MC Template Revisions 01/16/18

1. Add multiplier "n.ca" to bolt shear strength in bolt bearing capacity of beam web (Double Angle Bolted-Bolted
Connection) on MC templates only (A51)

2. Revise the k-distance used in Web Compression Buckling Check (k.col ---> kdes.col) (A50)

3. Revise Bearing Capacity Equation (A52)


4. Remove additional clear distance in computing weld length for bottom beam flange connection (MC 2 or 3 Way -
Top Condition) (C21)

5. Revise CJP weld capacity on MC Directly Welded Beam Flanges to Stiffener Plate (C22)

6. Revise shear plate weld length computation on MC Top Condition (Dd20)


7. Remove repeated tolerance in Default Computation of Cap Plate Thickness (Dj2)

8. Revise to retain landing and change k.col to kdes.col in scheme (Ea6)

9. Revise computation for default thickness of top and bottom stiffener plate (2-way perpendicular and 3 way MC)
(Eb12)
10. Add Bearing Capacity Check of Stiffener Plate at Column Web for MC 2 Way Perpendicular (Eb10)

11. Revise Stiffener Plate to Column Web Connection using Fillet Weld, PJP and CJP (Eb11)

12. Revise argument for reinforcement requirement of Bolted Beam Flange Connection (Ee2)

13. Revise Cap Plate Design Forces on MC 2-Way Perpendicular, 3-Way and 4-Way (F19)
14. Add argument for fully developed bearing strength of beam flanges (H47)

15. Revise Force Acting on the column web with single doubler plate (F20)

16. Revise weld length of Direclty Welded Beam Web to Column Flange considering weld access hole (H48)
17. Revise Plastic Section Modulus of Flange Panel Zone Shear (A53)

18. Revised Plate Yielding Interaction Result Box Argument for Directly Welded Beams Two-Way Perpendicular and
2 Way Strong Axis & 1 Way Weak Axis (Eb13)
19. Revise Cap Plate to Column Weld Check (Dj1)

20. Add word "Backup" to fall under Ldp.ex for MC 2-Way perpendicular only (Ea7)

21. Revise Load and Weld Capacity of Cap Plate to Column Web on MC 2-Way Perpendicular Top Condition (Dj3)

22. Add consideration of number of doubler plate in effective weld size of shear plate to column web MC
connection (Dd21)
23. Revise Flange Forces for Directly Welded Flange Plate to Beam Flange Connection (F21)

24. Add "n.ca" multiplier to consider two planes subject to rupture for MC web connection only (Dc10)

25. Revise Unsupported Length for Compression Capacity of Welded Beam Flange to Girder Flange (A54)

26. Revise Governing Force to check for Shear Yielding of Girder Web of 2 Way MC (Bolted Flange Plate at Backspan
and Directly Welded Beam Flange Cantilever) (A55)

27. Revise Stiffener Weld Force of Beam to Girder (MC Uneven Depth) (F22)
28. Add the missing beam block shear check for MC011-1-2 (A56)

29. Add the missing shear rupture capacity of reduced section for MC011-1-2 (A57)

30. Add the missing shear capacity of reduced section for MC011-1-2 (A58)

31. Remove weld check of shear plate to girder flange on MC011-1-2 (Dd22)
32. Revise Weld Check of Flange Plate to Girder Flange (De4)

33. Add tension rupture check of flange plate to girder flange (De5)