You are on page 1of 109

CDU/VDU RELOCATION

FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Revamp, Utilities & Offsites works within SOCAR HAOR


Modernization and Reconstruction Project

CDU/VDU unit Transportation Report

0 21.09.2017 ISSUED FOR INFORMATION (IFI) AG TK BK


Rev. Date Issue, Modification Prepared Checked Approved
CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Table of Contents
1  GENERAL ........................................................................................ 3 
1.1  INTRODUCTION .......................................................................................................... 3 
2  OBJECTIVES ................................................................................... 3 
3  DEFINITIONS .................................................................................. 4 
4  HEAVY EQUIPMENT – CRITICALS ONLY ........................................... 4 
5  PROPOSED HEAVY TRANSPORT ROUTE .......................................... 5 
6  CONCLUSION ................................................................................ 29 
7  ATTACHMENTS ............................................................................. 29 

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 2/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

1 GENERAL
1.1 INTROD UCTION
This document describes the observations and outlines the type of restrictions located by the outcomes
of the suggested main route survey recently executed from Socar Azerneftyagh to Socar HAOR for the
Feasibility Study of CDU/VDU Relocation in Baku, Azerbaijan.
The survey has been executed to identify the possible heavy transport route/s for the transportation of
the existing CDU/VDU units to Haydar Aliyev Oil Refinery for re-installation and integration to the Socar
HAOR Project.
Crude & Vacuum Distillation (CDU/VDU) critical items are above the allowable sizes and weight.
Therefore examination of the routes have been done considering special transport equipment to be
used, movement at night, blocking the roads by police, vehicle movement opposite direction.
It has to be noted that the survey has been focused on the identification of any possible heavy
transport route from Azerneftyagh CDU/VDU units location (ref. layout is available on attachment-2 of
this document) to Socar HAOR plant entrance. From refinery entrance to equipment final location (ref.
to general key plan on attachment-3 of this document) will be further assessed in line with HAOR
Project Heavy Transport Routing Survey Report BD0928-0000-HOC-RE-004.
New equipment location plan already studied and available attached (ref. attachment 4) on this
documentation for aiding further assessment.
This report is prepared based on the survey dated 1st September 2017and the information contained
herein may be further integrated and/or modified during the next phases of the Project.
The main routes analysis is at preliminary level and will be verified and confirmed by the specialized
heavy transport contractor once the final dimensional and weight data of the critical equipment items
are available.

2 OBJECTIVES

Survey is made to navigate all restrictions along the suggested route. Provided photos define most
critical areas and obstacles which shows limitations and restrictions. Main objectives of the survey were
considered as follows:

- To identify main obstacles and restrictions along the suggested transport routes and, in general, along
the surveyed main roads.
- To propose preparatory works necessary to allow the transport along the identified routes.
- To identify transportation concerns considering equipment dimensions and weights.
- To identify single piece or dismantling options based on the dimensions available and transport
limitations.
- To identify and propose access ways and transport routes for the equipment, up to Socar HAOR plant
entrance locations.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 3/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

3 DEFINITIONS

Project HAOR MODERNIZATION FEED PROJECT

HAOR the Heydar Aliyev Oil Refinery plant is the final Client

SOCAR IPMT SOCAR Integrated Project Management Team constituted by


resources of SOCAR, KBR and SOCAR-KBR

Contractor Tekfen Construction

Project Delivery Process PDP

4 HEAVY EQUIPMENT – CRITICALS ONLY


Based on the drawings provided below table summarizes the lists of the critical heavy equipment.
Equipment dimensions and weights are clarified by the existing Vendor drawings.

Empty Length Ø ID
T. Dwg No Tag No Item Description
Weight (kg) (mm) (mm)
8457 C-202-C005 C-301 Vacuum Column 118,070.00 44,466.00 4,700.00
8457 C-202-C001-A C-201 Crude Column 84,290.00 50,136.00 3,794.00
8457 C-202-E015 E-302 VAC. Reside / Stm Generator 24,622.00 7,825.00 2,240.00
8457 C-202-D019 D-209 A Kerosene Clay Filters 23,900.00 11,600.00 3,162.00
8457 C-202-D019 D-209 B Kerosene Clay Filters 23,900.00 11,600.00 3,162.00
8457 C-202-D020 D-210 Diesel Salt Dryer 22,600.00 9,300.00 3,264.00
8457 C-202-E002 E-102 Crude/Kero. P.A Exchanger 20,518.00 8,029.00 2,070.00
8457 C-202-E001 E-101 Crude/Diesel Product Exchanger 19,760.00 7,759.00 1,860.00
8457 C-202-D021 D-211 Diesel Sand Filter 19,500.00 8,700.00 3,162.00

Table 1 – Critical Heavy Equipment

For items that are not able to transport without saddle considered by Contractor and technical
drawings generated by engineering study. All saddle drawings are available on attachments
(Attachment- 5-14) of this document and referenced on below table (Table 2).

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 4/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Length Saddle
T. Dwg No Tag No Item Description Saddle Drawings Reference
(mm) Qty
Attachment-5 TKF-00-PM-
8457 C-202-C001-A C-201 Crude Column 50,136.00 REP-0005 Saddle-1-Rev1 4.00
C201
Attachment-6 TKF-00-PM-
8457 C-202-C005 C-301 Vacuum Column 44,466.00 REP-0005 Saddle-2-Rev1 4.00
C301
Kerosene Attachment-7 TKF-00-PM-
8457 C-202-C002/3 C-202-203 Stripper/Diesel 20,674.00 REP-0005 Saddle-3-Rev1 3.00
Stripper C202-C203
Attachment-8 TKF-00-PM-
Naphtha Sand
8457 C-202-D017 D-207 7,150.00 REP-005 Saddle-4 Rev.0 D- 2.00
Filters
207-Layout1
Attachment-9 TKF-00-PM-
Kerosene Clay
8457 C-202-D019 D-209 A 11,600.00 REP-005 Saddle-5 Rev.0 D- 2.00
Filters
209A-B-Layout1
Attachment-9 TKF-00-PM-
Kerosene Clay
8457 C-202-D019 D-209 B 11,600.00 REP-005 Saddle-5 Rev.0 D- 2.00
Filters
209A-B-Layout1
Attachment-10 TKF-00-PM-
8457 C-202-D020 D-210 Diesel Salt Dryer 9,300.00 REP-005 Saddle-6 Rev.0 D- 2.00
210-Layout1
Attachment-11 TKF-00-PM-
8457 C-202-D018 D-208 Kerosene Salt Dryer 8,400.00 REP-0005 Saddle-7-Rev0 2.00
D208 D-208
Attachment-12 TKF-00-PM-
8457 C-202-D021 D-211 Diesel Sand Filter 8,700.00 REP-0005 Saddle-8-Rev0 2.00
D211 D-211
Attachment-13 TKF-00-PM-
8457 C-202-C004 C-204 AGO Stripper 12,620.00 REP-0005 Saddle-9-Rev1 3.00
C204
MVGO Attachment-14 TKF-00-PM-
8457 C-202-C007/6 C-302-303 Stripper/HVGO 20,950.00 REP-005 Saddle-10 Rev.1 C- 3.00
Stripper 302-303-Layout1

Table 2 – Saddle References

5 PROPOSED HEAVY TRANS PORT ROUTE

The route survey has been focused on the identification of any possible internal heavy transport route
for the equipment listed in Table 1.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 5/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

• Legend
______
Blue Solid Line: Preferred Main Route
______
Yellow Solid Line: Alternative Route
____
Yellow Dotted Line: Secondary Alternative Route
L1 to L16 Red Location Marks: Key Location / Obstruction
Transport height considered as 7 meters;
  Load: 5.5 meters with support saddle
  Trailer: 1 meter
  Turn table: 0.5 meter

Note: Below photos and suggested route shall be read in conjunction with CDU-VDU Route Planned to Socar
HAOR Rev.04 (Attachment-1) of this document.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 6/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Initial obstruction on the Blue line is the pedestrian crossing at location 1 (L1). Space at both ends of the bridge
is wide enough to travel.
Photos below visualize the present condition of the available spaces.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 7/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 1

Option1:

Remove trees
and partially the
property wall at
Nobel Prospekti
at location 1 (L1)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 8/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 2

Option1:

Demolish 50 cm
height wall next
to bridge and
removal of small
trees and
leveling and fill
the railaway
partially. The
railaway shall be
closed/blocked
off during
operations.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 9/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

A new road being constructed connecting Nobel Street to Babek Street. Half of the road is already complete
and in use, it is assumed that the remainder will be complete and operational well before subject transport
operations.

Below photo taken from the Babek Street looking down to the Nobel Street.

Photo 4

Currently
suggested road is
under
construction. As a
second option
Yusif Sәfәrov
kucesi seems
feasible but longer
than this route.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 10/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

As an alternative Yusif Seferov Street can be utilized to reach to Babek Street location 15 (L15) is the
connection to Babek Street with a large area to maneuver. Connection ramp slope and width is convenient.

Below photos visualize the large area to maneuver prior to ramp up to the Babek Street.

Photo 33

Alternate Yusif
Seferov Street
wide view.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 11/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 34

Alternate Yusif
Seferov
connection to
Babek street.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 12/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Overhead power cables zigzag on the Babek Street at location L3. It is observed that current routing from one
side of the road to the other and back is offsetting the existing buildings. Re-routing overhead or underground
will permenantly clear the obstruction.

Photo 7

High voltage
overhead
power lines at
Babәk Street
cross the main
road, cables to
be re-routed
either above or
underground.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 13/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 8

High Voltage
power lines at
Babәk Street.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 14/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Overhead pipelines at location 4 (L4) is the main obstruction on route to HAOR roundabout. Road elevation can
be lowered either temporarily or permanently or the pipes re-routed underground.

Photo 9

HAOR pipelines
crossing Babek
street gradually
lower the road
elevation

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 15/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 10

HAOR pipelines
crossing Babek
street gradually
lower the road
elevation

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 16/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 11

Pipes re-route
from
underground
or
lower the road
elevation
temporarily or
permanently.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 17/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Last overhead obstruction on the Babek Street is the cable crossing at location 5 (L5).
Line elevation is high at opposite side of the road. Travel at opposite direction with temporary power shutdown
only for the travel duration enable safe access through.

Photo 13

Babek street
Location 5
(L5) view

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 18/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 14

Start
traveling at
opposite
direction well
before this
cable
crossing.
Line
elevation
high at
opposite
direction.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 19/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Traveling at opposite direction; soft take-off from Babek street towards the HAOR roundabout at location 6 (L6).

Photo 15

Soft take-off
from Babek
street
towards
HAOR
roundabout
Travel at
opposite
direction

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 20/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 16

Babek street
towards
HAOR
roundabout
Travel at
opposite
direction wide
view.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 21/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Minor cable crossing on the road leading to HAOR roundabout.

Photo 17

Minor Cable
to be lifted or
removed on
location 7 (L7)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 22/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

From Mikayil Aliyev Street onwards refinery is located on the left, optional entrance to be investigated with
Employer.

Photo 18

Piperack 5 m
to be temporary
removed on
location 8 (L8)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 23/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

From Contractor point of view the best option is maneuvering final left turn from Mikayil Aliyev Street
roundabout to equipment final location 9 (L9) and destruction of wall for direct entrance to the CDU/VDU layout. 

Photo 19

Wall to be
demolished
on location 9
(L9)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 24/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

As an alternative the yellow line from location L11 to the left turn towards the refinery no obstructions observed
at Babek Street. After the turn on the road from Babek Street to the refinery plot south-west corner there are
minor pipe and cable crossings to re-route, visualized at the below photos.

Photo 23

Gas pipe 4,5 m


height to be
temporary
removed on
location 11 (L11)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 25/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 24

Telephone
Cable 4,5 m to
be lifted or
removed on
location 12
(L12)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 26/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 26

Telephone
Cable to be
lifted or
removed on
location 13
(L13)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 27/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

On the road parallel to the south wall of the refinery plot there are several piperacks hence Tekfen’s suggestion
is to to open an access through HAOR wall before the first piperack. HAOR internal routes at south west corner
potential entrance to be evaluated.

Photo 28

Option 1
Pipe rack and
pipe line
removed on
location 14
(L14) for
entrance
instead Tekfen
suggested to
demolish wall
to allow the
access of
Heavy
Equipment or
gradually lower
the road
elevation.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 28/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Photo 31

Option 2
Entrance
suggested
demolishing wall
to allow the
access of Heavy
Equipment.
HAOR internal
route from this
point shall be
assessed
further.

6 CONCL USION
Blue route is best feasible and available route with minimum demolishing/re-routing requirement for heavy
equipment transportation arriving to the CDU/VDU layout location and also has an alternative Yellow route
arriving to the southwest corner of the HAOR plot.
Following further consideration of HAOR internal route options, Tekfen will work together with the Employer to
finalize the route and proceed with the preparation work to support permit arrangements and obstacle removal
works in coordination with the local authorities.

7 ATTACHMENTS

All attachments referred below table are integral part of this document.

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 29/30


CDU/VDU RELOCATION
FROM AZERNEFTYAGH TO HEYDAR ALIEV OIL REFINERY

CDU/VDU UNIT TRANSPORT ROUTE REPORT

DOC NO TKF-00-PM-REP-0005

UNIT REV : 0

Page
Item No Document Description File Format
Number
Powepoint
Attachment-1 CDU-VDU Route Planned to Socar HAOR Rev.04 66 Pages
Presentation (.pptx)
TKF-00-PP-PLN-0003-B-Rv.0 - OLD EQUIPMENT Portable Document
Attachment-2 1 Page
LOCATION PLAN Format (.pdf)
Portable Document
Attachment-3 TKF-00-PP-PLN-0003-A-Rv.0 - GENERAL KEY PLAN 1 Page
Format (.pdf)
TKF-00-PP-PLN-0003-C-Rv.0 - NEW EQUIPMENT Portable Document
Attachment-4 1 Page
LOCATION PLAN Format (.pdf)
Portable Document
Attachment-5 TKF-00-PM-REP-0005 Saddle-1-Rev1 C201 1 Page
Format (.pdf)
Portable Document
Attachment-6 TKF-00-PM-REP-0005 Saddle -2-Rev1 C301 1 Page
Format (.pdf)
Portable Document
Attachment-7 TKF-00-PM-REP-0005 Saddle -3-Rev1 C202-C203 1 Page
Format (.pdf)
Portable Document
Attachment-8 TKF-00-PM-REP-005 Saddle -4 Rev.0 D-207-Layout1 1 Page
Format (.pdf)
Portable Document
Attachment-9 TKF-00-PM-REP-005 Saddle -5 Rev.0 D-209A-B-Layout1 1 Page
Format (.pdf)
Portable Document
Attachment-10 TKF-00-PM-REP-005 Saddle -6 Rev.0 D-210-Layout1 1 Page
Format (.pdf)
Portable Document
Attachment-11 TKF-00-PM-REP-0005 Saddle -7-Rev0 D-208 1 Page
Format (.pdf)
Portable Document
Attachment-12 TKF-00-PM-REP-0005 Saddle -8-Rev0 D-211 1 Page
Format (.pdf)
Portable Document
Attachment-13 TKF-00-PM-REP-0005 A Saddle tt-9-Rev1 C-204 1 Page
Format (.pdf)
Portable Document
Attachment-14 TKF-00-PM-REP-005 Saddle -10 Rev.1 C-302-303-Layout1 1 Page
Format (.pdf)

TEKFEN CONSTRUCTION & INSTALLATION CO. INC. 30/30


CDU/VDU Route Planned to Socar HAOR
Location 1 Details main CDU/VDU Route to Socar HAOR
Location 1 (L1) Photos
1
Location 1 (L1) Photos
2
Possible access between the crossing 
and CPC wall
Location 1 (L1) Photos
3
Location 2 Details main CDU/VDU Route to Socar HAOR
Location 2 (L2) Photos
4
New road under construction
Location 2 (L2) Photos
5
Location 2 (L2) Photos
6
New road connection to Babek street
Location 3 Details main CDU/VDU Route to Socar HAOR
Location 3 (L3) Photos
7
Cable zigzag above road
Location 3 (L3) Photos
8
Re‐route cables – above or 
underground
Location 4 Details main CDU/VDU Route to Socar HAOR
Location 4 (L4) Photos
9
HAOR Pipelines crossing Babek street
Location 4 (L4) Photos
10
Location 4 (L4) Photos
11
Location 4 (L4) Photos
Re‐route pipes underground or 12
Lower the road elevation temporarily or permanently
Location 5 Details main CDU/VDU Route to Socar HAOR
Location 5 (L5) Photos
13
Location 5 (L5) Photos
14
Start traveling at opposite direction well before this cable 
crossing. 
Line elevation high at opposite direction.
Location 6 Details main CDU/VDU Route to Socar HAOR
Location 6 (L6) Photos
15
Soft take‐off from Babek street towards HAOR roundabout
Travel at opposite direction
Location 6 (L6) Photos
16
Location 7 Details main CDU/VDU Route to Socar HAOR
Location 7 (L7) Photos
17

Minor cable re‐route
Location 8 Details main CDU/VDU Route to Socar HAOR
Location 8 (L8) Photos
18
Piperack 5 m to be 
temporary removed
Location 9 Details main CDU/VDU Route to Socar HAOR
Location 9 (L9) Photos
19

Final destination is just behind the wall
Location 10 Details Alternate Route to Socar HAOR
Location 10 (L10) Photos
20
Turn towards HAOR roundabout
Location 10 (L10) Photos
21
Minor cable re‐route
Location 11 Details Alternate Route to Socar HAOR
Location 11 (L11) Photos
22

Minor pipe re‐route
Location 11 (L11) Photos
23
Location 12 Details Alternate Route to Socar HAOR
Location 12 (L12) Photos
24
Minor cable re‐route
Location 12 (L12) Photos
25
Location 13 Details Alternate Route to Socar HAOR
Location 13 (L13) Photos
26
Location 13 (L13) Photos
27

Minor cable re‐route
Location 14 Details Alternate Route to Socar HAOR
Location 14 (L14) Photos
28
HAOR piperack
Location 14 (L14) Photos
29
Location 14 (L14) Photos
30
Location 14 (L14) Photos
31
Location 14 (L14) Photos
32
HAOR South‐West corner
potential alternatives to 
be evaluated further.
Location 15 Details Alternate Route to Socar HAOR
Location 15 (L15) Photos
33
Alternate large area to maneuver
Location 15 (L15) Photos
34
Connection to Babek street
Location 16 Details Route Connecting to BWS Route
Location 16 (L16) Photos
35
Pedestrian crossing and cables
Location 16 (L16) Photos
36
Location 17 Details Route Connecting to BWS Route
Location 17 (L17) Photos
37
Cables connecting to a SS
Location 17 (L17) Photos
38
Location 17 (L17) Photos
39
Location 18+ Details Route Connecting to BWS Route
Location 18 (L18) Photos
40
Railway bridge
Location 18 (L18) Photos
41
Location 18 (L18) Photos
42
Location 18+ (L18+) Photos
43
Pedestrian crossing
Location 18+ (L18+) Photos
44
Location 18+ (L18+) Photos
45
Traffic signs
Location 18+ (L18+) Photos
46
Location 18+ (L18+) Photos
47
REFERENCE DRAWINGS Number
GENERAL NOTES
1 19/09/2017 GENERAL REVISION R.S. - N.K. U.M.G.
0 21/08/2017 SKETCH DRAWING R.S. - D.B. U.M.G.
BAKU CDU/VDU PROJECT
UNIT 202
EXISTING CRUDE COLUMN (C-201)
SHIPPING SADDLE SKETCH
- - - - A1 NONE 1
REFERENCE DRAWINGS Number
GENERAL NOTES
1 19.09.2017 GENERAL REVISION EK - NK UMG
0 21.08.2017 SKETCH DRAWING EK - DB UMG
BAKU CDU/VDU PROJECT
UNIT 202
- - - - A1 NONE 1
REFERENCE DRAWINGS Number

GENERAL NOTES

ELEVATION VIEW

0 19.09.2017 SKETCH DRAWING C.A. - N.K. U.M.G.

SHIPPING SADDLE DETAIL (SD-1)


(HOLD) BAKU CDU/VDU PROJECT
UNIT 202

EXISTING NAPHTHA, SAND FILTERS (D-207)


SHIPPING SADDLE SKETCH

435 TKF-00-PM-REP-005 Att-4 - - - - A1 NONE 0


REFERENCE DRAWINGS Number

GENERAL NOTES

ELEVATION VIEW

0 19.09.2017 SKETCH DRAWING C.A. - N.K. U.M.G.

BAKU CDU/VDU PROJECT


UNIT 202

SHIPPING SADDLE DETAIL (SD-1) EXISTING KEROSENE CLAY FILTERS (D-209 A/B)
(HOLD) SHIPPING SADDLE SKETCH

435 TKF-00-PM-REP-005 Att-5 - - - - A1 NONE 0


REFERENCE DRAWINGS Number

GENERAL NOTES

ELEVATION VIEW

0 19.09.2017 SKETCH DRAWING C.A. - N.K. U.M.G.

BAKU CDU/VDU PROJECT


UNIT 202
SHIPPING SADDLE DETAIL (SD-1)
(HOLD)
EXISTING DIESEL SALT DRYER (D-210)
SHIPPING SADDLE SKETCH

435 TKF-00-PM-REP-005 Att-6 - - - - A1 NONE 0


REFERENCE DRAWINGS Number
GENERAL NOTES
1 19/09/2017 GENERAL REVISION R.S. - N.K. U.M.G.
0 21/08/2017 SKETCH DRAWING R.S. - D.B. U.M.G.
BAKU CDU/VDU PROJECT
UNIT 202
EXISTING AGO STRIPPER (C-204)
SHIPPING SADDLE SKETCH
- - - - A1 NONE 1
REFERENCE DRAWINGS Number

GENERAL NOTES

1 19.09.2017 GENERAL REVISIONS C.A. - N.K. U.M.G.


0 21.08.2017 SKETCH DRAWING C.A. - D.B U.M.G.

BAKU CDU/VDU PROJECT


UNIT 202

C-302 EXISTING MVGO STRIPPER


C-303 EXISTING HVGO STRIPPER
SHIPPING SADDLE SKETCH

SHIPPING SADDLE DETAIL (SD-1,SD-2)


(HOLD) 435 TKF-00-PM-REP-005 Att-10 - - - - A1 NONE 1