Velocity Pressure:
𝑁 𝑚
𝑞𝑧 = 0.613𝐾𝑧𝐾𝑧𝑡𝐾𝑑𝑉 2 ( 2 ) ; 𝑉 𝑖𝑛
𝑚 𝑠
𝑞𝑧 = 0.613(0.99)(1.0)(0.85)(72.2222)2
𝐿 39 𝑚
= 40 𝑚 = 0.975
𝐵
Surface Cp
Surface Cp
-0.1629
1
ℎ = 5.5 𝑚 + 2 (4 𝑚) = 7.5 𝑚
ℎ 7.21 𝑚
= = 0.206
𝐿 35 𝑚
4𝑚
𝜃 = tan−1 (20.5 𝑚) = 11.0409°
𝑁
𝑝 = 𝑞𝐺𝐶𝑝 − 𝑞𝑖(𝐺𝐶𝑝𝑖) (𝑚2 ) (Eqn. 207B.4-1)
WALL PRESSURE
Windward Wall
𝑝 = 2690.6443 𝑁⁄𝑚2 (0.85)(0.80) − 2690.6443 𝑁⁄𝑚2 (0.18)
Leeward Wall
Side Wall
ROOF PRESSURE
Leeward Roof
(Simplified Method)
1 1
𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑃𝑢𝑟𝑙𝑖𝑛𝑠 = × 𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑡𝑟𝑢𝑠𝑠 = (2.5 𝑚) = 0.8333 𝑚
3 3
𝑅𝑜𝑜𝑓 𝑂𝑣𝑒𝑟ℎ𝑎𝑛𝑔 = 1 𝑚
2𝑚
𝜃 = tan−1 ( ) = 5.5722°
20.5 𝑚
By Interpolation:
Purlin
Truss
Roof Overhang
Zone 2 -3.2322
Zone 3 -3.8767
Purlin
Zone 1 1.4652 -2.4944
Truss
Roof Overhang
Zone 1 -4.3635
Zone 2 -5.2335
OPTION 2 Holding Pens
(Simplified Method)
𝑆𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑇𝑟𝑢𝑠𝑠 = 3 𝑚
1 1
𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑆𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑃𝑢𝑟𝑙𝑖𝑛𝑠 = × 𝑠𝑝𝑎𝑐𝑖𝑛𝑔 𝑜𝑓 𝑡𝑟𝑢𝑠𝑠 = (3 𝑚) = 1 𝑚
3 3
𝑅𝑜𝑜𝑓 𝑂𝑣𝑒𝑟ℎ𝑎𝑛𝑔 = 1 𝑚
1𝑚
𝜃 = tan−1 ( ) = 5.7106°
10 𝑚
By Interpolation:
Purlin
Truss
Roof Overhang
Zone 2 -3.2322
Zone 3 -3.8767
Purlin
Zone 1 1.3959 -2.4597
Truss
Roof Overhang
Zone 1 -4.3635
Zone 2 -5.2335