Hsp = B/P

𝑅𝑝. 400.000/𝑗𝑎𝑚
= 𝑅𝑝. 10.170,043/𝑚3
39.3312 𝑚3 /𝑗𝑎𝑚
𝑅𝑝. 750.000
( )
7 𝑗𝑎𝑚 𝑘𝑒𝑟𝑗𝑎
= 𝑅𝑝. 5.033,725/𝑚3
21.285 𝑚3 /𝑗𝑎𝑚

no ket satuan volume harga satuan total


galian dengan excavator Rp Rp
1 m3 720.00
kapasitas 0.34 m3 10,170,043.00 7,322,430,960.00
pemuatan dengan dump Rp Rp
2 m3 720.00
truck kapasitas 7m3 5,033,725.00 3,624,282,000.00
Rp
Harga Pekerjaan
10,946,712,960.00