Table 2 - REQUIRED PERMIT TO CONSTRUCT PORT PROJECT

A. PROJECT'S MAIN PERMITS & CLEARANCES:


CATEGORY RESPONSIBLE OFFICE
NO. DESCRIPTION ISSUED BY COMPLETION PERIOD
L P C OWNER CONTRACTOR SUB-CON

1 SEC REGISTRATION Securities and Exhange Commission - Manila (SEC) O O Maximum 90 days
DTI, Construction Industry Authority of the Philippines,
2 CONTRACTOR'S LICENSE O O Maximumn 90 days
Contractor's Accreditation Board.
Local Mayor's Office where the Headquarters or the project
3 BUSINESS PERMIT O O Maximum 60 days
is located
ECC - ENVIRONMENTAL COMPLIANCE
4 Environmental Management Bureau (EMB) of the DENR, O Maximum 180 - days
CERTIFICATE OF THE PROJECT
PERMIT TO CONSTRUCT (COMMERCIAL PORT
5 Phillipine Port Authority (PPA) / MARINA O O 90 days for both BUP & JETTY
/ BUP / JETTY)
BUILDING PERMIT: FOR STRUCTURES TO BE
6 Office of the Building Official (OBO), Local Gov't. Unit O 90 days together w/ BUP & JETTY
CONSTRUCTED AT OFFSHORE, IF ANY

7 LOCATIONAL CLEARANCE Municipal Planning & Development Office (MPDO), LGU O 30 days for both BUP & JETTY

GROUND PREP & EXCAVATION PERMIT Office of the Building Official (OBO), Local Gov't. Unit O 90 days together w/ BUP & JETTY

8 BARANGAY CLEARANCE Barangay where Project is located O O 3 to 7 days

9 ECC for Batching Plant (if needed) Environmental Management Bureau (EMB) of the DENR, O Within 90 days

10 BUILDING PERMIT for Batching Plant Office of the Building Official (OBO), LGU O Within 90 days

11 PTO, Permit to Operate Generator Sets Environmental Management Bureau (EMB) of the DENR, O Within 60 days

12 PTO, Permit to Operate Batching Plant Environmental Management Bureau (EMB) of the DENR, O Within 60 days
WATER DISCHARGE PERMIT
13 Environmental Management Bureau (EMB) of the DENR, O Within 60 days
(Batching Plant)
PERMIT TO DRILL WATER SOURCE (if
14 National Water Resource Board (NWRB) - Manila O
necessary)

A. OTHER GOVERNMENT REQUIREMENTS FOR THE PROJECT


1 Certificate of Registration (Rule 1020) Department of Labor & Employment (DOLE), O O Maximum 60 days

2 Building Permit for Temporary Facilities Office of the Building Official (OBO), LGU O O Maximum 45 days
Locational Clearance for Business and
3 Municipal Planning & Development Office (MPDO), LGU O O Maximum 15 days
Temporary Facilities
Barangay Clearance for Business &
4 Barangay where project is located O O Maximum 7 days
Temporary Facilities
5 Occupancy Permit for Temporary Facilities Office of the Building Official (OBO), LGU O O Maximum 30 days
Protected Areas Management Board - Superintendent's
6 PAMB CLEARANCE O FOR PROTECTED AREAS ONLY
Office - (c/o EMB-DENR Regional Office)
SAPA - SPECIAL USE AGREEMENT FOR
7 Environmental Management Bureau (EMB) of the DENR O FOR PROTECTED AREAS ONLY
PROTECTED AREAS
L LICENSES
P PERMITS
C CLEARANCES