order is generally the first branch after the demolition; first remove the
non-load part, after the removal of load-bearing part.
Beam plate support mold when the concrete strength to meet the requirements of the
reference to the relevant provisions.
Before the removal of the template stent, the technical personnel should be handed over to the
demolished personnel and written procedures.
Demolition operations must be carried out from top to bottom, is strictly prohibited from top
to bottom at the same time operations. The height difference of the segmentation should not
be greater than two steps.
Multi-storey building template bracket removal, should be removed above the removal layer of
not less than two layers of the template bracket.
When the wheeled scaffolding is dismantled, pay attention to the removal order of the bar, the
pole and the scissors and other components. It is forbidden to throw the component to the
ground and spread it to the ground.
On the demolition of the components to be timely inspection, renovation, maintenance,
remove the unqualified components.

Fourth, the wheel claw scaffolding construction quality control

1, support mold frame must be based on the relevant norms and standards for the design and
acceptance of the tall template project must be required expert demonstration, if necessary,
the preparation of emergency programs.

2, erect the quality of the component itself

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 18/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

The steel pipes used for the pole and the crossbar shall not have cracks, scarring, delamination,
misalignment, hard bending, burrs, indentations and deep strokes. Steel pipe diameter, wall
thickness, the end of the deviation; steel pipe surface corrosion depth; steel pipe bending
deformation should be consistent with the relevant rigid requirements. The welding quality of
the pole and the roulette, the welding quality of the crossbar and the plug meet the
requirements, the welding strength of the roulette wheel 60KN does not destroy, and the
welding strength of the bar plug is not damaged.

3, the strength of bearing surface


Whether it is erected on the foundation or has been built on the floor have to be calculated to
meet the strength requirements. If not satisfied to take measures to reinforce in the lower. The
bottom of the pole must be fitted with a base or pad.

4, the pole and the bar connection node must be fastened, the erection of the pole should be
accurately placed on the positioning line. All the pole and the bar to form a solid overall force
together.

5, scissors support the erection of the fast scaffolding scaffolding-related requirements.

6, support the erection of technical requirements to allow deviation and test methods see table
below

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 19/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

5, wheeled scaffolding construction points to pay attention

In addition to complying with the relevant requirements of the "fastener frame specification",
consider the following:
1, the template bracket construction requirements
(1) between the pole must be step by step full of two-way horizontal bar, to ensure that the
two directions sufficient design stiffness;
(2) beam and floor load difference is large, you can use a different pole spacing, but only in a
direction variable pitch, while the other direction unchanged.

2, the design of the pole step


(1) When the frame structure load in the pole height of different height changes, it can be used
to set the distance;
(2) when the middle of the strengthening layer or bracket is very high, along the height
distribution of large changes in force, can be used on the next small variable step set, but not
too much change;
(3) high support frame step to 0.9 ~ 1.5m is appropriate, should not exceed 1.5m.

3, the framework of the overall design


(1) tall template project is strictly prohibited using wheeled scaffolding, support frame height
should be ≦ 5m;
(2) In any case, the top and bottom of the high support frame (the setting floor of the
sweeping pole) must be provided with a horizontal reinforcement layer, the horizontal
reinforcement layer shall be provided with horizontal diagonal or scissors;

http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 20/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

(3) support frame must have more than 4 vertical and horizontal continuous unit body; does
not meet the pole spacing of the location, the use of fastener-type steel pipe support frame
erection, and with other frame body complete connection.

4, scissors support the design


(1) along the stent around the facade should be full of scissors brace, scissors brace with steel
pipe erection;
(2) the central according to the need and according to the size of the framework of the grid,
every 10 ~ 15m set.

5, the top of the support point of the design


(1) support should be used to support the way, to prohibit the horizontal bar directly to
withstand vertical load;
(2) The length of the cantilever of the horizontal pole of the top bracket is not more than
650mm. The length of the adjustable pole insertion pole shall not be less than 250mm. The
screw of the U type shall not exceed 200mm.

6, support frame erection requirements


(1) to ensure that the vertical deviation of the pole and horizontal deviation of the bar is less
than the "fastener frame specification" requirements;
(2) foundation bearing design to meet the requirements of bearing capacity.

7, the use of construction requirements


(1) carefully designed concrete pouring program to ensure that the template support during
the construction of balanced load, it is best to use from the central to the two sides of the
expansion of the pouring way;
(2) strict control of the actual construction load does not exceed the design load, the
emergence of more than the maximum load to have the appropriate control measures, steel
and other materials can not be stacked above the stent;
(3) pouring process, sent to check the stent and support the situation, found sinking, loose and
deformation of the situation in a timely manner.

Source: Dou Ding construction

recent activities:
1, September 7 - the 9th Beijing: National steel residential cutting-edge technology forum .
Combined with the bottleneck of the development of steel structure residential projects, invited Guo
http://mp.weixin.qq.com/s/HJRPn9AEODKuum6KOkiZvg 21/22
9/7/2017 A comprehensive study of wheelchair scaffolding construction technology (package will), not to be missed! The

Yanlin , Yu Yinquan, Wang Lijun, Chen Zhihua, Zhao Tian , Yang Qiangyue, Xu Hang, Lu Qinggang, Guo
Qing, Su Lei, Zhang Jun and other industry experts and scholars in-depth exchange of steel structure
research, Construction of successful experience. Details click
2, September 21 , 2021 September 21: the national project general contracting project
management experience exchange. Invited Zhou Wen company, Zhang waves, Yang Yong, Xue
Feng, Wu Yi Xia, Zhang Huai Yong, Li Yuefei, Li Shudong, Yang Hua country, Zhang Yong, Lear Long,
Zhang Yajie, Tan Jinghui experts and other industries in-depth discussion of the engineering
contracting (EPC) essay Road , And visit the Zaha Wushu - Lize SOHO project. Details click
=========================

About "Construction Technology" magazine


"Construction Technology" magazine was founded in 1958 , is the only domestic
construction system of national professional science and technology journals. The latest
technical coverage of the construction of the latest technology, with its practical and
content-rich features, by the engineering and technical personnel welcome and praise,
circulation in the field of domestic construction far ahead.