Professional Documents
Culture Documents
The roller shown in Figure 1.1 below is known as a Tamping Foot or Pad roller, its drum
is covered with spaced feet and it has a vibrating function. This type of roller is suitable
for a wide range of materials, in particular cohesive soils as well as broken up granular
materials. This roller was being used to compact broken shale in preparation for the
construction of the main tunnel exit road.
Behind the roller a horizontal beam is running across the face of the row of piles. The
beam is held in place by soil anchors which are spaced at every third pile. The beam
provides resistance against bending loads in the piles; its use reduces the number of
anchors required. Without the restraining beam every pile would need an anchor which
would probably be more expensive and time consuming.
The excavator was extremely efficient at moving the material; I watched it fill a 12 tonne
capacity truck with 4 bucket loads. However, the process was being slowed down with
difficult access for the trucks off a main road and not enough trucks being used. This
meant that the excavator was often idle while waiting for the next truck to fill. This
highlighted the fact that earthmoving processes are often chains and it is the process as a
whole which must be efficient. The large excavator is an expensive piece of equipment
and it is important to use it and its operator in the most efficient manner possible. If this
process was more efficient the task would be finished earlier and the excavator could then
be used elsewhere on the site.
Interestingly the excavator has a fire extinguisher mounted on the front as a precaution in
case of fire. I noticed that most of the large excavators on site had one, but the smaller
ones did not.
The dozer has a ripper mounted on its rear which allows it to break and loosen hard soil
and some types of rock. The ripper is mounted using four hydraulic jacks which enables
the operator to keep the tooth of the ripper perpendicular to the ground regardless of
depth. This is important because the ripper is generally most efficient at this angle; it also
helps to reduce wear on the tooth of the ripper.
This dozer had been used to break up soil and shale with its ripper and then push the
material into a large pile which will be used as backfill at a later stage. The dozer has
been driven up onto the fill to keep it out of the way while a grader and rollers work on
the area that was prepared using it. Its ripper has been driven into the fill to help keep it
stable, the grade of the fill pile was much steeper than it appears in the photo. The
combination of tracks and large engine power made this an easy task for the dozer.
It is important that trucks exiting the site onto roadways have reasonably clean tyres.
Muddy or dirty tires will not have good traction on the road which could be extremely
dangerous, especially for a truck with a large payload. It is also important to keep public
roadways as clean as possible. Trucks exiting with muddy tires will leave dirt on the
asphalt roads which makes the road unsafe for motorists. This was a crucial
consideration at this exit point as it opened directly on to the Gore Hill Freeway which is
a very busy road with cars travelling at 80-90 km per hour.
After the grids were loaded on to a truck I watched the excavator change attachments and
was surprised at how quickly this was done. It took the excavator approximately 30
seconds to remove the toothed bucket and attach a flat edged bucket. I was told that it
would not be so easy with all types of attachments, for example a rock drill might be
slightly harder to position and attach.
Figure 1.8 shows the excavator using the back of the flat edged bucket to spread crushed
rock around the truck access point. This is another technique that is commonly used to
try and minimise the amount of dirt and mud that is on a trucks tires when it exits the site
on to the main road. Watching this excavator at work really showed me the versatility of
hydraulic excavators as well as the importance of having a skilled operator in order to
take full advantage of their capacity.
There are three office areas on the site which are shown below in Figure 2.1, they are
relatively small most likely one or two people per room. These are easily portable
buildings which are hired from the construction equipment company Coates. Each office
has bars on the window to provide security, which is an important consideration on
construction sites. The offices would probably be used for the day to day managerial
work associated with running the site, communications and storage of plans and other
documents.
The yellow pole in the foreground of the photo is a small temporary telegraph pole which
has also been hired. The pole has been used to connect the offices with a power supply
and with communications such as telephone lines and internet connections, which are
essential to running the project. A small first aid room is located slightly out of picture to
the right of the third office. This provides the workers with the facilities to treat minor
injuries that may occur on site
The machinery sections and boom of the crane are delivered to the site on large trailers.
A mobile crane would then be used to assemble them at the desired location. The crane
builds itself higher one tower section at a time using a climbing frame which fits over the
top most section of tower. The slewing unit is detached from the top of the tower and
hydraulic rams in the climbing frame push it up. The crane operator then lifts another
section of tower into the gap opened by the climbing frame where it is bolted into place
by a crew of workers.
This photo highlights another significant advantage of the tower crane, the limited space
that it takes up on site.
Once a bag was loaded onto a pallet the tower crane was used to distribute the supplies
either to an area of the site were it would be used or to a storage area (Figure 2.6). A
purpose built yellow cage was used to make sure that the load was secure and could not
fall during the lift. This is important as the crane lifts the pallets over areas of the site
where people are working. The cage is suspended from the crane’s cable, lowered over
the pallet and then two horizontal bars are slid through the bottom of the pallet and loops
on the bottom of the cage. To ensure that this process was conducted safely, the worker
securing the cage checked very carefully that each pallet was in good condition before it
was loaded and that the cage was secure (Figure 2.5).
Watching this once again highlighted the advantage of having the tower crane on site. It
was capable of quickly moving material and equipment to all areas of the site. Before
coming to this site I had thought that because they were so large, tower cranes would
mainly be used for high and heavy lifts that other cranes couldn’t reach. However, this
crane was constantly in use performing numerous small lifts.
Once the wall has been erected with cement and all reinforcement has been placed it is
filled with concrete by pouring through the open hollow sections at the top. This type of
wall is relatively easy to fabricate, provides excellent durability and strength and is
commonly used in multi story buildings.
In Figure 2.9 an outer brick wall is being constructed around the completed concrete wall.
Interestingly, I was told that this is being provided at the clients request as an aesthetic
feature and is not required in a structural capacity. The exposed reinforcement protruding
from the tops of the walls will be incorporated into the concrete slab that makes up the
next level of the building.
Figures 2.10 and 2.9 show wooden beams that are being supported by load bearing
falsework frames. The frames have adjustable jacks at the top which enables fine
adjustment of the height. Cross bracing in the frames prevents the buckling of vertical
members under load.
In order to construct the next level of the building thin precast concrete slabs will be
lifted into place on top of the beams. These slabs act as permanent formwork for the
bottom of the main slab which will be poured on top. The precast slabs have looped
reinforcements protruding from the top. This provides a good structural bond between the
precast slab and the poured main slab creating a slightly thicker composite slab.
A grid of reinforcement bars is placed on top of the precast slabs and the side sections of
formwork are erected. Figure 2.10 shows a section of the building which has the precast
slabs placed. Most of the reinforcement is in place and the beginnings of the side forms
can be seen at the back.
Once all the reinforcement is placed and the side formwork has been completed the main
slab can be poured. Initially the weight of the poured concrete will be taken by the
falsework frames. Once the concrete hardens and gains strength the frames can be
removed and the slab will be self supporting.
The whole process will be repeated as the next level of the building is constructed with
this slab being the floor of the new level and the roof of the level underneath. Figure 4.12
shows a section of a main slab that has been completed with the reinforcement from the
wall beneath coming through.
I found it interesting that different sections of the building were always at different stages
of construction. At one section the block walls were being erected, at the next the
falsework was erected and the wooden beams were placed. At another section the
preparation for pouring the main slab would be underway.
Greater efficiency is achieved by staggering the activities that are taking place on site. It
enables the company to split their workforce into a set of teams which can always be
performing the same function. For example, one team may construct the block walls,
another might place falsework and formwork. This increases the output of individuals
and teams as there is a learning curve associated with repeated activities.
Furthermore, the amount of required equipment is reduced, for example the falsework
frames are not required at all sections of the site at the same time and so the total number
of frames required is reduced.
There was a significant amount of advertising at the site as well with the main contractor
(Key Concrete Systems), Subcontractors, the security company and the crane company
having various signage placed around the site.
References
Anderson, T., 2006, Construction Study Guide, Module 1: Equipment, Technology &
Process