Professional Documents
Culture Documents
proposal for
Sand Refinery
at Keenakele Estate
in North WesternProvince,
Sri Lanka.
1
INDEX Page
Phase 1. (Permeable) 4.
Phase 2. ( Operational) 5.
Phase 2..
Grand Summary. 8.
2
Project Scope ( Overview)
At phase 2 the developer intends to transport raw materials to the site, process
those to necessary quality simultaneously and sale of the product at the market rate by
reasonable profit margin after deducting all the operational and permeable cost.
3
Phase 1. (permeable)
At north west corner of the land near south entrance a office premises of 3.0 sqs:
is proposed to be constructed to facilitate operational manager of the factory. It is
proposed to made out of Rubble foundation, walls made out of cement sand blocks, with
clay tile roof. Next to it ; towards North; a factory premises with warehouse of 30.0 Sqs:
is proposed to be constructed where the necessary machineries are going to be installed
and finished products to be stored. It also proposed to be constructed out of rubble
foundations, R.C.C. columns with Asbestos roof.
The developer intend to construct a 20.0’ diameter well to supply water for
washing plant.
4
Phase 2. ( Operational)
After completion of Phase 1 of the development plan the developer wishes to start
operational stage by transporting raw material (raw Silica) from a site situated at village
called Madampe in Madampe Divisional Secretrey’s Division by dump trucks. Targeted
quantity to be transported to factory premises per a day is 510 Cubes by using 3.0 Cubes
capacity trucks, ie; 170 trips per a day.
2. Processing mechanism.
The developer intends to load the raw materials to processing machinery by using
one back hoe and one loader.
5
Phase 3. Financial analysis. (Analytical)
6
3.2 Working capital requirements for a month at operational stage in Phase 2.
3.3.1 Following assumption are made before arrival in to Profit and Loss
calculation
3.3.1.1 100% of raw materials transported to the site are utilized for processing.
Ie; 26*510 = 13260.00 Cubes.
3.3.1.2 Consider 5% loss for debris and other residual materials.
Ie; 13260 -13260*5% =12597 Cubes.
3.3.1.3 Consider100% sales of production at the end of each month.
3.3.1.4 Consider efficiency of processing is 100% throughout every month.
3.3.2 Projected cash inflow per each month =SLR 88.180 million
(ie;12597* 7000/=)
3.2.1.6 Projected cash outflow per each month =SLR 59.048 million
3.3.3 projected profit per month =SLR 29.132 million
7
Grand Summary (Financial aspect)