Group members: Denis, Andrey, Harman, and Joyce

Network

7 3 11

0 Complete roof

7 4 11
TS= 0 FS= 0

7 4 8 11 7 13

3 Install windows 0 Rough- in frame

0 1 3 3 2 7 10 1 11 11 2 13 13 9 15 15 10 16
TS= 3 FS= 3 TS= 0 FS= 0
0 Pour foundation 0 Erect frame 0 Paint 0 Cleanup

0 3 3 3 4 7 7 5 8 10 8 11 13 2 15 15 1 16
TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0
3 Install doors 2 Install door opener

10 1 11 12 1 13
TS= 3 FS= 3 TS= 2 FS= 2

7 6 10

1 Install electrical

8 3 11
TS= 1 FS= 1
Group members: Denis, Andrey, Harman, and Joyce

After crashing "Rough- in frame" activity


Project
Path Duration:
1 2 3 7 9 10 16 1 2 3 7 9 10 15
duration:

3 4 4 2 2 1 3 4 4 1 2 1

Path Path
1 2 4 7 9 10 13 1 2 4 7 9 10 12
duration: duration:

3 4 1 2 2 1 3 4 1 1 2 1

Path Path
1 2 5 7 9 10 13 1 2 5 7 9 10 12
duration: duration:

3 4 1 2 2 1 3 4 1 1 2 1

Path Path
1 2 5 8 9 10 12 1 2 5 8 9 10 12
duration: duration:

3 4 1 1 2 1 3 4 1 1 2 1

Path Path
1 2 6 7 9 10 15 1 2 6 7 9 10 14
duration: duration:

3 4 3 2 2 1 3 4 3 1 2 1

Path Path
1 2 6 8 9 10 14 1 2 6 8 9 10 14
duration: duration:

3 4 3 1 2 1 3 4 3 1 2 1
Group members: Denis, Andrey, Harman, and Joyce

Through above processing, we shorten 1 day in the “Rough-in frame” work package to get the bonus, because this unit is the cheapest among all
packages. After crashing network is showing below:

7 3 11

0 Complete roof

7 4 11
TS= 0 FS= 0

7 4 8 11 7 12

3 Install windows 0 Rough- in frame

0 1 3 3 2 7 10 1 11 11 1 12 12 9 14 14 10 15
TS= 3 FS= 3 TS= 0 FS= 0
0 Pour foundation 0 Erect frame 0 Paint 0 Cleanup

0 3 3 3 4 7 7 5 8 10 8 11 12 2 14 14 1 15
TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0
3 Install doors 1 Install door opener

10 1 11 11 1 12
TS= 3 FS= 3 TS= 1 FS= 1

7 6 10

1 Install electrical

8 3 11
TS= 1 FS= 1
Group members: Denis, Andrey, Harman, and Joyce

Network Diagram after fast-tracking

7 3 11

0 Complete roof

7 4 11
TS= 0 FS= 0

7 4 8 11 7 13

3 Install windows 0 Rough- in frame

0 1 3 3 2 7 10 1 11 11 2 13 12* 9 14 14 10 15
TS= 3 FS= 3 TS= 0 FS= 0
0 Pour foundation 0 Erect frame 0 Paint 0 Cleanup

0 3 3 3 4 7 7 5 8 10 8 11 12* 2 14 14 1 15
TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0 TS= 0 FS= 0
3 Install doors 1 Install door opener

10 1 11 12 1 13
TS= 3 FS= 3 TS= 2 FS= 2

7 6 10

1 Install electrical

8 3 11
TS= 1 FS= 1
Group members: Denis, Andrey, Harman, and Joyce

According to the resource constrained, We are fast-tracking the painting in 1 day. We will start to paint the walls as soon as they are fixed. So we
will need to coordinate people passing the cables and pipes, then putting dry-walls and after people painting them, as we will be painting at the
same time with installing the walls. With fast tracking the painting we can finish the project within 15 days.

ID Duration Task Name Start Finish 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1 3 Pour foundation 0 3

2 4 Erect frame 3 7

3 4 Complete roof 7 11

4 1 Install windows 7 8

5 1 Install doors 7 8

6 3 Install electrical 7 10

7 2 Rough- in frame 11 13

8 1 Install door opener 10 11

9 2 Paint 13 15

10 1 Cleanup 15 16