You are on page 1of 27

NEWSLETTER

AUSTRALIAN CENTRE FOR GEOMECHANICS Vo l u m e N o . 3 3 December 2009

IN THIS EDITION
• Sublevel caving – past and future, Page 1
• In-pit risks, Page 7
• Mine closure planning, Page 11
• Mining-induced seismicity, Page 15
• Tailings disposal, Page 17
• Mine tailing solutions, Page 20
• Increasing value of paste, Page 21
• ACG event schedule, Page 24

First International Seminar on


the Reduction of Risk in the
Management of Tailings The Captain's pit in Malmberget. Photo courtesy of LKAB
and Mine Waste

29 September – 1 October 2010,


Perth, Western Australia
Sublevel caving — past and
Mine Waste 2010 will tackle the full future by William Hustrulid, University of Utah; and the
Colorado School of Mines, USA, and Rudolph Kvapil, USA
range of issues that constitute risks
in the management of mining wastes,
particularly tailings and waste risk.
Introduction and rational way, there are good possibilities
This forum will encourage debate
The sublevel caving technique according to of developing a mining method which can be
amongst practitioners, researchers and
early mining books (Peele, 1918) evolved in applied, technically as well as economically, on
regulators about the key shortcomings
the U.S. from top slicing. It was a logical next any orebody of suitable size, location and rock
in industry’s current understanding
step in the mine geometry scale-up process. mechanical properties.”
of the performance of mining waste
Block caving, in turn, was the logical scale-up In spite of some searching, the modern
storage facilities and associated risks
from sublevel caving. origins of today’s version could not be
faced by owners and operators of these
facilities. Janelid (1972) indicates, “ In the first clearly identified. Possibly it was developed
application of sublevel caving, the ore was not in the iron mines of Sweden. Janelid (1972)
Abstracts due 1 March 2010 drilled and blasted completely between two indicates, “For a long time, sublevel caving was
sublevels, but certain parts were broken by the predominant mining method at Grängesberg.
www.minewaste2010.com induced caving (hence the name sublevel caving). During the last ten years (since about 1960),
As the method is applied today, the whole however, block caving has given 70% of the
The views expressed in this newsletter are those of quantity of ore between the different sublevels production.”
the authors and may not necessarily reflect those is broken (or at least should be) using controlled In 1960, the sublevel caving technique
of the Australian Centre for Geomechanics. drilling and blasting. If this is done in a proper was being used by 19 Swedish mines with a
Continued page 2
Continued from page 1 the economic benefits which can be achieved LKAB being a leader in this regard. Figure
total yearly production of about 9.5 Mton through the development of the correct 3 provides a comparison of the sublevel
(Ohlsson, 1961). Figure 1 is a sketch of method are extraordinarily large.” caving mining geometries appropriate
the method as practiced at LKAB’s Kiruna In Czechoslovakia in 1950, Rudolf for the years 1963, 1983 and 2003 at
Mine at about that point in time. Kvapil was given the task of determining the Kiruna Mine. Some of the important
the causes of problems in bins and silos parameters are tabulated in Table 1.
and, based on this new understanding,
to develop ways of improving their
performance. It was evident to him that it
would first be necessary to determine the
basic gravity flow principles for granular
and coarse materials since they must
be completely different from principles
describing the flow of liquids which were
then available for use. He decided that
the only realistic way to proceed was Figure 3 The sublevel caving geometry at the Kiruna
to construct and test a large number of Mine at three different points in time (Marklund and
Hustrulid, 1995)
models and to make in situ observations.
Many of these models and the knowledge At the Kiruna Mine today the sublevel
Figure 1 Composite section view of the sublevel gained are described in his recent book spacing is 28.5 m. In certain sectors of
caving mine at Kiruna in 1957 Figure 3 The sublevel caving geometry at the Kiruna Mine at three different points
(Kvapil, 2004). In 1965, Kvapil joined Janelid LKAB’s timeMalmberget
(Marklund andMine, the sublevel
Hustrulid, 1995)
The scale was small, certainly by today’s at KTH and began applying the gravity flow spacing is as high as 30 m.
At the Kiruna Mine today the sublevel spacing is 28.5 m. In certain sectors of LKAB’s
standards, with a sublevel spacing of 9 m, a principles gained in the study of bins and
Malmberget Mine, the sublevel spacing is as high as 30 m.
drift size of 5 x 3.5 m, and a sublevel drift silos to sublevel caving. Table 1 Summary of some important
spacing of 10 m centre-to-centre. Figure 2 shows the application ofTable
this1 Summary of some
design important design
parameters parameters
(Marklund and (Marklund and Hustrulid
1995)
As Janelid (1961, 1972) pointed out, type of model to a sublevel cave design. In Hustrulid, 1995)
“Sublevel caving is in many respects simple. It this particular case, the sublevel spacing is Year
can be used in orebodies with very different 12.5 m, the drift dimension is 5 x 3.5 m, Parameter 1963 1983 2003
Drift width (m) 5 5 7
properties and it is easy to mechanize. the sublevel drift spacing is 12 m and the Drift height (m) 3.5 4 5
However, from other points of view such as burden is 2 m. These closely resemble the Sublevel height (m) 9 12 27
recovery, dilution and similar, the method is sublevel dimensions used by the Kiruna Sublevel drift spacing
(m) 10 11 25
unfavorable.The designs which are used and Mine in the early 1980s. It is interesting Blasthole diameter
the measures which can be taken to eliminate to note that the design is based on a (mm) 45 57-76 115
the disadvantages are poorly understood. In drawbody width (WT) to drawpoint width Burden (m) 1.6 1.8 3
Holes/ring 9 9 10
the end of the 1950’s, model tests regarding (WD) ratio of 1.7. Tons/ring (t) 660 1080 9300
gravity flow in material resembling broken Tons/metre of drift
rock were started at the Division of Mining, (t/m) 400 600 3100
the Royal Institute of Technology (KTH) in
Stockholm.The purpose was to study how the Today,push
Today, with the continuing with the continuing
to increase push
mining scale, to
a fundamental question is wheth
geometrical design of various parameters in the gravity flow principles
increase which servedscale,
mining as theadesign basis for the small-scale sublevel
fundamental
caving mine designs of the past can be applied at much larger scales or whether some othe
sublevel caving are influenced by the motion question
approach is required. is whether
This article will providethe gravity
some flow
thinking in that regard.
which is induced in the material when ore principles which served as the design
is loaded in a sublevel drift. Some of these basis for the small-scale sublevel caving
model tests were performed as a part of mine designs of the past can be applied
senior theses and others by assistants and at much larger scales or whether some
research engineers. Model tests and extensive other approach is required. This article will
Figure 2 Application of gravity flow principles to
literature studies on sublevel caving have sublevel caving design (Kvapil,1982, 1992) provide some thinking in that regard.
also been carried out in Kiruna together with Mine marker studies
conducting practical tests underground.The Over the past few years, the scale of
results achieved have been so encouraging that sublevel caving has increased markedly with
continued research work is well justified since

© Copyright 2009. Australian Centre for Geomechanics (ACG), The University of Western Australia (UWA). All rights reserved. No part of this newsletter
may be reproduced, stored or transmitted in any form without the prior written permission of the Australian Centre for Geomechanics, The University of
Western Australia.

The information contained in this newsletter is for general educational and informative purposes only. Except to the extent required by law, UWA and the
ACG make no representations or warranties express or implied as to the accuracy, reliability or completeness of the information contained therein.
To the extent permitted by law, UWA and the ACG exclude all liability for loss or damage of any kind at all (including indirect or consequential loss or
damage) arising from the information in this newsletter or use of such information.You acknowledge that the information provided in this newsletter is
to assist you with undertaking your own enquiries and analyses and that you should seek independent professional advice before acting in reliance on the
information contained therein.

2 Australian Centre for Geomechanics • December 2009 Newsletter


Caving
Mine marker studies area. It was decided to install markers in the the sides of the fan indicating that the ore
fans so one could estimate the ellipsoid of flow was small. On the other hand, a large
It is one thing to study flow principles extraction.” number of markers were recovered from
in a laboratory setting and quite another Figure 5 shows the fan geometry and the central part of the fan indicating that
to show that they apply in the reality of Table 3 summarises some of the important the predominant ore flow pattern was in
a mine setting. One way of doing this is parameters. the center. This type of flow behavior will
through marker studies. Figure 4 shows result in early dilution. Figure 7 shows the
some results from the first marker studies results in Figure 6 in the form of a contour
conducted as part of the overall KTH plot.
sublevel caving research programme
conducted at the Grängesberg iron mine in
central Sweden in the early 1970s.

e thing to study flow principles in a laboratory setting and quite another to show that
ply in the reality of a mine setting. One way of doing this is through marker studies.
4 shows some results from the first marker studies conducted as part of the overall
ublevel caving research programme conducted at the Grängesberg iron mine in central
n in the early 1970s.

Figure 5 Fan geometry for the Kiruna sublevel cave


Figure 5 Fan geometry for the Kiruna sublevel cave
Table 3 Summary of some important
Table 3 Summary of some important factors concerning the Kiruna marker tests
factors concerning the Kiruna marker tests
.
Figure 7 Contour plots showing the percent
Parameter Value recoveries at the different marker positions
Sublevel drift spacing (m) 25
Sublevel spacing (m) 27
Recently, comprehensive marker studies
Hole diameter (mm) 114
have been carried out at the Perseverance
Burden (m) 3
and Ridgeway sublevel caving mines in
Figure 4 Results of the Grängesberg marker tests Sublevel drift width (m) 7
(Janelid, 1972) Australia. At the Perseverance Mine, the
Sublevel drift height (m) 5
overall flow pattern as demonstrated using
4 Results of the Grängesberg marker tests (Janelid, 1972)
Some of the relevant parameters are Front inclination (degrees) 80
the markers is shown in Figure 8. Some of
of the relevant summarised
parameters areinsummarised
Table 2. in Table 2. the important parameters are presented in
Figure 6 shows the results of the Table 4.
2 Design parameters at Grängesberg Figure 6 shows the results of the recovered markers expressed as a percentage of the total
Table 2 Design parameters at Grängesberg recovered markers expressed as a
number of markers installed at each particular
percentage of the totallocation.
number of markers
Parameter Value
Sublevel drift spacing (m) 7 installed at each particular location.
Sublevel spacing (m) 13
Hole diameter (mm) 41
Burden (m) 1.5
Sublevel drift width (m) 3.0 slashed to 3.5
Sublevel drift height (m) 3
Front inclination (degrees) 90

Figure 4, it appears that Figure


From the flow4,width is of thethat
it appears orderthe
of 5flow
m. Since the drift width is
the flow width to drift width ratio is 1.43. Due to the roof curvature, the effective
width is of the order of 5 m. Since the
ion width is somewhat less and the ratio would be corresponding slightly larger.
drift width is 3.5 m, the flow width to
driftforwidth
quite a long time ratio
the next is 1.43.
group Due
of mine to the
marker testsroof
to be performed. As noted by
iro et al (2001)curvature, the effective extraction width
is somewhat less and the ratio would be
ublevel caving layout used at Kiruna has reached dimensions that are far beyond those Figure 8 Section showing the rings with the draw
rmed the basiscorresponding
for the developmentslightly
of thelarger.
early design guidelines. Thus, there was a pattern superimposed. Perseverance Mine
It flow
verify the gravity tookpattern
quite for
a long timelarge
this very for the
sublevel caving area. It was decided
all markers in the
nextfans so oneofcould
group mineestimate
markerthetests
ellipsoid
to beof extraction.”
performed. As noted by Quinteiro et al.
Figure 6 some
Percentage of the recovered markers at a particular position
5 shows the fan geometry and Table 3 summarises of the important parameters.
(2001), “The sublevel caving layout used at “It is one thing to study flow
Kiruna has reached dimensions
It can bethat arethat
seen far only a Figure 6 Percentage
very small numberof the
of recovered
markersmarkers at a
were recovered principles
from inthe
the sides of a laboratory
beyond those that formed particular position
fanthe basis for the
indicating that the ore flow was small. On the other hand, a large number setting and were
of markers quite another to
development of the earlyrecovered
design guidelines.
from the central part of the fan indicating that the predominant ore flowthat
show pattern wasapply in the
they
Thus, there was a need to verify the gravity It can be seen that only a very small reality of a mine setting.”
flow pattern for this very large sublevel caving number of markers were recovered from

Australian Centre for Geomechanics • December 2009 Newsletter 3


omprehensive marker studies have been carried out at the Perseverance and
ublevel cavingSublevel
mines indrift height (m)
Australia. 4.8
At the Perseverance Mine, the overall flow
emonstrated usingFront inclination
the markers is shown in Figure 8. Some of the important
(degrees) 75
are presented in Table 4.
Figure 10 “Silo” type of flow pattern. Kvapil (1955), Janelid and Kapil (1965)
esult from the Ridgeway Mine marker studies is shown in “average”
The Figure 9. Table 5 flow width/drift width ratios (W /W ) for the four cases are
primary f d
s some of the important parameters. summarised in Table 6.
Section showing the rings with the draw pattern superimposed (Perseverance
Table 4 Summary of some important Table6 6AAcomparison
Table comparison of marker
of the the marker flow patterns
flow patterns
factors concerning the Perseverance
ummary of some important factors concerning the Perseverance marker testsDrift width Level Flow width
marker tests
Mine (Wd) interval (Wf) Wf/Wd
Parameter Value
(m) (m) (m)
Sublevel drift spacing (m) 14.5
Grängesberg 3.5 13 4.9 1.4
Sublevel spacing (m) 25
Hole diameter (mm) 102
Kiruna 7 27 10.3* 1.5
Burden (m) 3 Perseverance 5 25 7.1 1.4
Sublevel drift width (m) 5.1
remnants. Its mobility
Ridgeway 5.9 varies 25
with location and10.0
- 30 with time (it changes
1.7 with the
Sublevel drift height (m) 4.8 geometry).
* Arbitrarily taken as the 30% contour
Front inclination
(degrees) 75 Finally,
The Wf /W most rock materials
d ratio of 1.4 – 1.7 seems
upon being
of the blasted
fan which would
is the like
primary to bulk (swell) of
provider
The
to Wf/W
apply for50%.ratioIn
dsmall ofsublevel
scale 1.4 – 1.7caving,
sublevel seems toit apply
caving is the offor small
sublevel
swell space scale
drift
for thesublevel
ore in caving
located at the
the geometries
ring.bottom
As endasof th
An example Table showing markersome
5 summarises recovery
of theat the Ridgeway well as mine.
geometries veryas(After
the large
primary
well asscale. These
veryprovider
large results
of swell
scale. are space
inshown
agreement
for thewith
in Table ore
7, thethe
in early
the
availablering.sublevel
freeAs caving
shown
swell is in Table
esult from the
2009) Ridgeway Mine marker studies is shown in Figure
geometry 9. Table
recommended 5 by Kvapil (see Figure 2) which used 1.7.
s some of the
important parameters concerning the
important parameters.
These free swell is highly mining scale dependent.
results are in agreement with highly mining scale dependent.
Ridgeway marker tests. the early sublevel caving geometry
In retrospect, by
recommended there are(see three reasons
2) why this Tableis a7 very logical
Available “free”result:
swell for the
ummary of Tabledesign
Table Kvapil 7 Available Figure
“free” swell for the different LKAB designs
5 parameters from the
Summary of design Ridgeway Mine
parameters which1.used The1.7.middle holes of the ring are fired first and
different LKAB can make first use of the swell volume
designs
from the Ridgeway Mine offeredthere
In retrospect, by the are underlying
three reasonssublevel drift.
Parameter Value 2. isThe
why this central
a very logical holes are drilled subvertical,Design
result: fairly parallel, "Free" Swell close to one
and relatively
Sublevel drift spacing (m) 14 1. The middle holesThe
another. of the ring is
result area fired
relatively high and 1963uniform specific24.0 charge compared to the
Sublevel spacing (m) 30 first and can make
other holesfirst in theuseround.
of the Thus, one would 1983
expect the best, 17.9 most uniform
Hole diameter (mm) 102 swell volume offered by the underlying
fragmentation. 2003 5.5
Burden (m) 2.6 sublevel drift.
3. The ore material in the central part of the round can make the best use of the effect of
Sublevel drift width (m) 6 2. The central holes are drilled subvertical,
gravity
As the in directing it to the drawpoint.
Sublevel drift height (m) 4.7 fairly parallel, andscale hasclose
relatively increased
to one over the As years
the scale inhas
theincreased
quest toover reduce
the the specific de
As indicated earlier,
available small-scale
free swell hasphysical model test results
correspondingly decreased.have historically
With the played LKAB
current a very d
Front inclination another. The result is a relatively high years in the quest to reduce the specific
important role in the dimensioning of sublevel caves. In the construction of these models, the
(degrees) 80 about
and uniform 5%. charge
specific Since compared
it is located to at development,
the bottom the of the fan, free
available the swell
ore in hasthe near vicin
sand or other material is simply poured into the forms. As such, the properties are uniform
and
the other has a much
holes
the mobilities
in the greater
round. Thus,
are the same
access
one to this
independentcurrent
volume and
correspondingly
of position
the chance
decreased. With tothe
bulk. The ore at th
g the results ofInthe markerthe
reviewing tests from of
results thethe
Grängesberg,
marker Kiruna, Perseverance
would expect
the theand
fan, best,
on themost
otheruniform
hand, has little LKAB within
chance design
to bulk itthe model.
isand
only about
its
In 5%.
a sublevel cave,
mobility is very low
mines, it is interesting
tests from to
thenote that they all
Grängesberg, basically reveal athis
Kiruna, type isofnot the case.
“silo”
fragmentation.
material
All of the material in theSince
flow mobility alone, one would
fan itisisdrilled
expect locatedand blasted.
at the
significant bottom Because
of the of the fan
differences
wn in FigurePerseverance
10, even if the
anddrilling
Ridgewaypattern
mines,extends geometry,
it is far outside
3. The ofore the amount
thematerial
“silo.” in theof explosive/unit
central part of volume
fan, theand orehence
in thethe nearfragmentation varies the mech
vicinity of the drift
in
interesting to note that they all basically throughout
the round between
can fan.the
the make thesand
The best models
ore material
use and
of thein thereality
centre
has a muchparticularly
partgreater
of the fan asand
access the sublevel
tothe
thislower
volume scaleofistheincre
part fan
reveal a type of “silo” flow such as shown has effect ofmarker
a much higher
gravity intest results
specific
directing tohave
itcharge verythat
the than high significance.
at the
and theboundaries
chance to bulk. of the
The ring.
ore atFurthermore,
the the
in Figure 9 even if the drilling pattern “cave” which lies in front of the blasted slice
drawpoint. is an eclectic
extremities of themixture
fan, on the of other
wastehand,
rock and ore
extends far outside of the “silo.” Sublevel
As indicated cave layout
earlier, small-scale physical rules has based
little chance uponto bulkmarker test input
and its mobility is
model test results have historically played very low. Based on material mobility alone,
a very important role in the dimensioning one would expect significant differences
of sublevelBased
caves. Inupon the resultsofof the four
the construction in themarker
mechanics tests,of it appears
flow betweenthat the the Wf can be e
constant times the
these models, the sand or other material iswidth of the W
sand . As a first approximation,
d models and reality, particularly as
simply poured into the forms. As such, the the sublevel scale is increased. Hence,
properties are uniform and Wthe
f = mobilities
(1.4 – 1.7) Wthe d marker test results have very high
are the same independent of position significance.
within the model. In a sublevel cave, this is
Some preliminary design rules Sublevel for initialcave planninglayout arerules
summarised
based below:
not the case. All of the material in the fan
• Sublevel drift
is drilled and blasted. Because of the fan size (width upon(W d ) and
marker height
test (H
input
d ): determined based on e
• Sublevel
geometry, the amount interval (HS): theBased
of explosive/unit theoretical
upon themaximum
results of thevalue
four is based on the
volume and hence the long, straight holes.
fragmentation varies This, in turn,
marker tests,isitbased
appearson thethehole
that diameter
Wf can be (D). T
throughout the fan. based
The oreon recovery
material in theand dilution
expressedconsiderations
as a constant times which are due
the width of to manag
centre part of the fan and the lower part
pulsation. the Wd. As a first approximation,
of the fan has a much higher specific charge
• Hole diameter (D): based on the
than that at the boundaries of the ring.
available drilling equipment
Wf = (1.4 – 1.7) Wd (1)
and the a
long holes.
Furthermore, the “cave” which lies in front
Figure 9 “Silo” type of flow pattern. Kvapil (1955), • isSpacing
of the blasted slice of mixture
an eclectic the sublevel
of drifts
Some(S d):
preliminary design rules for initial
Janelid and Kapil (1965) waste rock and ore remnants.SIts d = (2.4
mobility – 2.7) W
planning
d are summarised below:
varies with location and with time (it • Sublevel
• Ring spacing (burden (B)): based upon the damage drift size (width (Wd) radius
and (Rd) concep
The “average” primary flow width/drift changes with the extraction geometry). height (Hd): determined based on
Hustrulid and Johnson (2008):
width ratios (Wf /Wd) for the four cases Finally, most rock materials upon being equipment.
are summarised in Table 6. blasted would like to bulk (swell) of the • Sublevel interval (HS): the theoretical
order of 50%. In sublevel caving, B it= is2 the
Rd maximum value is based on the ability
Where
sublevel drift located at the bottom end
Pe Exp 2.65
Rd / rh = 20
Pe ANFO ρ rock
4 Australian Centre for Geomechanics • December 2009 Newsletter Rd = damage radius (m)
r = hole radius (m)
available free swell has correspondingly decreased. With the current LKAB design it is only
about 5%. Since it is located at the bottom of the fan, the ore in the near vicinity of the drift
has a much greater access to this volume and the chance to bulk. The ore at the extremities of
the fan, on the other hand, has little chance to bulk and its mobility is very low. Based on

Caving
material mobility alone, one would expect significant differences in the mechanics of flow
between the sand models and reality particularly as the sublevel scale is increased. Hence, the
marker test results have very high significance.

Sublevel cave layout rules based upon marker test input


to drill long, straight holes. This, in turn, Implications for future sublevel caving. However, it is very important that
is based on the hole diameter (D). The
Based upon the results of the four marker tests, it appears caving
that thedesigns
Wf can be expressed as a the undercut be completely formed. The
constant timesactual
the limit
widthis of
based
the on
Wdrecovery and
. As a first approximation, marker studies would indicate that the flow
dilution considerations which are due to The results of the marker studies would stream is much narrower than previously
managing ore/waste
Wf = (1.4 – 1.7) Wd pulsation. suggest that modifications in (1)
some of the thought. If rock mass flow does not occur
• Hole diameter (D): based on the current, very large scale sublevel caving over the full drilled width, the remaining
available
Some preliminary drillingrules
design equipment andplanning
for initial the designs should
are summarised be considered. Assuming
below: portions could form remnants and
ability to charge long holes.
• Sublevel drift size (width (Wd) and height (Hd): determined based onis equipment.
that the drift width not changed, the transmit loads to the production level with
• Spacing of the sublevel drifts (Sd): results suggest
• Sublevel interval (HS): the theoretical maximum value is based on the ability that the sublevel
to drift
drill catastrophic consequences. This means that
spacing should be reduced.
long, straight holes. This, in turn, is based on the hole diameter (D). The actual limit is Presuming current undercut designs based upon front
based on recovery
Sd = (2.4 and– 2.7) Wd considerations
dilution (2) which
that there
are due is no change in the
to managing sublevel
ore/waste caving will have to be re-evaluated.
pulsation. height, this means that the overall mining
Future possibilities to maintain/
• Ring spacing (burden (B)): based scale would decrease and the specific
• Hole diameter (D): based on the available drilling equipment and the ability to charge increase scale
long upon
holes.the damage radius (Rd) concept development would increase. One way of
discussed by Hustrulid and Johnson maintaining the current scale is to increase There are two possibilities, at least, to
• Spacing of the sublevel drifts (Sd):
(2008) the width of the sublevel drift. Figure 10 try and maintain or possibly even grow
Sd = (2.4 – 2.7) Wd (2)
shows one possibility. the scales used today. One possibility
• Ring spacing (burden (B)): based upon the damage radius (Rd) concept discussed by
B = 2 Rd (3) deals with using more of the sublevel drift
Hustrulid and Johnson (2008):
for swell than just that taken by the ore
Where: falling down. This involves changing the
B = 2 Rd (3)
blasting pattern and initiation sequence
Where
so that the ore at the lower part of the
Pe Exp 2.65 (4) ring is propelled far out into the drift. A
Rd / rh = 20 (4)
Pe ANFO ρ rock second possibility which also involves a
change in the blasting is to use the available
RRd ==damage
damage radius
radius (m)
(m) swell space more effectively. This means
rhr =d =hole
hole
radius
radius
(m)
(m) permitting the ore in the lower part of the
PPe Exp ==explosion
h
pressure for the explosive
explosion pressure for the ring to only swell 20%, rather than 50%.
Pexplosive
e ANFO = explosion pressure for ANFO = 1600 MPa
e Exp
This would thereby increase by a factor of
ρrock = rock density (g/cm3)
Pe ANFO = explosion pressure for ANFO = 2.5 the amount of ore in the ring which has
1600 MPa Figure 10 Silo design with super-scale extraction a chance to swell. Accomplishing both of
ρrock = rock density (g/cm3) drifts, patterned after Kvapil (1992) these possibilities should be well within the
2.65 = density of typical rock (g/cm ) 3
This has advantages with respect to the capabilities of electronic detonators with
• Hole toe spacing (ST): based upon the silo shape and the parallel hole drilling. very precise timing.
burden However, one must be concerned with A problem with today’s typical ring
ST = 1.3 B geomechanics issues (drift and brow drilling design is that the hole spacing
• Spacing for parallel holes (SP): based stability). Furthermore, the draw must be changes from very small near the drift to
upon the burden well controlled over the entire face. large at the hole ends. The parallel hole
If one wants to preserve the specific design used in the silo design avoids this
SP = B (5) development ratios in place today, one problem. Without a major change in drift
would need to increase the sublevel width, one is confined to a rather narrow
• Front inclination: 70–80 degrees height. However, this has problems with pattern. Figure 11 shows one possible
(forward) hole deviation, maintenance of long holes, futuristic design involving special drilling
If it is assumed that: charging of very long holes, and dealing technology and the blasting innovations
D = 115 mm with ore/waste pulsation over a much which better use the available “free” swell
Drift dimensions: 7 m wide by 5 m high longer draw duration. This seems like a space.
Explosive: emulsion (Pe Exp = 3900 MPa) very difficult alternative to achieve on a The design presents an opportunity
Rock density = 4.6 g/cm3 day-to-day basis. On this basis, it would to achieve improved fragmentation, an
Sublevel interval: 25 m based on drilling seem that in the future mining companies increase in ore mobility, and a more
ability and control of pulsation will be looking toward smaller scale designs uniform distribution of ore mobility over a
One finds that the remaining dimensions than today and not larger. The current very much wider front. An understanding of how
are: large-scale designs may actually be too the ore actually flows in sublevel caving will
Sublevel drift spacing: 17–19 m large-scale. lead to better designs. The marker studies
Burden: 2.7 m are an important step along that path.
Front caving implications
Toe spacing (fanned): 3.5 m
Toe spacing (parallel): 3 m This article has only dealt with standard “The results of the marker
Front inclination: 80o selected sublevel caving. There are a number of
studies would suggest that
It is noted that the new sublevel drift variants, however. Front caving is a variety
modifications in some of
spacing rule has very limited basis and must of the sublevel caving technique which is
be carefully complemented with further quite often used. It is, for example, a very the current, very large scale
testing. interesting technique for the creation of sublevel caving designs
the undercut required in block and panel should be considered.”

Australian Centre for Geomechanics • December 2009 Newsletter 5


5 th
International Seminar on
Deep and High Stress Mining
6–8 October | Santiago - CHILE

Figure 11 New possibilities for large-scale sublevel caving


2010
Pontificia Universidad Católica
Future studies Acknowledgement de Chile, in collaboration
In closing, the authors believe that This edited article is from the paper with the Australian Centre for
it is time to seriously revisit the entitled, “Sublevel caving - past and Geomechanics, the University
recommendation made by Janelid (1961) present” featured in the proceedings of of Toronto, and the University of
nearly 50 years ago with regard to small- the 5th International Conference and Witwatersrand, is organising an
scale sublevel caving,“The results achieved Exhibition on Mass Mining, Lulea, Sweden, International Seminar on Deep
have been so encouraging that continued 9–11 June 2008. and High Stress Mining.
research work is well justified since the As the mining industry
economic benefits which can be achieved faces new challenges to
through the development of the correct extract mineral resources at
method are extraordinarily large.” William Hustrulid increasing depths, the Deep
In spite of their obvious value, field University of Utah; and Mining International Seminar
the Colorado School of series provides a forum for
studies are few and far between in the
Mines, USA
mining business. In addition, if conducted, the industry, academics
it is very difficult for others to access the and researchers to share
results and perhaps gain and offer new information, experience and
insights. This must change if the mining ideas on deep and high stress
business is to meet the technical, economic mining.
and safety challenges the future has to offer. For more details contact
There is a real danger that today’s
sublevel caving designs are far from CAVING deepmining2010@ing.puc.
cl or visit http://web.ing.puc.

2010
optimum due to a poor understanding cl/~deepmining2010/
of the fundamental processes involved.
In the past, the application of sublevel
caving has primarily been to iron ore,
particularly magnetite, which because of its Second International Collaborating Organisations
very forgiving magnetic property, permits Symposium on Block and
easy and inexpensive separation from the
Sublevel Caving
waste. The same is not true with other
minerals, for example copper porphyry and 20–22 April 2010,
gold ores. For these, it is very expensive Novotel Langley Hotel,
to separate ore and waste. It would Perth, Australia
appear that prior to fully committing to
any sublevel caving design, a pilot project
The growing popularity of caving
should be run with a carefully planned and methods around the world is largely
executed program of data collection. One due to the very low production cost
very important piece of information to and the intrinsic safety associated
be extracted is the draw width. It is also with this mining approach. More
very important to develop the required than 50 technical papers are
draw control techniques to be applied in expected to be presented at this
the mine. Ore/waste pulsation, which is three day event.
inherent in very high draw designs, makes
practical draw control very difficult.Visual www.caving2010.com
viewing of the cave front is not enough.

6 Australian Centre for Geomechanics • December 2009 Newsletter


Open pit
orebody that was deposited as an evaporate

The changing profile of risk associated


with in-pit placement of waste
by Raymond Yost, Rio Tinto Minerals – Boron Operations, USA

Introduction article is to discuss the background to that foundation material (basalt), generally
work, the nature of the risk analysis and results in factors of safety well in excess
Risk, risk assessment and risk analysis assessment, and to present preliminary of industry required limits. Furthermore,
have a number of meanings across a range results. the mineralised zone at the site is confined
of disciplines. At the most fundamental, to a single geologic unit. Extraction of
Background and site characterisation
risk is simply a combination of uncertainty the borate layer represents complete
in an outcome and consequences for that The Boron open pit mine is located extraction of the resource, so dumping
outcome. Risk analysis or risk assessment near the town of Boron, California in the over mined out areas does not present
is the process of identifying, quantifying, Mojave Desert Geologic Province. The any risk of covering potentially economic
and communicating those uncertainties mining operation extracts borates from mineralised zones. The north slope of the
and outcomes. In geological engineering, a lenticular orebody that was deposited pit was therefore an attractive option
risk has traditionally been tied to the as an evaporite and is encased in layers for overburden disposal given that it was
calculation of a factor of safety of a slope, of low permeability claystone. The clay stable, composed of a higher strength unit,
or potential failure geometry, and has and borate sequence is bounded on the and close to active mining operations. A
historically been a qualitative assessment bottom by a layer of basalt, which is in risk assessment was conducted prior to
of a calculated value. Advances in the turn underlain by feldspar-rich sandstone the large-scale placement of overburden on
computational power of stability analysis (arkose) with interbeds of clayey sand (the the slope.
software programs have set the stage for Tropico Formation). Poorly to moderately
more quantitative assessments. Depending consolidated and cemented arkose covers Structure of the risk assessment and
on the scale of the slope under evaluation, the borate and clay sequence. An intrusive input variables
and given the variation inherent in earth body, composed primarily of quartz Mining in the most general sense,
materials in general, almost every input monzonite, bounds the deposit to the balances two basic elements – benefits
can be considered to vary over a range of south. realised against the potential for loss. In
potential values. The sequence of Tropico-basalt- this case, they have been incorporated
As such, risk assessment in geological evaporites-sediments has been tilted and into the risk assessment. Benefits are
engineering often considers both aleatory dips moderately; 5 to 15° to the south. realised if the ground and overburden
uncertainty - the variability inherent to Faulting has offset the orebody into three dump remain stable throughout the project
natural materials, and epistemic uncertainty primary components and a number of life and costs are incurred if they do not.
- the variability related to the ability to sub-blocks. Evaluating risk in this case is therefore a
model a phenomenon. It is uncommon, The open pit operation was initiated in matter of determining the potential for
however, that risk assessment considers a the late 1950s in the northwestern portion slope instability along with the values
temporal element, i.e. how the inputs, and of the deposit where the borate layer was of the benefits and costs. Stability is a
therefore the associated risk, change with generally closest to the surface. Over the function of the geology, the potential
time. To an extent this is to be expected past 60 years, the pit has expanded to the for a seismic event, the pore pressure,
as many inputs do not significantly change south and east and has deepened as the the size of the dumped volume and the
over the course of a project life. However, higher elevation ores have been mined out. slope configuration. While some of these
elements such as pore pressure, the surface Slope failures that have occurred during variables remain constant over the project
topography of an excavation, the weight open pit mining operations typically form life, most of them change to a large enough
distribution on a potential failure plane, due to a combination of pore pressure, degree that they affect the probability of a
the probability of a seismic event and the high-angle faults (which act as a back plane) slope failure. A thorough risk assessment
properties of low strength materials can and low-strength beds of clayey sand or therefore requires an evaluation of
all change to a magnitude that materially claystone. All of the open pit slopes are conditions through the full time line of the
affects the outcome of a risk analysis. No designed in recognition of these variables. project.
attempt has been made in this assessment The design of the north wall, however, The risk assessment was structured to
to look at equipment or personnel is also governed by the orientation of evaluate the potential for slope failure.
temporal exposure. the orebody. As offset on most faults is The risk through time was quantified via
To evaluate the effect of the aleatory, relatively minimal, the overall slope of a series of steps to establish a probability
epistemic and temporal variation, research the wall generally follows the overall of failure, determine the magnitude of
was conducted at the Rio Tinto Minerals orientation of the orebody. potential negative outcomes and model the
– Boron Operations open pit mine near The overall slope angle of the wall, expected values. Specific tasks included:
Boron, California. The purpose of this in conjunction with the strength of the

Australian Centre for Geomechanics • December 2009 Newsletter 7


1) Estimating the probability of an outcome
(a slope failure) through the use of
limit equilibrium analysis and statistical
sampling of analysis inputs.
2) Estimating the likely extent of negative
results (failure clean-up) through the
use of numerical and empirical methods
Figure 1 Pit topography at year 2010
to develop a model of post-failure
topography. • Probability of failure – 5.0% (with seismic load).
3) Estimating the likely extent of positive • Probability of failure – 0.55% (without seismic load).
results (savings associated with dumping • Failure volume (in section) 28,350 m3 (with seismic load).
near the area of extraction as opposed • Failure volume (in section) 28,700 m3 (without seismic load).
to ex-pit dumps) through an evaluation • Probability of seismic event – 5.0%.
of equivalent tonne miles (ETM).
4) Using the probability of an outcome At this beginning stage, ore (blue and green units) is close to the toe of potential
and the estimated costs and benefits to failure and subject to burial should failure occur. Failure volume is relatively high, but
establish expected costs and benefits the probability of failure is relatively low. The probability of a seismic event occurring is
with time. relatively low.
5) Adjusting the timing of benefits and costs
(benefits are expected to be realised
early while costs are expected to be
realised later) with a discount rate.
6) Estimating a net expected sum of
benefits at distinct points.

Once these values were estimated,


the risk was determined as the net sum Figure 2 Pit topography for ultimate pit
of expected benefits and costs. A value
greater than zero implied that the outcome • Probability of failure – 81.20% (with seismic load).
had a positive expected economic value, • Probability of failure – 41.60% (without seismic load).
while a net sum of less than or equal • Failure volume (in section) 39,500 m3 (with seismic load).
to one implies that the outcome had a • Failure volume (in section) 39,250 m3 (without seismic load).
negative expected economic value and a • Probability of seismic event – 70.0%.
negative risk. The evaluation was repeated
at appropriate time increments for a range At this final stage, failure volume increased by approximately 40%, but the probability of
of in-pit dump volumes to determine if, and failure increased, on average, to approximately 60%. The potential for a seismic event has
how much, waste could be economically increased as well, but the ore zone is farther away from the toe of slope and is less likely to
placed in the pit. be covered by a slope failure.
Results Modelling post-failure runout

To illustrate the interplay of the A combination of numerical modelling and empirical evaluation was used to develop
various inputs to the risk assessment, potential post-failure topography. Post-failure profiles were developed for all sections with a
the start and end points of one of the probability of failure greater than 0.01% regardless of the factor of safety. The configuration
analyses are presented in Figure 1, from of the runout was based on an assessment of historical slope failures at the site. At Boron
the limit equilibrium analysis through this was the angle of repose of the failed material relative to the dip angle of the underlying
empirical modelling, to the final economic failure plane, and adjusted for the geometry of the runout area.
assessment for a 30 million t in-pit waste
dump.

“Risk in the most general sense,


balances two basic elements Figure 3 Topography for failure at 2010 for 30 million tonne dump
– benefits realised against the
potential for loss.” The ratio of the clean-up area to the post-failure area is 18.5%. The runout was contained
to some extent by the concave geometry of runout area resulting in a low overall angle of
repose.

8 Australian Centre for Geomechanics • December 2009 Newsletter


horizontally. By determining the total ETMs necessary to move a quantity o
ex-pit location versus an in-pit location, a difference in the hauling effort co

Open pit
determined. That difference, along with a unit cost of an ETM, obtained by
total haul costs for a unit time period by the total ETMs for that time period
be used to determine a total value. That total value divided by the quantity o
tonnes) was used as the estimate for the unit ton value of in-pit dumping. Th
below illustrates the concept for the difference between hauling 100 million
a northern dump versus an in-pit dump.
At the other end, the clean-up costs
[(ETM north – ETM
can include thosein-pit ) * $/ETM]/100
charges along with amillion t =
average unit value
range of fees associated within-pit
realised by hauling to dump versus north d
consulting,
additional equipment, accelerating stripping
To establish the cost oftofailure clean-up,
continue mining records
in otherfrom partsthe 1997-1998 slope f
of the
Figure 4 Topography for failure at ultimate pit for 30 million tonne dump reviewed. Despite extensive documentation,
site, overtime there is still
costs, contracting andconsiderable
leased variat
constitutes ‘clean-up’ costs. On one end of the spectrum,
equipment. Based on the previous two the costs can be m
labor and
The ratio of the clean-up area to the post-failure area is 22.5%. The removal of material
equipment charges associated with removing
assessments, a range of values was obtained
the portion of failure
necessary to re-establish
below the toe of failure has allowed considerable runout. The overall angle of repose has
access into a mining area or to uncover buried ore
for both the unit cost of cleaning up a
the other end, the clean-up costs can include those charges along with a rang
increased. tonne of failure debris and the unit value of
associated with consulting, additional equipment, accelerating stripping to c
Benefits and costs dumping a tonne of overburden in the pit.
mining in other parts of the site, overtime costs, contracting and leased equi
Assessing benefits and costs began with establishing values for dumping a on unitthe
of previous Economics ofa in-pit
waste in two assessments, rangedumping
of values was obtained for both th
cleaning up
the pit and for cleaning up a unit of failure debris from the pit. The value of dumping tonnes a tonne of failure debris and the unit value of dumping a tonne o
The final step was to use weighted (by
in the
in the pit is a function of reducing both horizontal and vertical haul distances. pit.
Reducing the probability of a seismic event) average
the haul distance generally means that additional truck hours are available. These truck values for the expected volume of failure
hours are either used to haul additional waste, or, if enough truck hours are offsetEconomics
by the of In-Pit Dumping
debris, the expected value of the volume
short hauls, a truck(s) could be parked. The difference in either case is reflected by overall of material that would have to be cleaned
lower haulage costs. The problem lies in translating these lower overall costs Theintofinalwhat
stepthe
was to use weighted (by the probability of a seismic event) av
up, and the associated expected costs and
specific unit cost difference is for dumping a portion of the waste in the pit forversus
the expected
hauling volume of failure debris, the expected value of the volume
benefits with time.Values of benefits and
all waste outside of the pit. that would have to be cleaned up, and the associated expected costs and ben
costs were shifted with time by using a
time. Values of benefits and costs were shifted with time by using a discoun
To accomplish this, it was necessary to evaluate haul costs with a unit that accounted discount/interest rate of 7%.
of 7%.
for both the difference in horizontal and vertical travel distances associated with hauling
to a site outside of the pit, versus hauling to a site inside the pit. The value used was the Table 1 Summary of benefits and costs
Table 1 Summary of benefits and costs shifted with time
ETM, which assumes a difference in hauling effort for moving a unit of waste vertically shifted with time
versus horizontally. By determining the total ETMs necessary to move a quantity of waste DIFFERENCE
DUMP SIZE
to an ex-pit location versus an in-pit location, a difference in the hauling effort could be YEAR (TONNES) H/L L/H
determined. That difference, along with a unit cost of an ETM, obtained by dividing the total 2010 30,000,000 positive positive
haul costs for a unit time period by the total ETMs for that time period, could then be used 2015 30,000,000 positive positive
to determine a total value. That total value divided by the quantity of waste (in tonnes) was 2020 30,000,000 positive positive
used as the estimate for the unit ton value of in-pit dumping. The formula below illustrates 2032 30,000,000 positive positive
the concept for the difference between hauling 100 million t of waste to a northern dump 2036 30,000,000 negative negative
versus an in-pit dump.
The negative values in the Thefinal row indicate
negative values inthat
the for
finalthe difference between
row
[(ETMnorth – ETMin-pit) * $/ETM]/100 million t = expected benefits and low expected
indicate costs
that for the(H/L) (bestbetween
difference case), and the low exp
average unit value realised by hauling to in-pit dump versus north and dump
high expected coststhe L/H
high(worst case),
expected the dump
benefits and size
low of 30 million t is no
design in this case. expected costs (H/L) (best case), and the
To establish the cost of failure clean-up, records from the 1997-1998 slope failure were low expected benefits and high expected
reviewed. Despite extensive documentation, there is still considerable variation in what costs L/H (worst case), the dump size of 30
constitutes ‘clean-up’ costs. On one end of the spectrum, the costs can be merely the labor million t is not a feasible design in this case.
and equipment charges associated with removing the portion of failure debris necessary to This method of risk assessment has
re-establish access into a mining area or to uncover buried ore reserves. helped Rio Tinto to understand the
interplay of a number of variables that
influence the risk associated with placing
overburden on the north slope of the open
pit. While the 30 million t dump option
proved to not be an economically feasible
option, other volumes evaluated in the
course of research do have positive values
throughout the mine life. The methodology
Article references are available from the ACG.

described here has allowed Rio Tinto


Minerals to identify those cases and
proactively manage risk in the present and
throughout the life of the project.

Ray Yost,
Rio Tinto Minerals -
Boron Operations,
USA
Rio Tinto’s Boron open pit operation was initiated in the 1950s

Australian Centre for Geomechanics • December 2009 Newsletter 9


ACG Open Pit Rock Mass
Seventh Large Open Pit Modelling Seminar
Mining Conference 2010 29–30 July 2010, Burswood
Convention Centre, Perth
27–28 July 2010, Perth, Western Australia This seminar will maximise the
dissemination of geotechnical rock mass
High demand for commodities, record fuel prices and a scarcity of skilled personnel modelling and synthetic rock modelling
have been replaced and surpassed by the recent global financial crisis as the primary technologies to industry.
issues facing the mining industry. As demand for commodities improves the incentive
to continue to drive operational and safety improvements will become paramount. The trend of open pit operations
The Seventh Large Open Pit Mining Conference 2010 (LOP 2010) will provide the mining to steeper and deeper levels
opportunity to chart that progress in large open pit mines around the world has seen an increase in the stress
environment and greater uncertainty
The conference will provide the forum for operations with major achievements, along about the mechanical behaviour of
with those operators implementing changes, the chance to outline their innovations slopes, elevating mine worker safety
and to share and explore experiences with others. Consistent with the aims of The and productivity risks. To better
AusIMM, the Conference will allow members and the industry to keep abreast of identify, understand and manage these
technical developments and provide a forum to share views and opinions within the potential geotechnical risks (including
large open pit sector. seismic hazard) associated with slope
stability failure, the ACG will host this
For more information, please contact: two day seminar immediately following
Katy Andrews, The AusIMM The AusIMM’s Seventh Large Open Pit
Phone: +61 3 9658 6125 Mining Conference 2010.
Fax: +61 3 9662 3662
kandrews@ausimm.com.au Please visit,
www.acg.uwa.edu.au/events_courses

CSIRO helps redefine large


open pit design
PUBLISHING

Many of the uncertainties surrounding The new Guidelines For Open Pit Slope innovative mining geomechanics research
the development of a large open pit Design was officially released at the Slope with best practice” he said. “The book
mine have now been overcome with the Stability conference in Santiago, Chile, outlines for today’s practitioners what
publication of the 496-page “Guidelines 9 November. It is a direct outcome of works best in different situations and
For Open Pit Slope Design”. the “Large Open Pit” research project why, what doesn’t work and why not, and
The publication is the result of four and comprises 14 chapters that follow what is the best approach to satisfy best
years of effort and support from a group the life of mine sequence from project practice in a range of situations.”
of 12 mining companies representing the development to closure. Guidelines For Open Pit Slope Design
majority of the world’s production of CSIRO Earth Science and Resource is available from CSIRO publishing for
diamonds and base metals. Engineering’s Dr John Read is one of two AU$195. www.publish.csiro.au/
Open pit mining is an efficient way editors and has also authored a number of
to mine many deposits. But there are chapters in the book.
complications. Make the slope of the Dr Read has over 40 years experience
pit too shallow and you have to move as a practitioner and consultant in the
millions of additional tonnes of valueless mining industry, with special interests and
overburden. But if it’s too steep, you risk expertise in rock slope stability and open
failure with subsequent risk to people and pit mine design and investigation tasks in
property. Australia, Fiji, Papua New Guinea, Brazil,
Up until now, the only handbook of Argentina, Chile, Canada, South Africa and
this type available to open pit mine slope Zambia.
design practitioners, including engineering He says that each chapter is written
geologists, geotechnical engineers, by an industry practitioner with specific
mining engineers, civil engineers and experience in the topic being described.
mine managers has been the “CANMET “The purpose of the book is to be
manual” last published in 1977. a new generation guideline that links

10 Australian Centre for Geomechanics • December 2009 Newsletter


Mine closure
Mine closure planning in South America
by Hugo Rojas,Teck Resources, Chile; and Roger Higgins, Teck Resources, Canada

The Chilean town of Andacollo and Teck's Carmen de Andacollo mine are close neighbours.This leads to a very close relationship between the community, for both
operations and closure planning

Introduction
desertification and new environmental started operations before the Base Law
Mining is an important activity in standards have demanded a new way of the Environment Nr. 19300 (1997) and
the economy of many South American of mining. This includes social and Regulations of the Environmental Impact
countries. It is predominantly a formal environmental impact studies and closure Assessment System were enacted.
sector, regulated and facilitated by laws and plans that are developed from the time With respect to financial guarantees,
regulations; it is also a leading contributor when a mining project commences. mining companies have to provide these
of export earnings that is integrated into This article presents for comparison the in annual instalments, over a period of five
the global economy. The contribution of most important elements of mine closure years, or during the period of remaining
the mining sector can represent up to standards in Chile, Argentina and Peru. mine life (if this is shorter).
10% of the gross domestic product and
Mine closure legal framework Argentina
over 50% of the value of all exports of a
country with a strong and predominant Chile The law on environmental protection
mining sector. Mining has a multiplier effect On 7 February 2004, modifications to for mining activity and its supplementary
- generating synergies with other economic mining safety regulations came into force regulations does not contain specific
and social sectors in the community and in Chile, establishing an obligation for all regulations for mining companies to submit
region where it was developed. mines to prepare closure plans within abandonment and closure plans for the
However, society does not always have a five years. The objective is… “to prevent, approval of authorities. This matter is open
good perception of the mining industry. In minimize and/or control the risks and to different interpretations.
part, this may be due to the environmental negative effects that might result from or According to the Second Section of the
liabilities left behind by legacy mining continue to take place after the cessation Complementary Title, the following must
sites that date back to times when there of the operations of a mine site, in the be considered:
was neither awareness of the impact that life and integrity of the people working a) Environmental impact: modification of
mining can have, nor a “modern” legal there, and of those who, under defined and the environment, whether beneficial or
and supervising framework. Until recently, specific circumstances, are related to the detrimental, direct or indirect, temporary
regulations requiring companies to prepare operation and are within the influence of or permanent, reversible or irreversible,
abandonment and closure plans were its facilities and infrastructure”. may be potentially caused by mining
largely absent. In 2009, draft law addresses the closure activity.
The world has changed and the scope of mine facilities and sites of the b) Environmental impact report: a
requirements for mining projects are extractive mining industry. This draft document that describes a mining
evolving. Compliance with international legislation differentiates between those project, the environment where it is
agreements, such as those of biological projects that have an environmental developed, the environmental impact
diversity, community engagement, resolution and those that do not. The it will cause and the environmental
climate change, and the struggle against second group are those mines that protection measures proposed for

Australian Centre for Geomechanics • December 2009 Newsletter 11


adoption. The EIR must address and periods for review, updating and
“measures and actions for prevention accountability.
and mitigation of environmental
Observations
impact, and rehabilitation, restoration
or recomposition of the altered • The legal norms of closure plans in
environment”. South America differ in their scope,
c) Environmental impact declaration: depth and citizen involvement. This leads
an administrative act based on the to different requirements for mining
mining environmental standards in operations of similar characteristics.
force, approving an EIR, passed by the • The review and update of closure plans
application authority, and in which are is a matter of interest for governments,
set the specific conditions that the as well as for organised communities and
holder company must comply with mining companies.
during all stages of the mining project. • Even where there is a deficiency in the
An aspect that is not regulated in law regarding mine site closure, there are
Argentina is community involvement in companies that progressively design and
the approval process of an EIR. apply high quality closure plans.
• The design of closure plans in
Peru
engineering stages prior to the
Peru applies regulations for mine closure construction of projects and their These proceedings are a hard-bound, black
and white publication featuring 53 papers,
to every mining activity, with the purpose application from the beginning of the comprising 622 pages.
of preventing, minimising and controlling its operations, represent an advantage
potential risks and effects to human health, for companies and should be seen as www.acg.uwa.edu.au/shop
safety, the environment, the surrounding an opportunity to prevent, minimise
ecosystem and property. The regulations and control risks and negative effects
were passed in 2005, and the articles that might occur after the end of the
clearly specify when and what details must operations.
be presented to the Director General • The globalisation of markets,
of Mining Environmental Affairs of the the requirement to comply with
Ministry of Energy and Mines. international norms and standards, 5th International Conference on
The mine closure plan complements the the exchange and development of Mine Closure
study of environmental impact and the technical knowledge, together with open
programme of environmental management communication channels worldwide, 23-26 November 2010
corresponding to a site’s operations. will result in the further evolution of Casa Piedra Events Centre
The filing of the mine closure plan is an mine closure regulations, both legal and Santiago, Chile

obligation for every owner of mining self-imposed. This will improve mining
activity that is in operation, beginning processes and practices, environmental RESPONSIBLE CLOSURE: LIVING
mining operations or resuming mining stewardship and the efficient use of UP TO COMMUNITIES’ AND
operations — after having been suspended resources. STAKEHOLDERS’ EXPECTATIONS
or stopped by the validity of the law, • The voices and actions of communities CONFERENCE THEMES
or where there is no an approved mine that feel affected by mining will continue
closure plan. to grow, and constructive relationships • Designing and planning for closure
The approval of a mine closure plan leads with communities will be vital. • Progressive closure planning
to the constitution of guarantees through • A good closure plan will contribute to • Closure costs and financing
which assurance is given that the owner obtaining and maintaining the social • Proactive stakeholder engagement
of a mining activity can comply with the licence to operate. • Long term water management
obligations stated in the mine closure plan. • Mine site reclamation and rehabilitation
In the event of a breach, the Ministry of • Control and monitoring
Energy and Mines can execute the closure • Soil ecology
tasks. • Mine cluster, redeployment,
An important aspect of the regulations redevelopment and decommissioning
is the provision that allows citizen • Mine legacies and relinquishment
involvement. Every stakeholder can present Hugo Rojas, • Legal and regulatory issues
Teck Resources, Chile
their observations and make contributions. • Mining heritage and tourism
Once the closure plan is approved, it is • Recent closure case studies
to be executed in a progressive manner
during the life of the mining operation. At Send your abstracts by 25 January 2010 to:
operation end, the remainder of the areas, mc@mineclosure2010.com
works and facilities that, due to operational
Roger Higgins, For further information, please visit:
reasons had not been closed during the Teck Resources, Canada
production stage must be closed. The
regulations also establish mechanisms
www.mineclosure2010.com

12 Australian Centre for Geomechanics • December 2009 Newsletter


Underground
The student chosen to undertake the project was Natalie Kari, a 3rd year mining engineering
student at Laurentian University. While Marty provided supervising guidance from afar, a site
based introduction to the use of MS-RAP was provided by Johan Wesseloo, ACG. Natalie
was technically an employee of Allstate Explorations NL during her time at Beaconsfield, and

Summer vacation students in winter as such she technically reported to myself.

Natalie provided the Beaconsfield Gold Mine with a substantial analysis of its seismic data,
by Peter Hills,Tasmania Mine
particularly Joint
that Venture,
collected overBCD Resources
the 18 (Operations)
month period NL when stoping had
to June 2009
recommenced in earnest following the 2006 accident. The database remained live for much
of her stay, allowing Natalie to observe and understand all the aspects of data capture
A phone call from Professor Marty through the ISSI
Management system,
Plan. The ACG its software
transfer MS-RAP
to MS-RAP, offeredandtheitsopportunity
analysis as to an immediate
enhance the tool
through Omori Analysis after stope blasts, and as a longer term management tool in updating
Hudyma in February 2009 was my management of seismicity in the day-to-day operation of the mine.
EVP maps. She expended a significant effort in analysing data to assist in the refinement of
introduction to the idea of offering Following
re-entry an accident
protocols, and theatlatter
the mine in early
formed 2006,ofallher
the basis aspects of the mining
final report. operation
A synopsis were
of that report
summer vacation experience to students redesigned
follows under the
this article. Theumbrella of a Case to Manage
key to understanding Underground
the basis Safety
of a detailed (oranalysis
data Case forsuch as
during the winter. The concept had real Safety).
Natalie The Casecan
performed for only
Safetybewas developed
gained in four tranches
by observing by Coffey from
the environment Mining, and covered
which the data is
merit. We had engaged summer students obtain.
mining ofConsequently, she went
capital and operating underground
access development to (Pfitzner,
inspect 2006),
the geotechnical environment
sill driving (Sidea, Scott
at Beaconsfield before with somewhat regularly, and2007),
and Reeves, everystoping
effort inwas made toaseismic
the generally introduceeast her
zonetoof as
the many facets
mine (King, of mining
Thomas
mixed results. This is not usually a measure geomechanics at Beaconsfield
and Scott, 2007), and stoping inasthe possible. Asactive
seismically a result,
westthezonereport
where she theultimately produced
most significant
has real practical application in the ongoing management of seismicity at the mine.
of the desire of the student to “have a changes were required (Scott and Reeves, 2007). A key requirement of the Case for Safety
go”, but rather it is the coincidence of was the establishment of protocols to manage seismicity, and MS-RAP was a key tool in that
The experience of hosting a project focused summer vacation student was a positive one for
the engagement with permanent staff endeavour.
the Beaconsfield Gold Mine. Our continued use of MS-RAP as a tool in the management of
wanting to take annual leave. Inevitably, Hills and
seismicity hasPenney (2008) describe
been enhanced the management
as a result. of seismicity
The fact that the summerat thevacation
Beaconsfield
student came
the students are slotted in to fill the roles in Gold Mine when
the winter in some detail. was
vacation Of particular utilityofwithin
not the focus MS-RAP
mine staff was isa the ability to
significant implement
factor in ensuring
of absent staff, while receiving insufficient Omori
that Analysis
maximum (Figure
benefit 1) to
could bemonitor
obtainedand
bymanage re-entry
all parties times into
concerned. areas excluded
In particular, after to
the benefit
guidance and mentoring from remaining thestope
students ofSeismic
blasts. early career international
analysis is coupled experience
with intensive cannot be over-emphasised.
monitoring (Figure 2) (Penny, Hills
staff who are left to carry the burden. and Walton, 2008), including stress change using H1 cells, and the impact of that change
Furthermore, summer vacation students Article
on thereferences
rock mass are
and available
the installedonsupport
requestusing SMART instruments. Stope blasting is a
often simply want a job to earn some key trigger for stress change (Figure 3), and as a consequence it is the primary trigger for
money and gain some experience. Marty, seismic activity.
however, was keen to see a student
undertake a project and complete real
work. The project was to be titled
Retrospective Analysis of Mining Induced
Seismicity at Beaconsfield Gold Mine. It
seemed ideal. A summer vacation student
with a defined project, arriving in the
winter when minimal leave was planned
by site personnel would avoid all the usual
pitfalls of a summer placement, and so
it was agreed that a placement could be
made.
The Beaconsfield Gold Mine has
experienced seismicity since 2003.
Increasing incidents of seismic events saw
the installation of a temporary seismic
array logging six uniaxial channels in
early 2004, and this was replaced by a
Figure
Figure1. Omorianalysis
1 Omori Analysis following
following a stopeablast
stope blast
permanent array logging 12 channels (nine
uniaxial and one triaxial) in mid 2005. The
system was upgraded in 2007 and again in
2009, and currently logs 24 channels (12
uniaxial and four triaxial).
In late 2005, the Beaconsfield Gold Mine
signed on to be a minor sponsor of the
ACG’s Mine Seismicity and Rockburst
Risk Management project. Sponsorship
commenced from January 2006 and has
continued since then. At the time of the
original sponsorship, the Beaconsfield Gold
Mine had been experiencing significant
mining-induced seismicity for a period
of two years. Much effort had been
expended on developing an understanding
of the seismicity and procedures to deal
with it were being implemented through
the development of a Ground Control Figure 2 Intensive monitoring at Beaconsfield showing the SMART cables (grey) and stress monitoring
(HI cells) (yellow)

Australian Centre for Geomechanics • December 2009 Newsletter 13


the aspects of data capture through the
ISSI system, its transfer to MS-RAP, and
its analysis as an immediate tool through
Omori Analysis after stope blasts, and as a
longer term management tool in updating
EVP maps. She expended a significant
effort in analysing data to assist in the
refinement of re-entry protocols, and the
latter formed the basis of her final report.
A synopsis of that report follows this
article. The key to understanding the basis
of a detailed data analysis such as Natalie
performed can only be gained by observing
the environment from which the data is
obtained. Consequently, Natalie went
underground to inspect the geotechnical
environment regularly, and every effort was
made to introduce her to as many facets
of mining geomechanics at Beaconsfield
Figure 2. A plot of raw micro-strain change data illustrating the impact of stope blasting (and as possible. As a result, the report she
Figure 3 A plot of raw micro-strain change data illustrating the impact of stope blasting (and non
nonblast-related seismicity)
blast-related on the local
seismicity) on stress field stress field
the local ultimately produced has real practical
Figure 2. A plot of raw micro-strain change data illustrating the impact of stope blasting (and application in the ongoing management of
non blast-related seismicity) on the local stress field
seismicity at the mine.
The experience of hosting a project
focused summer vacation student was a
positive one for the Beaconsfield Gold
Mine. Our continued use of MS-RAP as
a tool in the management of seismicity
has been enhanced as a result. The fact
that the summer vacation student came
in the winter when vacation was not the
focus of mine staff was a significant factor
in ensuring that maximum benefit could
be obtained by all parties concerned. In
particular, the benefit to the students
of early career international experience
cannot be over-emphasised.

Article references are available on request.


Figure 4 A plot of energy index/cumulative apparent volume
Figure 3.3.AAplot
Figure plotofofenergy
energy index/cumulative apparentvolume
index/cumulative apparent volume

This is especially in the west zone of months.


the mine where mining is conducted The student chosen to undertake Peter Hills,
remotely (Hills, Mills, Penney and Arthur, the project was Natalie Kari, a 3rd year Tasmania Mine Joint Venture,
2008), and exclusion zones of at least 50 mining engineering student at Laurentian BCD Resources (Operations)
NL
m are enforced. Other features within University. While Marty provided
the MS-RAP package are also regularly supervising guidance from afar, a site
interrogated to assist in the management based introduction to the use of MS-RAP
of seismicity, including the various graphical was provided by Johan Wesseloo, ACG.
analyses such as energy index/cumulative Natalie was technically an employee of
apparent volume (Figure 3) and apparent Allstate Explorations NL during her time
stress history, and mapping features such as at Beaconsfield, and as such she technically
excavation vulnerability potential. reported to myself.
Real management decisions were being Natalie provided the Beaconsfield Gold
made and influenced by the use of MS-RAP, Mine with a substantial analysis of its
but the potential of the package was not seismic data, particularly that collected
fully realised because a significant database over the 18 month period to June 2009
of seismic data had not been collectively when stoping had recommenced in earnest
reanalysed recently. A project was ready following the 2006 accident. The database
made, provided somebody could be remained live for much of her stay, allowing
dedicated to the task for a period of a few Natalie to observe and understand all

14 Australian Centre for Geomechanics • December 2009 Newsletter


Underground
Understanding mining-induced seismicity
at Beaconsfield Gold Mine
by Natalie Kari, Laurentian University, Canada

A project was undertaken at the The seismic source mechanism at each having a disproportionately intense seismic
Beaconsfield Gold Mine to investigate the seismic source, for the one year time response to distant mine blasts. Identifying
current mining-induced seismicity at the period March 2008 – February 2009, seismic sources that do not follow
operation. The objectives of the project was compared to the seismic source expected trends is often an indicator of
were to identify all of the main seismic mechanism over the last four years (June locations which have a strong geological
sources currently active in the mine and to 2005 – June 2009). In almost all cases, the control. These locations require particular
rate the seismic sources with regards to: analysis showed that the seismic source vigilance with respect to monitoring and
• Seismic source mechanism (the rock mechanism remained constant over time. underground inspections.
mass failure mode causing the seismic This is an important conclusion, as it Post blast re-entry times were estimated
events). means that it is the local rock mass failure for 73 production blasts, using 90% of the
• Seismic hazard (the largest expected mechanism that is controlling the nature total seismic energy as a re-entry criterion.
seismic event that would be expected). of the seismicity, irrespective of the nearby The overall distribution of re-entry times is
• How mining activities (particularly stope mining influences. When the current shown in Figure 1. Using this 90% of total
blasting) affects the rate of seismicity seismic response to mining is similar to the seismic energy re-entry criterion, 59 of the
from each of the seismic sources. past seismic response to mining, it gives production blasts had a possible re-entry
• The ability for seismic monitoring to be greater confidence in using the current time of less than 12 hours, with 14 blasts
used as a re-entry tool for each of the seismicity to understand future seismicity. requiring a re-entry time of more than 12
seismic sources. Overall, the majority of seismic source hours. Figure 2 shows that re-entry times
The seismic analyses in this project were mechanisms at the Beaconsfield Gold Mine are somewhat controlled by local seismic
all conducted using the ACG’s MS-RAP are related to the volumetric fracturing sources and vary spatially in the mine. It
program (Mine Seismicity Risk Analysis associated with mining-induced stresses as was concluded that for the Beaconsfield
Program). a direct response to mine blasting. Gold Mine, a 24 hour re-entry period is
Post blast re-entry times were estimated for 73 production blasts, using 90% of the total seismic
The complex geology and geological An investigation of how mining activities, usually conservative, although at times it
energy as a re-entry criterion. The overall distribution of re-entry times is shown in Figure 1.
structures of the Beaconsfield Gold Mine, particularly
Using this 90%stopeofblasting, affectsenergy
total seismic re-entry may
the rate be required.
criterion, 59 of theIt is suggestedblasts
production that other
had a
including faults, contact zones, shears, of seismicity
possible from
re-entry each
time of the
of less main
than hours, with 14tools,
12 seismic blastssuch as theaseismic
requiring re-entryhazard
time ofmapping
more than
bedding and splays, contribute to the 12 hours.was
sources Figure 2 showsThe
conducted. thatproximity
re-entry times are somewhat controlled
tool in MS-RAP, by local
be used seismic sources
in conjunction
challenges of mining within the Tasmanian and varyofspatially
of each the seismicin thesources
mine. Ittowas theconcluded thatwithforthe
there-entry
Beaconsfield Gold
analysis Mine,
when a 24 hour
making a
re-entry period is usually conservative, although at times it may be required. It is suggested that
reef. More than 8500 seismic events stopetools,
other blastssuch
was as considered.
the seismicAs expected,
hazard mapping toolfinal decision on
in MS-RAP, be re-entry following each
used in conjunction with the
were recorded at the Beaconsfield Gold seismic sources
re-entry analysis in whenclose proximity
making blast. Infollowing
a finaltodecision on re-entry addition,each
it is important that it is
blast. In addition,
Mine between March 2008 and February important
mine blasts that
havethisa analysis procedure
higher rate of inducedbe continued thistoanalysis
monitor procedure
future changes in seismological
be continued to
2009, including nine events larger than patterns and
seismicity their
than potential
stopes effectatonfurther
located re-entry times. monitor future changes in seismological
local magnitude +1.0. A cluster analysis distances. However, two particular seismic patterns and their potential effect on re-
identified 56 groups of seismic events sources did not follow this trend; often entry times.
during this period, of which 23 were
particularly active and investigated in detail.
Each group was analysed to determine the
seismic source mechanism, seismic hazard
and the rock mass response to production
blasting in the mine. This analysis helped
to describe the character of each seismic
source and highlight the seismic sources
most likely to cause operational issues at
the mine. When higher hazard seismic
sources can be identified, a range of
seismic risk mitigation techniques can
be used to manage the hazard. Ten of
the seismic sources were found to have
a qualitative seismic hazard rating of
moderate-high to high. The seismic hazard
rating is a good indicator of the likelihood
of larger magnitude events.
Figure 11. Distribution
Figure Distributionof re-entry times
of re-entry for 73
times forproduction blasts at
73 production Beasonsfield
blasts Gold MineGold
at Beaconsfield in 2008 andin2009
Mine 2008
and 2009.

Australian Centre for Geomechanics • December 2009 Newsletter 15


limitations to all of the analyses undertaken
in this study. Sound judgment should be
undertaken when utilising the information
provided. Focus should be placed on
minimising personnel exposure to areas of
the mine where seismic hazard is greatest.
It is important that all available data and
tools continue to be utilised in order to
minimise the seismic risk.
Acknowledgments
This project would not have been
possible without the support, insights
and direction of several people. I would
like to express my gratitude to Marty
Hudyma, Laurentian University, and
Peter Hills, Beaconsfield Gold Mine for
providing me with this opportunity and
whose supervision and direction played an
invaluable role in this project. I would like
to thank Johan Wesseloo for conducting
Figure 2 Location of the blasts for which the re-entry analysis was conducted a site visit and help in using MAP3D. I am
also grateful to Tim Parkin, Toby Collins and
An excavation vulnerability potential seismic hazard, or which sources are Jerome Paterson, Beaconsfield Gold Mine
(EVP) map was built for the Beaconsfield more prone or likely to have large for providing me with guidance during the
Gold Mine. The EVP map identifies regions events. It is apparent that some course of my project. Notable thanks to
of the mine that need particular attention seismic sources are more active than Roger Hill for helping me understand the
with regard to seismic risk management others; the seismic system shows this geology of the mine.
procedures such as re-entry times, clearly. It is important to note that the
enhanced ground support, etc. Other key most seismically active sources do not
points have also come to light during the necessarily have the highest seismic Natalie Kari,
course of this project: hazard. Laurentian University,
1. The Beaconsfield Gold Mine data is 4. Daily analysis and management of seismic Canada
well behaved. It provides good source data is fundamental to understanding
parameters and locations and follows seismic risk.
standards and expected trends in seismic 5. At this time, the analysis did not show
data. any acceleration of event rate or Natalie’s project, undertaken between
2. The seismic data gives a clear indication increased seismic hazard with depth May and August 2009, was a joint effort
of where the seismic problems are indicating that there are no obvious between Beaconsfield Gold NL, Laurentian
located within the mine and where problems with incrementally deepening University and the ACG. Similar student
there are no seismic problems. This is the mine. summer undergraduate projects have been
important for future planning, and shows 6. It is recommended that one person at organised each year, for the last ten years,
that seismic monitoring is a key tool for the mine be dedicated to analysing the for sponsors in the ACG’s “Mine Seismicity
forecasting future problems. seismic data and familiar with MS-RAP, and Rockburst Risk Management” project.
3. The back-analysis shows that seismic using it to its maximum potential.
data identifies the areas with higher It is important to note that there are

Mine Seismicity and Rockburst Risk Management Project


Since its commencement in 1999, the goal “Advancing the Strategic Use of Seismic Data
of the ACG’s MSRRM research project has in Mines”, is currently underway and aims to
been to advance the application of seismic develop the strategic use of seismic data and
monitoring in the mining industry to quantify promote an increased understanding of the
and mitigate the risk of mine seismicity and rock mass seismic response to mining. The
rockbursting. This has seen close involvement ACG acknowledges the generous support
at research sponsor sites by undertaking and encouragement of its Phase IV research
detailed site seismic analysis, testing or project sponsors. Additional project sponsors
experimental work and providing seismic are sought.
system technical support and advice as For further information please contact
required. project leader, Johan Wesseloo, ACG via
Phase IV of this research project, entitled acg@acg.uwa.edu.au

16 Australian Centre for Geomechanics • December 2009 Newsletter


Tailings
the runout distances and consequences of

The risk of
failure need careful consideration. These
considerations also apply to in-pit storages.
if there are underground workings below

tailings disposal them.


Low strength

Strength influences runout distances


and the assessed consequences of failure.
In addition, it also relates directly to
bearing capacity and the safe access over
the tailings for activities including raising
and capping. The strength of geotechnical
materials is tricky to define. It varies
with time and is dependent on the rate
by Keith Seddon, ATC Williams of loading. Almost all tailings start out as
slurries, i.e. liquid. After deposition, some
tailings progress towards the solid state
faster than others. But this does not mean
Introduction Management of risk that any tailings dam can be treated like a
waste dump.
In September 2010, the ACG will host Tailings storage and disposal does not Geochemistry/acid potential
the First International Seminar on the rank high on the scale of overall mine
Reduction of Risk in the Management production costs. But it does weigh Many types of tailings contain a
of Tailings and Mine Waste in Perth. The heavily in terms of the overall risk to proportion of sulphur, which may oxidise
purpose of this article is to reflect on an operation, both initially with permits to form sulphuric acid. This in turn has the
some of the issues that contribute to that and approvals, and in relation to ongoing potential to mobilise trace heavy metals,
risk. It is written from the perspective of a operations. There is nothing like a well and make even small amounts of seepage
consultant. publicised tailings dam incident to damage a very undesirable consequence. Little can
A well known website (www.wise- a company’s “license to operate”. So, be done to eliminate this basic hazard; the
uranium.org/mdas.html) catalogues tailings increasingly we see that management geochemistry of the orebody is not open
dam failures. In the (nearly) 30 years since of mine tailings is about understanding to negotiation. However, in the future
1980, it lists 52 incidents, spread across 20 and management of risk. The risk based possibly more attention will be given to
different countries, and all continents. An approach is not unique to tailings storages. attempts to remove sulphides as part
“incident” is broadly defined and includes It is also widely used for management of of the process, and reduce the residual
everything from contaminated seepage into water dams and other activities. hazard in the tailings. The potential for acid
groundwater, and (relatively minor) spills Two examples demonstrate the trend production impacts both on operations
from broken pipes, all the way through with respect to dam safety. The NSW and on closure requirements for a storage.
to overtopping during storm events, Dams Safety Committee is currently in It needs to be evaluated during the design
catastrophic failure and collapse. The list the process of a comprehensive re-casting of all tailings dams, and may need to be
is by no means complete. Additionally, of its requirements in order to integrate monitored routinely over the mine life.
inspection of the list shows an over- a risk based approach. And, the ANCOLD Process chemistry
representation of events from North tailings dam guidelines (originally issued in
America, mostly related to small leaks and 1999) are being updated with increased The tailings solids may prove to be
spills. Are the North Americans worse at emphasis on risk. For this approach to relatively benign, but it is necessary
managing their operations than the rest of be effective, a core requirement for to consider the process and how this
the world? Or, is it more likely that they management is to be fully committed to influences the chemistry of the decant
are simply subject to greater scrutiny and the process, through adequate support and water. This includes processes that use
higher standards? These questions aside, resources. cyanide (gold tailings), high pH (bauxite
what can we learn from this list about the red-mud), and low pH (laterite nickel), and
Fundamental hazards
risks of tailing storages? elevated levels of salinity should also be
• Incidents occur across all mineral types. There are at least four fundamental included.
• Incidents occur across the full range of hazards that need to be considered for all Many of the decisions relating to
company size and status. tailings storages. process chemistry are fundamental to the
• Incidents occur in both developed and Potential energy [“Gravity is a bitch”] feasibility and design of the whole mine
under-developed countries. and concentration / beneficiation process,
• The frequency of incidents does not All above ground storages place tailings and may be considered as “constraints” to
appear to be decreasing. in an elevated location relative to some the tailings dam designer. However, when
position around the storage. In the event these conditions occur, they are likely to be
If you have a tailings dam on your site, it of a breach, this potential energy may powerful drivers of the subsequent design.
is a risk. convert to kinetic energy. This means that The author is looking forward to the day

Australian Centre for Geomechanics • December 2009 Newsletter 17


that a laterite nickel process co-locates and what can be done with the storage accumulated water over an extended wet
with a bauxite refinery, and the two waste in the future. This is typically something period. Either extreme rainfall occurs on
streams are combined to neutralise each like changing the method of raising, or the top of already high pond levels, or the
other. previous water management procedures, mine simply has too much water on the
or the method and location of tailings site. If excess water is accumulating in a
Factors contributing to risk
discharge. It is not always a fully informed tailings dam, it may be that the original
In risk management terminology, it is or considered decision. It may be taken water balance, for the site as well as just
usual to define risk as consequence x under the stress of requirements to reduce the tailings dam, needs to be re-evaluated.
probability of failure. Consequence relates costs in the short term, or delay the In addition, if water balance is an issue,
to hazard, and is typically measured in requirement for a raise, without regard to provisions for monitoring to include
terms of loss of life, or cost of remediation. longer term consequences. So if anyone records of all water flows associated with
Management of risk can address both ever has a decision like this to make, please the tailings storage (i.e. flow meters on the
of these components. For instance, the put your guns back in their holsters, discuss pumps, and records of storage volumes)
consequence of a failure will be dependent it with your consultant, and think through should be included in the design and the
on the location and size of a dam, and the long term consequences, and the OM, and should be assessed either as part
factors such as the strength of the implications for safety. of routine surveillance, or as a specially
contained tailings. Most of these types of Water management [“Soil particles and water commissioned study.
issues need to be addressed during site are natural enemies.With tailings you have Capacity problems [“We’re running out of
selection and design. It is too late to do both together”] space in the tailings dam and have to do
anything about location after a dam is built. something fast…”]
On the other hand, there are many issues Many operational problems associated
related to the operation and management with tailings dams, and many of the This situation that shouldn’t happen,
of a tailings dam that impact directly on recorded “incidents” can be traced directly but frequently does. The problem is that
the probability of failure, whether this to water issues. Excessive water can affect existing safe design, construction and
is explicitly recognised during design or dam safety in a number of independent operating procedures may be compromised
not. The following discussion covers both ways: in the process. The cause is basically a
operation and management components, • Overtopping (followed by erosion and lack of planning, and oversight of the
but is slightly biased towards operational breach). development of the storage. Underlying
issues. • Increased seepage leading to piping or reasons may include:
Poor communication internal erosion. • An increase in the mine resource
• High seepage (“phreatic”) surfaces in without any commensurate adjustment
Many problems stem from poor embankments, resulting in reduced to storage capacity.
communication, i.e. between the designer stability. • Increase in throughput without
and site management, or management Water balance and storm water recognising that this will fill the storage
and operators. The designer (often management in a tailings storage is usually faster.
a consultant) may make particular addressed as part of the design. Either • Incorrect density of deposited tailings in
assumptions regarding the way the dam appropriate freeboard levels are set to the storage used in design (this should
will be operated and raised. Typically, these ensure that there is an adequate void space always be checked during production).
matters will be covered in a design report. left in the storage to retain decant and • Raise construction delayed (as a cost
But the implementation of these lies storm water at safe levels, or a high level saving measure), for too long.
with the mine, and personnel rarely have emergency spillway is incorporated into • Failure to appreciate the length of
time to read design reports. A common the design. time required for the sequence of
solution is to have an “operations and Some believe that if tailings dams contain investigation, design, approvals, tendering,
maintenance manual” (OM) to cover deleterious substances (solids and/or mobilisation and construction that may
these aspects. A good OM manual needs process water) then provision of a spillway be associated with works to raise a
to be comprehensive, structured, well is incompatible, in that it “admits” that storage, or start a new one.
written, and be easily understood by all there may be discharge events, however Whole of life planning
users. Usually the details require input infrequent these may be. Alternatively, it
from both the designer and the mine, and is a far better thing to accept that in an Development (and periodic updating) of
a co-operative approach to preparation is extreme event there may be a discharge a whole of mine life plan for tailings storage
required. of some water (most likely highly diluted is an excellent way of focusing on the
Tailings dams are not static structures, by all the storm runoff), rather than put forward requirements for tailings storage.
they are continually being raised or the security of the whole storage at risk Site selection and investigation
modified in some way, and all OMs need of overtopping and failure. At least two
to be regularly checked and upgraded to major failures of tailings dams (Baia Mare, There is no doubt that some tailings
mirror these changes. Romania in 2000, and Merriespruit, South dams are built on sites that are less
Bad decisions [“It seemed like a good idea at Africa in 1994) could have been avoided by than ideal. This includes sites with poor
the time”] the inclusion of emergency spillways. foundation conditions, locations where
Excess water in a dam may be the seepage quality is a risk to groundwater,
There comes a time in the life of some result of a single, isolated, extreme and sites where excessively high
storages when a decision is made that rainfall event. However, it is more likely embankments are required to achieve
fundamentally effects safety performance, to be a combination of events relating to the necessary storage volume. In many

18 Australian Centre for Geomechanics • December 2009 Newsletter


Tailings
cases these sites are dictated by existing often integrally linked to pond locations Why is there a risk associated with this?
topography and/or lease boundaries, and and beach development, and has major Primarily because of a failure to plan. Many
are often the result of choosing the “least implications for the ongoing safe of the things that are needed for closure
bad option”. It is important to appreciate operation of the storage. should have already been done well before.
that even if the starter dam is relatively • Monitoring and surveillance: monitoring • What are the revegetation requirements?
modest, the final storage may grow to be a is the collection of data that relates to What cover is required to get things to
major structure. A full and comprehensive the performance of a dam, e.g. seepage grow (schedule cover trials)?
geotechnical and hydrogeological flows, water levels, filling rate and • What is the final landform and capping
investigation should be carried out as part storage levels, settlement and movement design?
of the initial feasibility studies to enable etc. There needs to be provision for • Where is the material for this going to
the viability of the final structure to be these data to be reviewed at appropriate come from?
established. intervals, and the significance of the Planning for closure should be
Construction issues readings evaluated. Surveillance is the incorporated in initial design, and should
ongoing process of evaluation and continue throughout operations.
Construction control, or the lack of it, assessment of the safety of a dam based Corporate memory
can have a major impact on the adequacy on data obtained from inspections and
of tailings dams. This applies particularly to monitoring, and is seen as a very valuable Site personnel often take valuable
raises, where both the construction and contribution to risk identification and knowledge with them when they do go.
supervision may be largely undertaken reduction. Many regulatory authorities In some cases the consultant has better
by the mine. The design will have been now require regular surveillance reports records of a site history than the mine,
prepared on the expectation of certain to be prepared on tailings dams with but no mine should rely on them. All sites
standards of foundation preparation, significant or high failure consequences. should maintain a library/archive that
material selection and placement etc. It Some mining companies have similar contains copies of all reports, records etc.,
is important that these standards should internal requirements. relating to each of its tailings storages. If a
be achieved, and close and continued • Dust: dust from a tailings storage is site is ever sold, these documents should
involvement by the designer throughout sometimes a major environmental be required by the new owner as an
construction is essential. Many regulatory headache. One of the perceived “fixes” integral part of due diligence.
authorities recognise this and include a for this is to pond water on the tailings.
requirement for an acceptable “sign off” This should not be attempted without Article references are available on request.
of construction, and also of design changes consideration of the consequences.
during construction. Closure planning
Other operational issues
Eventually, all tailings storages have to Keith Seddon,
Other items that impact on safety and be closed, and the costs of closure can ATC Williams
risk are: be significant, especially when the time is
• Tailings deposition management: this is “now”, not “still 10 years down the track”.

Australian Centre for Geomechanics • December 2009 Newsletter 19


Mine tailings solution:
ACG–EIGG alliance is
your one-stop shop
The ACG and the Environmental Our industry-supported research geochemical analysis and characterisation
Inorganic Geochemistry Group, Curtin projects have included Metallurgical Mine of mining waste, water quality and AMD,
University seek to demystify the Tailings Rehabilitation, Saline Tailings Disposal including trace element analysis, carbon-
complexities surrounding the hazards and and Decommissioning and the current An sulphur determination, high performance
challenges of mine tailings by providing Effective Stress Approach to Mine Backfill. ion chromatography, fluoride selective
a one-stop shop for your total mine The ACG has provided industry with electrode, anodic stripping voltammetry,
tailings research, education and training the tools and knowledge to improve the gravimetric and grain-size determination,
requirements. stability and safety of mine tailings storage diatom and pollen analysis.
facilities, mitigate geotechnical and stability
Australian Centre for
hazards, explore rock drainage and the
Geomechanics safe and efficient use of mine waste in
Through its further education courses, the backfilling of mining voids. The ACG
publications, training products and research has addressed the broader issues of
activities, the ACG has established itself tailings behaviour for a number of mining
as a leading provider of mine tailings companies.
geotechnology, information and best
Environmental Inorganic
practice. Since 1992, under the direction
of Associate Professor Richard Jewell and
Geochemistry Group, Curtin
UWA Professor of Mining, Andy Fourie, University of Technology
ACG has researched and documented EIGG comprehensively examines acid
the hazards and challenges of mine waste mine drainage – one of the greatest
management. hazards facing more than 60% of gold
More than 1,000 mine tailings mining operations, as well as coal and
professionals have attended our metalliferous mines.Via its designated
education courses; including the series analytical facilities and innovative testing,
of international seminars on paste EIGG is able to characterise waste and to
and thickened tailings (now in its provide a comprehensive picture of current
thirteenth year). The ACG has produced environmental quality, as well as predictive
internationally reputed publications such analysis of potential acid mine drainage
as the “Paste and Thickened Tailings – A and pollution risk offering avoidance and
Guide” and “Handbook on Mine Fill”, and remediation strategies. The EIGG laboratories provide a full range of
with industry sponsorship developed state- EIGG has direct experience of assisting mine waste characterisation and environmental
of-the-art training products such as the industry with tailings and waste rock geochemical analysis
“Tailings – From Concept to Closure; Best management protocols for mine closure.
Practices for Tailings Disposal – A training EIGG was established in 1998 and is Together, the ACG and EIGG can
DVD for owners and operators of tailings directed by Associate Professor Ron provide operations with a comprehensive
storage facilities”. Watkins. It researches the geochemical analytical support to tailings and mine
background and pollution of the natural, waste management combining all aspects
mining and built environment. It focuses on of mechanical, structural and geochemical
assessing the geochemical environment and security.
providing solutions to current and potential
pollution problems.
EIGG has an international profile with Ron Watkins
research projects undertaken in 10 Department of Applied
countries, as well as WA and Victoria. Geology, Curtin University
It has active research programmes
in a range of fields of environmental
geochemistry, including mining pollution
and rehabilitation, hydrogeology, urban
geochemistry, geochemistry and health Andy Fourie
(medical geology), past environments and The University of
Western Australia
climate change.
Tailings – From Concept to Closure training DVD It has comprehensive facilities for the
available from www.acg.uwa.edu.au/shop

20 Australian Centre for Geomechanics • December 2009 Newsletter


Paste
Increasing value in mining operations
through the application of paste
by Nick Slade and Stephen Wilson, Golder Paste Technology (Europe) Ltd; Florencio Felipe,
Xstrata Copper, Mount Isa Copper Operations; Frank Palkovits, Golder Paste Technology Ltd

Introduction
to the beneficiation of the ore into a saleable product beyond the mill. This often means
Mineral waste more effort and money is spent on analysis and investment in the process of getting the ore
The creation of mineral waste by out of the ground and through the mill, with less emphasis and consideration of the waste
metaliferous mining is inevitable and in management options.
most situations leads to 90 to 99% of the Often capital cost constraints can limit the resources available to develop or improve an
amount of material extracted from the operation. Consequently, it is not uncommon that management of a milled waste is often
ground requiring disposal. Many years ago undertaken by conventional slurries tailings disposal and where it is used as backfill is often
waste may have been disposed of without through conventional cemented hydraulic fill. This is the simpler and more conventional
controls, creating what we would describe option but does not necessarily afford the best value for the business.
as environmental and health hazards. Financial analysis
Mining companies face a range of factors
which form a very different environment Given that discounted cash flow and Net Present Value (NPV) are the most commonly
in which to manage the same waste today. used indicators of a project’s financial strength, a thorough financial examination of waste
These include more ethical operating management solutions for a project should be undertaken. This is important as the lowest
practices towards the environment and capital cost option may not be the most value adding option to the project or operation.
local communities, increasing regulation The merits of analysing a project over its lifecycle can be said to be a more strategic
with respect to the environment, scarcity assessment than that purely focused on operating cost or technical simplicity.
and cost of water and a realisation that A financially favourable alternative to conventional slurry disposal and hydraulic backfill is
longer term liabilities are therefore higher to engineer the material to a paste for both applications.
than they once were for remediation of a
Paste and slurry
mining project.
More recently, waste has been disposed A technically correct appreciation of paste is commonly said to include the following
of in a fashion aimed at reusing whatever characteristics:
can be beneficial to the mine. Examples
include reusing process water and using • Non-settling mixture of solids and water.
tailings to form backfill in underground • Exhibiting minimal water bleed when left idle.
mines. Scientific and engineering advances • Meaningful slump (ASTM, 2008) measures no more than 253 mm.
have lent themselves to helping manage the • With no critical flow velocity.
mining waste streams more efficiently and • Percent solids dependent on particle size distribution and other factors.
productively. • Enabling semi-dry waste management.
Drivers for change Slurry

Drivers for change are always ultimately Figure 1 shows what the slump looks like for the differing natures of material and as this
financial. The recognition of costs as much is the most simple and common test for evaluation it is worthy of note.
as opportunities presented by not requiring
as much fresh water in a mine, or the
benefits added by using the tailings waste
as backfill for the mining process, lead to
changes in attitude, operations and the
financial position of a business.
Influences on the decisions mining
companies make with regard to managing
waste are driven by the business Paste – 177 mm slump Paste – 253 mm slump Slurry – no slump
characteristics and culture of the company. Figure 1 Examples of the slump cone test for differing tailings slumps
These can include: how its business goals
For a typical metaliferous tailings the main differences in solids and water content are indicated in Table 1.
relate to the short or longer term value of For a typical metaliferous tailings the main differences in solids and water content are
the company, what approach it chooses to indicated in Table 1.
take to manage financial risk, and its cash Table 1 –Indicative solids and water parameters for slurry and paste materials
flow status. Table 1 Indicative solids and water parameters for slurry and paste materials
It is not uncommon that mining
Material Type Solids Content (%wt) Free Water (ltr/100 tonnes)
companies focus managing costs rationally Slurry 40 50,000
on the parts of the business which lead Paste 70 5,000

Paste application benefits


Surface disposal benefits
Recent technology development has supported
Australianthe application
Centre for tailings
for Geomechanics disposal
• December as a paste.
2009 Newsletter 21 Some respo
mining companies and regulators today are looking at more holistic waste management approaches.
Paste application benefits to almost all methods utilising backfill: Financial case example
Surface disposal benefits • Reduction in the volume of material Surface disposal in South America
placed as waste on surface in a
Recent technology development has deposition facility. A large mine in South America has an
supported the application for tailings • Permits the generation of a larger size opportunity to increase the value of its
disposal as a paste. Some responsible ore reserve in the underground mine. asset with the application of paste tailings
mining companies and regulators today are • An increase in productivity as a result of disposal rather than a conventional
looking at more holistic waste management reduced production cycle time. slurry tailings facility. The mine is a large
approaches. These elements can lead to significant operation producing approximately
Approaches which take that move operational cost savings and revenue 150,000 tpd of tailings with a tailings
towards minimising waste generation enhancements. solids concentration around 55% wt. By
are fundamentally important to manage Paste application as backfill yields thickening the tailings towards 70% wt
efficient operations with respect to opportunities to reduce risk and add value solids, significant gains are identified. The
development and closure capital costs and by: project outcome highlighted the following
operational costs. The knock-on effects of • Increased mining productivity. key benefits from the application of paste
resource consumption and waste disposal • Reduced cycle time and cement for tailings deposition:
that were previously considered as free consumption. • Virtually eliminating water re-handling
are now of major financial significance to • Full range of plant tailings can be utilised. associated with the tailings deposition.
worldwide mining activities and operations. • Simplified stope preparation. • Reduction in water consumption.
The immediate and long-term liability • Improved underground mining • Reduction in water abstraction.
of waste materials and the associated conditions (less water, slimes, pumping). • Prolonging the life of the existing facility.
water run-off can amount to a major • Reduced surface disposal volume. • Opportunity to increase production (by
portion of the cost to a business and increasing tailings capacity).
Value and cost
can present significant obstacles in the • Reduce deposited tailings liquefaction
permitting of disposal sites. Minimising this Shareholder value potential.
cost and liability (risk) through reduced If the business driver or goal is These aspects provide a range of savings,
surface disposal volumes and hazards, and shareholder value and the used notably in water abstraction and re-
innovative surface storage brings benefits representation is NPV (Runge, 1998), handling, to the operation. The key financial
to any project. This is particularly so in then it is appropriate to consider this gains in this example are:
relatively dry (hot or cold) climates or during evaluations of all key potential • Operating costs reduced by A$30M to
highly populated areas as these place expenditures to ensure that value based 40M per annum.
higher value / cost on consumption of decisions are made. • NPC cost reduction of 40% for the life
water and the value of socio-economic and Net present value of the tailings deposition system.
environmental impact. Recognising this opportunity for the
As the majority of mines and mining Intuitively, where the NPV is increased business, the operation is advancing its
projects fall into this situation they are for a project, even with increased capital project work towards the use of paste for
increasingly important financial drivers, expenditure, basic theory suggests the the deposition of its tailings.
especially for larger scale projects. project will make a financial return and the
Conclusions
In summary, the key risk reducing and project should go ahead. In practice there
value adding benefits to depositing tailings are limitations to this theoretical outcome, As indirect and direct costs to mining
as a paste, rather than a slurry, include: such as available capital within the business operations become greater and the focus
• Smaller tailings disposal footprint (up to or indeed the capital finance market place, on delivery of sustainable projects is
40%); with a steeper beach angle (up to as has been witnessed in 2009, or the risk linked to business success, the case for
5 degrees). associated with the mining project. In such paste applications is clear in a variety of
• Smaller dam engineering. cases, the financial imperative for a project situations. Consideration of a range of
• Lower water consumption. may not just be a positive NPV, but it may key internal and external factors clearly
• Negligible bleed water release. also be the return on the investment, suggests whether the application of paste
• No critical velocity required to avoid the payback period or the inherent risk is warranted for analysis and study on a
settling. involved in the project as compared to new project or existing operation. Strategic
• Reduced closure cost (10 to 75% other projects the business is assessing. perspectives of the project and business
depending on the characteristics of the Net present cost must also be examined to ensure value is
Article references are available on request.

waste). maximised.
• Reduced operating risk liability. Net Present Cost (NPC) is also used.
• Reduction in contamination/leachate This reflects the discounted cash flow and
potential. time cost of the expenditure and is used
• Potential to not require impervious liner in isolation from the NPV because the Nick Slade,
and monitoring systems (saving A$17-22/ revenue data was either not relevant to Golder Paste Technology
m2). the analysis or did not change. In relevant (Europe) Ltd, UK
Principal Sponsor examples, NPV has been stated where the
Backfill benefits
revenue did change as part of the analysis.
The disposal of tailings as backfill to an
underground mine brings three clear gains

22 Australian Centre for Geomechanics • December 2009 Newsletter


Mine closure
Corporate (ir) on closure objectives and procedures
during the environmental permitting stage,

responsibility: what is it
it could be even more difficult to obtain
alignment when unexpected or unplanned
closure occurs. Consequently, companies

really worth when times needed to manage this process carefully.


A consistent theme throughout the

are tough? break-out session was how to address the


socio-economic aspects of mine closure.
It was felt that the “social conversation
by Sonia Finucane, Bioscope Environmental Consulting Pty Ltd is still an externality”, with little or no
consideration of the socio-economic
This question was posed as part of a guiding proponents on what information on aspects in closure planning and cost
break-out session during the ACG and closure planning should be provided during estimates. This was even more evident
Centre for Land Rehabilitation’s (CLR) the environmental impact assessment when unexpected closure occurred,
Fourth International Mine Closure phase, including closure cost estimates. It as many of the social and community
Conference held in Perth in September was noted that developing closure cost benefits of a mining project often took
2009. This session provided delegates with estimates during the permitting phase was a number of years to be realised and
a forum to explore corporate responsibility important but could be difficult, particularly these opportunities were reduced or lost
in relation to mine closure, using a for those projects expected to have a altogether when a mine ceased operations
hypothetical mining project as a case study. mine life of many decades as there was a prematurely. Where community assets
The hypothetical project comprised a decreasing level of accuracy in the closure (such as health or recreational facilities)
remote greenfields gold mine owned by a cost estimate with increasing length of were in development, when unexpected
mid-sized mining company. It was proposed mine life. It was also noted that the focus closure occurred there was concern about
that the mine would have a fly in – fly out of closure cost estimates developed at who would be responsible for completing
workforce of about 300 employees and an this stage of a project was usually on and maintaining these assets. Often, this
operational life of 50 years. decommissioning and rehabilitation, with responsibility falls to local government
A technical panel provided perspectives little or no allowance made for the socio- authorities acting on behalf of the
from different groups of stakeholders. economic aspects of mine closure. community. Therefore, it was suggested
The panel comprised Darren Murphy This second scenario examined that life-cycle costing be undertaken
(SKM), Graham Cobby (WA Department corporate responsibility when a company when a mining company first proposed
of Minerals and Petroleum), Mark Batty was faced with unexpected or unplanned development of community assets so that
(Western Australian Local Government closure. Under this scenario, the mine had local government and the community
Association), Kado Muir (Aboriginal obtained environmental and other permits understood the cost of completing and
Heritage Consultants and Traditional and had been operating successfully for five maintaining these assets in the event of
Owner), and Cathy Gupanis (Paladin years when an unexpected and significant unexpected or unplanned mine closure.
Energy). The session was facilitated by drop in commodity prices occurred. This
Sonia Finucane with assistance from Don forced the mine into temporary shutdown
Burnside (URS Australia) and Talitha Santini and, despite the company’s earlier good Ground Control Groups Update
(CLR). intention, it appeared that the only solution
The first part of the break-out session was to close the mine permanently. The Eastern Australia Ground
examined corporate responsibility during company had prepared a closure plan as a Control Group
the permitting phase of the hypothetical condition of its environmental approval and A meeting was held in October 2009
project. Initial discussion examined the had established a closure provision, but this in Tasmania on “Ground vibrations —
type of closure commitments that would was considered to be insufficient to pay for blasting and seismicity, and its effect on
be reasonable for the proponent to make full project closure so early in mine life. ground support”. The meeting was well
at this early stage of the project life. Key In discussing this scenario, a number of attended by more than 65 members and
topics included what should take priority topics including what the company should Dr Phil Dight, ACG Winthrop Professor
in making closure commitments and how do to demonstrate corporate responsibility Geotechnical Engineering presented a
the company should balance the need when faced with unexpected closure were talk on microseismicity and the influence
of regulators and other stakeholders considered. Is corporate responsibility of rock fracturing on deep open pits. For
for certainty in closure outcomes with something to be spoken about only in good details regarding the next meeting, please
the need for continual improvement times? What is it really worth when times visit www.eagcg.org
for a project with a long mine life. It are tough? Unexpected closure usually
was concluded that there was a need triggers a review of company priorities and Ground Control Group (WA)
for proponents to agree with their responsibilities, the extent of closure risks The group met last month at the WA
stakeholders on mine closure targets for and liabilities, and the adequacy of closure School of Mines, Kalgoorlie to discuss
both environmental and social factors, but provisions and bonds. During discussion on paste fill. A survey on the future of the
that gaining alignment on priorities could this point, the importance of stakeholder group is being undertaken and can be
be difficult. engagement during these reviews was obtained from the GCGWA secretary
There was also discussion about the role recognised and it was commented that if it via emjones@barrick.com
of government and other stakeholders in was difficult to get stakeholder alignment

Australian Centre for Geomechanics • December 2009 Newsletter 23


ACG Event Schedule*
Practical Rock Mechanics in Mining Short Course Perth, 24–25 March 2010

Preconditioning Workshop Perth, 19 April 2010

Second International Symposium on Block and Sublevel Caving Perth, 20–22 April 2010

Advanced Mine Seismicity Seminar Perth, 8–11 June 2010

Rheology Workshop Perth, 22–23 June 2010

Open Pit Rock Mass Modelling Seminar Perth, 29–30 July 2010

Ground Support for Underground and Open Pit Mines (Basic Level) Short Course Perth, 25–26 August 2010

Tailings Workshop Perth, 28 September 2010


First International Seminar on the Reduction of Risk in the Management of Tailings Perth, 29 September –
and Mine Waste 1 October 2010
Blasting for Stable Slopes (Open Pit) Perth, 17–19 November 2010

In-Pit Waste Storage and Management Seminar Perth, 8–9 December 2010

14th International Seminar on Paste and Thickened Tailings Perth, 4–8 April 2011
* The ACG event schedule is subject to change. For event updates, please visit www.acg.uwa.edu.au/events_and_courses

ACG Underground Drilling and Blasting – A safety training DVD


for underground metalliferous mine workers
All underground mine workers will be exposed to drilling and blasting processes. The aim of this new DVD is to provide workers with the critical
knowledge on drilling and blasting to aid appreciation of the importance of these mining processes and their related hazards. The DVD will feature
an introduction to the rock breaking process in mining and a description of explosives and how they work. The second part of the DVD will cover
development drilling and blasting practices; while the third part will cover production drilling and blasting. The ACG acknowledges the project sponsors’
generous support.

The ACG invites your organisation to sponsor this new training DVD. Contact the ACG for more information.

For many mining companies, ACG training products have become an integral and essential component of their training programmes. For the full list of the
ACG’s successful suite of geotechnical mine worker training DVDs, please visit www.acg.uwa.edu.au/training_products.

The ACG team wishes you and your


Festive Greetings family a very merry Christmas and a
happy New Year. We thank you for your
support and encouragement during 2009
and look forward to an exciting 2010.
Our office will be closed from Wednesday
23rd December 2009, reopening on
Wednesday 6th January 2010.

Australian Centre for Geomechanics PO Box 3296 – Broadway, Nedlands, Western Australia, AUSTRALIA 6009
Ph + 61 8 6488 3300 Fax +61 8 6488 1130 acginfo@acg.uwa.edu.au www.acg.uwa.edu.au
24 Australian Centre for Geomechanics • December 2009 Newsletter
ACG December 2009 Newsletter
Article References

Sublevel caving — past and future


by William Hustrulid, University of Utah; and the Colorado School of Mines, USA, and Rudolph Kvapil, USA

Bullock, R.L., and Hustrulid, W.A. (2001), Planning the underground mine on the basis of mining method, Underground Mining
Methods: Engineering Fundamentals and International Case Studies (Ed. W.A. Hustrulid and R.L. Bullock), SME, Littleton,
Colorado, pp 29-48.
Coates, D.F. (1981), Rock Mechanics Principles, Monograph 874 (revised), CANMET Energy, Mines and Resources.
Hollins, B., and Tucker, J. (2004), Drawpoint analysis using a marker trial at the Perseverance nickel mine, Leinster, Western
Australia, Proceedings, MassMin 2004, Santiago, Chile, pp
Hustrulid, W., and Johnson, J. (2008), A gas pressure-based drift round blast design methodology, Proceedings, MassMin 2008,
Luleå, Sweden
Janelid, I. (1961), Introductory speech, Sublevel Caving Discussion Meeting, Series B, Number 32, March 29, 1962, pp 3-7.
Janelid, I. (1972), Study of the gravity flow process in sublevel caving. International Sublevel Caving Symposium, Stockholm,
September.
Janelid, I., and Kvapil, R. (1965), Sublevel caving, Int. Jour. Rock Mech. and Min. Sci. vol. 3, pp 129-153.
Johansson, C.H. and Persson, P-A (1970), Detonics of High Explosives, Academic Press, London, 330pp.
Kvapil, R. (1955), Theory of the Flow of Granular and Coarse Materials in Hoppers (In Czech), State Technical Literature
Publishing Company (SNTL), Prague.
Kvapil, R. (1982), The mechanics and design of sublevel caving systems, Underground Mining Methods Handbook (Ed W.A.
Hustrulid), SME, AIME, New York, pp 880- 897.
Kvapil, R. (1992), Sublevel caving. SME Mining Engineering Handbook, 2nd Edition (Ed H.L. Hartman), SME, Littleton, Colorado,
pp 1789-1814.
Kvapil, R. (2004), Gravity Flow in Sublevel and Panel Caving - A Common Sense Approach. Book/CD published with very limited
circulation.
Larsson, L. (1996), Personal communication.
Larsson, L. (2007), Personal communication.
Marklund, I., and Hustrulid, W. (1995), Large-scale underground mining, new equipment and a better underground environment
– result of research and development at LKAB, Sweden, Institution of Mining and Metallurgy, V104, pp A164-A168.
September- December.
McCormick, R.J. (1968), How wide does a drawpoint draw? Engineering and Mining Journal, 169(6):106-116.
Minelco (2007), From the Minelco selection, www.minelco.com
Newman, T. (1997), “Blasting of intact ore against caved waste rock at Kiruna, Senior Thesis, University of South Australia.
Newman, T., Hustrulid, W., and Quinteiro, C (2008), Sublevel caving trial - blasting of an ore slice against caved rock at the Kiruna
mine, Proceedings, MassMin 2008, Luleå, Sweden
Nordqvist, a (2007), Personal communication.
Ohlsson, K. (1961), Summary of contributions regarding sublevel caving in Sweden in 1960, Sublevel Caving Discussion Meeting,
Series B, Number 32, March 29, 1962, pp 8-15
Peele, R. (1918), Mining Engineers’ Handbook. John Wiley & Sons, New York.
Quinteiro, C., Hustrulid, W., and Larsson, L. (2001), Theory and practice of very large scale sublevel caving, Underground Mining
methods – Engineering Fundamentals and International Case Studies (Ed: Hustrulid and Bullock: pp381-384), SME,
Littleton,Colorado.
Redaelli, L.L. (1963), Sublevel caving at Koskullskulle, Mine and Quarry Engineering, June, pp 261-264.
Sandström, P.O. (1972), Application and optimization of sublevel caving techniques, Engineering and Mining Journal, 173(6):112
- 125.
Simetric (2007), Density of materials, www.simetric.co.uk/si_materials.htm
Szwedzicki, T., and Cooper, R. (2007), Ore flow and fragmentation at Perseverance mine, Proceedings, 1st International
Symposium on Block and Sub-Level Caving, Southern African Institute of Mining and Metallurgy, pp 133 – 146.
The changing profile of risk associated with
in-pit placement of waste
by Raymond Yost, Rio Tinto Minerals – Boron Operations, USA

A-Grivas, D. and Harr, M. E., 1979, A Reliability Approach to the Design of Soil Slopes, Design Parameters in Geotechnical
Engineering, Proceedings of the 7th European Conference, Soil Mechanics and Foundation Engineering, pp. 95-100.
Brox, D. R., and Newcomen, H. W., 2004, Utilizing Strain Criteria to Predict Highwall Stability Performance, Society of Mining and
Metallurgical Engineering Annual Meeting, Denver, CO.
Call, R. D., Savely, J. P., and Nicholas, D. E., 1977, Estimation of Joint Set Characteristics from Surface Mapping Data: Monograph
1 on Rock Mechanics Applications in Mining. Papers presented at the 17th U.S. Symposium on Rock Mechanics (Snowbird,
Utah, August, 1976), pp. 65-73, New York; Society of Mining Engineers.
Chowdhury, R. N. and A-Grivas, D., 1982, Probabilistic Model of Progressive Failure of Slopes, Journal of Geotechnical
Engineering, Division American Society of Civil Engineers, vol. 108, pp. 803-819.
Chowdhury, R. N., 1984, State of the Art Report on Probabilistic Methods in Landslide Studies, IV International Symposium on
Landslides, vol. 1, pp. 209-228.
Chowdhury, R. N. and Derooy, E. R., 1985, Progressive Reliability of a Strain-Softening Slope, Transactions of the Institution of
Engineers, Australia, vol. CE27, pp. 79-94.
Cooper, D. M. 1962, Slope Stability (June 13th Slide), internal memorandum
Cooper D. M. 1963, Comparison of Major Slides (June, 1962 and April, 1963), internal memorandum.
Cooper, D. M. 1964, Slope Stability, South Wall (Continuation of the June 1962 Slide) EP-0543, internal memorandum
Cooper, D. M. and Paulsen, J. C. 1963, Handling of the April, 1963 Slide, Report Number BE-75, internal memorandum.
Cooper, D. M. and Paulsen, J. C. 1965, South Wall Remedial Action (Meeting, March 10,1965), internal memorandum
Eisebraun, G. F., 1970, Unloading of the Northeast Pit Wall (Extension 17), internal memorandum.
Fell, R., 1994, Landslide Risk Assessment and Acceptable Risk, Canadian Geotechnical Journal, vol. 31, pp. 261-272.
GAB Robins, 2000, re: Open it Wall Failure - Fourteenth Report, fax to Royal & Sun Alliance, April 12, 2000.
Glass, C. E., Savely, J. P., and Call, R. D., 1978, Determining Seismic Risk for Economic Optimum Slope Design, 19th U.S.
Symposium on Rock Mechanics, Nevada, pp. 1-6.
Hachich, W. and VanMarcke, E. H., 1983, Probabilistic Updating of Pore Pressure Fields, Journal of Geotechnical Engineering,
Division American Society of Civil Engineers, vol. 109 (3), pp. 373-387.
Heslop, T.G. and Milne, P. R. G., 2003, A Practical Example of a Risk-Based Approach to the Design of an Open Pit, Fifth Large
Open Pit Mining Conference, Kalgoorlie, Australia, p. 215 – 224.
Krahn, J., 2004, Stability Modeling with SLOPE/W: An Engineering Methodology, GEO-SLOPE International Ltd. Calgary, Alberta,,
Canada.
Li, K. S., 1991a Fallacies of Current Probabilistic Approaches to Progressive Slope Failure, Sixth International Conference
on Applications of Statistics and Probability in Civil Engineering, vol. 2, pp 784-791.
Li, K. S., 1991b Some Common Mistakes in Probabilistic Analysis of Slopes, Landslides: Proceedings of the Sixth International
Symposium, Christchurch, vol. 1, pp. 475-480.
Maddocks, C. A., 1981, Extensions 22S and K-1 Design, internal memorandum.
Maddocks, C. A., 19872, July 1984 East Wall Slide, internal memorandum.
Marek, J. M. and Savely, J. P., 1978, Probabilistic Analysis of the Plane Shear Failure Mode: 19th US Symposium on Rock
Mechanics, Nevada.
McMahon, B. K., 1971, Statistical Method for the Design of Rock Slopes, Proceedings of the First Australian – New Zealand
Conference for Geomechanics, Melbourne, Australia.
Miller, S.M., Whyatt, J. K., McHugh, E. L., 2004, Applications of the Point Estimation Method for Stochastic Rock Slope
Engineering, in Gulf Rocks 2004: Rock Mechanics Across Borders and Disciplines, Proceedings of the 6th North American
Rock Mechanics Conference, Huston, TX.
Morriss, P. and Stoter, H. J., 1983, Open-cut Slope Design Using Probabilistic Methods, Proceedings of the Fifth Congress,
International Society of Rock Mechanics, Section C, pp. 107 – 112.
National Research Council (NRC), 1995, Probabilistic Methods in Geotechnical Engineering, The National Academy of Sciences,
Washington D.C.
Norrman, J. 2004, On Bayesian Decision Analysis for Evaluating Alternative Actions at Contaminated Sites, Rapport 67, Swedish
Geotechnical Institute, Goteberg, Sweden, 266 pgs.
Siefke, J. W., 1970, Geological Aspects of Slope Failure in Extension 17, internal memorandum.
Siefke, J. W., 1982, Slope Stability, internal memorandum.

Stacey, T. R., Terbrugge, P. J., Keyter, G. J., and Xianban, Y., 2003, Extension Strain – A New Concept in Open Pit Slope Stability
and its Use in the Explanation of Two Slope Failures, Fifth Large Open Pit Mining Conference, Kalgoorlie, Austraila,
p. 259 – 266.
U.S. Army Corps of Engineers (USACE), 1995, Introduction to Probability and Reliability Methods for Use in Geotechnical
Engineering, Department of the Army, Washington D.C., Technical Letter No. 1110-2-547
U.S. Army Corps of Engineers (USACE), 1999, Risk-Based Analysis in Geotechnical Engineering for Support of Planning Studies,
Department of the Army, Washington, D.C., Technical Letter No.1110-2-556
Vanmarcke, E. H. 1980, Probabilistic Stability Analysis of Earth Slopes, Engineering Geology, vol. 16, pp. 29-50.
Zavodni, Z. M., 2001, Time-Dependent Movement of Open Pit Slopes, Slope Stability in Surface Mining, Society for Mining,
Metallurgy and Exploration, pp. 81-87.

Summer vacation students in winter


by Peter Hills, Tasmania Mine Joint Venture, BCD Resources (Operations) NL

Hills, P.B. & Penney, A.R., 2008. Management of seismicity at the Beaconsfield Gold Mine, Tasmania. In, Proceedings of the
Tenth AusIMM Underground Operators’ Conference 2008. The Australasian Institute of Mining & Metallurgy: Melbourne.
Pp. 157-170.
Hills, P.B., Mills, J., Penney, A.R., & Arthur, S., (2008). The development and implementation of a fully remote stoping method at
Beaconsfield Gold Mine, Tasmania. In, Proceedings of the Narrow Vein Mining Conference 2008. The Australasian Institute
of Mining & Metallurgy: Melbourne. Pp. 199-206.
King, R., Thomas, S. & Scott, C., 2007. Geotechnical assessment – resumption of ore production (East Zone). Coffey Mining P/L
Report No. HZ00054.01.BH.
Penney, A.R., Hills, P.B. & Walton, R.J., (2008). The use of geotechnical instrumentation to optimise an engineered mine design
at Beaconsfield Gold Mine, Tasmania. In, Proceedings of the Narrow Vein Mining Conference 2008. The Australasian
Institute of Mining & Metallurgy: Melbourne. Pp. 165-172.
Pfitzner, M., 2006 Geotechnical assessment – resumption of decline developments. Coffey Mining P/L Report No.
HZ00054.01.A1.
Scott, C. & Reeves, I., 2007. Geotechnical assessment – resumption of ore production (West Zone). Coffey Mining P/L Report
No. HZ00054.01.BY.
Sidea, D., Scott, C. & Reeves, I. 2007. Geotechnical assessment – resumption of ore driving development. Coffey Mining P/L
Report No. HZ00054.01.AT.

The risk of tailings disposal


by Keith Seddon, ATC Williams

Australian National Committee on Large Dams “Guidelines on Tailings Dam Design Construction and Operation” October 1999.
“Safety of Tailings Dams” http://www.wise-uranium.org/mdas.html
Standards Australia AS/NZS 4360:2004 Risk Management.

Increasing value in mining operations


through the application of paste
by Nick Slade and Stephen Wilson, Golder Paste Technology (Europe) Ltd; Florencio Felipe, Xstrata Copper,
Mount Isa Copper Operations; Frank Palkovits, Golder Paste Technology Ltd

Runge I,C,1998. Mining Economics and Strategy. (Society for Mining, Metallurgy and Exploration, Inc) United States.
ASTM C143 / C143M – 08, 2008. Standard Test Method for Slump of Hydraulic-Cement Concrete. (ASTM International) United
States.
MacNamara, L. 2009. (FLSmidth Dorr Oliver Eimco Ltd) Personal Communication on large scale applications and paste thickener
evolution.

You might also like