PROJECT : BEVERLY HILLS 43 PRGRESS UPDATE 23-APR-2018

VILLAS (G+1+P) AT AL FOR CIVIL WORKS


RAYYAN CITY
CLIENT : HALUL REAL ESTATE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

43 Villas at Beverly Hills, Al Rayyan City ‐ Approved 18 439 22‐Feb‐17


CONSTRUCTION 439 22‐Feb‐17
PROFILE 1 367 22‐Feb‐17
VILLAS 5&6 78 15‐Apr‐18
ARCHITECTURAL & MEP WORKS 78 15‐Apr‐18
ARCHITECTURAL WORKS 78 15‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 76 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 3
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 10 15‐Apr‐18
Installa on of Handrails/ balustrade complete with accessories‐ G 3 50% 15‐Apr‐18
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
PAINTING AND DECORATIVE WORKS 76
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 3
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9 15‐Apr‐18
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 5% 15‐Apr‐18
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 78
Applicaton of 1st coat paint‐ FF 2 0%
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 1 19‐May‐18
Terrazo skir ng works‐ RF 1 50% 19‐May‐18
ROOFING WORKS 3
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 8 15‐Apr‐18
Install Handrails complete with accessories‐ RF 2 5% 15‐Apr‐18
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 1
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 8
Pergola installa on works 8 0%
VILLAS 7&8 78 21‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
ROOF FLOOR SLAB CONCRETE WORKS 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 78 21‐Apr‐18
ARCHITECTURAL WORKS 78 21‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 76 28‐May‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 65 28‐May‐18
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 80% 28‐May‐18
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%

Page 1 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 26
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 2
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74
MASONRY, FLOOR/WALL/CEILING FINISHING WO 3
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
ROOFING WORKS 3
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 1
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 12 21‐Apr‐18
External surface Paint prepara on 3 5% 21‐Apr‐18
Main Entrance Porch Marble Works 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
VILLAS 9&10 91 10‐Feb‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 91 10‐Feb‐18
ARCHITECTURAL WORKS 91 10‐Feb‐18
GROUND FLOOR ARCHITECTURAL WORKS 76 02‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 36 02‐Apr‐18
Ceramic Floor Tiling works Dry Area‐ GF 4 50% 02‐Apr‐18
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 68
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%

Page 2 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

FIRST FLOOR ARCHITECTURAL WORKS 86 20‐Mar‐18


MASONRY, FLOOR/WALL/CEILING FINISHING WO 53 20‐Mar‐18
Internal Stairs Marble Laying‐ FF 2 90% 20‐Mar‐18
Ceramic Floor Tiling works Dry Areas‐ FF 7 10% 02‐Apr‐18
Wet area waterproofing works‐ FF 3 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 2
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74 20‐Mar‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 38 20‐Mar‐18
Internal Stairs Marble Skir ng works‐ RF 1 88.57% 20‐Mar‐18
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Internal Stairs Marble Laying‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
ROOFING WORKS 61
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 1
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 88 10‐Feb‐18
External Plastering Works 6 95% 10‐Feb‐18
External surface Paint prepara on 3 0%
Main Entrance Porch Marble Works 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Installa on of Water Meters 2 0%
VILLAS 3&4 41 01‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 41 01‐Apr‐18
ARCHITECTURAL WORKS 41 01‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 36 24‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 30 24‐Apr‐18
Internal Stairs Marble Laying‐ GF 2 50% 24‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 23
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%

Page 3 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

TOILET AND LIGHTING FIXTURES 3


Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 39
MASONRY, FLOOR/WALL/CEILING FINISHING WO 35
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 41 01‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 14 01‐Apr‐18
Internal Plastering works‐ RF 5 95% 01‐Apr‐18
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 7
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 5
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 29 01‐Apr‐18
External Plastering Works 6 90% 01‐Apr‐18
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
Installa on of Water Meters 2 0%
VILLAS 11 78 15‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths concrete works 1 0%
Roof plinths Form works 1 0%
ARCHITECTURAL & MEP WORKS 78 15‐Apr‐18
ARCHITECTURAL WORKS 78 15‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 76 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 54 15‐Apr‐18
Internal Stairs Marble Laying‐ GF 2 90% 15‐Apr‐18
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%

Page 4 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

TIMBER AND METAL WORKS 9


Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 76
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78 18‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75 18‐Apr‐18
Internal Stairs Marble Laying‐ FF 2 50% 18‐Apr‐18
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 41
MASONRY, FLOOR/WALL/CEILING FINISHING WO 4
Terrazo floor Tiling works‐ RF 2 0%
Internal Stairs Marble Laying‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 7
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 19
External Plastering Works 6 0%
Main Entrance Porch Marble Works 3 0%
External surface Paint prepara on 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
VILLAS 1&2 88 07‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 88 07‐Apr‐18
ARCHITECTURAL WORKS 88 07‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 86 07‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75 07‐Apr‐18
Internal Plastering works‐ GF 12 95% 07‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%

Page 5 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Internal Stairs Marble Laying‐ GF 2 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 75
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 77 07‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 74 07‐Apr‐18
Internal Plastering works‐ FF 12 95% 07‐Apr‐18
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 41
MASONRY, FLOOR/WALL/CEILING FINISHING WO 28
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 7
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 10
MASONRY, FLOOR/WALL FINISHING WORKS 5
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 36
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
WATER TANK 77
ARCHITECTURAL & MEP WORKS 77
Internal Waterproofing Works for Water Tanks 10 0%
Block Works for Pump Room 3 0%
Installa on of steel Acess Hatch to Water Tanks 5 0%
Pump Room Internal Plastering works 8 0%

Page 6 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of Steel Ladder to Watar Tanks 8 0%
Applica on of Epoxy Coa ng for Stairs And Pump Room Floor 5 0%
Laying of Screed Concrete for Pump Room Floor And Stairs 5 0%
Applica on of Paint for Pump Room 5 0%
PROFILE 1 MEP UTILITY WORKS/ EXTERNAL FINISHING WORKS 352 22‐Feb‐17
BOUNDARY WALL WORKS 334 22‐Feb‐17
External Boundary Wall Foo ng Concre ng Works 50 100% 22‐Feb‐17
External Boundary Wall Block works 45 98% 15‐Mar‐17
Internal Par on Wall Foo ng Concre ng Works 45 98% 31‐Mar‐17
Internal Par on Wall Block Works 30 80% 15‐Mar‐18
External Boundary Wall Plastering works 40 80% 21‐Apr‐18
Internal Par on Wall Plastering Works 24 0%
STORM WATER SYSTEM 43 15‐Oct‐17
Fixing of Covers for Soak Aways and road Gullies 5 70% 15‐Oct‐17
Road Gully reinforcement and Formworks 10 0%
Road Gully Concre ng Works 8 0%
Excava on and Laying Storm Water Pipelines, Backfilling 12 0%
DRIVEWAY AND WALKWAY WORKS 63 01‐Apr‐18
Kerbstone laying works 20 10% 01‐Apr‐18
Sandbedding and Interlock laying works in Driveway 30 5% 15‐May‐18
Sandbedding and Interlock laying works in Walkway 20 5% 15‐May‐18
Fixing of Manhole Covers 4 0%
Fixing of JRC Manhole Covers 5 0%
Fixing of Valve BoxCovers 12 0%
Fixing of Electrical Manhole Covers 6 0%
FINAL TESTING AND COMMISSIONING + SNAGGING WORKS 30
Final Tes ng and Commissioning of Systems & Snagging Works 30 0%
PROFILE 2 274 03‐May‐17
VILLAS 12&13 109 22‐Feb‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 109 22‐Feb‐18
ARCHITECTURAL WORKS 109 22‐Feb‐18
GROUND FLOOR ARCHITECTURAL WORKS 76 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 69 15‐Apr‐18
Internal Stairs Marble Laying‐ GF 2 50% 15‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 76
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 76
MASONRY, FLOOR/WALL/CEILING FINISHING WO 34
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%

Page 7 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 107 22‐Feb‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 47 22‐Feb‐18
Internal Plastering works‐ RF 5 94.87% 22‐Feb‐18
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 22
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 14&15 82 01‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 82 01‐Apr‐18
ARCHITECTURAL WORKS 82 01‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 73
MASONRY, FLOOR/WALL/CEILING FINISHING WO 65
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 52
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8

Page 8 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Paint surface prepara on and applica on of  pu y‐ FF 3 0%


Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 78 01‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 7 01‐Apr‐18
Internal Plastering works‐ RF 5 95% 01‐Apr‐18
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 65
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
MOSQUE 78
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 78
ARCHITECTURAL WORKS 78
GROUND FLOOR ARCHITECTURAL WORKS 73
MASONRY, FLOOR/WALL/CEILING FINISHING WO 65
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 40
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 66
MASONRY, FLOOR/WALL/CEILING FINISHING WO 63
Internal Plastering works‐ FF 12 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%

Page 9 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 50
MASONRY, FLOOR/WALL/CEILING FINISHING WO 33
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 37
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 65
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 16&17 111 22‐Feb‐18
ARCHITECTURAL & MEP WORKS 111 22‐Feb‐18
ARCHITECTURAL WORKS 111 22‐Feb‐18
GROUND FLOOR ARCHITECTURAL WORKS 73
MASONRY, FLOOR/WALL/CEILING FINISHING WO 65
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 52
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%

Page 10 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 107 22‐Feb‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 36 22‐Feb‐18
Internal Plastering works‐ RF 5 94.87% 22‐Feb‐18
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 65
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 20 78
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths concrete works 1 0%
Roof plinths Form works 1 0%
ARCHITECTURAL & MEP WORKS 78
ARCHITECTURAL WORKS 78
GROUND FLOOR ARCHITECTURAL WORKS 73
MASONRY, FLOOR/WALL/CEILING FINISHING WO 65
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 52
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%

Page 11 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74
MASONRY, FLOOR/WALL/CEILING FINISHING WO 57
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 5
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 65
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 18&19 81 21‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 81 21‐Apr‐18
ARCHITECTURAL WORKS 81 21‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 73 26‐May‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 69 26‐May‐18
Wet area waterproofing works‐ GF 3 0%
Internal Stairs Marble Laying‐ GF 2 50% 26‐May‐18
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 52
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 76 26‐May‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 54 26‐May‐18
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%

Page 12 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Internal Stairs Marble Laying‐ FF 2 50% 26‐May‐18


Suspended Ceiling works Dry Area‐ FF 5 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 8
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74 26‐May‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 57 26‐May‐18
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 50% 26‐May‐18
Internal Stairs Marble Skir ng works‐ RF 1 50% 26‐May‐18
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 5 21‐Apr‐18
ROOFING WORKS 5 21‐Apr‐18
Roof Waterproofing works‐ UR 5 50% 21‐Apr‐18
ELEVATION RENDERING WORKS 65
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
SUBSTATION 3
ARCHITECTURAL & MEP WORKS 3
External Pain ng Works 3 0%
SWIMMING POOL AND PUMPROOM 73 21‐Apr‐18
SWIMMING POOL PUMP ROOM WORKS 73 21‐Apr‐18
SWIMMING POOL PUMP ROOM STRUCTURAL WORKS 46 21‐Apr‐18
Excava on of Site Area for Swimming Pool Pump room 4 90% 21‐Apr‐18
Prepara on for Blinding & Applying An ‐Termite Treatement 1 0%
Ra  Blinding + Curing 1 0%
Waterproofing Works for Ra 2 0%
Reinforcement and Formworks For Ra 3 0%
Ra  Concre ng + Curing 1 0%
Reinforcement, MEP Works for Walls 4 0%
Formworks For Wall 3 0%
Wall Concre ng + curing 1 0%
Form Work For Top Slab and Stair 2 0%
MEP Services for Top Slab 2 0%
Reinforcement Works For Top Slab and Stair 3 0%
Concre ng of Top Slab and Stair 1 0%
Ver cal Waterproofing Works on Walls External 3 0%
Backfilling External sides of Pump Room Walls 2 0%
SWIMMING POOL PUMP ROOM ARCHITECTURAL/ MEP WO 24
Pump Room Internal Plastering works 8 0%
Applica on of Epoxy Coa ng for Stairs And Pump Room Floor 4 0%
Applica on of Paint for Pump Room 4 0%
Installa on of Stair GI Handrails 4 0%
SWIMMING POOL WORKS 41
SWIMMING POOL STRUCTURAL WORKS 41
Excava on of Site Area for Swimming Pool 3 0%
Prepara on for Blinding & Applying An ‐Termite Treatement 1 0%
Ra  Blinding + Curing 1 0%
Waterproofing Works for Ra 2 0%
Reinforcement, MEP and Formworks For Ra 6 0%
Ra  Concre ng + Curing 1 0%
Reinforcement, MEP Works for Walls 5 0%
Formworks For Wall 3 0%

Page 13 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Wall Concre ng + curing 1 0%
Ver cal Waterproofing Works on Walls External 2 0%
Backfilling External sides of Swimming Pool Walls 2 0%
SWIMMING POOR ARCHITECHURAL/ MEP WORKS 3
Internal Waterproofing Works for Swimming Pool 3 0%
VILLAS 21 & 22 79
STRUCTURAL WORKS 17
SUPER STRUCTURE CONCRETE WORKS 17
ROOF FLOOR SLAB CONCRETE WORKS 8
Column reinforcement works going to Roof Floor 5 0%
Column formwork going to Roof Floor Slab 2 0%
Column Concrete pour going to Roof Floor Slab 2 0%
Formwork for Slab & Stair @Roof Floor 2 0%
Reinforcement for Slab & Stair @Roof Floor 2 0%
Concrete pour for Slab & Stair+Curing @Roof Floor 1 0%
UPPER ROOF SLAB CONCRETE WORKS 7
Column reinforcement works going to Upper Roof Floor 2 0%
Column formwork going to Upper Roof Floor Slab 2 0%
Column Concrete pour going to Upper Roof Floor Slab 1 0%
Reinforcement for Slab @Upper Roof Floor 4 0%
Formwork for Slab @Upper Roof Floor 4 0%
Concrete pour for Slab +Curing @Upper Roof Floor 1 0%
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 68
ARCHITECTURAL WORKS 68
GROUND FLOOR ARCHITECTURAL WORKS 68
MASONRY, FLOOR/WALL/CEILING FINISHING WO 68
Block work‐ GF 5 0%
Internal Plastering works‐ GF 5 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 13
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
FIRST FLOOR ARCHITECTURAL WORKS 55
MASONRY, FLOOR/WALL/CEILING FINISHING WO 34
Block work‐ FF 5 0%
Internal Plastering works‐ FF 5 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
TIMBER AND METAL WORKS 26
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 5
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 37
MASONRY, FLOOR/WALL/CEILING FINISHING WO 28
Block work‐ RF 4 0%
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%

Page 14 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 22
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 6
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 26
Scaffolding for external rendering works 3 0%
External Plastering Works 3 0%
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 6 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
CLUBHOUSE 92 14‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 92 14‐Apr‐18
ARCHITECTURAL WORKS 92 14‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 91 14‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 88 14‐Apr‐18
Block work‐ GF 5 60% 14‐Apr‐18
Internal Plastering works‐ GF 5 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 21
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 74
MASONRY, FLOOR/WALL/CEILING FINISHING WO 52
Block work‐ FF 12 0%
Internal Plastering works‐ FF 5 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
TIMBER AND METAL WORKS 9
Installa on of Windows Complete with Frame‐ FF 2 0%

Page 15 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 60
MASONRY, FLOOR/WALL/CEILING FINISHING WO 43
Block work‐ RF 4 0%
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 30
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 5
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 29
Scaffolding for external rendering works 2 0%
External Plastering Works 4 0%
External surface Paint prepara on 2 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
PROFILE 2 MEP UTILITY WORKS/ EXTERNAL FINISHING WORKS 274 03‐May‐17
STORM WATER SYSTEM 30
Road Gully reinforcement and Formworks 10 0%
Road Gully Concre ng Works 8 0%
Excava on and Laying Storm Water Pipelines, Backfilling 20 0%
BOUNDARY WALL WORKS 74 03‐May‐17
External Boundary Wall Block works 45 95% 03‐May‐17
Internal Par on Wall Block Works 5 60% 01‐Apr‐18
Internal Par on Wall Plastering Works 5 0%
External Boundary Wall Plastering works 40 50% 07‐May‐18
DRAINAGE SYSTEM 6 20‐Aug‐17
Excava on and Laying Drain PIpes, Backfilling. 6 97.94% 20‐Aug‐17
POTABLE WATER SUPPLY SYSTEM 20 21‐Oct‐17
Excava on and Laying of Water Supply Pipes, Backfilling. 20 95% 21‐Oct‐17
ELECTRICAL POWER SUPPLY SYSTEM 67 10‐Sep‐17
Electrical Manhole excava on Works 6 94.89% 10‐Sep‐17
Electrical Manhole reinforcement and Formworks 6 95% 14‐Sep‐17
Electrical Manhole Concre ng Works 6 95% 16‐Sep‐17
Excava on and making provisions for laying power cables 45 95% 18‐Sep‐17
DRIVEWAY AND WALKWAY WORKS 50 22‐Jul‐17
Backfilling, Levelling and Compa on of Driveway area 20 95% 22‐Jul‐17
Kerbstone laying works 20 10% 21‐May‐18
Sandbedding and Interlock laying works in Driveway 30 0%
Sandbedding and Interlock laying works in Walkway 20 0%
Fixing of Manhole Covers 4 0%
Fixing of JRC Manhole Covers 5 0%
PROFILE 3 304 28‐Mar‐17
VILLAS 42&43 88 15‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%

Page 16 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 88 15‐Apr‐18
ARCHITECTURAL WORKS 88 15‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 83 15‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75 15‐Apr‐18
Internal Plastering works‐ GF 12 95% 15‐Apr‐18
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 18
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 72
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
Applica on of 2nd coat (final paint coat)‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 78
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 18
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 7
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 74
MASONRY, FLOOR/WALL/CEILING FINISHING WO 57
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 66
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 17
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
ELEVATION RENDERING WORKS 65
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 40&41 88 14‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2

Page 17 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

TOP OF ROOF AND PARAPET WALL 2


Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 88 14‐Apr‐18
ARCHITECTURAL WORKS 88 14‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 79 14‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 75 14‐Apr‐18
Internal Plastering works‐ GF 12 20% 14‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 41
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 42
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 76 21‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 73 21‐Apr‐18
Internal Plastering works‐ FF 12 5% 21‐Apr‐18
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 19
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 48
MASONRY, FLOOR/WALL/CEILING FINISHING WO 31
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 40
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 17
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 10
MASONRY, FLOOR/WALL FINISHING WORKS 5
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 65
Applicaton of 1st coat paint on External surfaces 2 0%

Page 18 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 38&39 78 14‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 78 14‐Apr‐18
ARCHITECTURAL WORKS 78 14‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 67 14‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 63 14‐Apr‐18
Internal Plastering works‐ GF 12 80% 14‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 42
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 50
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 73 14‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 70 14‐Apr‐18
Internal Plastering works‐ FF 12 60% 14‐Apr‐18
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 19
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 10
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 39
MASONRY, FLOOR/WALL/CEILING FINISHING WO 22
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 31
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 17
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4

Page 19 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Paint surface prepara on and applica on of  pu y‐ RF 2 0%


Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 10
MASONRY, FLOOR/WALL FINISHING WORKS 5
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 27
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
VILLAS 36&37 77 21‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 77 21‐Apr‐18
ARCHITECTURAL WORKS 77 21‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 67 21‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 63 21‐Apr‐18
Internal Plastering works‐ GF 12 50% 21‐Apr‐18
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 42
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 46
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 41
MASONRY, FLOOR/WALL/CEILING FINISHING WO 41
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 19
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 33
MASONRY, FLOOR/WALL/CEILING FINISHING WO 16
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 25

Page 20 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 17
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 10
MASONRY, FLOOR/WALL FINISHING WORKS 5
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 21
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Pergola installa on works 8 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Garage Interlock laying works 4 0%
VILLAS 34&35 74
STRUCTURAL WORKS 6
SUPER STRUCTURE CONCRETE WORKS 6
TOP OF ROOF AND PARAPET WALL 6
Roof plinths reinforcement works 1 0%
Roof plinths Form works 5 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 74
ARCHITECTURAL WORKS 74
GROUND FLOOR ARCHITECTURAL WORKS 60
MASONRY, FLOOR/WALL/CEILING FINISHING WO 57
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 28
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 48
MASONRY, FLOOR/WALL/CEILING FINISHING WO 47
Internal Plastering works‐ FF 12 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
TIMBER AND METAL WORKS 13
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%

Page 21 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 38


MASONRY, FLOOR/WALL/CEILING FINISHING WO 21
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 25
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 13
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 10
MASONRY, FLOOR/WALL FINISHING WORKS 5
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 24
Scaffolding for external rendering works 3 0%
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
Garage Interlock laying works 4 0%
VILLAS 32&33 78
STRUCTURAL WORKS 51
SUB STRUCTURE CONCRETE WORKS 21
Excavate the site area for founda on 2 0%
Prepara on works for concrete blinding + termite treatment 3 0%
Rebar work for Foo ng & Columns Neck 3 0%
Founda on Blinding + Curing 1 0%
Form work for Foo ng & Columns Neck 2 0%
Concrete pour for Foo ng & Columns Neck 1 0%
Apply Bituminous Paint coat on the Foo ng & Columns Neck surfa 1 0%
Back fill up to the bo om of Grade Beam and Blinding for Grade Be 2 0%
Formwork and rebar work for Grade Beam 3 0%
Concrete pour for Grade Beam+Curing 1 0%
Apply Bituminous Paint coat for Ver cal surfaces 1 0%
Back fill up to Grade Slab Base 3 0%
Termite treatment + Polythene sheet 1 0%
MEP services @Grade Slab 1 0%
Formwork and rebar work for Grade Slab with Mesh + Filler board 1 0%
Concrete pour for Grade Slab + Curing 1 0%
SUPER STRUCTURE CONCRETE WORKS 30
FIRST FLOOR SLAB CONCRETE WORKS 9
Column reinforcement works going to Floor 1 3 0%
Column formwork going to Floor 1 Slab 2 0%
Column Concrete pour going to Floor 1 Slab 2 0%
Formwork for Slab & Stair @Floor 1 5 0%
MEP services for Slab @Floor 1 5 0%
Reinforcement for Slab & Stair @Floor 1 5 0%
Concrete pour for Slab & Stair+Curing @Floor 1 1 0%
ROOF FLOOR SLAB CONCRETE WORKS 12
Column reinforcement works going to Roof Floor 5 0%
Column formwork going to Roof Floor Slab 2 0%
Column Concrete pour going to Roof Floor Slab 2 0%
Formwork for Slab & Stair @Roof Floor 6 0%
Reinforcement for Slab & Stair @Roof Floor 6 0%
Concrete pour for Slab & Stair+Curing @Roof Floor 1 0%
UPPER ROOF SLAB CONCRETE WORKS 7
Column reinforcement works going to Upper Roof Floor 2 0%
Column formwork going to Upper Roof Floor Slab 2 0%
Column Concrete pour going to Upper Roof Floor Slab 1 0%
Reinforcement for Slab @Upper Roof Floor 4 0%

Page 22 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Formwork for Slab @Upper Roof Floor 4 0%
Concrete pour for Slab +Curing @Upper Roof Floor 1 0%
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 34
ARCHITECTURAL WORKS 34
GROUND FLOOR ARCHITECTURAL WORKS 34
MASONRY, FLOOR/WALL/CEILING FINISHING WO 34
Block work‐ GF 10 0%
Internal Plastering works‐ GF 12 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Wet area waterproofing works‐ GF 3 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 12
TIMBER AND METAL WORKS 12
Block work‐ FF 12 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 4
MASONRY, FLOOR/WALL/CEILING FINISHING WO 4
Block work‐ RF 4 0%
UPPER ROOF ARCHITECTURAL WORKS 5
MASONRY, FLOOR/WALL FINISHING WORKS 5
Block work‐ UR 5 0%
VILLAS 23&24 86 24‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 86 24‐Apr‐18
ARCHITECTURAL WORKS 86 24‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 59
MASONRY, FLOOR/WALL/CEILING FINISHING WO 55
Internal Plastering works‐ GF 15 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 27
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 27
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 86 24‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 83 24‐Apr‐18
Block work‐ FF 15 5% 24‐Apr‐18
Internal Plastering works‐ FF 12 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 19

Page 23 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
TOILET AND LIGHTING FIXTURES 3
Install Toilet appliance and accessories‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 60
MASONRY, FLOOR/WALL/CEILING FINISHING WO 43
Block work‐ RF 4 0%
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 24
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 17
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 4
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 11 28‐Apr‐18
MASONRY, FLOOR/WALL FINISHING WORKS 11 28‐Apr‐18
Block work‐ UR 5 5% 28‐Apr‐18
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 23
Scaffolding for external rendering works 3 0%
External Plastering Works 6 0%
External surface Paint prepara on 3 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Main Entrance Porch Marble Works 3 0%
Service Entry Marble works 2 0%
Garage Interlock laying works 4 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
VILLAS 25&26 79 14‐Apr‐18
STRUCTURAL WORKS 2
SUPER STRUCTURE CONCRETE WORKS 2
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 79 14‐Apr‐18
ARCHITECTURAL WORKS 79 14‐Apr‐18
GROUND FLOOR ARCHITECTURAL WORKS 72 14‐Apr‐18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 72 14‐Apr‐18
Block work‐ GF 10 50% 14‐Apr‐18
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
Suspended Ceiling works Dry Area‐ GF 5 0%
Suspended Ceiling works Wet Area‐ GF 3 0%
TIMBER AND METAL WORKS 19
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
Installa on of Windows Complete with Frame‐ GF 3 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 3 0%
Installa on of Handrails/ balustrade complete with accessories‐ G 3 0%
PAINTING AND DECORATIVE WORKS 10
Paint surface prepara on and applica on of  pu y‐ GF 3 0%

Page 24 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Applicaton of 1st coat paint‐ GF 2 0%
FIRST FLOOR ARCHITECTURAL WORKS 63
MASONRY, FLOOR/WALL/CEILING FINISHING WO 63
Block work‐ FF 12 0%
Internal Plastering works‐ FF 12 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
Ceramic Tile Skir ng works‐ FF 2 0%
Ceramic Floor Tiling works Wet Area‐ FF 5 0%
Internal Stairs Marble Laying‐ FF 2 0%
Suspended Ceiling works Dry Area‐ FF 5 0%
Suspended Ceiling works Wet Area‐ FF 3 0%
TIMBER AND METAL WORKS 8
Installa on of Windows Complete with Frame‐ FF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Installa on of Handrails/ Balustrade complete with accessories‐ F 3 0%
PAINTING AND DECORATIVE WORKS 11
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
Applicaton of 1st coat paint‐ FF 2 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 55
MASONRY, FLOOR/WALL/CEILING FINISHING WO 34
Block work‐ RF 4 0%
Internal Plastering works‐ RF 5 0%
Terrazo floor Tiling works‐ RF 2 0%
Terrazo skir ng works‐ RF 1 0%
Internal Stairs Marble Laying‐ RF 2 0%
Internal Stairs Marble Skir ng works‐ RF 1 0%
ROOFING WORKS 24
Roof Waterproofing works‐ RF 4 0%
Roof Terrace Tiling Works ‐ RF 3 0%
TIMBER AND METAL WORKS 8
Installa on of Windows Complete with Frame‐ RF 2 0%
Installa on of all Timber Doors, Base Units, Wall Units & Vanity U 2 0%
Install Handrails complete with accessories‐ RF 2 0%
PAINTING AND DECORATIVE WORKS 30
Paint surface prepara on and applica on of  pu y‐ RF 2 0%
Applicaton of 1st coat paint‐ RF 1 0%
Applica on of 2nd coat (final paint coat)‐ RF 1 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
ELEVATION RENDERING WORKS 22
Scaffolding for external rendering works 3 0%
External Plastering Works 6 0%
Main Entrance Porch Marble Works 3 0%
External surface Paint prepara on 3 0%
Service Entry Marble works 2 0%
Applicaton of 1st coat paint on External surfaces 2 0%
Pergola installa on works 8 0%
Garage Interlock laying works 4 0%
Applica on of 2nd coat (final paint coat) on External surfaces 2 0%
VILLAS 27&28 85 22‐Apr‐18
STRUCTURAL WORKS 52 22‐Apr‐18
SUPER STRUCTURE CONCRETE WORKS 52 22‐Apr‐18
FIRST FLOOR SLAB CONCRETE WORKS 16 22‐Apr‐18
Formwork for Slab & Stair @Floor 1 10 10% 22‐Apr‐18
Reinforcement for Slab & Stair @Floor 1 7 20% 22‐Apr‐18
Concrete pour for Slab & Stair+Curing @Floor 1 1 0%
ROOF FLOOR SLAB CONCRETE WORKS 16 28‐May‐18
Column reinforcement works going to Roof Floor 5 0%
Column formwork going to Roof Floor Slab 2 0%
Column Concrete pour going to Roof Floor Slab 2 0%
Formwork for Slab & Stair @Roof Floor 10 0%
Concrete pour for Slab & Stair+Curing @Roof Floor 1 0%
Reinforcement for Slab & Stair @Roof Floor 6 20% 28‐May‐18
UPPER ROOF SLAB CONCRETE WORKS 18
Column reinforcement works going to Upper Roof Floor 2 0%

Page 25 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Column formwork going to Upper Roof Floor Slab 2 0%
Column Concrete pour going to Upper Roof Floor Slab 1 0%
Formwork for Slab @Upper Roof Floor 4 0%
Reinforcement for Slab @Upper Roof Floor 4 0%
Concrete pour for Slab +Curing @Upper Roof Floor 1 0%
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 55
ARCHITECTURAL WORKS 55
GROUND FLOOR ARCHITECTURAL WORKS 51
MASONRY, FLOOR/WALL/CEILING FINISHING WO 47
Block work‐ GF 10 0%
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
Ceramic Floor Tiling works Wet Area‐ GF 5 0%
TIMBER AND METAL WORKS 4
Installa on of Kitchen Cabinets with Kitchen Hood‐ GF 4 0%
PAINTING AND DECORATIVE WORKS 10
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
FIRST FLOOR ARCHITECTURAL WORKS 39
MASONRY, FLOOR/WALL/CEILING FINISHING WO 39
Block work‐ FF 12 0%
Internal Plastering works‐ FF 12 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 19
MASONRY, FLOOR/WALL/CEILING FINISHING WO 19
Block work‐ RF 4 0%
Internal Plastering works‐ RF 5 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
VILLAS 29&30 89 24‐Apr‐18
STRUCTURAL WORKS 52 24‐Apr‐18
SUB STRUCTURE CONCRETE WORKS 20 24‐Apr‐18
Back fill up to the bo om of Grade Beam and Blinding for Grade Be 5 20% 24‐Apr‐18
Formwork and rebar work for Grade Beam 3 0%
Concrete pour for Grade Beam+Curing 1 0%
Apply Bituminous Paint coat for Ver cal surfaces 1 0%
Back fill up to Grade Slab Base 6 0%
Termite treatment + Polythene sheet 1 0%
Formwork and rebar work for Grade Slab with Mesh + Filler board 2 0%
MEP services @Grade Slab 1 0%
Concrete pour for Grade Slab + Curing 1 0%
SUPER STRUCTURE CONCRETE WORKS 32
FIRST FLOOR SLAB CONCRETE WORKS 12
Column reinforcement works going to Floor 1 5 0%
Column formwork going to Floor 1 Slab 2 0%
Column Concrete pour going to Floor 1 Slab 2 0%
Concrete pour for Slab & Stair+Curing @Floor 1 1 0%
ROOF FLOOR SLAB CONCRETE WORKS 11
Column reinforcement works going to Roof Floor 5 0%
Column formwork going to Roof Floor Slab 2 0%
Column Concrete pour going to Roof Floor Slab 2 0%
Formwork for Slab & Stair @Roof Floor 5 0%
Reinforcement for Slab & Stair @Roof Floor 4 0%
Concrete pour for Slab & Stair+Curing @Roof Floor 1 0%
UPPER ROOF SLAB CONCRETE WORKS 7

Page 26 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Column reinforcement works going to Upper Roof Floor 2 0%
Column formwork going to Upper Roof Floor Slab 2 0%
Column Concrete pour going to Upper Roof Floor Slab 1 0%
Reinforcement for Slab @Upper Roof Floor 4 0%
Formwork for Slab @Upper Roof Floor 4 0%
Concrete pour for Slab +Curing @Upper Roof Floor 1 0%
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 43
ARCHITECTURAL WORKS 43
GROUND FLOOR ARCHITECTURAL WORKS 34
MASONRY, FLOOR/WALL/CEILING FINISHING WO 34
Block work‐ GF 10 0%
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
FIRST FLOOR ARCHITECTURAL WORKS 32
MASONRY, FLOOR/WALL/CEILING FINISHING WO 32
Block work‐ FF 12 0%
Internal Plastering works‐ FF 12 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 4
MASONRY, FLOOR/WALL/CEILING FINISHING WO 4
Block work‐ RF 4 0%
UPPER ROOF ARCHITECTURAL WORKS 5
MASONRY, FLOOR/WALL FINISHING WORKS 5
Block work‐ UR 5 0%
VILLAS 31 80
STRUCTURAL WORKS 47
SUB STRUCTURE CONCRETE WORKS 16
Excavate the site area for founda on 2 0%
Prepara on works for concrete blinding + termite treatment 1 0%
Founda on Blinding + Curing 1 0%
Rebar work for Foo ng & Columns Neck 3 0%
Form work for Foo ng & Columns Neck 3 0%
Concrete pour for Foo ng & Columns Neck 1 0%
Apply Bituminous Paint coat on the Foo ng & Columns Neck surfa 1 0%
Back fill up to the bo om of Grade Beam and Blinding for Grade Be 1 0%
Formwork and rebar work for Grade Beam 1 0%
Concrete pour for Grade Beam+Curing 1 0%
Apply Bituminous Paint coat for Ver cal surfaces 1 0%
Back fill up to Grade Slab Base 1 0%
Termite treatment + Polythene sheet 1 0%
Formwork and rebar work for Grade Slab with Mesh + Filler board 2 0%
MEP services @Grade Slab 1 0%
Concrete pour for Grade Slab + Curing 1 0%
SUPER STRUCTURE CONCRETE WORKS 31
FIRST FLOOR SLAB CONCRETE WORKS 5
Column reinforcement works going to Floor 1 2 0%
Column formwork going to Floor 1 Slab 2 0%
Column Concrete pour going to Floor 1 Slab 2 0%
Formwork for Slab & Stair @Floor 1 1 0%
Reinforcement for Slab & Stair @Floor 1 2 0%
Concrete pour for Slab & Stair+Curing @Floor 1 1 0%
ROOF FLOOR SLAB CONCRETE WORKS 8
Column reinforcement works going to Roof Floor 5 0%
Column formwork going to Roof Floor Slab 2 0%
Column Concrete pour going to Roof Floor Slab 2 0%
Formwork for Slab & Stair @Roof Floor 2 0%
Reinforcement for Slab & Stair @Roof Floor 2 0%
Concrete pour for Slab & Stair+Curing @Roof Floor 1 0%
UPPER ROOF SLAB CONCRETE WORKS 16
Column reinforcement works going to Upper Roof Floor 2 0%
Column formwork going to Upper Roof Floor Slab 2 0%
Column Concrete pour going to Upper Roof Floor Slab 1 0%
Formwork for Slab @Upper Roof Floor 4 0%

Page 27 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Reinforcement for Slab @Upper Roof Floor 4 0%
Concrete pour for Slab +Curing @Upper Roof Floor 1 0%
TOP OF ROOF AND PARAPET WALL 2
Roof plinths reinforcement works 1 0%
Roof plinths Form works 1 0%
Roof plinths concrete works 1 0%
ARCHITECTURAL & MEP WORKS 45
ARCHITECTURAL WORKS 45
GROUND FLOOR ARCHITECTURAL WORKS 44
MASONRY, FLOOR/WALL/CEILING FINISHING WO 44
Block work‐ GF 10 0%
Internal Plastering works‐ GF 12 0%
Wet area waterproofing works‐ GF 3 0%
Ceramic Floor Tiling works Dry Area‐ GF 4 0%
Ceramic Wall Tiling works‐ GF 9 0%
Ceramic Tile Skir ng works‐ GF 4 0%
Internal Stairs Marble Laying‐ GF 2 0%
PAINTING AND DECORATIVE WORKS 10
Paint surface prepara on and applica on of  pu y‐ GF 3 0%
Applicaton of 1st coat paint‐ GF 2 0%
FIRST FLOOR ARCHITECTURAL WORKS 35
MASONRY, FLOOR/WALL/CEILING FINISHING WO 35
Block work‐ FF 5 0%
Internal Plastering works‐ FF 5 0%
Wet area waterproofing works‐ FF 3 0%
Ceramic Floor Tiling works Dry Areas‐ FF 7 0%
Ceramic Wall Tiling works‐ FF 5 0%
PAINTING AND DECORATIVE WORKS 3
Paint surface prepara on and applica on of  pu y‐ FF 3 0%
ROOF FLOOR/ROOF DECK ARCHITECTURAL WOR 18
MASONRY, FLOOR/WALL/CEILING FINISHING WO 18
Block work‐ RF 5 0%
Internal Plastering works‐ RF 5 0%
UPPER ROOF ARCHITECTURAL WORKS 15
MASONRY, FLOOR/WALL FINISHING WORKS 10
Block work‐ UR 5 0%
Plastering works‐ UR 5 0%
ROOFING WORKS 5
Roof Waterproofing works‐ UR 5 0%
PROFILE 3 MEP UTILITY WORKS/ EXTERNAL FINISHING WORKS 304 28‐Mar‐17
BOUNDARY WALL WORKS 286 28‐Mar‐17
External Boundary Wall Foo ng Concre ng Works 26 50% 28‐Mar‐17
External Boundary Wall Block works 45 75% 17‐Apr‐17
Internal Par on Wall Block Works 30 40% 01‐Apr‐18
Internal Par on Wall Plastering Works 24 0%
Internal Par on Wall Foo ng Concre ng Works 16 0%
External Boundary Wall Plastering works 40 25% 05‐May‐18
STORM WATER SYSTEM 24
Road Gully reinforcement and Formworks 10 0%
Road Gully Concre ng Works 10 0%
Excava on and Laying Storm Water Pipelines, Backfilling 12 0%
TELEPHONE SYSTEM 11 16‐Oct‐17
JRC Manholes excava on Works 4 30% 16‐Oct‐17
JRC Manhole reinforcement and Formworks 4 30% 17‐Oct‐17
JRC Manhole Concre ng Works 4 30% 19‐Oct‐17
Excava on and Laying PVC Duct, Backfilling. 4 45% 20‐Oct‐17
POTABLE WATER SUPPLY SYSTEM 24 10‐Oct‐17
Valve Box excava on Works 4 65% 10‐Oct‐17
Valve Box reinforcement and Formworks 4 65% 12‐Oct‐17
Valve Box Concre ng Works 4 65% 15‐Oct‐17
Excava on and Laying of Water Supply Pipes, Backfilling. 4 65% 16‐Oct‐17
ELECTRICAL POWER SUPPLY SYSTEM 32 17‐Sep‐17
Electrical Manhole excava on Works 6 45% 17‐Sep‐17
Electrical Manhole reinforcement and Formworks 6 45% 18‐Sep‐17
Electrical Manhole Concre ng Works 6 45% 20‐Sep‐17
Excava on and making provisions for laying power cables 10 45% 20‐Sep‐17
DRIVEWAY AND WALKWAY WORKS 86 10‐Jul‐17
Backfilling, Levelling and Compa on of Driveway area 20 90% 10‐Jul‐17
Fixing of Covers for Soak Aways and road Gulleis 5 70% 19‐Oct‐17
Kerbstone laying works 20 0%

Page 28 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE
Activity Name Original % % Actual Start Actual Finish
Duration PREVIOUS COMPLETE

Sandbedding and Interlock laying works in Driveway 30 0%
Sandbedding and Interlock laying works in Walkway 20 0%
EXTERNAL FINISHING WORKS 116
PROVISIONAL SUM ITEMS 108
Provisional Sum Items 108 0%
ENTRANCE TOWER WORKS 40
Entrance tower Structural Works 20 0%
Entrance tower Architectural Works 20 0%

Page 29 of 29 TASK filters: KJ14 INCOMPLETE WORKS,


KJ14 MECANICAL WORKS, KJ14 ONE