ID Task Task Name Duration Start Finish Predecessors Resource Names 16 May '16 23 May '16

Mode S S M T W T F S S M T W T F S
1 Centerline Marking 3 days 15-05-2016 17-05-2016
2 Barrication 9.88 days 18-05-2016 27-05-2016 1 barrication[1] barrication
3 Excavation with 188 days 21-05-2016 24-11-2016 2SS+3 days Excavation
Rolling and dismantling and
Compaction carting[1]
(Including Paved
shoulder)
4 Subgrade soil first 154 days 06-12-2016 08-05-2017 3FS+11 days subgrade[1]
layer (250mm) with
rolling and
compaction
(Including Paved
shoulder)
5 Subgrade soil second 144 days 13-05-2017 03-10-2017 4FS+4 days subgrade[1]
layer (250mm) with
rolling and
compaction
(Including Paved
shoulder)

6 Repairing damaged 179 days 22-10-2017 18-04-2018 5FS+18 days Manhole


manhole and raising raising[1]
of manholes
7 Pipe laying for catch 44 days 10-11-2017 23-12-2017 6SS+19 days NP3 pipes[1]
pit

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: final case study
Summary Manual Summary Rollup Progress
Date: 05-02-2018
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names 16 May '16 23 May '16
Mode S S M T W T F S S M T W T F S
8 Catch pit 7.5 days 27-11-2017 04-12-2017 7SS+17 days catchpit chamber
construction and frc cover[1]
9 Laying of cross utility 86 days 15-11-2017 08-02-2018 7SS+5 days NP3 pipes[1]
pipes
10 Utility chamber 5.25 days 01-12-2017 06-12-2017 9SS+16 days utility
construction chamber[1]
11 Granular Sub Base 73 days 05-12-2017 15-02-2018 10SS+4 days GSB[1]
with rolling and
compaction
(Including Paved
shoulder)
12 Dry Lean Concrete 2 days 07-03-2018 08-03-2018 11FS+19 days DLC[1]
13 Pavement Quality 42 days 19-03-2018 29-04-2018 12FS+10 days PQC and runner
Concrete beam[1]
14 Manhole Slab Casting 34 days 19-03-2018 21-04-2018 13SS
& Cover fixing
15 Pcc for paved 1.5 days 22-04-2018 23-04-2018 14 PCC[1]
shoulder
16 Kerb Placing for 0 days 23-04-2018 23-04-2018 15 Kerb stone[0]
footpath
17 Paver block placing 0 days 23-04-2018 23-04-2018 16 Paver blocks
on sand bedding for 60mm[0],utility
paved shoulder chamber[0]
18 PCC for foothpath 0 days 08-05-2018 08-05-2018 17FS+15 days PCC[0]

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: final case study
Summary Manual Summary Rollup Progress
Date: 05-02-2018
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names 16 May '16 23 May '16
Mode S S M T W T F S S M T W T F S
19 Paver block placing 0 days 08-05-2018 08-05-2018 18 Paver blocks
on sand bedding for 80mm[0]
Footpath

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: final case study
Summary Manual Summary Rollup Progress
Date: 05-02-2018
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3