You are on page 1of 91

HOTEL & COMPLEX OF AL NAJADAH SOUQ, DOHA

Monthly Report No.4 Rev 1.0 [APRIL 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ, Doha

              

Prepared By:

               

MAIN CONTRACTOR CLIENT CONSULTANT

URBACON TRADING & CONTRACTING PRIVATE ENGINEERING OFFICE Dar Al Handasal


April 2015

HOTEL & COMPLEX OF Al NAJADAH SOUQ, Doha

MONTHLY REPORT No. 4 Rev 1.0


APRIL 2015
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

Table of Contents 
 
 
SECTION 1: GENERAL INFORMATION 
 
1.1 ‐ Project Introduction and Location 
1.2 – Scope of Works 
1.3 – Work Breakdown Zoning 
1.4 ‐ Contract Particulars 
1.5 ‐ Financial Summary  
 
SECTION 2:  EXECUTIVE SUMMARY (PROGRESS OUTLINE) 
 
2.1 ‐ Site Progress / Construction Activities Summary 
2.2 ‐ Engineering and Technical Summary 
2.3 ‐ Plan for Next Month 
 
SECTION 3: PROGRAMME AND PROGRESS 
 

3.1 — PROGRESS FOR TECHNICAL SUBMISSION 
3.2 — PROGRESS FOR PROCUREMENT (LONG LEAD ITEM 
 
 
3.3 — WORK PROGRAM EVALUATION 
3.4 — AREAS OF CONCERNS 
 
SECTION 4: HEALTH, SAFETY & ENVIRONMENT 
 
 4.1 ‐HSE STATISTICS 
 4.2 ‐ HSE ACCOMPLISHMENTS 
 

1 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

SECTION 1: GENERAL INFORMATION 
 
1.1 — Project Introduction and Location 
 
Design  &  Build  of  Hotel  &  Complex  of  Al‐Najadah  Souq,  which  is  located  in  Doha‐Qatar  in 
Souq Area (Center Doha) 
 
1.2 — Project Scope of Works 
 
The Project Scope of Work shall be Design & Build of Hotel & Complex of  Al‐Najadah Souq 
which is divided but not limited to 
 
1. Dismantling of All Existing External Finishes. 
2. Studying of Existing Structures. 
3. Demolition of the Existing buildings and mosque. 
4. Renovation of existing traditional building administrative building including all MEP 
& Services & FF&E. 
5. Renovation of the car park building including all MEP & Services. 
6. Construction of 5 stars hotel (New Building) Including all Sub structure & super 
structure skeleton, MEP Services, Interior finishes & FF&E..Etc. 
7. Construction of bookshop(New Building Including all Sub structure & super structure 
skeleton, MEP Services , Interior finishes & FF&E..Etc. 
8. Construction of Multi‐purpose (New Building hall all Sub structure & super structure 
skeleton, MEP Services, Interior finishes & FF&E..Etc. 
9. Renovation of Market & Shops including all civil, Structural, architectural, MEP 
services, Interior finishes, security systems..Etc. (Shell & Core only) 
10. Construction of underground service trench between bookstore and Souq Al 
Najadah Pedestrian tunnel. 
11. External infrastructure landscaping ,including the plaza with special flooring for 
painting 
12. Services, Plant Rooms , Equipments in need for authority approval 
 
 
1.3 — WORK BREAKDOWN ZONING 
 
In  order  to  closely  monitor  the  work  progress,  the  entire  Project  has  been  divided  into 
working as follows. 
1.  Car Park  Building, Area = 23,018m2 
2.  Hotel and Multipurpose Hall Building, Area = 19,153m2 
3. Book Store Building , Area = 8,300 m2 
4. Existing souq Building‐Retail Shops, Area = 7,781 m2 
5. Existing Admiration Building Traditional , Area = 515m2 
6. Art Plaza, Area = 6900 m2 
2 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

1.4— CONTRACT PARTICULARS 
 
Client name  Private Engineering Office (PEO) 
Consultant name  Dar Al Handasa 
Contractor name  UrbaCon Trading and Contracting 
Contract Name  Hotel & Complex of Al Najadah SOUQ 
Contract Number (LOA number)  U‐295‐295‐14 HNCS 
Original Contract Price  860,000,000 QAR 
Revised Contract Price  N/A 
Original Contract Period (days)  669 Calendar Days 
Revised Contract Period (days)  N/A 
Percentage Time Elapsed  as of 30 April 
320 days out of 670 days = 47.76% 
2015 
Amount of Penalty for Delay  520,000 QAR/day  
Advance Payment  10% (86,000,000 QAR) 

10% (5% Upon issuance Completion Certificate ,5% upon 
Retention Money 
issuance of Defect Liability Performance Certificate) 

Validity of Performance Bond  18‐August‐2017 
Validity of Contractors All Risk Policy  14‐Apr‐2016 
Letter of Award date:  08 Jan 2015(Letter of Award only) Not Signed by UCC 
Signing of Contract Agreement date:  12‐January‐2015 (Letter of Award only) 
Original Start Date  15 Jun 2014 
Original Completion Date  14 Apr 2016 
Revised Completion Date  N/A 
Projected Completion Date  14 Apr 2016 
Maintenance Period  400 Calendar Days 
Planned Percentage Complete  19.96%(as of 30‐April‐2015) 
Actual Percentage Complete  17.09%(as of 30‐April‐2015) 
Variance / Slippage  ‐2.87% 

UCC does not accept the actual % of 17.09%& refers to the submission of
revised weightage % that leads to Actual % of 23%lead on construction
weightage of 65% instead of 55%

3 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

1.5 — FINANCIAL SUMMARY 

ITEM  QAR 
Original Contract Price  860,000,000 

Total value of variation orders issued to date  292,518,545.84 QR 

Adjusted Contract Price  1,152,518,545.84 

Total values of possible changes to the Contract   0 QR 

Anticipated final account (A)  1,152,518,545.84 

Monetary/Time Claims approved   0 days 

Advanced Payment (B)  86,000,000 QR  

Gross value of Interim Payment Certificates to date (C)  TA#02:239,680,753.68 

Retention held to date (D)   23,968,075.36 QR 

Recovery against Advanced payment made to date (E)  23,968,075.36 QR 

Any other deduction made to date (F)  0 QR 

Total deductions to date (G) = (D + E + F)  47,936,150.72QR 

Cumulative  Net  value  ‐Interim  payment  certificates  (C–  191,744,602.94 QR 


G) 
Percentage of Gross value of work certified (C/A) %  27.86% 

 
 
 

4 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

SECTION 2: EXECUTIVE SUMMARY (PROGRESS OUTLINE) 
 
 
2.1 — SITE PROGRESS / CONSTRUCTION ACTIVITIES SUMMARY 
 
Hotel Building: 
 
             1. Basement: 
                   Part 4: Slab Rebar & MEP works in Progress at First Floor level. 
                                Sand leveling at Basement level.                    
             2. Ground Floor: 
                               Block works in Progress. 
                               MEP Works in progress 
3. Mezzanine Floor: 
                               Block Works in Progress. 
                               MEP Works in progress 
              4. First Floor  
                  Block Works in Progress. 
                  MEP Works in progress 
                  Swimming Pool area Rebar & MEP Works in Progress. 
               5. Second Floor 
                   Par 3: Slab Concrete Done.  
                  Block Works in Progress. 
                  MEP Works in progress                   
 6. Third Floor 
                               Part 2 & 3: Slab Concrete Done. 
                  Part 3: Column Concrete done .De‐shuttering Works in progress. 
              7. Fourth Floor 
                  Part 2 & 3: Column Form & Concrete works done. 
                  Part 2 & 3: Slab Form Works in progress 
              8. Roof Floor 
                  Part 1: Form & Rebar Works in progress   
Book Store: 
             1. Basement: 
                              Block Works in Progress. 
                              MEP Works in progress.      
             2. Ground Floor: 
                               Structural Works Complete. 
3. Mezzanine Floor: 
                               Structural Works Complete. 
              4. First Floor  
                  Column Rebar & MEP Works in progress. 

5 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

SECTION 2: EXECUTIVE SUMMARY (PROGRESS OUTLINE) 
                                 
Book Store: 
              4. First Floor  
                  Column Form & Concrete Works in progress. 
                  Column De shuttering Works in progress. 
 
Shops & Market:  
                 Structural Repairing Works in Progress. 
                 External & Internal sidewall Preparation works in Progress 
 
Admin Building: 
               Sand Plastering Works in Progress 
Old Souq: 
        Structural Repairing Works in Progress. 
        Sand Plastering Works in Progress. 
        Block & Plastering Works in Progress. 
Car Park: 
 
      Demolishing Works in Progress. 
Hotel Extension: 
 
       Excavation Works in Progress. 
 
 
 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
6 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

2.2— ENGINEERING & TECHNICAL SUMMARY (Design Delivery Matrix attached) 
 
1. Design 
 
 Concept Design/Design Development is finished for all building,new 
design as per client needed modifications is sent to the 
Consultant/client and waiting for response for 2 month,Draft 
comments are sent & may cause big impact on progress on site 
 
 IFC drawings  in progress and send a draft copy to consultant ,Where 
Final IFC can’t be earned due to delay in DC2 Permit which is in delay 
due to new design modifications in Carpark, restaurant & multi‐
purpose hall buildings. 

 
2. Material 
 Many purchase orders are a ready made specially  hotel & Book Store  
Such as but not limited to (kitchen, Elevator,Metal Doors..Etc. 
 
3. Shopdrawings 
 
 Structural Shop drawings are in progress for Hotel Building, Bookstore 
 Architectural/MEP Shop drawings are in progress for Hotel building, 
Bookstore. 
                
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

7 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

2.3 — PLANS FOR NEXT MONTH 
 
1. Hotel 
a) Pouring Concrete Part 2,3 at Roof floor level 
b) Block works Complete at Second floor level 
c) Plastering Works in progress at First Floor level 
d) MEP Works at First & Second Floor level. 
e) Block Works in progress at Third Floor level 
 
2. Bookstore 
 
a) Pouring Concrete Second floor level. 
b) Plastering Works Done. 
c) Block Works in Progress at Ground Floor level. 
d) MEP Works in progress at Ground Floor level. 
 
3. Admin  Building 
 
a) Plastering Works Done. 
b) Painting Works in progress. 
 
4. Old Souq 
 
a) Plastering Works Done. 
b) Painting Works in progress. 
c) MEP Works in progress 
 
5. Car Park  
 
a) Demolishing  Works Done 
b) Foundation Works in Progress 
 
6. Hotel Extension : 
 
a)  Foundation Works in Progress 
 
 
 
 
 
 
 

8 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

 
 
SECTION 3: PROGRAM AND PROGRESS 
 
3.1 — PROJECT MILESTONES STATUS 
 
 
Milestones  Contract Schedule  Forecast/ Actual Date  Variance 
Letter of Award Date  08‐January‐2015  08‐January‐2015    0 
Design  Freeze(No  More  Changes 
05‐February‐2015       
in Design by Client) 
DC1  22‐March‐2015       
DC2  22‐March‐2015       

Design Finish  22‐March‐2015       

Shop drawings Finish  24‐Aug‐2015       
Permanent Power on Site  15‐Nov‐2015       
QCDD Approval  29‐March‐2016       
Project  Finish  Handing  over  to 
14‐Apr‐2016       
Client 

 
A = Actual    F = Forecast 
Notes: 
1‐ The Contract does not specify any intermediate milestones for this Project. The 
above milestones were developed for close monitoring purposes.  
2‐ A Master Baseline programme has been submitted and Approved as Noted. 
3‐ A detailed baseline was sent and not approved from consultant due to missing BOQ 
and some comments under preparation to be send again 
  
 
 
 
 
 
 

9 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

 
3.2 — PROGRESS FOR TECHNICAL SUBMISSION 
 
MATERIAL SUBMITTAL  CIVIL  MEP 

Approved  58  42 

Revise and Resubmit  16 41

Under Review  1 19

TOTAL  75 102

 
 
SHOP DRAWING SUBMITTAL  CIVIL  MEP 
Approved  90 15

Revise and Resubmit  203 30

Under Review  64 13

TOTAL  357 58

 
 

INSPECTION REQUESTS  CIVIL  MEP 


Replied  899 105

Pending  37 11

 
Total  936 116

 
 
 
 
 
 

10 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

3.3 — PROGRESS FOR PROCUREMENT  
SUBMISSION  DELIVERY 
MATERIAL DESCRIPTION 
PLANNED  ACTUAL  PLANNED  ACTUAL 
Pressure control Switch Package  22‐Apr‐15    1‐Jul‐15   

FAHU Package  26‐Apr‐15  5‐May‐15      2‐Sep‐15   

Split Ac Units Package  24‐Jun‐15    5‐Sep‐15   

Exhaust Air Fan  18‐May‐15  14‐April‐15  10‐Sep‐15   

Fan Ventilation Package  22‐May‐15  14‐April‐15  14‐Sep‐15   

Diesel Tank  5‐May‐15    28‐Aug‐15   

Heat Recovery Unit  23‐May‐15    1‐Sep‐15   

Bus Bar & Accessories  8‐Jun‐15    15‐Oct‐15   

MCC Panel  9‐Mar‐15    1‐May‐15   

Generator  9‐May‐15  25‐April‐15  15‐Sep‐15   

Transformer  25‐May‐15    1‐Oct‐15   

UPS System  25‐May‐15  25‐April‐15  14‐Oct‐15   

SMDB   29‐May‐15    10‐Aug‐15   

Fire hose reel and cabinet Package  2‐Apr‐15  7‐May‐15  12‐Jul‐15   

Fire Pumps  17‐May‐15  2‐May‐15  7‐Oct‐15   

FM 200 System  29‐Apr‐15  2‐May‐15    22‐Aug‐15   

Domestic Pump  24‐Jun‐15    19‐Sep‐15   

Submersible Pump  24‐Jun‐15    19‐Sep‐15   

 
 
 
 
 
 
 
 
 
 
 
11 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

3.4 — WORK PROGRAM EVALUATION 
 
Project target completion date    :  14 April 2016 
 
Project estimated completion date    :  14 April 2016 
 
Project Completion Variance / Delay   :  0 calendar days 
 
Project planned completion percentage  :  19.96% (As of 30‐April‐2015) 
 
  Project actual completion percentage     :  17.09% (As of 30April‐2015) 
 
  Variance/ Delay noted                              : ‐2.84% 
 
 
 
 
 
3.5 — AREAS OF CONCERNS 
(1)‐  Variation  and  new  contract  is  under  preparation  due  to  Changes  as  per  PEO  top 
management  visit  on  Thursday  15‐January‐2015  ,  which  may  lead  to  major  impacts  on 
construction such as but not limited to : 
a‐Demolish of car park building. 
b‐Establishing  a  new  furnished  apartments  building  at  car  park  location  with  2  basements 
for car parking. 
c‐Establishing new shops in book store location which will lead to structural. Architectural & 
interior design changes and will impact Construction progress. 
d‐Establishing new Hotel Hotel extension in restaurant location. 
 
(2)‐Delay in Approval of Concept Design from PEO 2 months till now , and reply may cause 
severe impact on construction. 
(3)‐Approval to End User for bookstore & methodology of work of heritage building causing 
delay in start of work. 
 
 
 
 
 
 

12 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS

SECTION 4: HEALTH, SAFETY & ENVIRONMENT 
 
4.1 — HSE ACCOMPLISHMENTS 
1. Tool  box‐meeting  hold  regularly  in  Weekly  basis  4‐5  times  almost  500  employees  are 
attend meeting. 
2. Fire extinguishers were secured maintained and monitored Monthly/color coded. 
3. Scaffolds were fixed, sustained and tagged, by a dedicated scaffold. 
4. PPEs were provided to concerned employees. 
5. Safety signage was placed on appropriate site area. 
6. HSE policy is well promoted and followed. 
 
4.2 — HSE STATISTICS 
JOB HOUR STATISTIC  Man‐Hours Worked
Current Month  317,110 
Accumulated Total  1,760,145 

Accident Free Man‐Hours   
 
JOB HOUR STATISTIC  Current  Cumulative 
Fatality (work related death)  0  0 

Serious Injurious Accident  0  0 

Moderate Injurious Incident  0  1 

Number of Lost Time Days (work related)  0  0 

Minor Injurious Events (no day lost / first aid & checkup)  4  21 

Serious Damage Accident (estimated over 10,000QR)  0  0 

Moderate Damage Incident (>< 1,000 & 10,000QR)  0  1 

Minor Damage Event (estimated below 1,000QR)  0  3 

Total Vehicle/Plant Events(9,10,11&12 Combined)  0  4 

Road Accident (outside project or facility locations)  0  0 
Fire (any size)  0  1 

Near Miss Reports  1  3 

Environmental Incident  0  0 

HSE Violation Issued  7  45 

HSE Induction given  400  3222 


 

13 of 11 Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

ATTACHMENT / RECORDS

1. Construction Progress S-Curve


2. Updated Baseline Program as of 26 March 2015
3. Weather Report
4. Contractor’s personnel recorded
5. Contractor’s equipment
6. Quality Control Report
7. HSE Report
8. Submittal Logs
9. Progress Photographs

Monthly Report no.4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

CONSTRUCTION S - CURVE

Monthly Report no. 4 [April 2015]


            HCNS  ‐OVER ALL PROJECT (S‐Curve)  
 

14.00% 120.00%

13.00%

11.66%
12.00%
100.00%

CUT OF DATE 30‐4‐2015

9.82%
10.00%

80.00%

8.52%

7.67%
7.53%
8.00%

6.76%
60.00%

6.00%

4.92%

4.14%
3.90%
40.00%

3.58%
3.35%
4.00%
3.14%
2.63%
1.90%

1.62%
20.00%
1.41%

1.36%
1.25%

2.00%
0.81%

0.69%
0.20%
0.13%

0.00% 0.00%
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Plan Incr 0.13% 0.20% 1.25% 1.41% 0.81% 1.36% 1.90% 2.63% 3.14% 3.35% 3.90% 4.92% 6.76% 7.53% 9.82% 8.52% 13.00% 11.66% 7.67% 4.14% 3.58% 1.62% 0.69%
Actual Incr 0.13% 0.20% 1.00% 1.25% 1.50% 1.25% 2.00% 2.75% 2.50% 2.35% 2.16%
Plan Cum 0.13% 0.33% 1.58% 2.99% 3.81% 5.17% 7.07% 9.69% 12.83% 16.18% 20.08% 25.01% 31.76% 39.29% 49.11% 57.63% 70.64% 82.30% 89.98% 94.11% 97.69% 99.31% 100.00%
Actual Cum 0.13% 0.33% 1.33% 2.58% 4.08% 5.33% 7.33% 10.08% 12.58% 14.93% 17.09%

Plan Incr Actual Incr Plan Cum Actual Cum


Hotel & Complex of AL Najada Souq(Detailed
Baseline)

Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
15-Jun-14 A 25-Apr-16 568 19.96% 17.09% -9 25-Apr-16, HOTEL & COMPLEX
HOTEL & COMPLEX OF AL-NAJADAH SOUQ REV1
15-Jun-14 A 25-Apr-16 686 63.3% 62.65% -12 25-Apr-16, General
General
Milestones 15-Jun-14 A 25-Apr-16 686 0% 0% -12 25-Apr-16, Milestones

GEN Project Start 15-Jun-14 A 0 100% 100% Project Start


GEN10 Letter of Award Date 15-Jan-15 A 0 100% 100% Letter of Award Date
GEN20 Design Freeze(No More Changes in Design by Client) 30-Apr-15 0 100% 0% 53 Design Freeze(No More Changes in Design by Client)
GEN50 Client to Provide Signed Contract 30-Apr-15 0 100% 0% 53 Client to Provide Signed Contract
GEN60 Issuance of Building Permit 27-May-15 0 100% 0% 53 Issuance of Building Permit
GEN30 DC2 28-Jul-15 0 100% 0% 3 DC2
A12710 DC1 28-Jul-15 0 100% 0% 3 DC1
A12740 Design Finish 28-Jul-15 0 100% 0% 3 Design Finish
A12810 Finish of Restaurant Building 05-Jan-16 0 0% 0% 107 Finish of Restaurant Building
A102160 Site Ready for Energization 05-Jan-16 0 0% 0% -3 Site Ready for Energization
A12760 Permanent Power on Site 06-Jan-16 0 0% 0% -3 Permanent Power on Site
A12840 Finish of External Networks 04-Feb-16 0 0% 0% 73 Finish of External Networks
A12800 Finish of Market & Shops 22-Feb-16 0 0% 0% 56 Finish of Market & Shops
A12830 Finish of Admin Building 23-Feb-16 0 0% 0% 56 Finish of Admin Building
A12790 Finish of Multi Purpose Building 03-Mar-16 0 0% 0% 45 Finish of Multi Purpose Building
A12780 Finish of Bookstore Building 12-Mar-16 0 0% 0% 37 Finish of Bookstore Building
A12820 Finish of Car Park Building 16-Apr-16 0 0% 0% -1 Finish of Car Park Building
A12770 Finish of Hotel Building 24-Apr-16 0 0% 0% -10 Finish of Hotel Building
A2250 Project Finish/Handing over to Client 25-Apr-16 0 0% 0% -12 Project Finish/Handing over to Clie
GEN40 QCDD Approval 25-Apr-16 0 0% 0% -12 QCDD Approval
Preliminaries
Preliminari 15-Jun-14 A 20-Apr-16 675 47.57% 46.65% -7 20-Apr-16, Preliminaries

Mobilization & Enabling Works


Mobilizatio 15-Jun-14 A 16-Oct-14 A 113 100% 100% 16-Oct-14 A, Mobilization & Enabling Works

15-Jun-14 A 01-Dec-15 443 75.82% 35.92% 116 01-Dec-15, Engineering


Engineering
Engineerin
Early Desig
Design Stage (Concept,Schematic,Develop..etc) 15-Jun-14 A 28-May-15 247 100% 80% 109 28-May-15, Early Design Stage (Concept,Schematic,Develop..etc)

Hotel Building
Build 15-Jun-14 A 14-May-15 151 100% 80% -12 14-May-15, Hotel Building
Book Store 20-Aug-14 A 14-May-15 101 100% 80% 13 14-May-15, Book Store
Multi Purposes
Purp Hall 23-Aug-14 A 18-May-15 131 100% 80% 121 18-May-15, Multi Purposes Hall
Restaurant 15-Sep-14 A 14-May-15 138 0% 0% 71 14-May-15, Restaurant
Market &S
&Shops,Old Souq 06-Sep-14 A 21-May-15 110 100% 80% 15 21-May-15, Market &Shops,Old Souq
Admin Bui
Building 24-Sep-14 A 14-May-15 132 100% 80% 30 14-May-15, Admin Building
Car Park 12-Jul-14 A 14-May-15 110 0% 0% 9 14-May-15, Car Park
External W
Works 21-Oct-14 A 14-May-15 115 100% 80% 2 14-May-15, External Works
Main Utilities
Utiliti 25-Nov-14 A 28-May-15 90 0% 0% 5 28-May-15, Main Utilities

Design Sta
Stage (IFC Drawings/BOQ's/Spec's) 20-Sep-14 A 28-Jul-15 371 100% 29.11% 60 28-Jul-15, Design Stage (IFC Drawings/BOQ's/Spec's)

Hotel Building
Build 20-Sep-14 A 14-Jun-15 209 100% 40% -12 14-Jun-15, Hotel Building
Book Store 06-Nov-14 A 02-Jun-15 83 100% 30.48% 13 02-Jun-15, Book Store
Multi Purposes
Purp Hall 15-Dec-14 A 28-Jul-15 306 100% 5.26% 60 28-Jul-15, Multi Purposes Hall
Restaurant 30-Apr-15 28-Jul-15 80 0% 0% 34 28-Jul-15, Restaurant
Market & S
Shops,Old souq 28-Sep-14 A 22-Jul-15 298 100% 18.13% 15 22-Jul-15, Market & Shops,Old souq
Admin Bui
Building 17-Dec-14 A 28-Jun-15 264 100% 14.53% 21 28-Jun-15, Admin Building
Car Park 16-Oct-14 A 02-Jun-15 70 0% 0% 9 02-Jun-15, Car Park

HOTEL AND COMPLEX OF ALNAJADA SOUQ HCNS-Detailed Baseline


Date Revision Checked Approved
28-Jan-2015 00 O.M I.H/E.A
(Summary Program 30-April-2015)

1/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)

Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
External W
Works 23-Mar-15 A 17-Jun-15 93 100% 4.89% -2 17-Jun-15, External Works
Main Utilities
Utiliti 09-Mar-15 A 14-Jun-15 35 0% 0% 4 14-Jun-15, Main Utilities

Shop Drawings
Draw Stage 20-Jan-15 A 01-Dec-15 294 24.65% 14.83% 66 01-Dec-15, Shop Drawings Stage

Hotel Building
Build Shop Drawings 20-Jan-15 A 10-Nov-15 251 30.56% 24.54% 83 10-Nov-15, Hotel Building Shop Drawings
Civil Shopdrawings
Shopd of Hotel 20-Jan-15 A 25-Aug-15 222 94.68% 29.57% -4 25-Aug-15, Civil Shopdrawings of Hotel
Architectural Shopdrawings of Hotel
Architectur 25-Feb-15 A 07-Sep-15 224 4.67% 26.98% 153 07-Sep-15, Architectural Shopdrawings of Hotel
MEP Shop
Shopdrawings of Hotel 14-Mar-15 A 18-Aug-15 188 0% 16.61% 189 18-Aug-15, MEP Shopdrawings of Hotel
ELV Shopdrawings
Shopd of Hotel 14-Jun-15 10-Nov-15 123 0% 0% -1 10-Nov-15, ELV Shopdrawings of Hotel
Book Store Shop Drawings 21-Jan-15 A 08-Oct-15 248 15.55% 12.36% 61 08-Oct-15, Book Store Shop Drawings
Civil Shopdrawings
Shopd of Book Store 21-Jan-15 A 06-Aug-15 234 45.39% 20.9% -6 06-Aug-15, Civil Shopdrawings of Book Store
Architectural Shopdrawings of Book Store
Architectur 25-Feb-15 A 08-Oct-15 233 0% 4% -2 08-Oct-15, Architectural Shopdrawings of Book Store
MEP Shop
Shopdrawings of Book Store 21-Mar-15 A 29-Aug-15 180 0% 17.94% 116 29-Aug-15, MEP Shopdrawings of Book Store
ELV Shopdrawings
Shopd of Book Store 30-Apr-15 20-Sep-15 119 0.35% 0% -10 20-Sep-15, ELV Shopdrawings of Book Store
Multi Purposes
Purp Hall Shop Drawings 14-Jun-15 31-Oct-15 114 61.44% 0% 57 31-Oct-15, Multi Purposes Hall Shop Drawings
Restaurant Shop Drawings
Restauran 30-Apr-15 03-Sep-15 120 0% 0% 86 03-Sep-15, Restaurant Shop Drawings
A2600 Demolishing Shop Drawings for Restaurant 30-Apr-15 03-Sep-15 120 100% 0% 86
A2610 Interior Shop Drawings for Restaurant 30-Apr-15 16-Aug-15 100 0% 0% 105
A2620 MEP Shop Drawings for Restaurant 28-May-15 25-Aug-15 80 0% 0% 86
Architectural Shopdrawings of Restaurant
Architectur 30-Apr-15 29-Jul-15 81 0% 0% 85 29-Jul-15, Architectural Shopdrawings of Restaurant
Market & S
Shops,Old Souq Shop Drawings 31-Mar-15 A 26-Nov-15 200 0% 7.86% 58 26-Nov-15, Market & Shops,Old Souq Shop Drawings
A2630 Architectural Shop Drawings 31-Mar-15 A 07-Oct-15 120 98.33% 9.2% 19
A2640 Demolishing Drawings 30-Apr-15 03-Sep-15 120 92.5% 0% -8
A2660 MEP Shop Drawings 30-Apr-15 22-Sep-15 140 62.86% 0% -12
A2650 Interior Shop Drawings 31-May-15 07-Nov-15 150 38.67% 0% 94
Architectur Shopdrawings of Market & Shops,Old Souq
Architectural 05-Apr-15 A 19-Sep-15 168 0% 14.29% 55 19-Sep-15, Architectural Shopdrawings of Market & Shops,Old S
MEP Shop
Shopdrawings of Market & Shops,Old Souq 28-Jun-15 26-Nov-15 146 0% 0% 32 26-Nov-15, MEP Shopdrawings of Market & Shops,Old
ELV Shopdrawings
Shopd of Market & Shops,Old Souq 30-Apr-15 26-Jul-15 72 0% 0% 1 26-Jul-15, ELV Shopdrawings of Market & Shops,Old Souq
Admin Building
Bui Shop Drawings 19-May-15 01-Dec-15 189 0% 0% 21 01-Dec-15, Admin Building Shop Drawings
A2680 Demolishing Drawings(Method of Repair) 03-Jun-15 13-Oct-15 120 75.83% 0% 18
A2700 MEP Shop Drawings 21-Jun-15 26-Nov-15 150 0% 0% 26
A2690 Interior Shop Drawings 28-Jun-15 01-Dec-15 150 0% 0% 11
Architectural Shopdrawings of Admin Building
Architectur 19-May-15 27-Aug-15 93 0% 0% -7 27-Aug-15, Architectural Shopdrawings of Admin Building
Car Park Shop
S Drawings 30-Apr-15 08-Nov-15 185 0% 0% 37 08-Nov-15, Car Park Shop Drawings
A2720 Demolishing Drawings 30-Apr-15 06-Aug-15 90 100% 0% 6
A2740 MEP Shop Drawings 30-Apr-15 06-Oct-15 150 92% 0% -11
A2710 Architectural Shop Drawings 19-May-15 22-Sep-15 120 100% 0% -6
A2730 Interior Shop Drawings 02-Jun-15 08-Nov-15 149 65.77% 0% 9
Architectural Shopdrawings of Car Park
Architectur 19-May-15 22-Oct-15 147 0% 0% 56 22-Oct-15, Architectural Shopdrawings of Car Park
External Works
W Shop Drawings 30-Apr-15 25-Oct-15 170 4.38% 0% 107 25-Oct-15, External Works Shop Drawings
A2760 Structural Drawings 30-Apr-15 03-Sep-15 120 0% 0% 38
A2770 Landscape Shop Drawings 30-Apr-15 06-Oct-15 150 17.33% 0% -5
A2780 MEP Shop Drawings 12-May-15 19-Oct-15 150 28% 0% -2
A2750 Architectural Shop Drawings 16-Jun-15 25-Oct-15 120 35.83% 0% 5
MEP Shop
Shopdrawings of External Works 01-Aug-15 19-Sep-15 53 0% 0% 141 19-Sep-15, MEP Shopdrawings of External Works
Main Utilities
Utiliti Shop Drawings 26-Jul-15 10-Nov-15 110 0% 0% 4 10-Nov-15, Main Utilities Shop Drawings

Material Submittals
S 02-Jan-15 A 21-Sep-15 242 6.77% 14.44% 45 21-Sep-15, Material Submittals

HOTEL AND COMPLEX OF ALNAJADA SOUQ HCNS-Detailed Baseline


Date Revision Checked Approved
28-Jan-2015 00 O.M I.H/E.A
(Summary Program 30-April-2015)

2/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)

Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
Civil & Architectural
Arc Materials 02-Jan-15 A 03-Sep-15 210 9.16% 9.55% 64 03-Sep-15, Civil & Architectural Materials
Electrical Materials
M 18-Jan-15 A 02-Aug-15 156 1.06% 17.67% 3 02-Aug-15, Electrical Materials
Mechanical Materials
Mechanica 20-Jan-15 A 21-Sep-15 242 8.37% 20.65% -3 21-Sep-15, Mechanical Materials
ELV Materials
Mater 30-Apr-15 01-Aug-15 83 0% 0% 3 01-Aug-15, ELV Materials
Special Items
Ite 05-Feb-15 A 24-Aug-15 197 17.65% 6.29% -4 24-Aug-15, Special Items

Method of Statements & Pre-qualifications 21-Dec-14 A 24-Nov-15 381 12.33% 29.58% 151 24-Nov-15, Method of Statements & Pre-qualifications

Civil & Architectural


Arc 21-Dec-14 A 24-Nov-15 381 28.36% 27.27% 151 24-Nov-15, Civil & Architectural
Electrical 07-Apr-15 A 24-Nov-15 227 3.29% 19.41% 151 24-Nov-15, Electrical
Mechanical 01-Jan-15 A 24-Nov-15 329 0% 42.81% 151 24-Nov-15, Mechanical
21-Jan-15 A 11-Feb-16 289 0% 0.7% 47 11-Feb-16, Procurement & Delivery
Procurement & Delivery
Procurem
Purchase Orders
O 21-Jan-15 A 25-Oct-15 232 0% 1.51% 35 25-Oct-15, Purchase Orders

Civil & Architectural


Arc Materials 21-Jan-15 A 14-Sep-15 193 0% 4.55% 74 14-Sep-15, Civil & Architectural Materials
Electrical Materials
M 06-Apr-15 A 29-Sep-15 168 0% 0.93% 6 29-Sep-15, Electrical Materials
Mechanical Materials
Mechanica 10-May-15 25-Oct-15 160 0% 0% -3 25-Oct-15, Mechanical Materials
ELV Materials
Mater 07-Jun-15 18-Aug-15 62 0% 0% 3 18-Aug-15, ELV Materials
Special Items
Ite 12-May-15 09-Sep-15 112 0% 0% -4 09-Sep-15, Special Items

Delivery Lead
Le Time 24-Jan-15 A 11-Feb-16 337 0% 0.51% 55 11-Feb-16, Delivery Lead Time

Civil & Architectural


Arc Materials 24-Jan-15 A 12-Dec-15 276 0% 1.39% 115 12-Dec-15, Civil & Architectural Materials
Electrical Materials
M 14-Apr-15 A 18-Jan-16 280 0% 0.36% 3 18-Jan-16, Electrical Materials
Mechanical Materials
Mechanica 10-May-15 11-Feb-16 277 0% 0% -3 11-Feb-16, Mechanical Materials
ELV Materials
Mater 15-Jun-15 21-Nov-15 159 0% 0% 3 21-Nov-15, ELV Materials
Special Items
Ite 20-May-15 02-Feb-16 258 0% 0% 7 02-Feb-16, Special Items

Final Deliv
Delivery Milestones 27-Jun-15 11-Feb-16 229 0% 0% 55 11-Feb-16, Final Delivery Milestones

Civil & Architectural


Arc Materials 27-Jun-15 12-Dec-15 169 0% 0% 115 Final
Final
Final
Delivery
Delivery
Delivery
Final
Final
Final
Final
for
Final
for
Final
Painting12-Dec-15,
Delivery
Delivery
Delivery
Final
for
Delivery
Final
PC
Final
Delivery
Final
Marble
Delivery
Paving
Delivery
Delivery
Delivery
Final
Delivery
for
for
for
for
for Civil & Architectural Materials Accessories
(Porcelain,Ceramic,Marble,Granite...etc)
Handrail
Joinery
Aluminium
Block
Curbstone
Gypsum
for
Delivery
Door
for
for
for
Plant
for
General
Wallpaper
FF
Final
Carpet
Curtains
Art
Glass
works
&
Mirrors
Signage
for
Ironmangery
&works
Delivery
Trees
ESanitary
Panel
lightingfor
wares
Bathroom Tiles
Electrical Materials
M 13-Aug-15 18-Jan-16 158 0% 0% 78 Final
Final
Final
Final
Final
Final
Delivery
Delivery
Final
Delivery
Final
Final
Delivery
Delivery
Final
Delivery
Final
Delivery
Final
Final
Delivery
Final
Delivery
Final
Final
Delivery
for
for
for
Delivery
for 18-Jan-16,
Delivery
for
Delivery
Fire
for
Delivery
GI
Delivery
Tray,Trunking
Delivery
MICC
for
Final
public
Fire
for
LV
UPS
Conduit
for
Alarm
for
Generators
Cable
ATS
for
SMDB
Capacitor
BMS
Rated
for
Delivery
for Electrical
Structured
Lighting
External
Smoke
System
Light
Cables
for
Address
for
for
Wiring
System
Transformer
Panel
LV
&HV
System
Bus
MV
MCC
Accessories
&fittings
LV
Panel
with
Panel
DBs
Detect
Panel
Control
Devices Materials
Bank/Power
for
bar
Light
Cables
System
Panel
cabling
supports(ICMS)
Earthing(Furse)
& Accessories
System
system
Factor
Mechanical Materials
Mechanica 17-Aug-15 11-Feb-16 177 0% 0% 55 Final
Final
Final
Delivery
Final
Final
Final
Final
Delivery
Final
Final
Delivery
Final
Final
Delivery
Final
Delivery
Final
Delivery
Final
Final
Delivery
Delivery
for
Delivery
Delivery
Delivery
Delivery
Final
for
Delivery
Split
Delivery
for
Delivery
for
for 11-Feb-16,
Supervisory
for
Condensing
Final
for
Delivery
concealed
for
Alarm
Final
for
FAHU's
Air
for
Exhaust
Fire
for
Diesel
for
for
water
for
Fire
Split
for
outlets
Delivery
GRP
FM Mechanical
Fans-Ventilation
Delivery
Landing
VRF
protective
Floor
Check
Domestic
Fire
for
AC
hose
200
tank
Air
heater
insulated
switch
units
Unit
Centrifugal
Condensing
water
Units
Drain
for
Fan
system
Valves
reel
Valve Materials
forBreeching
gate/Butterfly
and
pumps-(Booster
Exhaust
cabinet
&water
Jocky
pressure
Air
Unit
tank
and
Fan
Air
pumps
inlet
Fan
accessories
valves
control
with
&Connected
Submerib
cabinet
switche
ELV Materials
Mater 13-Oct-15 21-Nov-15 39 0% 0% 136 Final 21-Nov-15,
Final
Final
Delivery
Delivery
Delivery ELV
for for Materials
ooredoo
forData/Wifi
Audio/visual
CCTV
IPTV system
Special Items
Ite 17-Oct-15 02-Feb-16 108 0% 0% 64 Final Final
Delivery
Final 02-Feb-16,
Delivery
Delivery
for
Final
Final
lifts
for
Delivery
Delivery
&for
Pool Special
Escalators
Kitchen Items Equipment
Equipment
for
forLaundry
Chandeliers
Equipment
20-Jun-14 A 24-Mar-16 492 15.35% 17.03% 18 24-Mar-16, Construction
Construction
Construct
Hotel Building
Build 20-Jun-14 A 24-Mar-16 442 23.32% 24.47% 18 24-Mar-16, Hotel Building

Civil Works 20-Jun-14 A 01-Sep-15 325 70.28% 72.84% 46 01-Sep-15, Civil Works
Part 1 20-Jun-14 A 31-Aug-15 317 95% 92.55% -3 31-Aug-15, Part 1
Part 2 16-Aug-14 A 29-Jul-15 274 64.95% 88.05% 32 29-Jul-15, Part 2
Part 3 16-Aug-14 A 01-Sep-15 295 66.41% 76.23% 36 01-Sep-15, Part 3
Part 4 21-Dec-14 A 20-Aug-15 312 54.78% 34.53% 59 20-Aug-15, Part 4
Finishing Works
W 21-Mar-15 A 17-Mar-16 244 0% 0.86% 0 17-Mar-16, Finishing Works
Basement Floor 14-Jul-15 25-Feb-16 232 0% 0% -6 25-Feb-16, Basement Floor
Ground Floor
Flo 21-Mar-15 A 23-Feb-16 248 0% 0.99% 2 23-Feb-16, Ground Floor
Mezzanine Floor 05-Apr-15 A 29-Feb-16 233 0% 1.12% -10 29-Feb-16, Mezzanine Floor
First Floor 05-Apr-15 A 01-Mar-16 229 0% 3.34% -6 01-Mar-16, First Floor
Second Floor
Flo 21-Apr-15 A 24-Jan-16 214 0% 1.67% 22 24-Jan-16, Second Floor
Third Floor 13-Aug-15 08-Feb-16 186 0% 0% 17 08-Feb-16, Third Floor
Fourth Floor
Flo 23-Aug-15 01-Mar-16 198 0% 0% -6 01-Mar-16, Fourth Floor
Roof Floor 01-Sep-15 31-Dec-15 125 0% 0% 6 31-Dec-15, Roof Floor
Upper Roof
Roo Floor 22-Oct-15 15-Nov-15 25 0% 0% 75 15-Nov-15, Upper Roof Floor
Facades 01-Aug-15 17-Mar-16 240 0% 0% 0 17-Mar-16, Facades

HOTEL AND COMPLEX OF ALNAJADA SOUQ HCNS-Detailed Baseline


Date Revision Checked Approved
28-Jan-2015 00 O.M I.H/E.A
(Summary Program 30-April-2015)

3/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)

Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
MEP Works 11-Apr-15 A 24-Mar-16 350 0% 0.18% 22 24-Mar-16, MEP Works
Basement Floor 17-May-15 24-Mar-16 313 0% 0% 12 24-Mar-16, Basement Floor
Ground Floor
Flo 03-Aug-15 10-Dec-15 126 0% 0% 83 10-Dec-15, Ground Floor
Mezzanine Floor 19-Aug-15 12-Jan-16 152 0% 0% 63 12-Jan-16, Mezzanine Floor
First Floor 11-Apr-15 A 14-Feb-16 306 0% 1.76% 66 14-Feb-16, First Floor
Second Floor
Flo 03-Aug-15 24-Dec-15 150 0% 0% 119 24-Dec-15, Second Floor
Third Floor 18-Aug-15 02-Jan-16 141 0% 0% 75 02-Jan-16, Third Floor
Fourth Floor
Flo 27-Aug-15 07-Jan-16 139 0% 0% 69 07-Jan-16, Fourth Floor
Roof Floor 09-Nov-15 15-Mar-16 135 0% 0% -2 15-Mar-16, Roof Floor
Access to MEP Installations
Upper Roof
Roo Floor 16-Nov-15 14-Dec-15 30 0% 0% 75 14-Dec-15, Upper Roof Floor
Access to MEP Installations
Utility Rooms
Roo 19-Sep-15 05-Jan-16 89 0% 0% 29 05-Jan-16, Utility Rooms
Elevators 10-Sep-15 22-Feb-16 170 0% 0% 2 22-Feb-16, Elevators

Book Store 15-Dec-14 A 06-Feb-16 424 13.21% 20.07% -5 06-Feb-16, Book Store

Civil Works 15-Dec-14 A 03-Sep-15 263 37.35% 55.89% 78 03-Sep-15, Civil Works
Civil Works BF 15-Dec-14 A 01-Jun-15 170 80.57% 66.67% 50 01-Jun-15, Civil Works BF
Civil Works GF 08-Feb-15 A 27-May-15 92 57.81% 83.33% 167 27-May-15, Civil Works GF
Civil Works MF 14-Feb-15 A 25-Mar-15 A 32 78.41% 100% 25-Mar-15 A, Civil Works MF
Civil Works FF 01-Apr-15 A 22-Jul-15 55 0% 72.5% -10 22-Jul-15, Civil Works FF
Civil Works SF 22-Apr-15 A 11-Aug-15 55 0% 5% -10 11-Aug-15, Civil Works SF
Civil Works URF 11-Aug-15 03-Sep-15 25 0% 0% -10 03-Sep-15, Civil Works URF
Finishing Works
W 11-Apr-15 A 19-Jan-16 283 0% 0.81% -11 19-Jan-16, Finishing Works
Basement Floor 11-Apr-15 A 21-Dec-15 252 0% 3.96% -5 21-Dec-15, Basement Floor
Ground Floor
Flo 07-May-15 03-Jan-16 237 0% 0% -9 03-Jan-16, Ground Floor
Mezzanine Floor 14-Jul-15 07-Jan-16 180 0% 0% -9 07-Jan-16, Mezzanine Floor
First Floor 02-Aug-15 07-Jan-16 165 0% 0% -9 07-Jan-16, First Floor
Second Floor
Flo 20-Aug-15 19-Jan-16 157 0% 0% -11 19-Jan-16, Second Floor
Upper Roof
Roo Floor 03-Sep-15 03-Nov-15 60 0% 0% -10 03-Nov-15, Upper Roof Floor
Facades 04-Oct-15 17-Jan-16 113 0% 0% -9 17-Jan-16, Facades
MEP Works 08-Apr-15 A 17-Jan-16 222 0% 0.25% 16 17-Jan-16, MEP Works
Basement Floor 08-Apr-15 A 29-Dec-15 182 0% 1.23% 56 29-Dec-15, Basement Floor
Ground Floor
Flo 28-Jun-15 27-Dec-15 176 0% 0% 38 27-Dec-15, Ground Floor
Mezzanine Floor 21-Jul-15 24-Dec-15 163 0% 0% 3 24-Dec-15, Mezzanine Floor
First Floor 28-Jun-15 28-Dec-15 177 0% 0% 2 28-Dec-15, First Floor
Second Floor
Flo 24-Aug-15 17-Jan-16 152 0% 0% -10 17-Jan-16, Second Floor
Upper Roof
Roo Floor 03-Nov-15 05-Jan-16 68 0% 0% 3 05-Jan-16,
Access to MEP Upper Roof Floor
Utility Rooms
Roo 08-Sep-15 30-Dec-15 116 0% 0% 35 30-Dec-15, Utility Rooms
Elevator Works
W 17-Oct-15 06-Feb-16 120 0% 0% -5 06-Feb-16, Elevator Works

Multi Purpose
Purp Hall 11-Aug-15 24-Jan-16 169 0% 0% 12 Access to24-Jan-16,
MEP Multi Purpose Hall

Car Park 16-Oct-14 A 08-Feb-16 555 0% 0% 15 08-Feb-16, Car Park

Market & Shops


S 20-Dec-14 A 07-Feb-16 422 16.6% 10.65% -2 07-Feb-16, Market & Shops

Ground Floor
Flo Level 20-Dec-14 A 07-Feb-16 422 39.37% 25.25% -12 07-Feb-16, Ground Floor Level
Mezzanine Floor Level 02-Jun-15 21-Jan-16 228 0% 0% 6 21-Jan-16, Mezzanine Floor Level
Hallways 22-Nov-15 03-Feb-16 78 0% 0% 2 03-Feb-16, Hallways

Admin Building
Bui 03-Jan-15 A 15-Mar-16 402 7.61% 10.13% -7 15-Mar-16, Admin Building

Ground Floor
Flo Level 03-Jan-15 A 07-Jan-16 330 19.26% 18.95% 11 07-Jan-16, Ground Floor Level
Upper Floo
Floor Level 07-Mar-15 A 13-Dec-15 85 0% 7.5% -7 13-Dec-15, Upper Floor Level
External W
Works 19-Oct-15 31-Dec-15 80 0% 0% -7 31-Dec-15, External Works
Facades 02-Jan-16 15-Mar-16 78 0% 0% -7 15-Mar-16, Facades

HOTEL AND COMPLEX OF ALNAJADA SOUQ HCNS-Detailed Baseline


Date Revision Checked Approved
28-Jan-2015 00 O.M I.H/E.A
(Summary Program 30-April-2015)

4/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)

Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
Old Souq Area
A 30-Dec-14 A 30-Dec-15 351 7.66% 8.54% 15 30-Dec-15, Old Souq Area

Ground Floor
Flo level 30-Dec-14 A 23-Dec-15 344 24.7% 18.76% 23 23-Dec-15, Ground Floor level
Mezzanine Floor Level 21-Apr-15 A 06-Dec-15 135 0% 0.4% 41 06-Dec-15, Mezzanine Floor Level
Hallways 11-Apr-15 A 30-Dec-15 231 0% 13.02% 15 30-Dec-15, Hallways
Roof Floor 12-Sep-15 19-Dec-15 101 0% 0% 27 Access to19-Dec-15,
MEP Roof Floor

Restaurant Building 24-Dec-14 A 03-Dec-15 408 0% 0% 59 03-Dec-15, Restaurant Building

Ground Floor
Flo 24-Dec-14 A 18-Oct-15 358 0% 0% 88 18-Oct-15, Ground Floor
Mezzanine Floor 22-Jul-15 10-Sep-15 55 0% 0% 69 10-Sep-15, Mezzanine Floor
Hallway Floor
Fl 10-Aug-15 16-Nov-15 101 0% 0% 60 16-Nov-15, Hallway Floor
Facades 15-Oct-15 12-Nov-15 30 0% 0% 76 12-Nov-15, Facades
Specialities 07-Sep-15 03-Dec-15 90 0% 0% 59 03-Dec-15, Specialities

External W
Works 25-Aug-15 05-Mar-16 200 0% 0% 2 05-Mar-16, External Works

Undergrou Services/Utilities
Underground 25-Aug-15 05-Mar-16 200 0% 0% 2 05-Mar-16, Underground Services/Utilitie
Plaza 22-Sep-15 17-Jan-16 120 0% 0% 5 17-Jan-16, Plaza
19-Nov-15 25-Apr-16 169 0% 0% -12 25-Apr-16, Commissioning & Hand
Commissioning & Handing Over
Commissi

HOTEL AND COMPLEX OF ALNAJADA SOUQ HCNS-Detailed Baseline


Date Revision Checked Approved
28-Jan-2015 00 O.M I.H/E.A
(Summary Program 30-April-2015)

5/5
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

WEATHER REPORT

Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project No.U-295-295-14 HNCS

DATE HIGH (°C) LOW (°C) SUNNY/CLOUDY RAINY

1.4.2015 32° 23° √


2.4.2015 25° 24° √
3.4.2015 30° 5° √
4.4.2015 24° 21° √
5.4.2015 37° 24° √
6.4.2015 34° 25° √
7.4.2015 34° 24° √
8.4.2015 36° 24° √
9.4.2015 36° 25° √
10.4.2015 35° 25° √
11.4.2015 35° 27° √
12.4.2015 41° 25° √
13.4.2015 32° 25° √
14.4.2015 29° 23° √
15.4.2015 32° 22° √
16.4.2015 34° 22° √
17.4.2015 35° 25° √
18.4.2015 34° 25° √
19.4.2015 32° 25° √
20.4.2015 33° 22° √
21.4.2015 36° 22° √
22.4.2015 34° 24° √
23.4.2015 35° 27° √
24.4.2015 43° 28° √
25.4.2015 31° 24° √
26.4.2015 33° 23° √
27.4.2015 36° 24° √
28.4.2015 39° 25° √
29.4.2015 39° 26° √
30.4.2015 38° 25° √

Monthly Report no. 4 (April 2015)


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

MANPOWER REPORT

Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14 HNCS

COMPANY NON-MANUAL MANUAL TOTAL


Project Main Contractor

UCC 90 1102 1192


Sub-Contractor 94 94
Sub Consultant 11 11

TOTAL 101 1196 1297

Monthly Report no. 4 [April 2015]


            HCNS –Manpower Diagram 
 

 2,000  25,000

1,800 

1,800 

1,800 
1,750 

1,700 
 1,800

1,500 

1,500 
 1,600  20,000

1,300 

1,300 
 1,400

1296
1,150 
1133
1,100 
 1,200  15,000

1101
1100

1,000 
980 
 1,000

890 
890

720 
 800  10,000
700 
700
600 
600

 600
500 
500

350 
320 

 400  5,000
320
290 
290

150 
 200
57 
57

 ‐  ‐
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Plan Incr 57 290 320 500 600 700 890 980 1,100 1,150 1,300 1,500 1,750 1,800 1,800 1,800 1,700 1,500 1,300 1,000 720 350 150
Actual Incr 57 290 320 500 600 700 890 1100 1133 1101 1296
Plan Cum 57 346 666 1,166 1,766 2,466 3,356 4,336 5,436 6,586 7,886 9,386 11,136 12,936 14,736 16,536 18,236 19,736 21,036 22,036 22,756 23,106 23,256
Actual Cum 57 347 667 1167 1767 2467 3357 4457 5590 6691 7987

Plan Incr Actual Incr Plan Cum Actual Cum


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

CONTRACTOR’S EQUIPMENT

Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

EQUIPMENT DESCRIPTION QUANTITY

Bob Cat 5
TeleHandler 1
Small pickup 1
Forklift 1
Backhoe loader 1
JCB 0
Pickup 3 Ton 1
Mobile Crane 50Ton 0
Wheel Loader 0
Tower Crane 2
Hiab 10Ton 1
Bus 13

TOTAL 26

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

QUALITY CONTROL STATISTIC REPORT

Monthly Report no. 4 [April 2015]


Monthly Quality Statistics Report
U‐ 295 ‐ 295 ‐ 14 ‐ HCNS
APRIL 27, 2015

Inspection Requests
a b c d e f g h

Total Submitted Status Percentage


Cumulative Number of IR's 
PROJECT Cumulative Number of IR's  Total Approved Total Not Approved
received back from 
Pending with Consultant % Approved on First  % Not Approved on First Submittal 
This Month Up to Date Consultant
This Month Up to Date This Month Up to Date Submittal (e/c) (g/c)

Architectural 28 57 2 55 35 47 3 8 85.45% 14.55%

Civil 228 727 33 694 216 666 2 28 95.97% 4.03%

Electrical 38 66 5 61 33 59 0 2 96.72% 3.28%

Mechanical 11 36 1 35 10 30 0 5 85.71% 14.29%

MEP 49 102 6 96 43 89 0 7 92.71% 7.29%


HCNS 305 886 41 845 294 802 5 43 91.38% 8.62%

Submittals (Materials, Technical and Method of Statements)
a b c d e f g h
Total Submitted Status Percentage
DESCRIPTION Cumulative Number of  Cumulative Number of 
Submittals Pending with  Submittals received back  Total Approved Total Not Approved
% Approved on First  % Not Approved on First Submittal 
This Month Up to Date Consultant from Consultant
This Month Up to Date This Month Up to Date Submittal (e/c) (g/c)

Materials 33 157 21 136 10 87 5 49 63.97% 36.03%

Method Statement 20 41 5 36 12 30 3 6 83.33% 16.67%

Technical 36 160 11 149 25 95 5 54 63.76% 36.24%

Design Drawings 15 31 11 20 5 9 3 11 45.00% 55.00%

Shop Drawings 234 383 83 300 80 87 156 213 29.00% 71.00%


TOTAL 338 772 131 641 132 308 172 333 48.05% 51.95%
Note : This month submittals statistic has great changes in numbers because Design and Shop Drawing Submittals were included.

Non‐Conformance Reports
Cumulative Number NCR's  Cumulative Number NCR's Pending with  Cumulative Number of NCR's Closed
Outstanding NCR's 
% Outstanding NCR's Up to Date
This Month Up to Date This Month Up to Date This Month Previously Issued NCR's Up to Date Up to Date

1 11 0 0 0 0 9 2 81.82%
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS

HSE STATISTIC REPORT

Monthly Report no. 4 [April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-284-284-14-SDR

SUBMITTAL LOGS

Monthly Report no. 4 [April 2015]


ARCH Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

HCNS-IR-ARCH- Inspection request for surface preparation prior to application


N/A 1 ARCH  A L Grid M / 14-19 Old Souq UCC 7-Apr-15 8-Apr-15 Done
0019 of vetonit. Please see attached lay - out.

HCNS-IR-ARCH- Inspection Request for setting out layout of block work. See Grid C-G / 7-9 , B-D / 12,14-16 , J-L / 18,
N/A 1 ARCH  B L UCC 7-Apr-15 8-Apr-15 Done
0020 attached lay-out. G-I / 17 Old Souq

HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
N/A 1 ARCH  B L Grid M-K / 16 Hotel Ground floor UCC 5-Apr-15 7-Apr-15 Done
0021 ground floor. As per highlighted in attached key plan.
Grid H-M / 10-11 , H-M / 11-12 , H-M /
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
34 N/A 0 ARCH  B L 12-13 , H-M / 13-14 , H-M / 14-15 , H-M / UCC 1-Apr-15 4-Apr-15 Done
0033 first floor. As per highlighted in attached key plan.
15 - 16 , J-K / 18 Hotel 1st Floor
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
35 N/A 0 ARCH  D NL Grid N / 7-10 Hotel Ground floor UCC 1-Apr-15 4-Apr-15 Done
0034 ground floor. As per highlighted in attached key plan.

HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
35 N/A 1 ARCH  B L Grid N / 7-10 Hotel Ground floor UCC 5-Apr-15 6-Apr-15 Done
0034 ground floor. As per highlighted in attached key plan.

HCNS-IR-ARCH- Inspection request for application of vetonit base and finish.


36 N/A 0 ARCH  B L Grid M-N / 7-19 Old Souq UCC 4-Apr-15 8-Apr-15 Done
0035 Please find attached lay-out.

HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
37 N/A 0 ARCH  B L Grid N-R / 10-14 Hotel First floor UCC 4-Apr-15 6-Apr-15 Done
0036 first floor. As per highlighted in attached key plan.

HCNS-IR-ARCH- Inspection request for complete block work as a mock-up at


38 N/A 0 ARCH  B L Grid M / 18-19 Hotel Ground floor UCC 5-Apr-15 7-Apr-15 Done
0037 ground floor. As per highlighted in attached key plan.

HCNS-IR-ARCH- Inspection request for complete block work at ground floor. As Grid N-Q / 15-17 & M / 17-18 Hotel
39 N/A 0 ARCH  B L UCC 5-Apr-15 7-Apr-15 Done
0038 per highlighted in attached key plan. Ground floor

HCNS-IR-ARCH- Inspection request for complete block work for mock-up room.
41 N/A 0 ARCH  B L Grid N-R / 14-17 Hotel First floor UCC 8-Apr-15 9-Apr-15 Done
0040 As Per Highlighted in attached key plan.

HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
42 N/A 0 ARCH  B L Grid J-M / 16-19 Hotel second floor UCC 8-Apr-15 8-Apr-15 Done
0041 second floor. As per highlighted in attached key plan.

HCNS-IR-ARCH- Inspection Request for surface preparation prior application of


43 N/A 0 ARCH  D L Grid A-N / 1 Old Souq UCC 9-Apr-15 12-Apr-15 Done
0042 vetonit. See attached lay-out.

HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at Grid H-M / 5-10 & 19 / M-N & 20 / M - N
44 N/A 0 ARCH  B L UCC 14-Apr-15 19-Apr-15 Done
0043 second floor. As per highlighted in attached key plan. Hotel Second Floor

Grid 10 / N-P & 2 / N-P & 2-3 / P&15-16


HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
45 N/A 0 ARCH  B L / M & 13-14 / L&9 / N-Q Hotel Ground UCC 14-Apr-15 19-Apr-15 Done
0044 ground floor, as per highlighted in attached key plan.
floor.

HCNS-IR-ARCH- Inspection request for installation of block full height prior for Grid C-G / 7-9 , B-D / 12,14-16 , J-L / 18,
46 N/A 0 ARCH  B L UCC 15-Apr-15 19-Apr-15 Done
0045 rush coat. See attached lay-out G-I / 17 Old Souq
ARCH Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
47 N/A 0 ARCH  B L Grid N-R / 5-10 Hotel Second Floor. UCC 15-Apr-15 19-Apr-15 Done
0046 as per highlighted attached key plan.

HCNS-IR-ARCH- Inspection Request for application of vetonit base & finish Grid I-J / 10-19 , H-K / 12-15 , K-M / 13-
48 N/A 0 ARCH  D NL UCC 18-Apr-15 20-Apr-15
0047 coat. See attached lay-out. 14 Old Souq

HCNS-IR-ARCH- Inspection request for application of Vetonit. See attached lay- Grid I-J / 10-19 , H-K / 12-15 , K-M / 13-
N/A 1 ARCH  U/R L UCC 28-Apr-15
0047 out. 14 Old Souq

HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
49 N/A 0 ARCH  B L Grid N-R / 10-13 Hotel Second floor UCC 20-Apr-15 22-Apr-15 Done
0048 as per highlighted attached key plan.

HCNS-IR-ARCH- New Door opening at ground floor refer to new approved shop
50 N/A 0 ARCH  D L Grid M / 16-17 Hotel Ground floor UCC 20-Apr-15 20-Apr-15
0049 drawing as per the attached key plan.

HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
51 N/A 0 ARCH  B L Grid K-L / 19 Hotel Ground floor UCC 20-Apr-15 22-Apr-15 Done
0050 as per highlighted attached key plan.

HCNS-IR-ARCH- Mock-Up as explained in the meeting with PEO regards the Room.01 Beside Main Entrance as per
52 N/A 0 ARCH  D L UCC 20-Apr-15 20-Apr-15
0051 Heritage Building. attached plan.
Inspection request for setting out of block wall ( first layer )
HCNS-IR-ARCH-
53 N/A prior to block work from basement to ground floor as per 0 ARCH  B L Grid 6-14 / J-T Bookstore UCC 23-Apr-15 26-Apr-15 Done
0052
attached drawing and grid lines.

HCNS-IR-ARCH- Inspection request for 1st laying course of light weight block ,
54 N/A 0 ARCH  D L Grid H-M / 10-13 Hotel Second floor. UCC 23-Apr-15 25-Apr-15
0053 as per highlighted attached key plan

HCNS-IR-ARCH- 1st Course laying of light weight block at first floor as per
55 N/A 0 ARCH  B L Grid N-R / 2-5 Hotel first floor UCC 26-Apr-15 27-Apr-15 Done
0054 highlighted attached plan.

HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
56 N/A 0 ARCH  B L Grid H-M / 13-16 Hotel second floor UCC 26-Apr-15 27-Apr-15 Done
0055 as per highlighted attached key plan.

HCNS-IR-ARCH- 1st course laying of light weight block at mezzanine floor as


57 N/A 0 ARCH  B L Grid N-Q / 13-17 Hotel mezzanine floor UCC 26-Apr-15 27-Apr-15 Done
0056 per highlighted attached plan.

HCNS-IR-ARCH- Complete block work at first floor as per highlighted attached Grid N-R / 5-14 & H-M / 5-18 Hotel First
58 N/A 0 ARCH  B L UCC 26-Apr-15 28-Apr-15 Done
0057 plan floor
Grid Ground J-L / 11, G-I / 18,E-F,C-D /
HCNS-IR-ARCH- Inpspection request for surface preparation prior for plastering.
59 N/A 0 ARCH  B L 19 , M EZ J-L / 18, G-I / 17-18 , B-D / UCC 26-Apr-15 28-Apr-15 Done
0058 See attached lay out.
12,14-16 , D ,F / 7-8 Old Souq.
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block.
60 N/A 0 ARCH  U/R L Grid N-R /15-17 Hotel Second floor UCC 29-Apr-15
0059 As per highlighted attached key plan.

HCNS-IR-ARCH- 1st Course laying of light weight block at first floor as per
61 N/A 0 ARCH  U/R L Grid N-R / 1-2 Hotel first floor UCC 29-Apr-15
0060 highlighted attached plan.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Inspection request for column formwork from mezzanine level to 
HCNS-IR-CIVIL-0537 N/A 0 C A Ok L Grid 11‐13 / I ‐ T Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
first floor slab as per drawings and grid lines.

Inspection request for corewall formwork from mezzanine level to 
HCNS-IR-CIVIL-0538 N/A 0 C B Ok L Grid 11‐13 / I ‐ L , R Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
first floor slab as per attached drawing and grid lines.

Inspection request for column, wall concrete from mezzanine level 
HCNS-IR-CIVIL-0539 N/A 1 C B Ok L Grid 11‐13 / I ‐ T Bookstore UCC 4‐Apr‐15 4‐Apr‐15 Done
to first floor slab as per attached drawing and grid lines.

Inspection request of rebar 2nd floor slab. Please refer to the 
HCNS-IR-CIVIL-0540 N/A 1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
attached key plan for your reference.

Inspection request of form work for 2nd floor slab to proceed with 
HCNS-IR-CIVIL-0541 N/A concrete casting. Please refer to the attached key plan for your  1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for 2nd floor slab. Please 
HCNS-IR-CIVIL-0542 N/A 1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
refer to the attached key plan for your reference.
Installation of waterproofing membrane MASTERPREN.BG on raft 
HCNS-IR-CIVIL-0543 N/A prior to proceed with protection board. Please refer to the attached  1 C B Ok L Grid C‐H / 6 Hotel Basement UCC 2‐Apr‐15 4‐Apr‐15 Done
key plan for your reference.

Inspection request of rebar for wall at 3rd floor to proceed with form 
HCNS-IR-CIVIL-0545 N/A 1 C B Ok L Grid R‐H / 10‐14 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
work. Please refer to the attached key plan for your reference.

Inspection request of formwork for wall at 3rd floor to proceed with 
HCNS-IR-CIVIL-0547 N/A concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid R‐H / 10‐14 Hotel 3rd Floor UCC 4‐Apr‐15 5‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for wall at 3rd floor. 
HCNS-IR-CIVIL-0549 N/A 0 C B Ok L Grid R‐H / 4‐14 Hotel 3rd floor UCC 4‐Apr‐15 5‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request of rebar for ground floor slab around swimming 
HCNS-IR-CIVIL-0552 N/A 1 C B Ok L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 2‐Apr‐15 5‐Apr‐15 Done
pool. Please refer to the attached key plan for your reference.

Inspection request of form work for 1st floor slab and swimming 
HCNS-IR-CIVIL-0553 N/A pool wall to proceed with concrete casting. Please refer to the  1 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
attached key plan for your reference.

Inspection request for concrete casting C40 for swimming pool area 
HCNS-IR-CIVIL-0554 N/A slab and wall. Please refer to the attached key plan for your  1 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
reference.

Inspection request for blinding concrete above top layer as per 
HCNS-IR-CIVIL-0556 N/A 0 C B Ok L Grid 12‐14 / J‐T // 5‐7 / L‐S Bookstore UCC 1‐Apr‐15 4‐Apr‐15 Done
attached drg and grid lines.

Inspection request for applying antitermite before blinding concrete 
HCNS-IR-CIVIL-0557 N/A 0 C B Ok L Grid 12‐14 / A‐J // 5‐7 / J‐T Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
above top layer as per attached drg and grid lines.

Inspection request for back filling and compaction ( compaction test 
HCNS-IR-CIVIL-0558 N/A 0 C B Ok L Grid 13‐14 / J‐T Bookstore UCC 1‐Apr‐15 1‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Inspection request for back filling and compaction ( compaction test 
HCNS-IR-CIVIL-0559 N/A 0 C B Ok L Grid 1'‐5' / S‐T // 5‐7 / L‐T Bookstore UCC 1‐Apr‐15 4‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.

Inspection request for primer application above blinding prior to 
HCNS-IR-CIVIL-0560 N/A 0 C A Ok L Grid 13‐14 / B‐J Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
waterproofing as per attached drawing and grid lines.

Rebar for stair ‐ 2 from 1st floor to 2nd floor. Please refer to the 
HCNS-IR-CIVIL-0561 N/A 0 C B Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
attached key plan for your reference.

Form work for Stair‐2 from 1st floor to 2nd floor to proceed with 
HCNS-IR-CIVIL-0562 N/A concrete casting. Please refer to the attached key plan for your  0 C A Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for stair‐2 from 1st floor 
HCNS-IR-CIVIL-0563 N/A to 2nd floor. Please refer to the attached key plan for your  0 C B Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
reference.

Inspection Request of rebar for column at 3rd floor to proceed with 
HCNS-IR-CIVIL-0564 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
form work. Please refer to the attached key plan for your reference.

Inspection request of form work for column at 3rd floor to proceed 
HCNS-IR-CIVIL-0565 N/A with concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 5‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for column at 3rd floor. 
HCNS-IR-CIVIL-0566 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request of rebar for wall at 3rd floor to proceed with form 
HCNS-IR-CIVIL-0567 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
work. Please refer to the attached key plan for your reference.

Inspection request of form work for wall at 3rd floor to proceed with 
HCNS-IR-CIVIL-0568 N/A concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 5‐Apr‐15 6‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for wall at 3rd floor. 
HCNS-IR-CIVIL-0569 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request for double layer waterproofing prior to screed as 
HCNS-IR-CIVIL-0570 N/A 0 C B Ok L Grid 13‐14 / A‐J Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
per attached drawing and grid lines.

Inspection request for surface preparation and primer application 
HCNS-IR-CIVIL-0571 N/A above blinding prior to water proofing as per attached drawing and  0 C B Ok L Grid 13‐14 / J‐T Bookstore UCC 2‐Apr‐15 5‐Apr‐15 Done
grid lines.

Inspection request for protection screed above double layer water 
HCNS-IR-CIVIL-0572 N/A 0 C A Ok L Grid 13‐14 / A‐J Bookstore UCC 2‐Apr‐15 6‐Apr‐15 Done
proofing as per attached drawings grid lines.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Inspection request for back filling and compaction ( compaction test 
HCNS-IR-CIVIL-0573 N/A 0 C B Ok L Grid 5‐7 / J‐T Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.

Inspection request of form work for ground floor slab to proceed 
HCNS-IR-CIVIL-0574 N/A with concrete casting. Please refer to the attached key plan for your  0 C D Ok NL Grid A‐C / 2‐6 Hotel Ground floor UCC 2‐Apr‐15 6‐Apr‐15 Done
reference.
Inspection request of form work for ground floor slab to proceed 
HCNS-IR-CIVIL-0574 N/A with concrete casting. Please refer to the attached key plan for your  1 C B Ok L Grid A‐C / 2‐6 Hotel Ground floor UCC 13‐Apr‐15 14‐Apr‐15 Done
reference.

Depth of drilled hole for planting rebar for stair‐3 from 3rd floor to 
HCNS-IR-CIVIL-0575 N/A 0 C B Ok L Stair‐3 Hotel 3rd floor UCC 2‐Apr‐15 4‐Apr‐15 Done
4th floor. Please refer to the attached key plan for your reference.

Inspection request for raft rebar and formwork inspection prior to 
HCNS-IR-CIVIL-0576 N/A 0 C B Ok L Grid 1‐7 / A‐K Bookstore UCC 2‐Apr‐15 5‐Apr‐15 Done
concrete as per attached drawing and grid lines.

Inspection request for concrete casting C40 for ground floor slab. 
HCNS-IR-CIVIL-0577 N/A 0 C B Ok L Grid A‐C / 2‐6 Hotel Ground floor UCC 2‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request for concrete casting for raft as per attached 
HCNS-IR-CIVIL-0578 N/A 0 C B Ok L Grid 1‐7 / A‐K Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
drawing and grid lines.

Inspection request for surface preparation and primer application 
HCNS-IR-CIVIL-0579 N/A above blinding prior to water proofing as per attached drawing and  0 C A Ok L Grid 5‐7 / J‐T Bookstore UCC 2‐Apr‐15 6‐Apr‐15 Done
grid lines.

Inspection request for double layer waterproofing prior to screed as 
HCNS-IR-CIVIL-0580 N/A 0 C D Ok NL Grid 13‐14 / J‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
per attached drawing and grid lines.

Double layer of waterproofing membrane prior to screed as per 
HCNS-IR-CIVIL-0580 N/A 1 C B Ok L Grid I‐T / 7‐13 Bookstore UCC 6‐Apr‐15 7‐Apr‐15 Done
attached drawing and grid lines.

Inspection Request for Backfilling & Compaction ( Compaction Test 
HCNS-IR-CIVIL-0581 N/A 0 C B Ok L Grid ( S ‐ T / 1'‐8' ) Bookstore UCC 5‐Apr‐15 6‐Apr‐15 Done
will be done by third Party )

Rebar for column at 2nd floor to proceed with form work. Please 
HCNS-IR-CIVIL-0582 N/A 0 C A Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 11‐Apr‐15 12‐Apr‐15 Done
refer to the attached key plan for your reference.

Formwork for column at 2nd floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0583 N/A 0 C D Ok NL Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Formwork for column at 2nd floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0583 N/A 1 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 13‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection reqest for concrete casting C40 column at 2nd floor. 
HCNS-IR-CIVIL-0584 N/A 0 C D Ok NL Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Inspection reqest for concrete casting C40 column at 2nd floor. 
HCNS-IR-CIVIL-0584 N/A 1 C A Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 13‐Apr‐15 14‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Rebar for wall at 2nd floor to proceed with form work. Please refer 
HCNS-IR-CIVIL-0585 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
to the attched key plan for your reference.

Formwork for wall at 2nd floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0586 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 15‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request for concrete casting C40 for wall at 2nd floor. 
HCNS-IR-CIVIL-0587 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 15‐Apr‐15 16‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request of rebar for mezz. Floor slab. Please refer to the 
HCNS-IR-CIVIL-0588 N/A 0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
attached key plan for your reference.

Inspection request of form work for mezz. Floor slab to proceed with 
HCNS-IR-CIVIL-0589 N/A concrete casting . Please refer to the attached key plan for your  0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for mezz. Floor slab. 
HCNS-IR-CIVIL-0590 N/A 0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request for structural repairing for external column, 
HCNS-IR-CIVIL-0591 N/A 0 C D Ok NL N/7‐19 , A‐N / 19 , A‐N / 7 Old Souq UCC 5‐Apr‐15 5‐Apr‐15 Done
Beams, Arch wall and parapet wall. See attached layout

Inspection request for structural repairing for external column, 
HCNS-IR-CIVIL-0591 N/A 1 C A Ok L N/7‐19 , A‐N / 19 , A‐N / 7 Old Souq UCC 6‐Apr‐15 9‐Apr‐15 Done
Beams, Arch wall and parapet wall. See attached layout

Inspection request for back filling and compaction ( compaction test 
HCNS-IR-CIVIL-0592 N/A 0 C D Ok NL 13‐15 / A‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.

Inspection request for back filling and compaction ( compaction test 
HCNS-IR-CIVIL-0592 N/A 1 C A Ok L Grid S‐T / 1'‐8' Bookstore UCC 6‐Apr‐15 7‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.

Inspection request for blinding concrete above top layer as per 
HCNS-IR-CIVIL-0593 N/A 0 C B Ok L Grid 13‐15 / A‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
attached drg and grid lines.

HCNS-IR-CIVIL-0594 N/A Inspection for Drill hole Depth for ( 16mm ) rebar 0 C A Ok L Grid L‐N / 6 Hotel Ground floor UCC 5‐Apr‐15 6‐Apr‐15 Done

HCNS-IR-CIVIL-0595 N/A Inspection for rebar and shutter for lintel beam ( 16mm )  0 C A Ok L Grid L‐N / 6 Hotel Ground floor UCC 5‐Apr‐15 7‐Apr‐15 Done

HCNS-IR-CIVIL-0596 N/A Inspection for columns formwork 0 C D Ok NL Grid ( I‐N / 11‐13 ) & ( R‐T / 6'‐7' ) Bookstore UCC 5‐Apr‐15 6‐Apr‐15 Done

HCNS-IR-CIVIL-0596 N/A Inspection for columns formwork 1 C B Ok L Grid ( I‐N / 11‐13 ) & ( R‐T / 6'‐7' ) Bookstore UCC 7‐Apr‐15 8‐Apr‐15 Done


Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

HCNS-IR-CIVIL-0597 N/A Casting Concrete for Columns 0 C B Ok L Grid ( I‐N / 11‐13 ) & ( R‐T / 6'‐7' ) Bookstore UCC 7‐Apr‐15 8‐Apr‐15 Done

Inspection request of rebar for stair‐3 at 3rd to 4th floor. Please  Staircase ‐ 3 3rd floor to 4th floor Hotel 3rd 
HCNS-IR-CIVIL-0598 N/A 0 C A Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
refer to the attached key plan for your reference. floor

Inspection request of form work for stair‐3 at 3rd to 4th floor to 
Staircase ‐ 3 3rd floor to 4th floor Hotel 3rd 
HCNS-IR-CIVIL-0599 N/A proceed with concrete casting. Please refer to the attached key plan  0 C A Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
floor
for your reference.

Inspection request for concrete casting C40 for stair‐3 at 3rd to 4th  Staircaise‐3 3rd floor to 4th floor Hotel 3rd 
HCNS-IR-CIVIL-0600 N/A 0 C B Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
floor. Please refer to the attached key plan for your reference. floor

Inspection request for raft rebar and formwork inspection prior to 
HCNS-IR-CIVIL-0601 N/A 0 C B Ok L Grid ( 13‐14 / A ‐ T ) Bookstore UCC 7‐Apr‐15 9‐Apr‐15 Done
concrete as per attached drawing and grid lines.

HCNS-IR-CIVIL-0602 N/A Casting concrete for raft. 0 C B Ok L Grid ( 13‐14 / A ‐ T ) Bookstore UCC 7‐Apr‐15 11‐Apr‐15 Done

Double layer of waterproofing membrane prior to screed as per 
HCNS-IR-CIVIL-0603 N/A 0 C A Ok L Grid P‐T / 5‐7 Bookstore UCC 7‐Apr‐15 8‐Apr‐15 Done
attached drawing and grid lines.

Inspection Request for first floor beam rebar inspection as per 
HCNS-IR-CIVIL-0604 N/A 0 C A Ok L Grid 4‐13 / A‐J Bookstore UCC 7‐Apr‐15 9‐Apr‐15 Done
attached drawing and grid lines.

HCNS-IR-CIVIL-0606 N/A Inspection for steel rebars for W6 from mezzanine to First floor 0 C A Ok L Grird ( R‐T / 1' ) Bookstore UCC 7‐Apr‐15 8‐Apr‐15 Done

HCNS-IR-CIVIL-0607 N/A Inspection for columns and shear wall ( W6 ) formwork 0 C B Ok L Grid ( 1‐7 / A‐K ) & ( R‐S / 1') Bookstore UCC 8‐Apr‐15 9‐Apr‐15 Done

HCNS-IR-CIVIL-0608 N/A Casting concrete for column and Shear wall ( W6 ). 0 C B Ok L Grid ( 1‐7 / A‐K ) & ( R‐S / 1') Bookstore UCC 8‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0609 N/A Inspection for steel rebars for raft foundation 0 C A Ok L Grid ( P‐T / 5‐7 ) Bookstore UCC 8‐Apr‐15 9‐Apr‐15 Done

HCNS-IR-CIVIL-0610 N/A Inspection for raft foundation formwork 0 C B Ok L Grid ( P‐T / 5‐7 ) Bookstore UCC 8‐Apr‐15 9‐Apr‐15 Done

HCNS-IR-CIVIL-0611 N/A Casting concrete for raft foundation. 0 C B Ok L Grid ( 5‐7 / P‐T ) Bookstore UCC 8‐Apr‐15 11‐Apr‐15 Done

HCNS-IR-CIVIL-0612 N/A Application of packing rod and e‐poxy in the expansion joint. 0 C B Ok L Grid ( I‐J / 7 ) Bookstore UCC 8‐Apr‐15 9‐Apr‐15 Done

HCNS-IR-CIVIL-0613 N/A Inspection for Columns formwork 0 C B Ok L Grid P‐T / 5‐7 Bookstore UCC 9‐Apr‐15 11‐Apr‐15 Done


Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

HCNS-IR-CIVIL-0614 N/A Casting Concrete for columns. 0 C B Ok L Grid ( 1‐7 / D‐J ) Bookstore UCC 9‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0615 N/A Inspection for steel rebars for columns. 0 C A Ok L Grid ( D‐J / 1‐7 ) Bookstore UCC 11‐Apr‐15 12‐Apr‐15 Done

Installation of waterproofing membrane MASTERPREN.BG on raft 
HCNS-IR-CIVIL-0616 N/A and wall prior to proceed with protection board. Please refer to the  0 C A Ok L Grid G‐H / 6 Hotel Basement UCC 9‐Apr‐15 9‐Apr‐15 Done
attached key plan for your refrence.

Depth of drilled hole for planting rebar for stair‐3 from 4th floor to 
HCNS-IR-CIVIL-0617 N/A 0 C A Ok L Stair ‐3 Hotel 4th floor UCC 9‐Apr‐15 9‐Apr‐15 Done
roof. Please refer to the attached key plan for your reference.

Depth of drilled hole for planting rebar for stair‐4 from basement to 
HCNS-IR-CIVIL-0618 N/A ground floor. Please refer to the attached key plan for your  0 C A Ok L Stair‐4 Hotel Basement floor UCC 11‐Apr‐15 12‐Apr‐15 Done
reference.
Inspection request of rebar for stair‐3 at 4th floor roof. Please refer 
HCNS-IR-CIVIL-0619 N/A 0 C A Ok L Staircase‐3 4th floor roof Hotel 4th floor UCC 11‐Apr‐15 12‐Apr‐15 Done
to the attached key plan for your reference.

Inspection request of formwork for stair‐3 at 4th floor to roof to 
HCNS-IR-CIVIL-0620 N/A proceed with concrete casting. Please refer to the attached key plan  0 C A Ok L Staircase‐3 4th floor roof Hotel 4th floor UCC 11‐Apr‐15 12‐Apr‐15 Done
for your reference.

Inspection request concrete casting C40 for stair‐3 at 4th floor to 
HCNS-IR-CIVIL-0621 N/A 0 C A Ok L Staircase ‐3 4th floor to roof Hotel 4th floor. UCC 11‐Apr‐15 13‐Apr‐15 Done
roof. Please refer to the attached key plan for your reference.

Witness inspection request for compaction test ( 1st layer ) . Please 
HCNS-IR-CIVIL-0622 N/A 0 C D Ok NL Grid C‐J / 6‐7 Hotel UCC 11‐Apr‐15 12‐Apr‐15 Done
refer to the attached key plan for your reference.

Witness inspection request for compaction test ( 1st layer ) . Please 
HCNS-IR-CIVIL-0622 N/A 1 C A Ok L Grid C‐J / 6‐7 Hotel UCC 12‐Apr‐15 13‐Apr‐15 Done
refer to the attached key plan for your reference.

HCNS-IR-CIVIL-0623 N/A Inspection for columns formwork 0 C B Ok L Grid ( D‐J / 1‐7 ) Bookstore UCC 12‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0624 N/A Inspection for steel rebars for raft foundation 0 C A Ok L Grid ( I / 6 ) Bookstore UCC 12‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0625 N/A Inspection for raft foundation formwork 0 C B Ok L Grid ( I / 6 ) Bookstore UCC 12‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0626 N/A Casting concrete for raft foundation. 0 C A Ok L Grid ( I / 6 ) Bookstore UCC 12‐Apr‐15 13‐Apr‐15 Done

HCNS-IR-CIVIL-0627 N/A Casting Concrete for Columns 0 C B Ok L Grid ( I / 6 ) Bookstore UCC 12‐Apr‐15 13‐Apr‐15 Done


Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Witness inspection request of grouting for PT slab 2nd Floor. Please 
HCNS-IR-CIVIL-0628 N/A 0 C D Ok NL Grid J‐R / 4‐15 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
refer to the attached key plan for your reference.

Witness inspection request of grouting for PT slab 2nd Floor. Please 
HCNS-IR-CIVIL-0628 N/A 1 C B Ok L Grid J‐R / 4‐15 Hotel 2nd floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.

Witness inspection request for compaction test ( 2nd layer ) . Please 
HCNS-IR-CIVIL-0629 N/A 0 C A Ok L Grid C‐J / 6‐7 Hotel UCC 13‐Apr‐15 14‐Apr‐15 Done
refer to the attached key plan for your reference.

Inspection request for drilling & grouting for steel bars in staircase 
HCNS-IR-CIVIL-0630 N/A 0 C A Ok L Grid ( I‐J / 7 ) Bookstore UCC 13‐Apr‐15 14‐Apr‐15 Done
mid landing.

Grid ground floor 8‐10 / N‐P Hotel Ground 
HCNS-IR-CIVIL-0631 N/A Inspection for Drill hole Depth for ( 16mm ) rebar 0 C B Ok L UCC 13‐Apr‐15 14‐Apr‐15 Done
Floor

Inspection request of rebar for 4th floor slab. Please refer to the 
HCNS-IR-CIVIL-0632 N/A 0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
attached key plan for your reference.
Inspection request of form work for 4th floor slab to proceed with 
HCNS-IR-CIVIL-0633 N/A concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for 4th floor slab. Please 
HCNS-IR-CIVIL-0634 N/A 0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
refer to the attached key plan for your reference.

HCNS-IR-CIVIL-0635 N/A Inspection request for Drilling & grouting for steel bars in columns. 0 C D Ok NL Grid ( A / 1 ) Bookstore UCC 13‐Apr‐15 14‐Apr‐15 Done

HCNS-IR-CIVIL-0635 N/A Inspection request for Drilling & grouting for steel bars in columns. 1 C A Ok L Grid ( A / 1 ) Bookstore UCC 15‐Apr‐15 15‐Apr‐15 Done

Inspection Request of rebar for pour strip at 3rd floor. Please refer 
HCNS-IR-CIVIL-0636 N/A 0 C B Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
to the attached key plan for your reference.

Inspection request of form work for pour strip at 3rd floor to 
HCNS-IR-CIVIL-0637 N/A proceed with concrete casting. Please refer to the attached key plan  0 C A Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
for your reference.

Inspection Request for concrete Casting C40 for pour strip at 3rd 
HCNS-IR-CIVIL-0638 N/A 0 C B Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
floor. Please refer to the attached key plan for your reference.

Inspection request of Rebar for column at ground floor to proceed 
HCNS-IR-CIVIL-0639 N/A with formwork. Please refer to the attached key plan for your  0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
reference.

Inspection request of rebar for column at 4th floor to proceed with 
HCNS-IR-CIVIL-0640 N/A 0 C A Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 15‐Apr‐15 16‐Apr‐15 Done
formwork. Please refer to the attached key plan for your reference.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

HCNS-IR-CIVIL-0641 N/A Inspection for Column formwork 0 C A Ok L Grid ( I / 6 ) Bookstore UCC 14‐Apr‐15 15‐Apr‐15 Done

HCNS-IR-CIVIL-0642 N/A Casting Concrete for columns 0 C B Ok L Grid ( I / 6 ) Bookstore UCC 14‐Apr‐15 16‐Apr‐15 Done

Inspection request for rebar and shutter at ground floor as per  Grid Ground floor 8‐10 / N , 10/ N‐P Hotel 
HCNS-IR-CIVIL-0643 N/A 0 C B Ok L UCC 14‐Apr‐15 23‐Apr‐15 Done
highlighted key plan Ground floor

Inspection request of rebar for wall at ground floor to proceed with 
HCNS-IR-CIVIL-0644 N/A 0 C U/R U/R L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15
formwork. Please refer to the attached key plan for your reference.

HCNS-IR-CIVIL-0645 N/A Inspection for steel rebars for columns 0 C A Ok L Grid ( 1‐2 / A‐B ) Bookstore UCC 15‐Apr‐15 15‐Apr‐15 Done

HCNS-IR-CIVIL-0646 N/A Inspection for Column formwork 0 C B Ok L Grid ( 1‐2 / A‐B ) Bookstore UCC 15‐Apr‐15 18‐Apr‐15 Done

HCNS-IR-CIVIL-0647 N/A Casting Concrete for Mezzanine floor beam & slab 0 C B Ok L Grid A‐C / 1‐2 Bookstore UCC 19‐Apr‐15 20‐Apr‐15 Done

Inspection request of formwork for column at ground floor C1 ‐ 02 
HCNS-IR-CIVIL-0648 N/A No, C2 ‐ 04 No, C15 ‐ 01 No, to proceed with concrete casting. Please  0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
refer to the attached key plan for your reference.

Inspection request for concrete casting C40 for column C1‐02 No, C2‐
HCNS-IR-CIVIL-0649 N/A 04 No, C15 ‐ 01 No , at Ground floor. Please refer to the attached  0 C D Ok NL Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
Key plan for your reference.
Inspection request for concrete casting C40 for column C1‐02 No, C2‐
HCNS-IR-CIVIL-0649 N/A 04 No, C15 ‐ 01 No , at Ground floor. Please refer to the attached  1 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
Key plan for your reference.

Inspection request of formwork for column at 4th floor C11‐03 No , 
HCNS-IR-CIVIL-0650 N/A C33‐01 no, C34 ‐ 01 No, to proceed with concrete casting. Please  0 C B Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.

Inspection request for concrete casting C40 for column at 4th floor 
HCNS-IR-CIVIL-0651 N/A C11‐03 No , C33‐01 No , C3A ‐ 01 No . Please refer to the attached  0 C B Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 16‐Apr‐15 23‐Apr‐15 Done
key plan for your reference.

Inspection request of formwork for wall at ground floor to proceed 
HCNS-IR-CIVIL-0652 N/A with concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
reference.

Inspection request for concrete C40 for wall at ground floor. Please 
HCNS-IR-CIVIL-0653 N/A 0 C D Ok NL Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 16‐Apr‐15 Done
refer to the attached key plan for your reference.

Inspection request for concrete C40 for wall at ground floor. Please 
HCNS-IR-CIVIL-0653 N/A 1 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.

HCNS-IR-CIVIL-0654 N/A Inspection for steel rebars for mezzanine floor slab & Beam. 0 C B Ok L Grid ( 2‐4 / A‐E ) Bookstore UCC 16‐Apr‐15 19‐Apr‐15 Done


Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

HCNS-IR-CIVIL-0655 N/A Inspection for mezzanine beam & slab formwork 0 C B Ok L Grid ( 2‐4 / A‐E ) Bookstore UCC 16‐Apr‐15 19‐Apr‐15 Done

Inspection request of rebar for stair‐4 at basement to ground floor. 
HCNS-IR-CIVIL-0656 N/A 0 C A Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request of formwork for stair‐4 at basement to ground 
HCNS-IR-CIVIL-0657 N/A floor to proceed with concrete casting. Please refer to the attached  0 C B Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
key plan for your reference.

Inspection request for concrete casting C40 for stair‐4 at basement 
HCNS-IR-CIVIL-0658 N/A to ground floor. Please refer to the attached key plan for your  0 C B Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.

HCNS-IR-CIVIL-0659 N/A Inspection for Steel rebars for first floor beam including arches. 0 C D Ok NL Grid 6‐14 / I‐T Boosktore UCC 19‐Apr‐15 20‐Apr‐15 Done

HCNS-IR-CIVIL-0659 N/A Inspection for Steel rebars for first floor beam including arches. 1 C A Ok L Grid 6‐14 / I‐T Boosktore UCC 19‐Apr‐15 21‐Apr‐15 Done

Inspection for columns formwork ( from Mezzanine to first floor 
HCNS-IR-CIVIL-0660 N/A columns ) as per attached drawings [ 3 columns ( C16 ) and One  0 C B Ok L Grid ( 1 / A‐E ) Bookstore UCC 19‐Apr‐15 20‐Apr‐15 Done
Column ( C16A ) ]

Casting concrete for 4 Columns ( From Mezzanine to first floor ) as 
HCNS-IR-CIVIL-0661 N/A 0 C B Ok L Grid ( A‐E / 1 ) Bookstore UCC 19‐Apr‐15 20‐Apr‐15 Done
per attached drawing [ 3 Columns ( C16 ) and one Column ( C16A ) ]

HCNS-IR-CIVIL-0662 N/A Inspection for steel rebars for first floor slab including staircase 0 C B Ok L Grid ( 6‐14 / I ‐ T ) Bookstore UCC 19‐Apr‐15 21‐Apr‐15 Done

Inspection for first floor slab and beams formwork including 
HCNS-IR-CIVIL-0663 N/A 0 C B Ok L Grid ( I‐T / 6‐14 ) Bookstore UCC 19‐Apr‐15 21‐Apr‐15 Done
staircase

HCNS-IR-CIVIL-0664 N/A Casting Concrete for first floor slab including staircase 0 C B Ok L Grid ( I‐T / 6‐14 ) Bookstore UCC 19‐Apr‐15 21‐Apr‐15 Done

Depth of Drilled hole for planting rebar at 1st floor slab. Please refer 
HCNS-IR-CIVIL-0666 N/A 0 C D Ok L Grid Y2 ‐Y'2 / X1‐X5 Hotel 1st Floor UCC 19‐Apr‐15 20‐Apr‐15 Done
to the attached key plan for your reference.

Depth of Drilled hole for planting rebar at 1st floor slab. Please refer 
HCNS-IR-CIVIL-0666 N/A 1 C A Ok L Grid Y2 ‐Y'2 / X1‐X5 Hotel 1st Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
to the attached key plan for your reference.

Inspection request for steel rebars for columns from mezzanine floor 
HCNS-IR-CIVIL-0668 N/A to first floor columns ( as per attached drawing) ( 3 columns C18 & 1  0 C B Ok L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15 23‐Apr‐15 Done
column C17 and C108 and NC1 ( 40cm x 40cm )

Inspection request for columns from mezzanine floor to first floor 
HCNS-IR-CIVIL-0669 N/A columns ( as per attached drawing ) ( 3 columns C18 & 1 column C17  0 C B Ok L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15 23‐Apr‐15 Done
and C108 and NC1 ( 40cm x 40cm )
Casting Concrete for columns from mezzanine floor to first floor 
HCNS-IR-CIVIL-0670 N/A columns ( as per attached drawing ) ( 3 columns C18 & 1 column C17  0 C U/R U/R L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15
and C108 and NC1 ( 40cm x 40cm )
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Installation of Waterproofing membrane MASTERPREN.BG on 
HCNS-IR-CIVIL-0671 N/A external face of retaining wall prior to proceed with protection  0 C A Ok L Grid A‐C / 6 & A / 2‐6 Hotel Basement UCC 22‐Apr‐15 23‐Apr‐15 Done
board. Please refer to the attached key plan for your reference.

Inspection Request of rebar for 3rd floor slab. Please refer to the 
HCNS-IR-CIVIL-0672 N/A 0 C B Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
attached key plan for your reference.

Inspection request of formwork for 3rd floor slab to proceed with 
HCNS-IR-CIVIL-0673 N/A concrete casting. Please refer to the attached key plan for your  0 C A Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.

Inspection request for concrete casting C40 for 3rd floor slab. Please 
HCNS-IR-CIVIL-0674 N/A 0 C B Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.

Inspection request for column , wall rebar from first floor level to 
HCNS-IR-CIVIL-0675 N/A second floor slab as per attached drawing and grid lines ( C1B‐3, C9‐ 0 C B Ok L Grid ( I ‐ T / 6‐14 ) Bookstore UCC 23‐Apr‐15 25‐Apr‐15 Done
1 , C1‐6 , C10‐2, C6‐8 , CW5‐1 , W6‐1 , C12‐1 , C10A‐1 , C4A‐2 )

Inspection request for rebar for 4th floor PT slab. Please refer to the 
HCNS-IR-CIVIL-0676 N/A 0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
attached key plan for your reference.

Inspection request for formwork for 4th floor pt slab to proceed with 
HCNS-IR-CIVIL-0677 N/A concrete casting. Please refer to the attached key plan for your  0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.

Inspection request for concrete casting C50 for 4th floor PT slab. 
HCNS-IR-CIVIL-0678 N/A 0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Rebar for column at mezz. Floor to proceed with form work. Please 
HCNS-IR-CIVIL-0679 N/A refer to the attached key plan for your reference. ( C1‐05nos , C2‐07  0 C B Ok L Grid A‐G / 2‐5 Hotel Mezz. Floor UCC 23‐Apr‐15 25‐Apr‐15 Done
nos , C16‐02nos , C15‐05 nos , C22‐01 nos )
Grid Ground floor 9/N ‐ Q & 13‐14 / L , 
HCNS-IR-CIVIL-0680 N/A Inspection request for Drill hole depth as per highlighted Key plan. 0 C D D NL second floor 6 / L & 8‐L Hotel ground floor  UCC 23‐Apr‐15 25‐Apr‐15  
and second floor

Grid Ground floor 9/N ‐ Q & 13‐14 / L , 
HCNS-IR-CIVIL-0680 N/A Inspection request for Drill hole depth as per highlighted Key plan. 1 C U/R U/R L second floor 6 / L & 8‐L Hotel ground floor  UCC 29‐Apr‐15
and second floor

Rebar for column at mezz. Floor to proceed with form work. Please 
HCNS-IR-CIVIL-0681 N/A refer to the attached key plan for your reference. ( C16‐01 no , C15‐ 0 C A Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 25‐Apr‐15 Done
02 nos )

Formwork for column at mezz. Floor to proceed with concrete 
HCNS-IR-CIVIL-0682 N/A casting. Please refer to the attached key plan for your reference. ( C1‐ 0 C A Ok L Grid A‐G / 2‐4 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
05 nos , C2‐07 nos , C16‐01 nos , C15‐03 nos , C22‐01 no )

Inspection request for concrete casting C40 for column at Mezz. 
HCNS-IR-CIVIL-0683 N/A Floor. Please refer to the attached key plan for your reference. ( C1‐ 0 C B Ok L Grid A‐G / 2‐4 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
05nos , C2‐07 nos , C16‐01 nos, C15‐03 nos, C22‐01 no )
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Rebar for column at 4th floor to proceed with formwork. Please 
HCNS-IR-CIVIL-0684 N/A refer to the attached key plan for your reference. ( C1‐02 nos, C14‐ 0 C B Ok L Grid L‐Q / 5‐13 Hotel 4th floor UCC 25‐Apr‐15 26‐Apr‐15 Done
02 nos, C12‐05 nos , C11‐01 no , C29‐08 nos , C30‐01 no , C14‐01 no )

Inspection request for first floor rebar for slab, beam and stair. As 
HCNS-IR-CIVIL-0685 N/A 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
per attached drawing and grid lines.

Inspection request for first floor formwork for slab, beam and stair 
HCNS-IR-CIVIL-0686 N/A 0 C A Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
prior to concrete as per attached drawing and grid lines.

Inspection request for first floor concrete for slab, beam and stair as 
HCNS-IR-CIVIL-0687 N/A 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
per attached drawing and grid lines.

Inspection for column rebar ( 1 column C1 , 2 columns C10 , 1 
HCNS-IR-CIVIL-0688 N/A columns C5 , 2 columns C4A , 1 columns CW 5 , 1 columns C10A , 1  0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
columns C10C ) From first floor to second floor level.
Inspection for formwork for the following columns ( 4 columns C1 , 3 
HCNS-IR-CIVIL-0689 N/A columns C1B , 1 columns C9 , 6 column C8 ) from first floor level to  0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 26‐Apr‐15 Done
second floor level.
Concrete Casting for the following columns ( 4 columns C1 , 3 
HCNS-IR-CIVIL-0690 N/A Columns C1B , 1 column C9 , 6 column C8 ) from first floor level to  0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 27‐Apr‐15 Done
second floor level.

HCNS-IR-CIVIL-0691 N/A Inspection for waterproofing in the extension joint. 0 C A Ok L Grid ( I ‐ J  / 7 ) & ( I ‐ J / 14 ) Bookstore UCC 25‐Apr‐15 26‐Apr‐15 Done

HCNS-IR-CIVIL-0692 N/A Inspection for beam rebar in first floor slab. 0 C A Ok L Grid I‐T / 6‐8 Bookstore UCC 25‐Apr‐15 27‐Apr‐15 Done

Formwork for column at mezz. Floor to proceed with concrete 
HCNS-IR-CIVIL-0693 N/A casting. Please refer to the attached key plan for your reference. (  0 C A Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
C16‐01 nos , C15‐02 nos )
Inspection request for concrete casting C40 for column at Mezz. 
HCNS-IR-CIVIL-0694 N/A Floor. Please refer to the attached key plan for your reference. ( C16‐ 0 C B Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 27‐Apr‐15 Done
01 no , C15‐02 nos )
Formwork for column at 4th floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0695 N/A Please refer to the attached key plan for your reference. ( C1‐02 nos,  0 C A Ok L Grid J‐Q / 5‐13 Hotel 4th. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
C12‐04 nos , C11‐01 no , C29‐05 nos )
Inspection request for concrete casting C40 for column at 4th floor. 
HCNS-IR-CIVIL-0696 N/A Please refer to the attached key plan for your reference. ( C1‐02 nos  0 C B Ok L Grid J‐Q / 5‐13 Hotel 4th. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
, C12‐04 nos , C11‐01 no , C29‐05 nos )

HCNS-IR-CIVIL-0697 N/A Inspection for formwork for beams from first floor slab. 0 C A Ok L Grid I‐T / 6‐8 Bookstore UCC 25‐Apr‐15 27‐Apr‐15 Done

HCNS-IR-CIVIL-0698 N/A Concrete casting for beams in first floor slab. 0 C B Ok L Grid I‐T / 6‐8 Bookstore UCC 25‐Apr‐15 27‐Apr‐15 Done

Rebar for column at 4th floor to proceed with formwork . Please 
HCNS-IR-CIVIL-0699 N/A refer to the attached key plan for your reference ( C11‐05nos, C18A ‐  0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
01 no, C12‐01 no , C14‐03 nos , C33‐01no , C30‐10 no , PC1‐04nos )
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Rebar for wall at 4th floor to proceed with formwork . Please refer to 
HCNS-IR-CIVIL-0700 N/A the attached key plan for your reference. ( SW1‐01 nos & SW2‐01 no  0 C B Ok L Grid K‐Q / 10 Hotel 4th floor UCC 26‐Apr‐15 28‐Apr‐15 Done
)

Rebar for wall at Mezz. Floor to proceed with formwork. Please refer 
HCNS-IR-CIVIL-0701 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 26‐Apr‐15 28‐Apr‐15 Done
to the attached key plan for your reference. ( CW7‐01 no )

Inspection request for rebar for stair‐1 from ground to mezz.floor. 
HCNS-IR-CIVIL-0702 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 28‐Apr‐15 Done
Please refer to the attached key plan for your reference.

Inspection request for formwork for stair‐1 from ground to 
HCNS-IR-CIVIL-0703 N/A mezz.floor to proceed with concrete casting. Please refer to the  0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 28‐Apr‐15 Done
attached key plan for your reference.

Inspection request for concrete casting C40 for stair‐1 from ground 
HCNS-IR-CIVIL-0704 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 27‐Apr‐15 Done
to mezz. Please refer to the attached key plan for your reference.

Installation of waterproofing membrane MASTERPREN.BG on raft 
HCNS-IR-CIVIL-0705 N/A prior to proceed with protection board. Please refer to the attached  0 C B Ok L Grird A‐C / 6 & A / 2‐6 Hotel basement UCC 26‐Apr‐15 27‐Apr‐15 Done
key plan for your reference.

Inspection for corewall rebar ( CW4 and W6 ) , and for columns rebar 
HCNS-IR-CIVIL-0706 N/A 0 C D D NL Grid I‐T / 6‐14 Bookstore UCC 27‐Apr‐15 28‐Apr‐15
( C6 and C12 )

Inspection for corewall rebar ( CW4 and W6 ) , and for columns rebar 
HCNS-IR-CIVIL-0706 N/A 1 C U/R U/R L Grid I‐T / 6‐14 Bookstore UCC 28‐Apr‐15
( C6 and C12 )

Inspection request for formwork for columns ( 6 columns C6 , 2 
HCNS-IR-CIVIL-0707 N/A columns C4a , 1 CW 5 , 1 C10a , 1 column C10c ) from first floor level  0 C D Ok NL Grid J‐T / 6‐13 Bookstore UCC 26‐Apr‐15 28‐Apr‐15 Done
to second floor level.

Inspection request for formwork for columns ( 6 columns C6 , 2 
HCNS-IR-CIVIL-0707 N/A columns C4a , 1 CW 5 , 1 C10a , 1 column C10c ) from first floor level  1 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 28‐Apr‐15 29‐Apr‐15 Done
to second floor level.
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Concrete Casting for columns ( 6 columns C6 , 2 columns C4a , 1 CW 
HCNS-IR-CIVIL-0708 N/A 0 C D Ok NL Grid J‐T / 6‐13 Bookstore UCC 26‐Apr‐15 28‐Apr‐15 Done
5 , 1 C10a , 1 column C10c ) from first floor to second floor level.

Concrete Casting for columns ( 6 columns C6 , 2 columns C4a , 1 CW 
HCNS-IR-CIVIL-0708 N/A 1 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 28‐Apr‐15 29‐Apr‐15 Done
5 , 1 C10a , 1 column C10c ) from first floor to second floor level.

Formwork for column at 4th floor to proceed with concrete casting. 
Please refer to the attached key plan for your reference. ( C11‐
HCNS-IR-CIVIL-0709 N/A 0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 28‐Apr‐15 Done
05nos, C12‐02nos, C14‐04nos , C29‐03nos, C18A‐01no, C30‐01no , 
C33‐01no , PC1‐04 nos )
Inspection request for concrete casting C40 for column at 4th floor. 
Please refer to the attached key plan for your reference. ( C11‐05nos 
HCNS-IR-CIVIL-0710 N/A 0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
, C12‐02nos , C14‐04nos , C29‐03nos , C18A‐01 No , C30‐01no , C33‐
01 no , PC1‐04 nos )
Rebar for wall at 4th floor to proceed with formwork . Please refer to 
HCNS-IR-CIVIL-0711 N/A the attached key plan for your reference. ( CW1‐01no , CW2‐01 no ,  0 C B Ok L Grid J‐Q / 13‐15 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
SW2‐01 no )
Formwork for wall at 4th floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0712 N/A Please refer to the attached key plan for your reference. ( SW1‐01 no  0 C A Ok L Grid K‐Q / 10 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
& SW2‐01 no )
Inspection request for concrete casting C40 for wall at 4th floor. 
HCNS-IR-CIVIL-0713 N/A Please refer to the attached key plan for your reference. ( SW1‐01 no  0 C B Ok L Grid K‐Q / 10 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
& SW2‐01 no )

Inspection request for column rebar from first floor level to second 
HCNS-IR-CIVIL-0714 N/A floor as per attached drawing and grid lines ( C1‐9 , C1C‐2 , C2‐2 , C3‐ 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
1 , C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7 ‐2, C10B‐1 )

Inspection request for column shutter from first floor level to second 
HCNS-IR-CIVIL-0715 N/A floor as per attached drawing and grid lines ( C1‐9, C1C‐2 , C2‐2 , C3‐ 0 C U/R U/R L Grid 1‐14 / A ‐ J Bookstore UCC 28‐Apr‐15
1 , C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7‐2 , C10B‐1 )

Inspection Request for column casting from first floor level to second 
HCNS-IR-CIVIL-0716 N/A floor as per attached drawing and grid lines ( C1‐9 , C1C‐2 , C2‐2 , C3‐ 0 C U/R U/R L Grid 1‐14 / A ‐ J Bookstore UCC 28‐Apr‐15
1 ,C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7‐2 , C10B‐1 )

Inspection for formwork for columns ( 2 columns C10 , 1 column C1 , 
HCNS-IR-CIVIL-0720 N/A 1 column C5 and 1 column C6 ) from first floor level to second floor  0 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
level.

Concrete casting for columns ( 2 columns C10 , 1 column C1 , 1 
HCNS-IR-CIVIL-0721 N/A column C5 and 1 column C6 ) from first floor level to second floor  0 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
level.

Rebar for column at 3rd floor to proceed with form work. Please 
HCNS-IR-CIVIL-0722 N/A refer to the attached key plan for your reference. ( C11‐11 nos , C12‐ 0 C B Ok L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 27‐Apr‐15 29‐Apr‐15 Done
02 nos, C1‐01 no )

Formwork for wall at 4th floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0723 N/A Please refer to the attached key plan for your reference. ( SW2‐01no  0 C A Ok L Grid J‐M / 13 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
)
Civil Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status Update L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

Inspection request for concrete casting C40 for wall at 4th floor. 
HCNS-IR-CIVIL-0724 N/A Please refer to the attached key plan for your reference. ( SW2‐01 no  0 C B Ok L Grid J‐M / 13 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
)
Witness inspection request for compaction test ( 1st layer ) . Please 
HCNS-IR-CIVIL-0725 N/A 0 C D D NL Grid C‐A / 3‐7 Hotel UCC 28‐Apr‐15 29‐Apr‐15
refer to the attached key plan for your reference.
Witness inspection request for compaction test ( 1st layer ) . Please 
HCNS-IR-CIVIL-0725 N/A 1 C U/R U/R L Grid C‐A / 3‐7 Hotel UCC 29‐Apr‐15
refer to the attached key plan for your reference.

Formwork for column at 3rd floor to proceed with Concrete casting. 
HCNS-IR-CIVIL-0726 N/A 0 C U/R U/R L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
Please refer to the attached key plan for your reference.

Inspection request for concrete casting C40 for column at 3rd floor. 
HCNS-IR-CIVIL-0727 N/A Please refer to the attached key plan for your reference. ( C11‐11nos  0 C U/R U/R L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
, C12‐02 nos , C1‐01 no )
Inspection request of rebar for wall at 3rd floor to proceed with form 
HCNS-IR-CIVIL-0728 N/A work. Please refer to the attached key plan for your reference. ( CW6‐ 0 C U/R U/R L Grid K‐M / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
01no )

Inspection Request of rebar for stair‐2 from 2nd floor to 3rd floor. 
HCNS-IR-CIVIL-0729 N/A 0 C D D L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15 29‐Apr‐15
Please refer to the attached key plan for your reference.

Inspection request of formwork for stair‐2 from 2nd floor to 3rd 
HCNS-IR-CIVIL-0730 N/A floor to proceed with concrete casting. Please refer to the attached  0 C D D L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15 29‐Apr‐15
key plan for your reference.

Inspection request for concrete casting C40 for stair‐2 from 2nd floor 
HCNS-IR-CIVIL-0731 N/A 0 C U/R U/R L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15
to 3rd floor. Please refer to the attached key plan for your reference.

Inspection requet of rebar for 1st floor slab besides swimming pool. 
HCNS-IR-CIVIL-0732 N/A 0 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
Please refer to the attached key plan for your reference.
Formwork for wall at 4th floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0733 N/A Please refer to the attached key plan for your reference. ( CW2‐01no  0 C U/R U/R L Grid Q‐N / 13‐15 Hotel 4th floor UCC 29‐Apr‐15
& CW1‐01no )
Inspection request for concrete casting C40 for wall at 4th floor. 
HCNS-IR-CIVIL-0734 N/A Please refer to the attached key paln for your reference . ( CW2‐ 0 C U/R U/R L Grid Q‐N / 13‐15 Hotel 4th floor UCC 29‐Apr‐15
01no & CW1‐01 no )
Formwork for wall at mezz. Floor to proceed with concrete casting. 
HCNS-IR-CIVIL-0735 N/A Please refer to the attached key plan for your reference. ( CW7‐01no  0 C U/R U/R L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 29‐Apr‐15
)
Inspection request for concrete casting C40 for wall at mezz. Floor . 
HCNS-IR-CIVIL-0736 N/A Please refer to the attached key plan for your reference. ( CW7‐01  0 C U/R U/R L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 29‐Apr‐15
no )

Inspection for formwork for columns ( C6 , C12 and Shear wall W6 ) 
HCNS-IR-CIVIL-0740 N/A 0 C U/R U/R L Grid R‐T / 5‐7 Bookstore UCC 29‐Apr‐15
from first floor level to second floor level.

Concrete Casting for columns ( C6 , C12 and Shear wall W6 ) from 
HCNS-IR-CIVIL-0741 N/A 0 C U/R U/R L Grid R‐T / 5‐7 Bookstore UCC 29‐Apr‐15
first floor leve to second floor level.

Rebar for Beam at 4th floor to proceed with formwork. Please refer 
HCNS-IR-CIVIL-0742 N/A 0 C U/R U/R L Grid J / 6‐9 Hotel 4th floor UCC 29‐Apr‐15
to the attached key plan for your reference.
MEP Inspection Request (Mechanical)
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

Installation of Sleeves and Block out for HVAC, Plumbing and


HCNS-IR-MEP-M-
29 N/A firefighting services prior to concrete pouring slab along the 0 M B L Hotel Building , Fourth floor ucc 19-Apr-15 21-Apr-15 Done
029
grid line from grid lines 4-15 / J-Q at fourth floor hotel building.
Installation of Sleeves and Block out for HVAC , Plumbing and
HCNS-IR-MEP-M- firefighting services prior to concrete pouring slab along the
30 N/A 0 M B L Bookstore Building, first floor I-T / 14-6 UCC 18-Apr-15 20-Apr-15 Done
030 grid line from expansion joint : I-T / 14-6 at first floor bookstore
building.
Installation of sleeves and block out for HVAC , Plumbing and
HCNS-IR-MEP-M-
31 N/A firefighting services prior to concrete pouring slab along the 0 M B L Hotel Building , Fourth floor ucc 13-Apr-15 14-Apr-15 Done
031
grid Line: J-Q / 14-17 as per attached highlighted drawing.
Installation of sleeves and block out for plumbing and services
HCNS-IR-MEP-M-
32 N/A prior to concrete pouring slab along the grid lines 1-4 / A-E as 0 M B L Bookstore building , Mezzanine floor ucc 19-Apr-15 20-Apr-15 Done
032
per attached highlighted drawing.
Inspection for the installation of sleeves and block outs prior to
HCNS-IR-MEP-M- Hotel Building - Mezzanine Floor (
33 N/A slab concrete pouring in hotel building - mezzanine floor ( 0 M U/R L ucc 21-Apr-15
033 Gridline : 1-4 / B-K )
Gridline: 1-4 / B-K ) as per highlighted in the attached drawing.

Inspection for the installation of sleeves and block outs prior to


HCNS-IR-MEP-M- Hotel Building - Third floor ( Gridline : 1-
34 N/A slab concrete pouring in hotel building - third floor ( gridline : 1- 0 M D L ucc 21-Apr-15 23-Apr-15 Done
034 4 / J-R )
4 / J-R ) as highlighted in the attached drawing.

Inspection for the installation of sleeves and block outs prior to


HCNS-IR-MEP-M- Hotel Building - Third floor ( Gridline : 1-
34 N/A slab concrete pouring in hotel building - third floor ( gridline : 1- 1 M B L ucc 22-Apr-15 23-Apr-15 Done
034 4 / J-R )
4 / J-R ) as highlighted in the attached drawing.
Inspection for the installation of sleeves and block outs prior to
HCNS-IR-MEP-M-
35 N/A slab concrete pouring in bookstore first floor towards left of 0 M B L Bookstore Building - first floor ucc 25-Apr-15 28-Apr-15 Done
035
expansion joint from gridline J ( from expansion joint ) - A / 14-
ELECTRICAL Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

Installation of PVC conduits and boxes for lighting, small


power , earthing & lighting , CCTV , PA/GA , Access control ,
HCNS-IR-MEP-E-
N/A Security & safety , Data , FA System at mezzanine floor slab 1 E D NL Bookstore , First floor Grid at A-E / 4-13 UCC 9-Apr-15 12-Apr-15 Done
0037
prior to the concrete pouring for the first floor as per
highlighted and attached drawings.

Installation of PVC conduits and boxes for lighting, small


power , earthing & lighting , CCTV , PA/GA , Access control ,
HCNS-IR-MEP-E-
N/A Security & safety , Data , FA System at mezzanine floor slab 2 E B L Bookstore , First floor Grid at A-E / 4-13 UCC 15-Apr-15 16-Apr-15 Done
0037
prior to the concrete pouring for the first floor as per
highlighted and attached drawings.

Installation of PVC conduits and boxes for small power,


Lighting , fire alarm , Access control, CCTV , PA/GA , Data &
HCNS-IR-MEP-E-
N/A Telephone at Hotel - Second floor prior to the concrete pouring 0 E B L Hotel - Third Floor ( Gridline : H-R / 1-4 ) UCC 21-Apr-15 23-Apr-15 Done
0040
of Third floor ( Gridline: H-R / 1-4 ) as per attached highlighted
drawings.

Installation of PVC conduits and Boxes for small power,


HCNS-IR-MEP-E- Lighting , Fire alarm , CCTV at hotel - second floor columns
N/A 0 E B L Hotel - 2nd floor ( Gridline: H-R / 1-4 ) UCC 12-Apr-15 13-Apr-15 Done
0041 and walls ( Grid line: H-R /1-4 ) as per attached highlighted
drawings.

Installation of PVC Conduits and Boxes for small power ,


HCNS-IR-MEP-E- Lighting , Fire alarm , CCTV , data , security & safety , Earthing Bookstore - ground floor ( Gridline: A-K /
N/A 0 E B L UCC 6-Apr-15 7-Apr-15 Done
0042 , PA/GM at Bookstore - ground floor columns ( Gridlines: A-K / 1-7 )
1-7 ) as per attached highlighted drawings.

Installation of PVC conduits and boxes for lighting, CCTV ,


HCNS-IR-MEP-E- Hotel - Stair # 3 from third floor to fourth
N/A Speaker and fire alarm, in Stair case no . 3 from 3rd floor to 0 E B L UCC 6-Apr-15 7-Apr-15 Done
0043 floor
4th floor as per highlighted and attached drawings.

Installation of PVC conduits and boxes for lighting , small


power , earthing & lighting , CCTV , PA/GA , access control ,
HCNS-IR-MEP-E-
N/A security & safety , data , FA system at Mezzanine floor slab 0 E D NL Bookstore, First floor grid at E-J / 9-13 UCC 9-Apr-15 12-Apr-15 Done
0044
prior to concrete pouring for the first floor as per highlighted
and attached drawings.

Installation of PVC conduits and boxes for lighting , small


power , earthing & lighting , CCTV , PA/GA , access control ,
HCNS-IR-MEP-E-
N/A security & safety , data , FA system at Mezzanine floor slab 1 E B L Bookstore, First floor grid at E-J / 9-13 UCC 15-Apr-15 16-Apr-15 Done
0044
prior to concrete pouring for the first floor as per highlighted
and attached drawings.

Installation of PVC conduits & boxes for lighting , small power ,


fire alarm , CCTV , Data & Telephone , PA/GA System for
HCNS-IR-MEP-E-
N/A ground floor ( A-H / 1-5 ) prior to the concrete pouring in 0 E B L Hotel , Mezzanine floor Grid ( A-H / 1-5 ) UCC 21-Apr-15 22-Apr-15 Done
0045
mezzanine floor slab as per highlighted and attached
drawings.
ELECTRICAL Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

Installation of PVC Conduits and boxes for CCTV bookstore-


HCNS-IR-MEP-E- Bookstore - Ground floor ( Gridline: C-R
N/A ground floor columns ( Gridline: C-R / 13-14 ) as per attached 0 E B L UCC 11-Apr-15 12-Apr-15 Done
0046 / 13-14 )
highlighted drawings.

Installation of PVC conduits and boxes for lighting , PA&GA ,


HCNS-IR-MEP-E- Hotel - Fourth floor to roof stair no # 3 (
N/A Fire alarm , CCTV at fourth floor to roof floor stair # 3 ( Gridline 0 E B L UCC 11-Apr-15 13-Apr-15 Done
0047 Gridline: N-P / 17-18 )
: N-P / 17-18 ) as per attached highlighted drawings.

Installation of PVC conduits and boxes for lighting , small


HCNS-IR-MEP-E- power , RMS , PA&GA , fire alarm, CCTV , Data at Third floor Hotel fourth floor slab ( Gridline: H-R / 15-
N/A 0 E B L UCC 14-Apr-15 15-Apr-15 Done
0048 slab prior to the concrete pouring at fourth floor ( Gridline : H-R 17 )
/ 15-17 ) as per attached highlighted drawings.

Installation of PVC conduits and Boxes for small power & RMS
HCNS-IR-MEP-E- Hotel fourth column ( Gridline: H-R / 15-
N/A at fourth floor column. ( Gridline H-R / 15-17 ) as per attached 0 E B L UCC 15-Apr-15 16-Apr-15 Done
0049 17 )
highlighted drawings.

Installation of PVC conduits and boxes for lighting , fire alarm ,


HCNS-IR-MEP-E- PA/GA system , CCTV , Data & Telephone at ground floor stair Hotel - Ground floor stair NO:4 (
N/A 0 E B L UCC 16-Apr-15 22-Apr-15 Done
0050 no: 4 ( Gridline : P-Q / 2-3 ) as per attached highlighted Gridline: P-Q / 2-3 )
drawings.

Installation of PVC conduits and boxes for lighting, small


power , Earthing & Lighting , CCTV , PA/GA, Access Control ,
HCNS-IR-MEP-E-
N/A Security & Safety, Data , FA System At Ground & Mezzanine 0 E B L Bookstore, First floor Grid At I-T / 6-14 UCC 18-Apr-15 22-Apr-15 Done
0051
floor area prior to the concrete pouring for the first floor slab as
per highlighted and attached drawings.

Installation of PVC Conduits and Boxes for lighting , small


power , CCTV , PA/GA , Access Control, Security & Safety,
HCNS-IR-MEP-E- Bookstore, Mezzanine floor Grid at A-E /
N/A Data , FA System at ground floor slab prior to the concrete 0 E B L UCC 19-Apr-15 20-Apr-15 Done
0052 2-4
pouring for the mezzanine floor as per highlighted and
attached drawings.

Installation of PVC conduits and Boxes for lighting, small


power , CCTV , PA/GA , Access Control, Security & Safety ,
HCNS-IR-MEP-E-
N/A Data , FA System at third floor slab prior to the concrete 0 E D L Hotel , Fourth floor Grid at H-R / 4-15 UCC 20-Apr-15 22-Apr-15 Done
0053
pouring for the fourth floor as per highlighted and attached
drawings.

Installation of PVC conduits and Boxes for lighting, small


power , CCTV , PA/GA , Access Control, Security & Safety ,
HCNS-IR-MEP-E-
N/A Data , FA System at third floor slab prior to the concrete 1 E B L Hotel , Fourth floor Grid at H-R / 4-15 UCC 22-Apr-15   23-Apr-15 Done
0053
pouring for the fourth floor as per highlighted and attached
drawings.
ELECTRICAL Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

Installation of PVC conduits and boxes for lighting , small


HCNS-IR-MEP-E- power , CCTV , PA/GA , Access control , Security & Safety ,
N/A 0 E B L Bookstore , First floor Grid at I-T / 7-13 UCC 25-Apr-15 27-Apr-15 Done
0054 Data , FA System at first floor columns & core walls as per
highlighted and attached drawings.

Installation of PVC conduits and GI Back boxes for lighting ,


HCNS-IR-MEP-E- First floor , Mock up room ( suite type 04
N/A small power , data in mock up room ( suite type 04 , Twin type 0 E D NL UCC 27-Apr-15 27-Apr-15
0055 , Twin type 02 ) Grid ( M-R / 14-17 )
02 ) as per attached drawings.

Installation of PVC conduits and GI Back boxes for lighting ,


HCNS-IR-MEP-E- First floor , Mock up room ( suite type 04
N/A small power , data in mock up room ( suite type 04 , Twin type 1 E D L UCC 28-Apr-15 29-Apr-15
0055 , Twin type 02 ) Grid ( M-R / 14-17 )
02 ) as per attached drawings.

Installation of PVC conduits and boxes for lighting , small


power , earthing & lighting , CCTV , PA/GA , access control ,
HCNS-IR-MEP-E-
N/A security & safety , data , FA system at Mezzanine floor slab 0 E B L Bookstore , First floor grid at A-G / 1-6 UCC 26-Apr-15 27-Apr-15 Done
0056
prior to concrete pouring for the first floor as per highlighted
and attached drawings.

Installation of PVC conduits and boxes for lighting , small


HCNS-IR-MEP-E- Hotel , Fourth floor columns grid at H-R /
N/A power , Data , FA system , at fourth floor columns as per 0 E B L UCC 26-Apr-15 27-Apr-15 Done
0057 4-15
highlighted and attached drawings.

Installation of PVC conduits and Boxes for lighting , small


HCNS-IR-MEP-E- Hotel, fourth floor corewall Grid at H-R /
N/A power , data at fourth floor corewall as per highlighted and 0 E B L UCC 26-Apr-15 27-Apr-15 Done
0058 4-15.
attached drawings.

Installation of PVC Conduits and Boxes for CCTV , PA/GA at


HCNS-IR-MEP-E-
N/A Mezzanine floor slab prior to the concrete pouring for the first 0 E B L Bookstore, first floor grid at A-J / 13-14. UCC 26-Apr-15 27-Apr-15 Done
0059
floor as per highlighted and attached drawings.

Installation of PVC Conduits and Boxes for lighting , FA


HCNS-IR-MEP-E- Hotel, Ground floor Stair # 1 grid At E-F /
N/A System , CCTV , PA/GA at stair # 1 from ground floor to 0 E B L UCC 26-Apr-15 27-Apr-15 Done
0060 1-3.
mezzanine floor as per highlighted and attached drawings.

Installation of PVC conduits and boxes for lighting , small


HCNS-IR-MEP-E- Hotel , Mezzanine floor Stair # 1
N/A power , CCTV , Data & Telephone , PA/GA at mezzanine floor 0 E B L UCC 27-Apr-15 29-Apr-15 Done
0061 corewall grid at E-F / 1-3
stair # 1 Core wall as per highlighted and attached drawings.
ELECTRICAL Inspection Request
Approved  A

Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Originator Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. no. Al Handasah (1) Al Handasah

Installation of PVC conduits and Boxes for lighting , FA System


HCNS-IR-MEP-E- Hotel , Stair # 2 from 2nd floor to 3rd
N/A , CCTV , PA/GA at Stair # 2 from 2nd floor to 3rd floor as per 0 E B L UCC 27-Apr-15 29-Apr-15 Done
0062 floor grid at M-K / 1-3.
highlighted and attached drawings.

Installation of PVC conduits and Boxes for small power,


HCNS-IR-MEP-E-
N/A Earthing & Lighting, CCTV , Data at first floor columns & 0 E B L Bookstore, First floor Gird at I-T / 5-8 UCC 27-Apr-15 28-Apr-15 Done
0063
Corewalls as per highlighted and attached drawings.

Installation of PVC conduits and boxes for lighting , small


HCNS-IR-MEP-E- power , earthing & lighting , CCTV , fire alarm , security &
N/A 0 E B L Bookstore , first floor grid at A-J / 2-14 UCC 27-Apr-15 29-Apr-15 Done
0064 safety , Data at first floor columns & walls as per highlighted
and attached drawings.

Installation of PVC Conduits and boxes for lighting , small


HCNS-IR-MEP-E- power , earthing & lighting , CCTV , fire alarm system at first
N/A 0 E B L Hotel , third floor grid at H-R / 1-4 UCC 27-Apr-15 29-Apr-15 Done
0065 floor columns & corewalls as per highlighted and attached
drawings.
SOUQ ALNAJADA RENOVATION (SNR)

MATERIALS DELIVERED INSPECTION REQUEST LOG


Project No : 295-14 SNR
Client : Private Engineering Office LEGEND
Consultant : Dar Al Handasah 1) A = Accepted
Main Contractor : Urbacon General Contracting 2) AWC = Accepted With Comments
4) B = Unsatisfactory

Updated On :

MDIR No. Rev. Discipline Project Delivery Note No. Description Manufacture/ Supplier Sub. Date Reply. Date Status with Dar Status

Steel DSB X 12M X 12MM Qatar Steel Co


MDIR-CIVIL-0118 0 CIVIL HCNS 310415 4-Apr-2015 6-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 10MM
Qatar Steel Co
MDIR-CIVIL-0119 0 CIVIL HCNS 310415 Steel DSB X 12M X 12MM 4-Apr-2015 6-Apr-2015 Satisfactory Accepted - A
Blocks H G4 - T&G 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0120 0 CIVIL HCNS 2840 8-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
Blocks G4 Plain - T&G 10X25X60 /
Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0121 0 CIVIL HCNS 2824 Acico Glue 30KG / Bags 9-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
Blocks G4 - T&G 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0122 0 CIVIL HCNS 2815 8-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
3.0m X 25cm X 30cm - Lintels Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0123 0 CIVIL HCNS 2823 9-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
Hand Saw for block Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0124 0 CIVIL HCNS 2817 8-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
Blocks G4 - TG 20x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0125 0 CIVIL HCNS 2741 8-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 16MM Qatar Steel Co
MDIR-CIVIL-0126 0 CIVIL HCNS 9375 8-Apr-2015 11-Apr-2015 Satisfactory Accepted - A
STEEL DSB X 12M X 16MM
Qatar Steel Co
MDIR-CIVIL-0127 0 CIVIL HCNS 9425 STEEL DSB X 12M X 20MM 11-Apr-2015 15-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 20X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0128 0 CIVIL HCNS 2853 11-Apr-2015 15-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 30X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0129 0 CIVIL HCNS 2865 11-Apr-2015 15-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 30X25X60 /
Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0130 0 CIVIL HCNS 2876 ACICO Glue 11-Apr-2015 15-Apr-2015 Satisfactory Accepted - A
Repair Mortar Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0131 0 CIVIL HCNS 2854 11-Apr-2015 15-Apr-2015 Unsatisfactory Unsatisfactory
Blocks G4-TG 15X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0132 0 CIVIL HCNS 2926 14-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 30X25X60/
Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0133 0 CIVIL HCNS 2930 ACICO Glue 30Kg / bag 14-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 30X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0134 0 CIVIL HCNS 2919 14-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 20X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0135 0 CIVIL HCNS 2924 14-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 25X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0136 0 CIVIL HCNS 2925 14-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 20X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0137 0 CIVIL HCNS 2969 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 20X25X60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0138 0 CIVIL HCNS 2967 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Blocks G4-TG 20X25X60 /
Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0139 0 CIVIL HCNS 768 Blocks G4-TG 30X25X60 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 12MM Qatar Steel Co
MDIR-CIVIL-0140 0 CIVIL HCNS 41500816 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 16MM Qatar Steel Co
MDIR-CIVIL-0141 0 CIVIL HCNS 9574 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 16MM Qatar Steel Co
MDIR-CIVIL-0142 0 CIVIL HCNS 9549 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A
Steel DSB X 12M X 10MM /
Qatar Steel Co
MDIR-CIVIL-0143 0 CIVIL HCNS 313532 Steel DSB X 12M X 14MM 18-Apr-2015 25-Apr-2015 Satisfactory Accepted - A

U295/00QA/PQP/0016 Rev.00 November 2014


SOUQ ALNAJADA RENOVATION (SNR)

MATERIALS DELIVERED INSPECTION REQUEST LOG


Project No : 295-14 SNR
Client : Private Engineering Office LEGEND
Consultant : Dar Al Handasah 1) A = Accepted
Main Contractor : Urbacon General Contracting 2) AWC = Accepted With Comments
4) B = Unsatisfactory

Updated On :

MDIR No. Rev. Discipline Project Delivery Note No. Description Manufacture/ Supplier Sub. Date Reply. Date Status with Dar Status

Blocks H G4-TG 20x25x60 Qatar Aerated Concrete Industries Co. WLL


MDIR-CIVIL-0144 0 CIVIL HCNS 3049 22-Apr-2015
Blocks H G4-Plain 10x30x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0145 0 CIVIL HCNS 3048 22-Apr-2015
Blocks H G4-Plain 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0146 0 CIVIL HCNS 3028 22-Apr-2015
Blocks H G4-TG 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0147 0 CIVIL HCNS 3041 22-Apr-2015
Steel DSB X 12M X 12MM Qatar Steel Co
MDIR-CIVIL-0148 0 CIVIL HCNS KSIF/15426-N 23-Apr-2015
Renderoc LA Xtra-25 KG Al Gurg Fosroc LLC
MDIR-CIVIL-0149 0 CIVIL HCNS 1.11561E+11 23-Apr-2015
Blocks H G4-TG 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0150 0 CIVIL HCNS 3091 25-Apr-2015
Blocks H G4-TG 20x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0151 0 CIVIL HCNS 3088 25-Apr-2015
Blocks H G4-TG 10x30x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0152 0 CIVIL HCNS 3060 & 3061 25-Apr-2015
Blocks H G4-TG 20x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0153 0 CIVIL HCNS 3064 25-Apr-2015
Steek DSB X 12m X 16mm Qatar Steel Co
MDIR-CIVIL-0154 0 CIVIL HCNS 9707 25-Apr-2015
Blocks H G4-TG 15x25x60
Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0155 0 CIVIL HCNS 3115 / 3116 Acico glue 30kg / bag 28-Apr-2015
Blocks H G4-TG 15x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0156 0 CIVIL HCNS 3098 28-Apr-2015
Blocks H G4-TG 20x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0157 0 CIVIL HCNS 3117 28-Apr-2015
Blocks H G4-TG 30x25x60 Qatar Aerated Concrete Industries Co. WLL
MDIR-CIVIL-0158 0 CIVIL HCNS 3096 28-Apr-2015

U295/00QA/PQP/0016 Rev.00 November 2014


Satisfactory A Electrical Materials Delivered top Site Log Inspection Request
Unsatisfactory B
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15

Site Inspection Ref  Date Submitted to Dar  Pending days  Date received from Dar 


SR No. Originator Ref no. Inspection Details Rev Disc Status L/NL Area Originator Remarks
No. Al Handasah (1) Al Handasah

13 MDIR-E-0014 N/A PVC conduit pipe 25mm 0 E A L HCNS UCC 1-Apr-15 4-Apr-15 done

14 MDIR-E-0015 N/A PVC Pipes and Fittings. 0 E B L HCNS UCC 4-Apr-15 5-Apr-15

15 MDIR-E-0016 N/A GI Boxes 0 E A L HCNS UCC 20-Apr-15 22-Apr-15 done


SOUQ ALNAJADA RENOVATION (SNR)

MATERIALS DELIVERED INSPECTION REQUEST LOG


Project No : 295-14 SNR
Client : Private Engineering Office LEGEND
Consultant : Dar Al handasah 1) A = Accepted
Main Contractor : Urbacon General Contracting 2) AWC = Accepted With Comments
4) B = Unsatisfactory

Updated On :
Manufacture/
MDIR No. Rev. Discipline Project Delivery Note No. Description Sub. Date Reply. Date Status with Dar Status
Supplier
MDIR-MEP-0006 M HCNS Thermobreak Insulation Thermobreak Satisfactory
0 3264 15-Apr-2015 19-Apr-2015 A - Accepted
MDIR-MEP-0007 M HCNS UPVC Drainage pipes-above ground Pipes-Tech Satisfactory
0 15198 / 15176 16-Apr-2015 22-Apr-2015 A - Accepted
MDIR-MEP-0008 M HCNS Hangers and Supports Leminar / Weicco Satisfactory
0 15854 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0009 M HCNS Hilti Materials-Hangers , Supports and accessories Hilti Satisfactory
0 76321 & 76322 20-Apr-2015 22-Apr-2015 A - Accepted
MDIR-MEP-0010 M HCNS Aspen Aluminium Tapes Aspen Satisfactory
0 CR-583 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0011 M HCNS PPR Pipes and fittings. Aquatherm Satisfactory
0 CR-1201 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0012 M HCNS GI Duct Nippon Satisfactory
0 22042015 23-Apr-2015 25-Apr-2015 A - Accepted

U295/00QA/PQP/0016 Rev.00 November 2014


Approved - A A

Approved as Noted - AAN B

Review & Resubmit - RR C


HCNS Method Statement LOG
Not Approved - NA D

Under Review U/R U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

MS Submittal Ref. Document Ref L/N Area of Specialty of Date Pending Date
SN Rev Title Rev Disc Status Specialty Zone Originator Remarks
No. No. L Location Works Submitte days Commente
Internal and
Method Statement for Internal and External Internal and
27 U29529514-HCNS/MS/0022 0 MS-A-0002 0 A B L General General External UCC 4‐Apr‐15 9‐Apr‐15 Done
Plastering External Plastering
Plastering

B
Method Statement for the Installation of UPVC Drainage Pipes and  Installation of UPVC Drainage  Installation of UPVC 
28 U29529514-HCNS/MS/0023 0 MS‐M‐0009  0 MEP‐M L General General Radiant 5‐Apr‐15 8‐Apr‐15 Done
Fittings  Pipes and Fittings Drainage Pipes and Fittings

Installation of 
 Installation of Polypropylene 
B
Method Statement for the Installation of Polypropylene (PPR) Pipes  Polypropylene (PPR) Pipes 
29 U29529514-HCNS/MS/0024 0 MS‐M‐0002 0 MEP‐M L (PPR) Pipes and Fittings for  General General Radiant 5‐Apr‐15 8‐Apr‐15 Done
and Fittings for Water System and Fittings for Water 
Water System
System

U/R
REE‐HCNS‐DT‐0079
30 U29529514‐HCNS/MS/0025 0 Method Statement ‐ Installation of Fire Pumps 0 MEP L Installation of Fire Pumps General General Installation of Fire Pumps Radiant 7‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0012

Method Statement ‐ 
U/R
REE‐HCNS‐DT‐0081 Method Statement ‐ 
31 U29529514‐HCNS/MS/0026 0 Method Statement ‐ Instalaltion of Sanitary Wares 0 MEP L General General Instalaltion of Sanitary  Radiant 7‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0013 Instalaltion of Sanitary Wares
Wares
Method Statement ‐  Method Statement ‐ 

B
REE‐HCNS‐DT‐0089 Method Statement ‐ Installation and Testing of Fire Fighting Pipes,  Installation and Testing of Fire  Installation and Testing of 
32 U29529514‐HCNS/MS/0027 0 0 MEP L General General Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0011 Fittings, Sprinkles and Air Vents Fighting Pipes, Fittings,  Fire Fighting Pipes, Fittings, 
Sprinkles and Air Vents Sprinkles and Air Vents
Method Statement ‐  Method Statement ‐ 
B
REE‐HCNS‐DT‐0077
33 U29529514‐HCNS/MS/0028 0 Method Statement ‐ Installation of Grills and Diffusers 0 MEP L Installation of Grills and  General General Installation of Grills and  Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0004
Diffusers Diffusers

B
REE‐HCNS‐DT‐0076 Method Statement ‐  Method Statement ‐ 
34 U29529514‐HCNS/MS/0029 0 Method Statement ‐ Installation of Fans 0 MEP L General General Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0003 Installation of Plans Installation of Plans
Method Statement ‐  Method Statement ‐ 
Installation of Ducts,  Installation of Ducts, 
B
REE‐HCNS‐DT‐0075 Method Statement ‐ Installation of Ducts, Accessories and Thermal 
35 U29529514‐HCNS/MS/0030 0 0 MEP L Accessories and Thermal  General General Accessories and Thermal  Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0002 Insulation(including anchors and support)
Insulation(including anchors  Insulation(including anchors 
and support) and support)

B
REE‐HCNS‐DT‐0080 Method Statement ‐ Instalaltion of Refrigerant Copper Pipes and  Method Statement ‐  Method Statement ‐ 
36 U29529514‐HCNS/MS/0031 0 0 MEP L General General Radiant 7‐Apr‐15 12‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0005 Fittings (including anchors and supports) Instalaltion of Refrigerant  Instalaltion of Refrigerant 
Method Statement ‐ Testing of  Method Statement ‐ Testing 
B
REE‐HCNS‐DT‐0078
37 U29529514‐HCNS/MS/0032 0 Method Statement ‐ Testing of UPVC Drainage Pipes and Fitting 0 MEP L UPVC Drainage Pipes and  General General of UPVC Drainage Pipes and  Radiant 7‐Apr‐15 12‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0010
Fitting Fitting
Method Statement ‐ 
Method Statement ‐ 
U/R
Method Statement ‐ Installation of D X Spilts Units (Included anchors  Installation of D X Spilts 
38 U29529514‐HCNS/MS/0033 0 REE‐HCNS‐DT‐0088 0 MEP L Installation of D X Spilts Units  General General Radiant 9‐Apr‐15
and suport) Units (Included anchors and 
(Included anchors and suport)
suport)
Method Statement ‐ 
Method Statement ‐ 
Installation and Insulation 
Installation and Insulation of 
U/R
Method Statement ‐ Installation and Insulation of water supply copper  of water supply copper 
39 U29529514‐HCNS/MS/0034 0 REE‐HCNS‐DT‐0087 0 MEP L water supply copper pipes and  General General Radiant 9‐Apr‐15
pipes and fittings ( including anchors, supports, gauges and meters) pipes and fittings ( including 
fittings ( including anchors, 
anchors, supports, gauges 
supports, gauges and meters
and meters

B
Method Statement for Installation & Termination of LV Cables and   Installation & Termination of   Installation & Termination 
40 U29529514‐HCNS/MS/0035 0 HCNS‐MS‐E‐0006 0 MEP‐E L General General Radiant 14‐Apr‐15 20‐Apr‐15 Done
Wires  LV Cables and Wires  of LV Cables and Wires 

 Installation of Underground  Installation of Underground 
C
Method Statement ‐ Installation of Underground UPVC Ducts for 
41 U29529514‐HCNS/MS/0036 0 HCNS‐MS‐E‐009 REV.0 0 MEP‐E L UPVC Ducts for Electrical and  General General UPVC Ducts for Electrical  Radiant 15‐Apr‐15 20‐Apr‐15
Electrical and ELV Servics
ELV Servics and ELV Servics

C
 Installation of LV Distribution   Installation of LV 
42 U29529514‐HCNS/MS/0037 0 U29529514‐HCNS‐ME‐E‐0010 Method Statement ‐ Installation of LV Distribution Boards 0 MEP‐E L General General Radiant 15‐Apr‐15 20‐Apr‐15
Boards Distribution Boards

 Installation of Cable 
C
 Installation of Cable Trunking 
43 U29529514‐HCNS/MS/0038 0 MS‐E‐0007 Method Statement ‐ Installation of Cable Trunking for Electrical Ststem 0 MEP‐E L General General Trunking for Electrical  Radiant 15‐Apr‐15 20‐Apr‐15
for Electrical Ststem
Ststem

44 U29529514‐HCNS/MS/0039 0 MS‐A‐003 Method Statement for Renovation & Repairing of Heritage Building  0 A B L Renovation & Repairing  Heritage Building  Heritage Building  Renovation & Repairing UCC 21‐Apr‐15 27‐Apr‐15 Done

B
Method Statement ‐ Coring Through Concrete Structural for MEP   Coring Through Concrete   Coring Through Concrete 
45 U29529514‐HCNS/MS/0040 0 MS‐0018 0 C L General General UCC 23‐Apr‐15 27‐Apr‐15 Done
Services Structural Structural

 Installation and Testing of   Installation and Testing of 
46 U29529514‐HCNS/MS/0041 0 MS‐E‐011 Method Statement ‐ Installation and Testing of MMC (Capacitor Bank) 0 MEP‐E L General General UCC ‐ MEP 28‐Apr‐15
MMC  MMC 
Approved - A A

Approved as Noted - AAN B

Review & Resubmit - RR C


HCNS Method Statement LOG
Not Approved - NA D

Under Review U/R U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

MS Submittal Ref. Document Ref L/N Area of Specialty of Date Pending Date
SN Rev Title Rev Disc Status Specialty Zone Originator Remarks
No. No. L Location Works Submitte days Commente

B
Method Statement for Demolition of the Existing Restaurant and Old  Demolition of the Existing   Existing Restaurant   Existing Restaurant 
47 U29529514‐HCNS/MS/0042 0 MS‐C‐022 0 C L Demolition UCC 28‐Apr‐15 29‐Apr‐15 Done
Souq Restaurant and Old Souq and Old Souq and Old Souq
Approved - A A

Approved as Noted - AAN B

Revise & Resubmit - RR C


HNCS Pre‐qualification Submittal Log
Not Approved - NA D

Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Najada Souq As of: 13-May-15
Pendi
Pre-qualification Submittal Area of Date
SN Rev Document Ref No. Title Rev Disc Status L/NL Documents Specialty Originator Date Submitted: ng Remarks
Ref: Location Commented
days
6 SPQS-0005 0 FBTC-GRC-2015-DT-246 Pre-Qualification from M/S. Fibro 0 C C L Pre-qualification Pre-Qualification Documents General Fibro 7-Apr-15 11-Apr-15

Prequalification - M/s Consolidated Engineering System Consolidated Engineering


7 SPQS-0006 0 REE-HCNS-DT-0177
Co. for Fire Protection System
0 MEP - M C NL Pre-qualification Pre-Qualification Documents Hotel & Bookstore
System Co
15-Apr-15 18-Apr-15

Prequalification - M/s Consolidated Engineering System Consolidated Engineering


SPQS-0006 1 REE-HCNS-DT-0227
Co. for Fire Protection System
1 MEP - M U/R L Pre-qualification Pre-Qualification Documents Hotel & Bookstore
System Co
16-Apr-15

8 SPQS-0007 0 Transmittal No:0916 Pre-Qualification from M/s. Doha Extraco 0 C U/R L Pre-qualification Pre-Qualification Documents General Doha Extraco 16-Apr-15

Permit No. Prequalification - M/s. United Equipment Group


9 SPQS-0008 0
UEW8564/L02/2015 Dewatering and Dewatering Permit
0 C B L Pre-qualification Pre-Qualification Documents General United Equipment Group 22-Apr-15 23-Apr-15 Done

Joinery
10 SPQS-0009 0 ZWW/017/DT/506 Pre-Qualifications for M/s. Zebrano 0
Wokrs
U/R L Pre-qualification Pre-Qualification Documents Hotel & Bookstore Zebrano 29-Apr-15
Pre-Qualification of M/s JBK Controls for Fire Alarm
11 SPQS-0010 0 HCNS-REE-SCP-E-0001
System Controls
0 MEP-E U/R L Pre-qualification Pre-Qualification Documents General JBK Controls 27-Apr-15
Pre-Qualification of M/s Pacific Ocean Electrical Pacific Ocean Electrical
12 SPQS-0011 0 HCNS-REE-SCP-E-0002
Switchgear Wll for LV Panels
0 MEP-E U/R L Pre-qualification Pre-Qualification Documents Hotel & Bookstore
Switchgear
29-Apr-15
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

U29529514- UCC/295-295-14-HCNS/SD-S-RE-
83
HCNS/SDS/0013
1
H-4F-AABCO-0264
Hotel Fourth Floor- Part 1 Key Plan 1 S B L Part 1 Key Plan Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15 Done

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 1 AAO & Additional at Corner of Core Wall Part 1 AAO & Additional at Corner
85
HCNS/SDS/0013
1
H-4F-AABCO-0470 Reinforcement
1 S C L
of Core Wall Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15

Part 1 AAO, Sections, Chairs &


U29529514- UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 1 AAO, Sections, Chairs & Additional at corner of
87
HCNS/SDS/0013
1
H-4F-AABCO-0471 core wall reinforcement
1 S C L Additional at corner of core wall Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15
reinforcement

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 1 Punching Shear


89
HCNS/SDS/0013
1
H-4F-AABCO-0472
Hotel Fourth Floor - Part 1 Punching Shear Reinforcement 1 S C L
Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 1 Bottom B1& B2


91
HCNS/SDS/0013
1
H-4F-AABCO-0473
Hotel Fourth Floor -Part 1 Bottom B1& B2 Reinforcement 1 S C L
Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 1 Top T1 & T2


93
HCNS/SDS/0013
1
H-4F-AABCO-0474
Hotel Fourth Floor - Part 1 Top T1 & T2 Reinforcement 1 S C L
Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 1 Add Bottom & Top


95
HCNS/SDS/0013
1
H-4F-AABCO-0475
Hotel Fourth Floor - Part 1 Add Bottom & Top Reinforcement 1 S B L
Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15 Done

U29529514- UCC/295-295-14-HCNS-SD-M-GA- Adult & Kids


115
HCNS/SDS/0018
2
H-FF-PAB-0001
Najadah Hotel Adult & Kids Pool Mechanical Piping Layout 2 M C L Pool Mechanical Piping Layout
Pool
Hotel Palmera 6-Apr-15 14-Apr-15

U29529514- UCC/295-295-14-HCNS-SD-A-GA- Adult & Kids


120
HCNS/SDS/0018
2
H-FF-PAB-0003
Najadah Hotel Adult & Kids Pool Section Details 2 A C L Pool Section Details
Pool
Hotel Palmera 6-Apr-15 14-Apr-15

U29529514- UCC/295-295-14-HCNS-SD-A-GA- Adult & Kids


123
HCNS/SDS/0018
2
H-FF-PAB-0004
Najadah Hotel Adult & Kids Pool Installation Details 2 A C L Pool Installation Details
Pool
Hotel Palmera 6-Apr-15 14-Apr-15

U29529514- UCC/295-295-14-HCNS-SD-M-GA- Pool Mechanical Pump Room Adult & Kids


126
HCNS/SDS/0018
2
H-FF-PAB-0005
Najadah Hotel Adult & Kids Pool Mechanical Pump Room Section Details 2 M C L
Section Details Pool
Hotel Palmera 6-Apr-15 14-Apr-15

U29529514- UCC/295-295-14-HCNS-SD-M-GA- Pool Mechanical Builders Work Adult & Kids


128
HCNS/SDS/0018
2
H-FF-PAB-0006
Najadah Hotel Adult & Kids Pool Mechanical Builders Work Layout 1 M C L
Layout Pool
Hotel Palmera 6-Apr-15 14-Apr-15

U29529514- UCC/295-295-14-HCNS-SD-S-RE- Fourth Floor to


HCNS/SDS/0019
1
H-4F-AABCO-0269
Hotel Fourth Floor to Roof Floor - Part 1 Wall Reinforcement 1 S U/R L Part 1-Wall Reinforcement
Roof Floor
Hotel AABCO 26-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2 Key plan - Columns Fourth Floor to


HCNS/SDS/0023
1
H-4F-AABCO-0370
Hotel Fourth Floor to Roof Floor - Part 2 Key Plan - Columns Reinforcement 1 S U/R L
Reinforcement Roof Floor
Hotel AABCO 26-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Fourth Floor to


HCNS/SDS/0023
1
H-4F-AABCO-0371
Hotel Fourth Floor to Roof Floor - Part 2 - Columns Reinforcement 1 S U/R L Part 2- Columns Reinforcement
Roof Floor
Hotel AABCO 26-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2- Keyplan Add Bottom & Top


139
HCNS/SDS/0024
1
H-RF-AABCO-0395
Hotel Roof Floor - Part 2 Key Plan - Add Bottom & Top Reinforcement 1 S B L
Reinforcement
Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15 Done

Part 2- Additional Around Opening -


U29529514- UCC/295-295-14-HCNS/SD-S-RE- Hotel Roof Floor - Part 2 Additional Around Opening - Chair & Column PC2
141
HCNS/SDS/0024
1
H-RF-AABCO-0396 Reinforcement
1 S C L Chair & Column PC2 Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15
Reinforcement

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2- Additional Around Opening


143
HCNS/SDS/0024
1
H-RF-AABCO-0397
Hotel Roof Floor - Part 2 Additional Around Opening Reinforcement 1 S C L
Reinforcement
Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2- Punching Shear & Section


145
HCNS/SDS/0024
1
H-RF-AABCO-0398
Hotel Roof Floor - Part 2 Punching Shear & Section Reinforcement 1 S C L
Reinforcement
Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2 - Bottom B1 & B2


147
HCNS/SDS/0024
1
H-RF-AABCO-0399
Hotel Roof Floor - Part 2 Bottom B1 & B2 Reinforcement 1 S B L
Reinforcement
Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15 Done

U29529514- UCC/295-295-14-HCNS/SD-S-RE- Part 2 - Top T1 & T2


149
HCNS/SDS/0024
1
H-RF-AABCO-0400
Hotel Roof Floor - Part 2 Top T1 & T2 Reinforcement 1 S B L
Reinforcement
Roof Floor Hotel AABCO 18-Apr-15 29-Apr-15 Done

UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor to Roof Floor -Part 1 Columns Reinforcement and Key Part1 - Columns Reinforcement Fourth Floor to
SDS/0029 1
H-4F-AABCO-0265 Plan
1 S U/R L
and Key Plan Roof Floor
Hotel AABCO 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Fourth Floor to


SDS/0029 1
H-4F-AABCO-0266
Hotel Fourth Floor to Roof Floor -Part 1 Columns Reinforcement 1 S U/R L Part 1-Columns Reinforcement
Roof Floor
Hotel AABCO 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Upper Roof


SDS/0030 1
H-URF-AABCO-0410
Hotel Upper Roof Floor -Part 1 Beam Reinforcement 1 S C L Part 1 -Beam Reinforcement
Floor
Hotel AABCO 23-Apr-15 28-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Keyplan Columns Starter Basement


SDS/0031 1
BS-BF-AABCO-0013
Book Store Basement Floor Level Keyplan Columns Starter Reinforcement 1 S U/R L
Reinforcement Floor Level
Book Store AABCO 28-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Basement
SDS/0031 1
BS-BF-AABCO-0014
Book Store Basement Floor Level Columns Starter Reinforcement 1 S U/R L Columns Starter Reinforcement
Floor Level
Book Store AABCO 28-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Basement
SDS/0031 1
BS-BF-AABCO-0015
Book Store Basement Floor Level Columns Starter Reinforcement 1 S U/R L Columns Starter Reinforcement
Floor Level
Book Store AABCO 28-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Part2 -Key Plan - Beams Upper Roof


SDS/0033 1
H-URF-AABCO-0414
Hotel Upper Roof Floor - Part 2 Key Plan - Beams Reinforcement 1 S B L
Reinforcement Floor
Hotel AABCO 23-Apr-15 29-Apr-15 Done

UCC/295-295-14-HCNS/SD-S-RE-
181 SDS/0034 1
H-4F-AABCO-0349
Hotel Fourth Floor - Part 2 Keyplan 1 S C L Part 2 Keyplan Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 2 Add. Around Opening - Chair & Section & Add at Add. Around Opening - Chair &
183 SDS/0034 1
H-4F-AABCO-0350 Corner CW
1 S C L
Section & Add at Corner CW
Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 2 Add. Around Opening & Add at Corner Core Wall Add. Around Opening & Add at
185 SDS/0034 1
H-4F-AABCO-0351 Reinforcement
1 S C L
Corner Core Wall Reinforcement
Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
187 SDS/0034 1
H-4F-AABCO-0352
Hotel Fourth Floor - Part 2 Punching Shear Reinforcement 1 S C L Punching Shear Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
189 SDS/0034 1
H-4F-AABCO-0353
Hotel Fourth Floor - Part 2 Bottom B1 & B2 Reinforcement 1 S C L Bottom B1 & B2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Bottom B2 & Add Bottom


191 SDS/0034 1
H-4F-AABCO-0354
Hotel Fourth Floor - Part 2 Bottom B2 & Add Bottom Reinforcement 1 S C L
Reinforcement
Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
193 SDS/0034 1
H-4F-AABCO-0355
Hotel Fourth Floor - Part 2 Top T1 & T2 Reinforcement 1 S C L Top T1 & T2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
195 SDS/0034 1
H-4F-AABCO-0356
Hotel Fourth Floor - Part 2 Add Top & Top T2 Reinforcement 1 S C L Top & Top T2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
210 SDS/0037 1
H-RF-AABCO-0327
Hotel Roof Floor - Part 1 Key Plan 1 S B L Key Plan Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15 Done

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days
UCC/295-295-14-HCNS/SD-S-RE- Part 1-Additional Around Opening
212 SDS/0037 1
H-RF-AABCO-0328
Hotel Roof Floor- Part 1 Additional Around Opening Reinforcement 1 S C L
Reinforcement
Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Part 1- Punching Shear - Chair &


214 SDS/0037 1
H-RF-AABCO-0329
Hotel Roof Floor- Part 1 Punching Shear - Chair & Section Reinforcement 1 S C L
Section Reinforcement
Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Part 1-Bottom B1 & B2


216 SDS/0037 1
H-RF-AABCO-0330
Hotel Roof Floor - Part 1 Bottom B1 & B2 Reinforcement 1 S C L
Reinforcement
Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
218 SDS/0037 1
H-RF-AABCO-0331
Hotel Roof Floor - Part 1 Top T1 & T2 Reinforcement 1 S B L Part 1 Top T1 & T2 Reinforcement Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15 Done

UCC/295-295-14-HCNS/SD-S-RE- Part 1- Add Bottom & Top


220 SDS/0037 1
H-RF-AABCO-0332
Hotel Roof Floor - Part 1 Add Bottom & Top Reinforcement 1 S B L
Reinforcement
Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL-
229 SDS/0039 5
H-GF-UCC-0105
Hotel Ground Floor Blockwork Master Plan 5 A C NL Blockwork Master Plan Ground Floor Hotel UCC 5-Apr-15 6-Apr-15

UCC/295-295-14-HCNS/SD-A-BL-
230 SDS/0039 6
H-GF-UCC-0105
Hotel Ground Floor Blockwork Master Plan 6 A B L Blockwork Master Plan Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Blockwork Plan Partial -1 Light


235 SDS/0039 5
H-GF-UCC-0106
Hotel Ground Floor Blockwork Plan Partial-1 Light Weight Blocks 4 A C NL
Weight Blocks
Ground Floor Hotel UCC 5-Apr-15 6-Apr-15

UCC/295-295-14-HCNS/SD-A-BL- Blockwork Plan Partial -1 Light


236 SDS/0039 6
H-GF-UCC-0106
Hotel Ground Floor Blockwork Plan Partial-1 Light Weight Blocks 6 A B L
Weight Blocks
Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL-
241 SDS/0039 4
H-GF-UCC-0106
Hotel Ground Floor Blockwork Plan Partial -2 Light Weight Blocks 4 A C NL Blockwork Plan Partial - 2 Ground Floor Hotel UCC 4-Apr-15 4-Apr-15

UCC/295-295-14-HCNS/SD-A-BL- Blockwork Plan Partial -2 Light


242 SDS/0039 5
H-GF-UCC-0107
Hotel Ground Floor Blockwork Plan Partial - 2 Light Weight Blocks 5 A C NL
Weight Blocks
Ground Floor Hotel UCC 5-Apr-15 6-Apr-15

UCC/295-295-14-HCNS/SD-A-BL- Blockwork Plan Partial -2 Light


243 SDS/0039 6
H-GF-UCC-0107
Hotel Ground Floor Blockwork Plan Partial - 2 Light Weight Blocks 6 A B L
Weight Blocks
Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL-
248 SDS/0039 5
H-GF-UCC-0108
Hotel Ground Floor Blockwork Plan Partial - 3 Light Weight Blocks 4 A C NL Blockwork Plan Partial - 3 Ground Floor Hotel UCC 5-Apr-15 6-Apr-15

UCC/295-295-14-HCNS/SD-A-BL-
249 SDS/0039 6
H-GF-UCC-0108
Hotel Ground Floor Blockwork Plan Partial - 3 Light Weight Blocks 6 A B L Blockwork Plan Partial - 3 Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
268 SDS/0043 2
H-MZ-UCC-0109
Hotel Mezzanine Floor Master Plan Light Weight Blocks 2 A B L Master Plan Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
271 SDS/0043 2
H-MZ-UCC-0110
Hotel Mezzanine Floor Plan Partial -1 Light Weight Blocks 2 A B L Plan Partial 1 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
274 SDS/0043 2
H-MZ-UCC-0111
Hotel Mezzanine Floor Plan Partial -2 Light Weight Blocks 2 A B L Plan Partial 2 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
277 SDS/0043 2
H-MZ-UCC-0112
Hotel Mezzanine Floor Plan Partial -3 Light Weight Blocks 2 A B L Plan Partial 3 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-S-RE-
353 SDS/0062 0
BS-FF-UCC-0002
Book Store First Floor Level ARC Reinforcement Detail 0 S B L ARC Reinforcement Detail First Floor Book Store UCC 21-Apr-15 27-Apr-15 Done

UCC/295-295-14-HCNS/SD-S-RE- First Floor


376 SDS/0064 1
BS-FF-UCC-0001
Book Store First Floor Level Construction Joint Detail 1 S B L Construction Joint Detail
Level
Book Store UCC 12-Apr-15 13-Apr-15 Done

UCC/295-295-14-HCNS/SD-E-EL- Basement
377 SDS/0065 0
BS-BF-REE-0001
Book Store Basement Floor plan Lighting Layout 0 MEP-E D L Plan Lighting Layout
Floor
Book Store Radiant 5-Apr-15 9-Apr-15

UCC/295-295-14-HCNS/SD-E-EP--
378 SDS/0066 0
BS-FF-REE-0004
Book Store First Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout First Floor Book Store Radiant 5-Apr-15 9-Apr-15

UCC/295-295-14-HCNS/SD-A-BL-
379 SDS/0067 0
SSC-GF-UCC-0100
Souq Building Ground Floor Plan Concrete Blockwork 0 A B L Plan Light Weight Blocks Ground Floor Souq Building UCC 5-Apr-15 7-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
380 SDS/0067 0
SSC-MZ-UCC-0101
Souq Building Mezzanine Floor Concrete Blockwork 0 A B L Light Weight Blocks
Floor
Souq Building UCC 5-Apr-15 7-Apr-15 Done

UCC/295-295-14-HCNS-SD-E-EP- Master Second


381 SDS/0068 0
H-2F-REE-0018
Hotel Master Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout
Floor
Hotel Radiant 6-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
382 SDS/0068 0
H-2F-REE-0019
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
383 SDS/0068 0
H-2F-REE-0020
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
384 SDS/0068 0
H-2F-REE-0021
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-M- Basement
385 SDS/0069 0
HVAC-BS-BF-REE-0010
Book Store Ventilation Ducting Layout Basement Floor Plan 0 MEP-M D L Ventilation Ducting Layout
Floor
Book Store Radiant 6-Apr-15 13-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Master First


386 SDS/0070 0
FF-REE-0013
Hotel Master First Floor Plan Fire Alarm Layout 0 MEP-M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 6-Apr-15 9-Apr-15

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days
UCC/295-295-14-HCNS-SD-FA-H-
387 SDS/0070 0
FF-REE-0014
Hotel First Floor Plan Fire Alaram Layout 0 MEP-M D L Plan Fire Alarm Layout First Floor Hotel Radiant 6-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
388 SDS/0070 0
FF-REE-0015
Hotel First Floor Plan Fire Alaram Layout 0 MEP-M D L Plan Fire Alarm Layout First Floor Hotel Radiant 6-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
389 SDS/0070 0
FF-REE-0016
Hotel First Floor Plan Fire Alaram Layout 0 MEP-M D L Plan Fire Alarm Layout First Floor Hotel Radiant 6-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
390 SDS/0071 0
3F-REE-0021
Hotel Master Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel  Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
391 SDS/0071 0
3F-REE-0022
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel  Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
392 SDS/0071 0
3F-REE-0023
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel  Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
393 SDS/0071 0
3F-REE-0024
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel  Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
394 SDS/0072 0
2F-REE-0017
Hotel Master Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
395 SDS/0072 0
2F-REE-0018
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
396 SDS/0072 0
2F-REE-0019
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
397 SDS/0072 0
2F-REE-0020
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
398 SDS/0073 0
GF-REE-0005
Hotel Master Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
399 SDS/0073 0
GF-REE-0006 -1/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
400 SDS/0073 0
GF-REE-0007 -2/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
401 SDS/0073 0
GF-REE-0008 -3/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Master Roof


402 SDS/0074 0
RF-REE-0029
Hotel Master Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
403 SDS/0074 0
RF-REE-0030 - 1/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
404 SDS/0074 0
BF-REE-0031 -2/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
405 SDS/0074 0
BF-REE-0032 - 3/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Master Upper


406 SDS/0074 0
UF-REE-0033
Hotel Master Upper Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Roof Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-E-EP- Master First


407 SDS/0075 0
H-FF-REE-0014
Hotel Master First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout
Floor
Hotel Radiant 7-Apr-15 11-Apr-15

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

UCC/295-295-14-HCNS-SD-E-EP-
408 SDS/0075 0
H-FF-REE-0015 -1/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
409 SDS/0075 0
H-FF-REE-0016 -2/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
410 SDS/0075 0
H-FF-REE-0017 -3/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP- Room King


411 SDS/0076 0
H-GEN-REE-0039 - 1/1
Najadah Hotel Room King Type -1 Electrical Power 0 MEP‐E D L Electrical Power
Type -1
Hotel Radiant 7-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-E-EP-
412 SDS/0076 0
H-GEN-REE-0055 - 1/1
Najadah Hotel Twin Type Connecting -02 0 MEP‐E D L Connecting -2 Twin Type Hotel Radiant 7-Apr-15 11-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Master Fourth


413 SDS/0077 0
4F-REE-0025
Hotel Master Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H-
414 SDS/0077 0
4F-REE-0026 -1/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
415 SDS/0077 0
BF-REE-0027 -2/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
416 SDS/0077 0
BF-REE-0028 -3/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
Master
UCC/295-295-14-HCNS-SD-FA-H-
417 SDS/0078 0
MZ-REE-0009
Hotel Master Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Mezzanine Hotel Radiant 7-Apr-15 9-Apr-15
Floor
UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
418 SDS/0078 0
MZ-REE-0010
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
419 SDS/0078 0
MZ-REE-0011
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
420 SDS/0078 0
MZ-REE-0012
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

Master
UCC/295-295-14-HCNS-SD-FA-H-
421 SDS/0079 0
BF-REE-0001
Hotel Master Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Basement Hotel Radiant 7-Apr-15 9-Apr-15
Floor
UCC/295-295-14-HCNS-SD-FA-H- Basement
422 SDS/0079 0
BF-REE-0002 -1/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Basement
423 SDS/0079 0
BF-REE-0003 -2/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-FA-H- Basement
424 SDS/0079 0
BF-REE-0004 -3/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15

UCC/295-295-14-HCNS-SD-M- Master First


425 SDS/0080 0
HVAC-H-FF-REE-0013 -1/1
Hotel -Master First Floor Plan -HVAC Layout 0 MEP‐M C L Plan HVAC Layout
Floor
Hotel Radiant 8-Apr-15 14-Apr-15

UCC/295-295-14-HCNS-SD-M-
426 SDS/0080 0
HVAC-H-FF-REE-0014 -1/3
Hotel First Floor Plan -HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15

UCC/295-295-14-HCNS-SD-M-
427 SDS/0080 0
HVAC-H-FF-REE-0015 - 2/3
Hotel First Floor Plan HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

UCC/295-295-14-HCNS-SD-M-
428 SDS/0080 0
HVAC-H-FF-REE-0016 - 3/3
Hotel First Floor Plan HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15

Basement
UCC/295-295-14-HCNS/SD-S-RE- Book Store Basement Floor to Ground Floor - Part 1 Keyplan -Columns Part 1 -Keyplan Columns
429 SDS/0081 0
BS-BF-AABCO-0047 Reinforcement
0 S C L
Reinforcement
Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor

Basement
UCC/295-295-14-HCNS/SD-S-RE-
430 SDS/0081 0
BS-BF-AABCO-0126
Book Store Basement Floor to Ground Floor - Part 1 Columns Reinforcement 0 S C L Part 1- Columns Reinforcement Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor

Basement
UCC/295-295-14-HCNS/SD-S-RE-
431 SDS/0081 0
BS-BF-AABCO-0127
Book Store Basement Floor to Ground Floor - Part 1 Columns Reinforcement 0 S C L Part 1 - Columns Reinforcement Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor

UCC/295-295-14-HCNS/SD-M-BW- Master Fourth


432 SDS/0082 0
H-4F-REE-0013
Hotel Master Fourth Floor Builders Work Layout Drawing 0 MEP-M B L Builders Work Layout Drawing
Floor
Hotel Radiant 9-Apr-15 13-Apr-15 Done

UCC/295-295-14-HCNS/SD-M-BW- Builders Work Layout Drawing -


433 SDS/0082 0
H-4F-REE-0014
Hotel Fourth Floor Builders Work Layout Drawing -Sheet 1/3 0 MEP-M B L
Sheet 1/3
Fourth Floor Hotel Radiant 9-Apr-15 13-Apr-15 Done

UCC/295-295-14-HCNS/SD-M-BW- Builders Work Layout Drawing -


434 SDS/0082 0
H-4F-REE-0015
Hotel Fourth Floor Builders Work Layout Drawing -Sheet 2/3 0 MEP-M B L
Sheet 2/3
Fourth Floor Hotel Radiant 9-Apr-15 13-Apr-15 Done

UCC/295-295-14-HCNS/SD-M-BW- Builders Work Layout Drawing -


435 SDS/0082 0
H-4F-REE-0016
Hotel Fourth Floor Builders Work Layout Drawing -Sheet 3/3 0 MEP-M B L
Sheet 3/3
Fourth Floor Hotel Radiant 9-Apr-15 13-Apr-15 Done

UCC/295-295-14-HCNS/SD-E-EL- Room King


436 SDS/0083 0
H-GEN-REE-0059
Najadah Hotel Room King Type -1 Electrical Lighting Layout 0 MEP-E U/R L Electrical Lighting Layout
Type -1
Hotel Radiant 9-Apr-15

Room Twin
UCC/295-295-14-HCNS/SD-E-EL-
437 SDS/0083 0
H-GEN-REE-0075
Najadah Hotel Room Twin Type -02 Connecting Electrical Lighting Layout 0 MEP-E U/R L Electrical Lighting Layout Type -02 Hotel Radiant 9-Apr-15
Connecting

UCC/295-295-14-HCNS/SD-M-
438 SDS/0084 0
HVAC-BS-BF-REE-0011
Book Store Ventilation Ducting Layout Ground Floor Plan 0 MEP-M C L Ventilation Ducting Layout Ground Floor Book Store Radiant 15-Apr-15 19-Apr-15

UCC/295-295-14-HCNS/SD-M-
439 SDS/0085 0
HVAC-BS-FF-REE-0004
Book Store AC Ducting Layout First Floor Plan 0 MEP-M C L AC Ducting Layout First Floor Book Store Radiant 11-Apr-15 14-Apr-15

UCC/295-295-14-HCNS/SD-M-
440 SDS/0086 0
HVAC-BS-GF-REE-0002
Book Store AC Ducting Layout Ground Floor Plan 0 MEP-M C L AC Ducting Layout Ground Floor Book Store Radiant 12-Apr-15 14-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Mezzanine
441 SDS/0087 0
H-MZ-UCC-0001
Hotel Mezzanine Floor Level Construction Joint Detail 0 S B L Construction Joint Detail
Floor
Hotel UCC 22-Apr-15 27-Apr-15 Done

UCC/295-295-14-HCNS/SD-P-DR- Basement
442 SDS/0088 0
BS-BF-REE-0001
Book Store Basement Floor Plan Drainage Layout 0 MEP-M B L Drainage Layout
Floor
Book Store Radiant 13-Apr-15 18-Apr-15 Done

UCC/295-295-14-HCNS/SD-M-
443 SDS/0089 0
HVAC-BS-SF-REE-0005
Book Store AC Ducting Layout Second Floor Plan 0 MEP-M C L AC Ducting Layout Second Floor Book Store Radiant 14-Apr-15 19-Apr-15

UCC/295-295-14-HCNS/SD-A-BL-
444 SDS/0090 0
BS-GEN-UCC-0001
Book Store General Details Blockworks 0 A B L General Details Blockworks General Book Store UCC 14-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Basement
445 SDS/0090 0
BS-BF-UCC-0100
Book Store Basement Floor Master Plan Blockworks 0 A B L Master Plan Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days
UCC/295-295-14-HCNS/SD-A-BL- Basement
446 SDS/0090 0
BS-BF-UCC-0101
Book Store Basement Floor Partial -1 Blockworks 0 A B L Partial -1 Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Basement
447 SDS/0090 0
BS-BF-UCC-0102
Book Store Basement Floor Partial -2 Blockworks 0 A B L Partial - 2 Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-BL- Basement
448 SDS/0090 0
BS-BF-UCC-0103
Book Store Basement Floor Partial -3 Blockworks 0 A B L Partial - 3 Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done

UCC/295-295-14-HCNS/SD-A-GA- External Sections Enlarged External


449 SDS/0091 0
H-GEN-UCC-0221
Hotel External Sections Enlarged Parapet Details 0 A C NL
Parapet Details Sections
Hotel UCC 15-Apr-15 19-Apr-15

UCC/295-295-14-HCNS/SD-A-GA- External Sections Enlarged External


SDS/0091 1
H-GEN-UCC-0221
Hotel External Enlarged Parapet Details 1 A U/R L
Parapet Details Sections
Hotel UCC 26-Apr-15

Foundation to
UCC/295-295-14-HCNS/SD-S-RE-
450 SDS/0092 0
BS-BF-AABCO-0128
Book Store Foundation to Ground Floor Level Columns Reinforcement 0 S C L Columns Reinforcement Ground Floor Book Store AABCO 15-Apr-15 27-Apr-15
Level

Foundation to
UCC/295-295-14-HCNS/SD-S-RE-
451 SDS/0092 0
BS-BF-AABCO-0129
Book Store Foundation to Ground Floor Level Columns Reinforcement 0 S C L Columns Reinforcement Ground Floor Book Store AABCO 15-Apr-15 27-Apr-15
Level

UCC/295-295-14-HCNS/SD-S-RE-
452 SDS/0093 0
BS-FT-AABCO-0130
Book Store Foundation at (+2.500 B.O.F.) Bottom Bars Reinforcement ‐ B1 0 S C L Bottom Bars Reinforcement ‐ B1 Foundation Book Store AABCO 16-Apr-15 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
453 SDS/0093 0
BS-FT-AABCO-0131
Book Store Foundation at (+2.500 B.O.F.) Bottom Bars Reinforcement - B2 0 S C L Bottom Bars Reinforcement - B2 Foundation Book Store AABCO 16-Apr-15 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
454 SDS/0093 0
BS-FT-AABCO-0132
Book Store Foundation at (+2.500 B.O.F.) Top Bars Reinforcement - T2 0 S C L Top Bars Reinforcement - T2 Foundation Book Store AABCO 16-Apr-15 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
455 SDS/0093 0
BS-FT-AABCO-0133
Book Store Foundation at (+2.500 B.O.F.) Top Bars Reinforcement - T1 0 S C L Top Bars Reinforcement - T1 Foundation Book Store AABCO 16-Apr-15 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Book Store Foundation at (+2.500 B.O.F.) Additional Bottom Bars Additional Bottom Bars
456 SDS/0093 0
BS-FT-AABCO-0134 Reinforcement
0 S C L
Reinforcement
Foundation Book Store AABCO 16-Apr-15 26-Apr-15

UCC/295-295-14-HCNS/SD-S-RE- Part 1 Bottom B1 & B2 & Add Top AAO 
457 SDS/0094 0
H-URF-AABCO-0418
Hotel Upper Roof Floor ‐ Part 1 Bottom B1 & B2 & Add Top AAO Reinforcement 0 S B L
Reinforcement
Upper Roof Floor Hotel AABCO 19‐Apr‐15 29‐Apr‐15 Done

UCC/295-295-14-HCNS/SD-S-RE- Part 2 Bottom B1 & B2 & Add Top & AAO 
458 SDS/0095 0
H-URF-AABCO-0426
Hotel Upper Roof Floor ‐Part 2 Bottom B1 & B2 & Add Top & AAO Reinforcement 0 S B L
Reinforcement
Upper Roof Floor Hotel AABCO 19‐Apr‐15 29‐Apr‐15 Done

UCC/295-295-14-HCNS/SD-M-BW-
459 SDS/0096 0
BS-BF-REE-0006
Book Store Basement Floor Plan MEP Builders Work in Walls  0 MEP‐M C L Plan MEP Builders Work in Walls  Basement Floor  Book Store Radiant  19‐Apr‐15 25‐Apr‐15

UCC/295-295-14-HCNS/SD-P-WS-
460 SDS/0097 0
H-FF-REE-0013
Hotel Master First Floor Water Supply Layout 0 MEP‐M C L Water Supply Layout Master First Floor  Hotel Radiant  22‐Apr‐15 29‐Apr‐15

UCC/295-295-14-HCNS/SD-P-WS-
461 SDS/0097 0
H-FF-REE-0014
Hotel First Floor Plan Water Supply Layout - Sheet 1/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant  22‐Apr‐15 29‐Apr‐15

UCC/295-295-14-HCNS/SD-P-WS-
462 SDS/0097 0
H-FF-REE-0015
Hotel First Floor Plan Water Supply Layout - Sheet 2/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant  22‐Apr‐15 29‐Apr‐15

UCC/295-295-14-HCNS/SD-P-WS-
463 SDS/0097 0
H-FF-REE-0016
Hotel First Floor Plan Water Supply Layout - Sheet 3/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant  22‐Apr‐15 29‐Apr‐15

U295/00QA/PQP/008 Rev. 00 February 2015
Approved A

Approved as Noted B

Revise & Resubmit C HCNS Shop Drawing LOG


Not Approved D

Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15

SR Shop Drawing Originator Shop Orig. Area of Date Pendin


Rev Title Disc Status L/NL Specialty Zone Originator Date received Remarks
No. Submittal Number Drawing Numbers Rev Location Submitted: g days

UCC/295‐295‐14‐HCNS/SD‐P‐WS‐BS‐GF‐
464 SDS/0098 0
REE‐0008
Book Store Ground Floor Plan Water Supply Layout 0 MEP‐M C L Water Supply Layout Ground Floor Book Store Radiant  23‐Apr‐15 29‐Apr‐15

UCC/295-295-14-HCNS/SD-S-RE-
488 SDS/0100 0
H-4F-AABCO-0257
Hotel Fourth Floor ‐Part 1 Keyplan and Beams Reinforcement 0 S U/R L Part 1 Keyplan and Beams Reinforcement Fourth Floor Hotel AABCO 25-Apr-15

UCC/295-295-14-HCNS/SD-S-RE-
489 SDS/0101 0
H-4F-AABCO-0344
Hotel Fourth Floor- Part 2 Beams Reinforcement 0 S U/R L Part 2 Beams Reinforcement Fourth Floor Hotel AABCO 25-Apr-15

UCC/295-295-14-HCNS/SD-M- Basement
494 SDS/0103 0
HVAC-BS-BF-REE-0001
Book Store AC Ducting Layout Basement Floor Plan 0 MEP-M U/R L AC Ducting Layout
Floor
Book Store UCC-MEP 28-Apr-15

U295/00QA/PQP/008 Rev. 00 February 2015
Approved - A A

Approved as Noted - AAN B

Revise & Resubmit - RR C


HNCS Pre‐qualification Submittal Log
Not Approved - NA D

Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Najada Souq As of: 2-Mar-15

Pre-qualification Submittal Area of Pendin Date


SN Rev Document Ref No. Title Rev Disc Status L/NL Documents Specialty Originator Date Submitted: Remarks
Ref: Location g days Commented

REE-SNCP-DT-072/TS-SNCP- MEP-
1 SPQS-0001 0
PQ-004
Pre-qualification ELV System 0
ELV
C L Pre-qualification ELV System Pre-qualification Car Park Radiant 29-Jan-15 4-Feb-15

Pre-qualification of unisafe fire


2 SPQS-0002 0 REE Pre-qualification of unisafe fire protection specialist 1 MEP-M B L Pre-qualification
protection specialist
SNCP Radiant 29-Jan-15 4-Feb-15 Done

Landsca
3 SPQS-0003 0 PAB-DC-BD-0215-116 Palmera Company Profile 0
ping
C L Company Profile Landscaping Company Profile General Palmera 4-Feb-15 8-Feb-15

4 \

6
7

9
10

11

12

13
14
Approved - A A

Approved as Noted - AAN B

Revise & Resubmit - RR C


HCNS MATERIAL SUBMITTAL LOG
Not Approved - NA D

Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Material Submittal ‐ Copper Pipes and Fittings for Refrigerant Pipes(HVAC) 
97 MAS‐0078 1 UCC/MEP/MS/ME/0078
+ Sample
1 MEP-M B L Copper Pipes & Fittings Hotel & Bookstore Radiant 15‐Apr‐15 29-Apr-15 Done

Material Submittal for Pipe Hangers & Supports ‐ Plumbing Application (  Hotel and WEICCO/Leminar Air


122 MAS‐0096  2 UCC/MEP/MS/ME/031 R12
Response to Consultant's  Comments)
2 MEP-M D L Pipe Hangers & Supports
Bookstore Conditioning Industries
8‐Apr‐15 11‐Apr‐15

130 MAS-0101 1 UCC/MEP/MS/EL/018 Material Submittal for LV Cable & Single Core Wires 1 MEP-E B L LV Cables General Doha Cables 20-Apr-15 22-Apr-15

MAS‐0114 1 UCC/MEP/MS/EL/0024 Material Submittal for GI Conduits and Accessories 0 MEP‐E A L GI Conduits and Accessories General Al Hathboor Enterprises 28‐Apr‐15 29‐Apr‐15 Done

Hotel and Radiant / Aerodyne Cooling 


150 MAS‐0115  1 UCC/MEP/MS/ME/0032 Material Submittal for Flexible Duct Connector 1 MEP‐M B L Flexible Duct Connector
Bookstore System
13‐Apr‐15 15‐Apr‐15

UCC / Khalid Manufacturing 
152 MAS‐0116 1 UCC/MEP/MS/ME/027 Material Submittal for Curtain Fire Damper (Sample Only) 1 MEP‐M B L Curtain Fire Damper General
Company
4‐Apr‐15 8‐Apr‐15 Done

UCC/ Khalid Manufacturing 
154 MAS‐0117 1 UCC/MEP/MS/M/029  Material Submittal for Access Door (Sample Only) 1 MEP‐M B L Access Door General
Company
4‐Apr‐15 6‐Apr‐15 Done

Material Submittal ‐ Hangers and Supports + Sample (REPLY TO  Hotel and Radiant / Trade House


158 MAS‐0120 1 UCC/MEP/MS/EL/0033 R1
CONSULTANTS COMMENTS)
0 MEP‐E C NL Hangers and Supports
Bookstore Qatar Co.
11‐Apr‐15 13‐Apr‐15

Material Submittal ‐ Hangers and Supports + Sample (REPLY TO  Hotel and Radiant / Trade House


159 MAS‐0120 2 UCC/MEP/MS/EL/0033 R2
CONSULTANTS COMMENTS)
0 MEP‐E B L Hangers and Supports
Bookstore Qatar Co.
16‐Apr‐15 20‐Apr‐15 Done

Radiant / Qatar Air


Hotel and 
161 MAS‐0122 0 UCC/MEP/MS/ME/0034 Material Submittal for Flexible Duct  0 MEP‐M C NL Flexible Duct
Bookstore
Distribution Network 2‐Apr‐15 7‐Apr‐15
(Qad Net)

UCC / Qatar Air


Hotel and 
MAS‐0122 1 UCC/MEP/MS/ME/0034 Material Submittal for Flexible Duct  MEP‐M U/R L Flexible Duct
Bookstore
Distribution Network 29‐Apr‐15
(Qad Net)

Hotel and 
162 MAS‐0123 0 UCC/MEP/MS/ME/0036 Material Submittal for Hangers & Support for HVAC Duct 0 MEP‐M B L Hangers & Support for HVAC Duct
Bookstore
Radiant / Hilti 4‐Apr‐15 8‐Apr‐15 Done

Hotel and 
163 MAS‐0124 0 UCC/MEP/MS/EL/0037 Material Submittal for Electrical Supporting System (Alterante Submission) 0 MEP‐E D L Electrical Supporting System
Bookstore
Radiant / Hilti 4‐Apr‐15 5‐Apr‐15

Hotel and
164 MAS‐0125 0 UCC/MEP/MS//EL/0038 Material Submittal for Disconnect Switches / Isolationg Switch + Sample 0 MEP‐E B L Switches 
Bookstore
ABB 11‐Apr‐15 13‐Apr‐15 Done

Hotel and RADIANT / Seagull


165 MAS‐0126 0 UCC/MEP/MS/ME/0039 Material Submittal ‐ G.I. Rectangular Duct ( Alternative) + Sample 0 MEP-M B L Duct System
Bookstore Electromech
11‐Apr‐15 15‐Apr‐15 Done

Radiant / Equipment
Hotel and
166 MAS‐0127 0 UCC/MEP/MS/ME/042 Material Suibmittal ‐ Acoustic ‐ Liner 0 MEP-M D NL  Acoustic ‐ Liner
Bookstore
Trading & Contrating Co. 11‐Apr‐15 14‐Apr‐15 Rejected
WLL
Approved - A A

Approved as Noted - AAN B

Revise & Resubmit - RR C


HCNS MATERIAL SUBMITTAL LOG
Not Approved - NA D

Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Radiant / Equipment
Hotel and
MAS‐0127 1 UCC/MEP/MS/ME/0042 Material Submittal ‐ Duct Acoustic Liner 1 MEP-M U/R L  Acoustic ‐ Liner
Bookstore
Trading & Contrating Co. 25‐Apr‐15
WLL

Hotel and Radiant / Khalid


167 MAS‐0128 0 UCC/MEP/MS/ME/030 Material Submittal ‐ Grills and Diffusers + Sample (6No) 0 MEP-M B L Grilles & Diffusers
Bookstore Manufacturing Company
11‐Apr‐15 22‐Apr‐15 Done

Hotel and Radiant / Khalid


168 MAS‐0129 0 UCC/MEP/MS/ME/0043 Material Submittal ‐ Motorized Fire Smoke Damper 0 MEP-M B L Material Submittal ‐ Motorized Fire Smoke Damper
Bookstore Manufacturing Company
13‐Apr‐15 29‐Apr‐15 Done

RADIANT / Qatar
Hotel and
169 MAS‐0130 0 UCC/MEP/MS/ME/0041 Material Submittal for AC Condensate Drain Pipes & Fittings + Sample 0 MEP-M C L  AC Condensate Drain Pipes & Fittings
Bookstore
Pipeline & Fittings 13‐Apr‐15 16‐Apr‐15
Company

Hotel and Radiant / Khalid


170 MAS‐0131 0 UCC/MEP/MS/ME/0044 Material Submittal for Back Draft Dampers 0 MEP-M C NL Back Draft Dampers
Bookstore Manufacturing Company
14‐Apr‐15 16‐Apr‐15

Hotel and UCC / Khalid


MAS‐0131 1 UCC/MEP/MS/ME/0044 Material Submittal for Back Draft Dampers 1 MEP-M U/R L Back Draft Dampers
Bookstore Manufacturing Company
29‐Apr‐15

Hotel and Radiant / Khalid


171 MAS‐0132 0 UCC/MEP/MS/ME/0026 Material Submittal ‐ LOUVERS 0 MEP-M C NL LOUVERS
Bookstore Manufacturing Company
14‐Apr‐15 16‐Apr‐15  

Hotel and UCC / Khalid


MAS‐0132  1 UCC/MEP/MS/ME/0026 Material Submittal ‐ LOUVERS 1 MEP-M U/R L LOUVERS
Bookstore Manufacturing Company
29‐Apr‐15

Hotel and
172 MAS‐0133 0 REE‐HCNS‐DT‐0172 Material Submittal ‐ GRP Sectional Water Tanks  0 MEP-M C L GRP Sectional Water Tanks 
Bookstore
Radiant / Bijan Groups 14‐Apr‐15 29‐Apr‐15

Hotel and Radiant / Khalid


173 MAS‐0134 0 MS‐ME‐0047 Material Submittal ‐ Sound Attenuator 0 MEP-M U/R L Sound Attenuator
Bookstore Manufacturing Company
18‐Apr‐15

Hotel and Radiant / Leminar Air 


174 MAS‐0135 0 MS‐ME‐0049 Material Submittal ‐ Exhaust Fans 0 MEP-M U/R L Exhaust Fans
Bookstore Conditioning
18‐Apr‐15

Hotel and Radiant / Joint Gulf Business 


175 MAS‐0136 0 MS‐ME‐0050 Material Submittal ‐ Plumbing Valves 0 MEP-M U/R L  Plumbing Valves
Bookstore (JCB)
18‐Apr‐15

Hotel and Radiant / Aerodyne Cooling 


176 MAS‐0137 0 MS‐ME‐0052 MATERIAL SUBMITTAL ‐ DUCT TAPE AND STICK UP PINS + SAMPLE 0 MEP-M U/R L DUCT TAPE AND STICK UP PINS
Bookstore System
19‐Apr‐15

Hotel and Radiant / Aerodyne Cooling 


177 MAS‐0138 0 MS‐ME‐0051 MATERIAL SUBMITTAL ‐ DUCT SEALANT & GASKET 0 MEP-M U/R L DUCT SEALANT & GASKET
Bookstore System
19‐Apr‐15
Hotel and
178 MAS‐0139 0 MS‐ME‐0053 MATERIAL Submittal ‐ Fire Rated Duct + Sample 0 MEP-M U/R L  Fire Rated Duct
Bookstore
Radiant / FTC Qatar WLL 19‐Apr‐15

179 MAS‐0140 0 N/A Material Submittal ‐ Plaster Gypsum  0 ARCH B L  Plaster Gypsum  Hotel  Saudi Vetonit Company Ltd 20‐Apr‐15 22‐Apr‐15 Done

Material Submittal ‐ UPVC Cleaner, Solvent Cement, Lubricant for High   UPVC Cleaner, Solvent Cement, Lubricant for High  Hotel and


180 MAS‐0141 0 MS‐ME0054
Pressure UPVC Pipes + Sample
0 MEP-M A L
Pressure UPVC Pipes Bookstore
Radiant / PIPESTECH 22‐Apr‐15 29‐Apr‐15 Done
Approved - A A

Approved as Noted - AAN B

Revise & Resubmit - RR C


HCNS MATERIAL SUBMITTAL LOG
Not Approved - NA D

Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Hotel and
181 MAS‐0142 0 UCC/MEP/MS/ME/0056  Material Submittal ‐ UPVC Pipes and Fittings  0 MEP-M U/R L UPVC Pipes and Fittings 
Bookstore
Al Madadd Al Qatariah 25‐Apr‐15
Hotel and Al Riyadh Trading & 
182 MAS‐0143 0 UCC/MEP/MS/ME/0057 Material Submittal ‐ Water Hammer Arrester + Sample Board 0 MEP-M C L Water Hammer Arrester
Bookstore Contracting Company
25‐Apr‐15 27‐Apr‐15
Hotel and
183 MAS‐0144 0 UCC/MEP/MS/ME/0060 Material Submittal ‐ Fire Fighting Seamless Pipe 0 MEP-M U/R L  Fire Fighting Seamless Pipe
Bookstore
CESCO 25‐Apr‐15
Hotel and
184 MAS‐0145 0 UCC/MEP/MS/EL/0059  Material Submittal ‐ Uninterruptible Power System 0 MEP-E D L Uninterruptible Power System
Bookstore
Snap Power Solution 26‐Apr‐15 28‐Apr‐15
Hotel and
185 MAS‐0146 0 UCC/MEP/MS/ME/0061 Material Submittal ‐ Mechanical Identification Labels & Tags + Sample 0 MEP-M U/R L Mechanical Identification Labels & Tags
Bookstore
Alianza Trading & Advertising 28‐Apr‐15

Hotel and Leminar Air Conditioning 


186 MAS‐0147 0 UCC/MEP/MS/ME/0055 Material Submittal ‐ Copper Pipes and Fittings  for Water Supply + Sample 0 MEP-M U/R L Copper Pipes and Fittings  for Water Supply
Bookstore Industries 
28‐Apr‐15
Hotel and
187 MAS‐0148 0 UCC/MEP/MS/ME/0046  Material Submittal ‐ Insulation for refrigerant Pipes + Sample 0 MEP-M U/R L Insulation for refrigerant Pipes
Bookstore
Qatar Insulation Company 28‐Apr‐15

Hotel and
188 MAS‐0149 0 UCC/MEP/MS/ME/0062  Material Submittal ‐ Sprinklers 0 MEP-M U/R L  Sprinklers
Bookstore
CESCO 28‐Apr‐15
Hotel and 
189 MAS‐0150 0 UCC/MEP/MS/ME/0084  Material Submittal ‐ Insulation for Plumbing Pipes + Sample 0 MEP‐M U/R L Insulation for Plumbing Pipes
Bookstore
Qatar Insulation Company 28‐Apr‐15
Approved A
Approved as Noted B
Revise & Resubmit C  HCNS  Design Drawing LOG  
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received

Previous comment of
the submittals /
workshop meetings /
U29529514-HCNS-DS- Design Architectural Book discussion are not
12 1 2459-DT038-15 1 Revised Architectural Design Detail Drawings A C NL General ERGA 08-Apr-15 09-Apr-15
DD-0009 Drawings Drawings Store implemented
comments should be
revised before
submitting.

Revised Architectural Design Detail Drawings for Book Store - Draft IFC,
U29529514-HCNS-DS- List of Deliverables, Design Architectural Book
13
DD-0009
2 2459-DT045-15
Reply on the Commented Drawings received from DAR Drawings
A D L
Drawings
General
Store
ERGA 16-Apr-15 19-Apr-15
and Compliance Statement on the Arch. Comments received from DAR

Revised Structural Drawings & Calculations


Basement Floor Column Layout - 101 Rev. 1
Core Wall Details - 611 Rev. 1
Foundation Layout @m-1.5M LVL
Ground Floor Column Layout
Mezzanine Floor Column Layout
First Floor Column Layout
Second Floor Column Layout Revised
Revised Structural
U29529514-HCNS-DS- 2459-DT044-15 Lower Roof Column Layout Structural Book
16 2 0 S B L Design Drawings - General ERGA 13-Apr-15 22-Apr-15 Done
DD-0010 Ground Floor Slab Layout Drawings & Store
IFC & Calculations
Mezzanine Foor Slab Layout Calculations
First Floor Slab Layout
Second Floor Slab Layout
Lower Roof Slab Layout
Ground Floor Details
Schedule of Column
Beam Schedule

14-132-JCP-ST-TN-0117 -
Drawings
Drawing SR No. 1-5
14-132-JCP-ST-TN-0119- Design
U29529514-HCNS-DS- Structural Drawings for Hotel & James Revise and Resubmit
22 1 Drawings 2 Drawings - S B NL Structural Drawings General Hotel 19-Apr-15 22-Apr-15
DD-0015 Structural Design Calculation Cubitt Drawing SR No. 6-12
14-132-JCP-ST-TN-0118 - Draft IFC
AAN
Design Calculation

Design
Drawings -
Structural
U29529514-HCNS-DS- 14-132-JCP-ST-TN-0126 & Structural Drawings for Hotel & Draft IFC, James
DD-0015
2
14-132-JCP-ST-TN-0127
3
Structural Design Calculation Report Design
S U/R L Drawings& General Hotel
Cubitt
26-Apr-15
Calculations
Calculation
Report

Interior
Design
Drawings & Interior Design
FFE for Mock Drawings & FFE for
U29529514-HCNS-DS- HAI-DEN-IDD-100-NAJ-044- Interior Design Drawings & FFE for Mock up Rooms 129 & 132 (Suite
25
DD-0017
1
2015
1
Type 04 & Twin Type 02)
up Rooms A B L Mock up Rooms 129 General Hotel Highness 20-Apr-15 23-Apr-15 Done
129 & 132 & 132 (Suite Type 04
(Suite Type & Twin Type 02)
04 & Twin
Type 02)
Approved A
Approved as Noted B
Revise & Resubmit C  HCNS  Design Drawing LOG  
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received
B7 Souq Building Architectural Drawings
General Cover Sheet
14-132-JCP-AR-TN-0115 Drawing List
GN-001 Ground Floor Plan
B7-GN-001 Mezzanine Floor Plan
Roof Floor Plan Previous Submittal
U29529514-HCNS-DS- B7-A-101 Architectural Architectural B7 Souq B7 Souq James
27 0 1 Elevations A C NL 05-Apr-15 07-Apr-15 Submitted through Ts-
DD-0019 B7-A-102 Drawings Drawings Building Building Cubitt
Sections 0058 Rev. 0
B7-A-103
B7-A-201
B7-A-202

B7 Souq Building Architectural Drawings


General Cover Sheet - GN000 Rev. 2
Souq Building Drawing List -B7-GN-001 Rev. 2
Souq Building Ground Floor Plan - B7-A-101 Rev. 2
Souq Building Mezzanine Floor Plan - B7-A-102 Rev. 2
U29529514-HCNS-DS- Souq Building Roof Floor Plan - B7-A-103 Architectural Architectural B7 Souq B7 Souq James
1 14-132-JCP-AR-TN-0131 2 Souq Building Elevations 1,2 & 3 - B7-A-201 A U/R L 28-Apr-15
DD-0019 Drawings Drawings Building Building Cubitt
Souq Building Sections - B7-A-202
Souq Building Sections - B7 -A-203
Souq Building Door Schedules & Details - B7-A-601
Souq Building Door & Window Schedule - B7-A-602
Souq Building Miscellaneous Details -B7-A-801

Done
*Foundation
Structural
Retrofitting revised to
Design,
Structural Design, resubmit
U29529514-HCNS-DS- Structural Design Calculation Report, Structural Analysis Models and Analysis James
28 0 14-132-JCP-ST-TN-0102 0 S B L Analysis Models & General Hotel 08-Apr-15 12-Apr-15 *water tanks on roof
DD-0020 Structural Design Report Models & Cubitt
Design Report should be considered
Design
for P.T slob design
Report
*refer to comment
attached

Revised
Revised Design
U29529514-HCNS-DS- 2459-DT041-15 & Design Detail- MEP- Book
29
DD-0021
0
2459-DT042-15
0 Revised Design Detail - Electrical for Book Store - Draft IFC
Electrical - E
C L Detail - Electrical for General
Store
ERGA 15-Apr-15 29-Apr-15
Book Store
Draft IFC
Revised
Revised Design
Design Detail -
U29529514-HCNS-DS- MEP- Detail - Mechanical, Book
30 0 2459-DT039-15 0 Revised Design Detail - Mechanical, Fire Fighting & Plumbing Mechanical, U/R L General ERGA 11-Apr-15
DD-0022 M Fire Fighting & Store
Fire Fighting
Plumbing
& Plumbing
855.CCL.DTN PTD-AI/MA-
0015
1. UCC/295-295-14-HCNS/SD-
S-GA-H-L4-CCL-0001 Rev. 0 1. Hotel Level 4 -General Arrangement & Load Key Plan
Design 1st Drawing (General
2. UCC/295-295-14-HCNS/SD- 2. Hotel Level 4- Tendon Layout - Sheet 1/2
Drawings Arrangement) Revise &
U29529514-HCNS-DS- S-TL-H-L4-CCL-0002 P1/2 3. Hotel Level 4 - Tendon Layout - Sheet 2/2
31 0 0 and S B NL Structural Drawings Level 4 Hotel CCL 18-Apr-15 21-Apr-15 Resubmit. Remaining
DD-0023 Rev. 0 4. Hotel Level 4 - Reinforcement Layout - Sheet 1/2
Calculations - Drawings Approved as
3. UCC/295-295-14-HCNS/SD- 5. Hotel Level 4 - Reinforcement Details - Sheet 2/2
Draft IFC Noted.
S-TL-H-L4-CCL-0002 P2/2 6. Level 4 - PT Calculation
Rev. 0
4. UCC/295-295-14-HCNS/SD-
S-RC-H-L4-CCL-0003 P1/2

Design
U29529514-HCNS-DS- UCC/295-295-14-HCNS/SD-S-
32
DD-0023
1
GA-H-L4-CCL-0001
1 Hotel Level 4-General Arrangement & Load Key Plan Drawings S B L Structural Drawings Level 4 Hotel CCL 23-Apr-15 27-Apr-15 Done
- Draft IFC
Approved A
Approved as Noted B
Revise & Resubmit C  HCNS  Design Drawing LOG  
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received

B8 Souq Building Architectural Drawings -Draft IFC


GN-000 -Cover
B8-GN-001 - Architectural Drawing List
B8-A-101 - Ground Floor Plan
B8-A-102 - Mezzanine Floor Plan
Previous Revision
B8-A-103- Roof Floor Plan Design B8-
U29529514-HCNS-DS- James Submitted through the
33
DD-0024
0 14-132-JCP-AR-TN-0120 1 B8-A-201- Elevation-1 & Section -D Drawing- A U/R L Architectural B8 - Souq Souq
Cubitt
20-Apr-15
Submittal TS-0097 Rev.
B8-A-202-Elevation-2 & Section -A Draft IFC Building
0
B8-A-203 - Elevation-3 & Section -E
B8-A-204- Elevation -4 & Sections -B& C
B8 -A-601 -Door Schedule & Details
B8-A-602 - Door & Window Schedule
B8-A-801 - Spiral Stair Details

B8 Existing Building Electrical / ELV Drawings


B8-E-00 - Cover Sheet
B8-E-00A -Electrical Drawing List
B8-E-01 - Electrical Legends, General Notes & Abbreviation
B8-E-02 - Lighting Fixtures
B8-E-101- Ground Floor Plan Lighting Layout
B8-E-201- Ground Floor Plan Small Power Layout
B8-E-202 - Mezzanine Floor Plan Small Power Layout
B8-E-203 - Roof Plan Small Power Layout
B8-E-301 - Ground Floor Plan CCTV System Layout B8 Electrical
B8 Electrical /ELV B8-
U29529514-HCNS-DS- B8-E-304 - CCTV System Schematic Diagram /ELV Design MEP- James
34
DD-0025
0 14-132-JCP-EL-TN-0122 0
B8-E-401 - Ground Floor Plan PA/GA System Layout Drawings - E
U/R L Design Drawings - B8 - Souq Souq
Cubitt
21-Apr-15
Draft IFC Building
B8-E-404 - PA/GA System Schematic Diagram Draft IFC
B8-E-501 - Ground Floor Plan Data & Telephone Layout
B8-E-504 - Data & Telephone Data Schematic Diagram
B8-E-601 - Ground Floor Plan Earthing Layout
B8-E-602 - Roof Floor Earthing Layout
B8-E-603 - Earthing Installation Details
B8-E-701 - DB Schedule, SMB- Single Line Diagram
B8-FA-101 - Ground Floor Fire Alarm Layout
B8-FA-102 - Mezzanine Floor Fire Alarm Layout

Design
U29529514-HCNS-DS- Design Drawings - James
35
DD-0026
0 14-132-JCP-ST-TN-0124 2 B2 Hotel Architectural Drawings Drawings - A U/R L
Draft IFC
General Hotel
Cubitt
22-Apr-15
Draft IFC

Design
Drawings - Hotel -
Design Drawings - Hotel -B2
U29529514-HCNS-DS- 14-132-JCP-ST-TN-0123 & Draft IFC, B2 James
36
DD-0027
0
14-132-JCP-ST-TN-0125
0 Structural Drawings & Design Report for B2 Hotel Extension
Design
S U/R L Draft IFC, Design Extensio
Extensio Cubitt
26-Apr-15
Report n
Calculation n
Report

UCC/295-295-14-HCNS/SD-E-
EP-H-GEN-REE-0045(Sheet Hotel Room Suite Type -04 (Mockup Room) Electrical & ELV Combined Layout  (Sheet  Mockup
1/2) 1/2) Design
U29529514-HCNS-DS- MEP- Design Drawings - Room-
37
DD-0028
0 & 0 & Drawings -
E
C NL
Draft IFC Suite
Hotel UCC-MEP 27-Apr-15 28-Apr-15
UCC/295-295-14-HCNS/SD-E- Hotel Room Suite Type ‐04 (Mockup Room) Electrical & ELV Combined Layout (Sheet 2/2) Draft IFC
Type 4
EP-H-GEN-REE-0045(Sheet
2/2)

Mockup
Design
U29529514-HCNS-DS- UCC/295-295-14-HCNS/SD-E- MEP- Design Drawings - Room-
38
DD-0029
0
EP-H-GEN-REE-0043
0 Hotel Room Twin Type -02 (Mockup Room) Electrical & ELV Combined Layout Drawings -
E
C L
Draft IFC Twin
Hotel UCC-MEP 27-Apr-15 29-Apr-15
Draft IFC
Type 2
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-CHNS

PROGRESS PHOTO

Monthly Report no. 4 [April 2015 ]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Hotel Building – Block works in Progress at Mezzanine floor level.

● Hotel Building – Slab Form & Rebar works in Progress at First floor level.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Hotel Building – Mock Room MEP Works in Progress.

● Hotel Building – Block Works in Progress at First Floor Level.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

Hotel Building – Column Concrete Done at Fourth level.

● Hotel Building –Column Concrete Works in Progress at Third floor level.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Shop & Market –Sand Plaster Works in Progress

● Shop & Market – Sand Plaster Works in Progress.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Book Store- Column Form & Concrete works in progress at first level

● Book Store –External slab Concrete Works in Progress at First floor level.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Book Store-Column Rebar Works in Progress at First floor level.

● Book Store – Column Form & Concrete works in progress at first level

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Book Store-Wall cutting Works in Progress

● Book Store – Block Works in Progress

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● HOTEL EXTENSION AREA – Excavation works in Progress

● HOTEL EXTENSION AREA – Excavation works in Progress

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● OLD SOUQ –Painting works in Progress.

●OLD SOUQ – Plastering works in Progress.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Heritage Building – Internal Sand plastering works in Progress.

● Heritage Building –Structural Repairing works in Progress.

Monthly Report no. 4[April 2015]


HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-14-HNCS

● Car Park – Demolishing works in progress..

● Car Park – Demolishing works in progress