Prepared By:
Table of Contents
SECTION 1: GENERAL INFORMATION
1.1 ‐ Project Introduction and Location
1.2 – Scope of Works
1.3 – Work Breakdown Zoning
1.4 ‐ Contract Particulars
1.5 ‐ Financial Summary
SECTION 2: EXECUTIVE SUMMARY (PROGRESS OUTLINE)
2.1 ‐ Site Progress / Construction Activities Summary
2.2 ‐ Engineering and Technical Summary
2.3 ‐ Plan for Next Month
SECTION 3: PROGRAMME AND PROGRESS
3.1 — PROGRESS FOR TECHNICAL SUBMISSION
3.2 — PROGRESS FOR PROCUREMENT (LONG LEAD ITEM
3.3 — WORK PROGRAM EVALUATION
3.4 — AREAS OF CONCERNS
SECTION 4: HEALTH, SAFETY & ENVIRONMENT
4.1 ‐HSE STATISTICS
4.2 ‐ HSE ACCOMPLISHMENTS
SECTION 1: GENERAL INFORMATION
1.1 — Project Introduction and Location
Design & Build of Hotel & Complex of Al‐Najadah Souq, which is located in Doha‐Qatar in
Souq Area (Center Doha)
1.2 — Project Scope of Works
The Project Scope of Work shall be Design & Build of Hotel & Complex of Al‐Najadah Souq
which is divided but not limited to
1. Dismantling of All Existing External Finishes.
2. Studying of Existing Structures.
3. Demolition of the Existing buildings and mosque.
4. Renovation of existing traditional building administrative building including all MEP
& Services & FF&E.
5. Renovation of the car park building including all MEP & Services.
6. Construction of 5 stars hotel (New Building) Including all Sub structure & super
structure skeleton, MEP Services, Interior finishes & FF&E..Etc.
7. Construction of bookshop(New Building Including all Sub structure & super structure
skeleton, MEP Services , Interior finishes & FF&E..Etc.
8. Construction of Multi‐purpose (New Building hall all Sub structure & super structure
skeleton, MEP Services, Interior finishes & FF&E..Etc.
9. Renovation of Market & Shops including all civil, Structural, architectural, MEP
services, Interior finishes, security systems..Etc. (Shell & Core only)
10. Construction of underground service trench between bookstore and Souq Al
Najadah Pedestrian tunnel.
11. External infrastructure landscaping ,including the plaza with special flooring for
painting
12. Services, Plant Rooms , Equipments in need for authority approval
1.3 — WORK BREAKDOWN ZONING
In order to closely monitor the work progress, the entire Project has been divided into
working as follows.
1. Car Park Building, Area = 23,018m2
2. Hotel and Multipurpose Hall Building, Area = 19,153m2
3. Book Store Building , Area = 8,300 m2
4. Existing souq Building‐Retail Shops, Area = 7,781 m2
5. Existing Admiration Building Traditional , Area = 515m2
6. Art Plaza, Area = 6900 m2
2 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS
1.4— CONTRACT PARTICULARS
Client name Private Engineering Office (PEO)
Consultant name Dar Al Handasa
Contractor name UrbaCon Trading and Contracting
Contract Name Hotel & Complex of Al Najadah SOUQ
Contract Number (LOA number) U‐295‐295‐14 HNCS
Original Contract Price 860,000,000 QAR
Revised Contract Price N/A
Original Contract Period (days) 669 Calendar Days
Revised Contract Period (days) N/A
Percentage Time Elapsed as of 30 April
320 days out of 670 days = 47.76%
2015
Amount of Penalty for Delay 520,000 QAR/day
Advance Payment 10% (86,000,000 QAR)
10% (5% Upon issuance Completion Certificate ,5% upon
Retention Money
issuance of Defect Liability Performance Certificate)
Validity of Performance Bond 18‐August‐2017
Validity of Contractors All Risk Policy 14‐Apr‐2016
Letter of Award date: 08 Jan 2015(Letter of Award only) Not Signed by UCC
Signing of Contract Agreement date: 12‐January‐2015 (Letter of Award only)
Original Start Date 15 Jun 2014
Original Completion Date 14 Apr 2016
Revised Completion Date N/A
Projected Completion Date 14 Apr 2016
Maintenance Period 400 Calendar Days
Planned Percentage Complete 19.96%(as of 30‐April‐2015)
Actual Percentage Complete 17.09%(as of 30‐April‐2015)
Variance / Slippage ‐2.87%
UCC does not accept the actual % of 17.09%& refers to the submission of
revised weightage % that leads to Actual % of 23%lead on construction
weightage of 65% instead of 55%
1.5 — FINANCIAL SUMMARY
ITEM QAR
Original Contract Price 860,000,000
Total value of variation orders issued to date 292,518,545.84 QR
Adjusted Contract Price 1,152,518,545.84
Total values of possible changes to the Contract 0 QR
Anticipated final account (A) 1,152,518,545.84
Monetary/Time Claims approved 0 days
Advanced Payment (B) 86,000,000 QR
Gross value of Interim Payment Certificates to date (C) TA#02:239,680,753.68
Retention held to date (D) 23,968,075.36 QR
Recovery against Advanced payment made to date (E) 23,968,075.36 QR
Any other deduction made to date (F) 0 QR
Total deductions to date (G) = (D + E + F) 47,936,150.72QR
SECTION 2: EXECUTIVE SUMMARY (PROGRESS OUTLINE)
2.1 — SITE PROGRESS / CONSTRUCTION ACTIVITIES SUMMARY
Hotel Building:
1. Basement:
Part 4: Slab Rebar & MEP works in Progress at First Floor level.
Sand leveling at Basement level.
2. Ground Floor:
Block works in Progress.
MEP Works in progress
3. Mezzanine Floor:
Block Works in Progress.
MEP Works in progress
4. First Floor
Block Works in Progress.
MEP Works in progress
Swimming Pool area Rebar & MEP Works in Progress.
5. Second Floor
Par 3: Slab Concrete Done.
Block Works in Progress.
MEP Works in progress
6. Third Floor
Part 2 & 3: Slab Concrete Done.
Part 3: Column Concrete done .De‐shuttering Works in progress.
7. Fourth Floor
Part 2 & 3: Column Form & Concrete works done.
Part 2 & 3: Slab Form Works in progress
8. Roof Floor
Part 1: Form & Rebar Works in progress
Book Store:
1. Basement:
Block Works in Progress.
MEP Works in progress.
2. Ground Floor:
Structural Works Complete.
3. Mezzanine Floor:
Structural Works Complete.
4. First Floor
Column Rebar & MEP Works in progress.
SECTION 2: EXECUTIVE SUMMARY (PROGRESS OUTLINE)
Book Store:
4. First Floor
Column Form & Concrete Works in progress.
Column De shuttering Works in progress.
Shops & Market:
Structural Repairing Works in Progress.
External & Internal sidewall Preparation works in Progress
Admin Building:
Sand Plastering Works in Progress
Old Souq:
Structural Repairing Works in Progress.
Sand Plastering Works in Progress.
Block & Plastering Works in Progress.
Car Park:
Demolishing Works in Progress.
Hotel Extension:
Excavation Works in Progress.
6 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS
2.2— ENGINEERING & TECHNICAL SUMMARY (Design Delivery Matrix attached)
1. Design
Concept Design/Design Development is finished for all building,new
design as per client needed modifications is sent to the
Consultant/client and waiting for response for 2 month,Draft
comments are sent & may cause big impact on progress on site
IFC drawings in progress and send a draft copy to consultant ,Where
Final IFC can’t be earned due to delay in DC2 Permit which is in delay
due to new design modifications in Carpark, restaurant & multi‐
purpose hall buildings.
2. Material
Many purchase orders are a ready made specially hotel & Book Store
Such as but not limited to (kitchen, Elevator,Metal Doors..Etc.
3. Shopdrawings
Structural Shop drawings are in progress for Hotel Building, Bookstore
Architectural/MEP Shop drawings are in progress for Hotel building,
Bookstore.
2.3 — PLANS FOR NEXT MONTH
1. Hotel
a) Pouring Concrete Part 2,3 at Roof floor level
b) Block works Complete at Second floor level
c) Plastering Works in progress at First Floor level
d) MEP Works at First & Second Floor level.
e) Block Works in progress at Third Floor level
2. Bookstore
a) Pouring Concrete Second floor level.
b) Plastering Works Done.
c) Block Works in Progress at Ground Floor level.
d) MEP Works in progress at Ground Floor level.
3. Admin Building
a) Plastering Works Done.
b) Painting Works in progress.
4. Old Souq
a) Plastering Works Done.
b) Painting Works in progress.
c) MEP Works in progress
5. Car Park
a) Demolishing Works Done
b) Foundation Works in Progress
6. Hotel Extension :
a) Foundation Works in Progress
SECTION 3: PROGRAM AND PROGRESS
3.1 — PROJECT MILESTONES STATUS
Milestones Contract Schedule Forecast/ Actual Date Variance
Letter of Award Date 08‐January‐2015 08‐January‐2015 0
Design Freeze(No More Changes
05‐February‐2015
in Design by Client)
DC1 22‐March‐2015
DC2 22‐March‐2015
Design Finish 22‐March‐2015
Shop drawings Finish 24‐Aug‐2015
Permanent Power on Site 15‐Nov‐2015
QCDD Approval 29‐March‐2016
Project Finish Handing over to
14‐Apr‐2016
Client
A = Actual F = Forecast
Notes:
1‐ The Contract does not specify any intermediate milestones for this Project. The
above milestones were developed for close monitoring purposes.
2‐ A Master Baseline programme has been submitted and Approved as Noted.
3‐ A detailed baseline was sent and not approved from consultant due to missing BOQ
and some comments under preparation to be send again
3.2 — PROGRESS FOR TECHNICAL SUBMISSION
MATERIAL SUBMITTAL CIVIL MEP
Revise and Resubmit 16 41
Under Review 1 19
TOTAL 75 102
SHOP DRAWING SUBMITTAL CIVIL MEP
Approved 90 15
Revise and Resubmit 203 30
Under Review 64 13
TOTAL 357 58
Pending 37 11
Total 936 116
3.3 — PROGRESS FOR PROCUREMENT
SUBMISSION DELIVERY
MATERIAL DESCRIPTION
PLANNED ACTUAL PLANNED ACTUAL
Pressure control Switch Package 22‐Apr‐15 1‐Jul‐15
11 of 11 Monthly Report no. 4 [April 2015]
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Doha, Qatar
Project no. U-295-295-15-HCNS
3.4 — WORK PROGRAM EVALUATION
Project target completion date : 14 April 2016
Project estimated completion date : 14 April 2016
Project Completion Variance / Delay : 0 calendar days
Project planned completion percentage : 19.96% (As of 30‐April‐2015)
Project actual completion percentage : 17.09% (As of 30April‐2015)
Variance/ Delay noted : ‐2.84%
3.5 — AREAS OF CONCERNS
(1)‐ Variation and new contract is under preparation due to Changes as per PEO top
management visit on Thursday 15‐January‐2015 , which may lead to major impacts on
construction such as but not limited to :
a‐Demolish of car park building.
b‐Establishing a new furnished apartments building at car park location with 2 basements
for car parking.
c‐Establishing new shops in book store location which will lead to structural. Architectural &
interior design changes and will impact Construction progress.
d‐Establishing new Hotel Hotel extension in restaurant location.
(2)‐Delay in Approval of Concept Design from PEO 2 months till now , and reply may cause
severe impact on construction.
(3)‐Approval to End User for bookstore & methodology of work of heritage building causing
delay in start of work.
SECTION 4: HEALTH, SAFETY & ENVIRONMENT
4.1 — HSE ACCOMPLISHMENTS
1. Tool box‐meeting hold regularly in Weekly basis 4‐5 times almost 500 employees are
attend meeting.
2. Fire extinguishers were secured maintained and monitored Monthly/color coded.
3. Scaffolds were fixed, sustained and tagged, by a dedicated scaffold.
4. PPEs were provided to concerned employees.
5. Safety signage was placed on appropriate site area.
6. HSE policy is well promoted and followed.
4.2 — HSE STATISTICS
JOB HOUR STATISTIC Man‐Hours Worked
Current Month 317,110
Accumulated Total 1,760,145
Accident Free Man‐Hours
JOB HOUR STATISTIC Current Cumulative
Fatality (work related death) 0 0
Serious Injurious Accident 0 0
Moderate Injurious Incident 0 1
Number of Lost Time Days (work related) 0 0
Minor Injurious Events (no day lost / first aid & checkup) 4 21
Serious Damage Accident (estimated over 10,000QR) 0 0
Moderate Damage Incident (>< 1,000 & 10,000QR) 0 1
Minor Damage Event (estimated below 1,000QR) 0 3
Total Vehicle/Plant Events(9,10,11&12 Combined) 0 4
Road Accident (outside project or facility locations) 0 0
Fire (any size) 0 1
Near Miss Reports 1 3
Environmental Incident 0 0
HSE Violation Issued 7 45
ATTACHMENT / RECORDS
CONSTRUCTION S - CURVE
14.00% 120.00%
13.00%
11.66%
12.00%
100.00%
CUT OF DATE 30‐4‐2015
9.82%
10.00%
80.00%
8.52%
7.67%
7.53%
8.00%
6.76%
60.00%
6.00%
4.92%
4.14%
3.90%
40.00%
3.58%
3.35%
4.00%
3.14%
2.63%
1.90%
1.62%
20.00%
1.41%
1.36%
1.25%
2.00%
0.81%
0.69%
0.20%
0.13%
0.00% 0.00%
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Plan Incr 0.13% 0.20% 1.25% 1.41% 0.81% 1.36% 1.90% 2.63% 3.14% 3.35% 3.90% 4.92% 6.76% 7.53% 9.82% 8.52% 13.00% 11.66% 7.67% 4.14% 3.58% 1.62% 0.69%
Actual Incr 0.13% 0.20% 1.00% 1.25% 1.50% 1.25% 2.00% 2.75% 2.50% 2.35% 2.16%
Plan Cum 0.13% 0.33% 1.58% 2.99% 3.81% 5.17% 7.07% 9.69% 12.83% 16.18% 20.08% 25.01% 31.76% 39.29% 49.11% 57.63% 70.64% 82.30% 89.98% 94.11% 97.69% 99.31% 100.00%
Actual Cum 0.13% 0.33% 1.33% 2.58% 4.08% 5.33% 7.33% 10.08% 12.58% 14.93% 17.09%
Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
15-Jun-14 A 25-Apr-16 568 19.96% 17.09% -9 25-Apr-16, HOTEL & COMPLEX
HOTEL & COMPLEX OF AL-NAJADAH SOUQ REV1
15-Jun-14 A 25-Apr-16 686 63.3% 62.65% -12 25-Apr-16, General
General
Milestones 15-Jun-14 A 25-Apr-16 686 0% 0% -12 25-Apr-16, Milestones
Hotel Building
Build 15-Jun-14 A 14-May-15 151 100% 80% -12 14-May-15, Hotel Building
Book Store 20-Aug-14 A 14-May-15 101 100% 80% 13 14-May-15, Book Store
Multi Purposes
Purp Hall 23-Aug-14 A 18-May-15 131 100% 80% 121 18-May-15, Multi Purposes Hall
Restaurant 15-Sep-14 A 14-May-15 138 0% 0% 71 14-May-15, Restaurant
Market &S
&Shops,Old Souq 06-Sep-14 A 21-May-15 110 100% 80% 15 21-May-15, Market &Shops,Old Souq
Admin Bui
Building 24-Sep-14 A 14-May-15 132 100% 80% 30 14-May-15, Admin Building
Car Park 12-Jul-14 A 14-May-15 110 0% 0% 9 14-May-15, Car Park
External W
Works 21-Oct-14 A 14-May-15 115 100% 80% 2 14-May-15, External Works
Main Utilities
Utiliti 25-Nov-14 A 28-May-15 90 0% 0% 5 28-May-15, Main Utilities
Design Sta
Stage (IFC Drawings/BOQ's/Spec's) 20-Sep-14 A 28-Jul-15 371 100% 29.11% 60 28-Jul-15, Design Stage (IFC Drawings/BOQ's/Spec's)
Hotel Building
Build 20-Sep-14 A 14-Jun-15 209 100% 40% -12 14-Jun-15, Hotel Building
Book Store 06-Nov-14 A 02-Jun-15 83 100% 30.48% 13 02-Jun-15, Book Store
Multi Purposes
Purp Hall 15-Dec-14 A 28-Jul-15 306 100% 5.26% 60 28-Jul-15, Multi Purposes Hall
Restaurant 30-Apr-15 28-Jul-15 80 0% 0% 34 28-Jul-15, Restaurant
Market & S
Shops,Old souq 28-Sep-14 A 22-Jul-15 298 100% 18.13% 15 22-Jul-15, Market & Shops,Old souq
Admin Bui
Building 17-Dec-14 A 28-Jun-15 264 100% 14.53% 21 28-Jun-15, Admin Building
Car Park 16-Oct-14 A 02-Jun-15 70 0% 0% 9 02-Jun-15, Car Park
1/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)
Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
External W
Works 23-Mar-15 A 17-Jun-15 93 100% 4.89% -2 17-Jun-15, External Works
Main Utilities
Utiliti 09-Mar-15 A 14-Jun-15 35 0% 0% 4 14-Jun-15, Main Utilities
Shop Drawings
Draw Stage 20-Jan-15 A 01-Dec-15 294 24.65% 14.83% 66 01-Dec-15, Shop Drawings Stage
Hotel Building
Build Shop Drawings 20-Jan-15 A 10-Nov-15 251 30.56% 24.54% 83 10-Nov-15, Hotel Building Shop Drawings
Civil Shopdrawings
Shopd of Hotel 20-Jan-15 A 25-Aug-15 222 94.68% 29.57% -4 25-Aug-15, Civil Shopdrawings of Hotel
Architectural Shopdrawings of Hotel
Architectur 25-Feb-15 A 07-Sep-15 224 4.67% 26.98% 153 07-Sep-15, Architectural Shopdrawings of Hotel
MEP Shop
Shopdrawings of Hotel 14-Mar-15 A 18-Aug-15 188 0% 16.61% 189 18-Aug-15, MEP Shopdrawings of Hotel
ELV Shopdrawings
Shopd of Hotel 14-Jun-15 10-Nov-15 123 0% 0% -1 10-Nov-15, ELV Shopdrawings of Hotel
Book Store Shop Drawings 21-Jan-15 A 08-Oct-15 248 15.55% 12.36% 61 08-Oct-15, Book Store Shop Drawings
Civil Shopdrawings
Shopd of Book Store 21-Jan-15 A 06-Aug-15 234 45.39% 20.9% -6 06-Aug-15, Civil Shopdrawings of Book Store
Architectural Shopdrawings of Book Store
Architectur 25-Feb-15 A 08-Oct-15 233 0% 4% -2 08-Oct-15, Architectural Shopdrawings of Book Store
MEP Shop
Shopdrawings of Book Store 21-Mar-15 A 29-Aug-15 180 0% 17.94% 116 29-Aug-15, MEP Shopdrawings of Book Store
ELV Shopdrawings
Shopd of Book Store 30-Apr-15 20-Sep-15 119 0.35% 0% -10 20-Sep-15, ELV Shopdrawings of Book Store
Multi Purposes
Purp Hall Shop Drawings 14-Jun-15 31-Oct-15 114 61.44% 0% 57 31-Oct-15, Multi Purposes Hall Shop Drawings
Restaurant Shop Drawings
Restauran 30-Apr-15 03-Sep-15 120 0% 0% 86 03-Sep-15, Restaurant Shop Drawings
A2600 Demolishing Shop Drawings for Restaurant 30-Apr-15 03-Sep-15 120 100% 0% 86
A2610 Interior Shop Drawings for Restaurant 30-Apr-15 16-Aug-15 100 0% 0% 105
A2620 MEP Shop Drawings for Restaurant 28-May-15 25-Aug-15 80 0% 0% 86
Architectural Shopdrawings of Restaurant
Architectur 30-Apr-15 29-Jul-15 81 0% 0% 85 29-Jul-15, Architectural Shopdrawings of Restaurant
Market & S
Shops,Old Souq Shop Drawings 31-Mar-15 A 26-Nov-15 200 0% 7.86% 58 26-Nov-15, Market & Shops,Old Souq Shop Drawings
A2630 Architectural Shop Drawings 31-Mar-15 A 07-Oct-15 120 98.33% 9.2% 19
A2640 Demolishing Drawings 30-Apr-15 03-Sep-15 120 92.5% 0% -8
A2660 MEP Shop Drawings 30-Apr-15 22-Sep-15 140 62.86% 0% -12
A2650 Interior Shop Drawings 31-May-15 07-Nov-15 150 38.67% 0% 94
Architectur Shopdrawings of Market & Shops,Old Souq
Architectural 05-Apr-15 A 19-Sep-15 168 0% 14.29% 55 19-Sep-15, Architectural Shopdrawings of Market & Shops,Old S
MEP Shop
Shopdrawings of Market & Shops,Old Souq 28-Jun-15 26-Nov-15 146 0% 0% 32 26-Nov-15, MEP Shopdrawings of Market & Shops,Old
ELV Shopdrawings
Shopd of Market & Shops,Old Souq 30-Apr-15 26-Jul-15 72 0% 0% 1 26-Jul-15, ELV Shopdrawings of Market & Shops,Old Souq
Admin Building
Bui Shop Drawings 19-May-15 01-Dec-15 189 0% 0% 21 01-Dec-15, Admin Building Shop Drawings
A2680 Demolishing Drawings(Method of Repair) 03-Jun-15 13-Oct-15 120 75.83% 0% 18
A2700 MEP Shop Drawings 21-Jun-15 26-Nov-15 150 0% 0% 26
A2690 Interior Shop Drawings 28-Jun-15 01-Dec-15 150 0% 0% 11
Architectural Shopdrawings of Admin Building
Architectur 19-May-15 27-Aug-15 93 0% 0% -7 27-Aug-15, Architectural Shopdrawings of Admin Building
Car Park Shop
S Drawings 30-Apr-15 08-Nov-15 185 0% 0% 37 08-Nov-15, Car Park Shop Drawings
A2720 Demolishing Drawings 30-Apr-15 06-Aug-15 90 100% 0% 6
A2740 MEP Shop Drawings 30-Apr-15 06-Oct-15 150 92% 0% -11
A2710 Architectural Shop Drawings 19-May-15 22-Sep-15 120 100% 0% -6
A2730 Interior Shop Drawings 02-Jun-15 08-Nov-15 149 65.77% 0% 9
Architectural Shopdrawings of Car Park
Architectur 19-May-15 22-Oct-15 147 0% 0% 56 22-Oct-15, Architectural Shopdrawings of Car Park
External Works
W Shop Drawings 30-Apr-15 25-Oct-15 170 4.38% 0% 107 25-Oct-15, External Works Shop Drawings
A2760 Structural Drawings 30-Apr-15 03-Sep-15 120 0% 0% 38
A2770 Landscape Shop Drawings 30-Apr-15 06-Oct-15 150 17.33% 0% -5
A2780 MEP Shop Drawings 12-May-15 19-Oct-15 150 28% 0% -2
A2750 Architectural Shop Drawings 16-Jun-15 25-Oct-15 120 35.83% 0% 5
MEP Shop
Shopdrawings of External Works 01-Aug-15 19-Sep-15 53 0% 0% 141 19-Sep-15, MEP Shopdrawings of External Works
Main Utilities
Utiliti Shop Drawings 26-Jul-15 10-Nov-15 110 0% 0% 4 10-Nov-15, Main Utilities Shop Drawings
Material Submittals
S 02-Jan-15 A 21-Sep-15 242 6.77% 14.44% 45 21-Sep-15, Material Submittals
2/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)
Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
Civil & Architectural
Arc Materials 02-Jan-15 A 03-Sep-15 210 9.16% 9.55% 64 03-Sep-15, Civil & Architectural Materials
Electrical Materials
M 18-Jan-15 A 02-Aug-15 156 1.06% 17.67% 3 02-Aug-15, Electrical Materials
Mechanical Materials
Mechanica 20-Jan-15 A 21-Sep-15 242 8.37% 20.65% -3 21-Sep-15, Mechanical Materials
ELV Materials
Mater 30-Apr-15 01-Aug-15 83 0% 0% 3 01-Aug-15, ELV Materials
Special Items
Ite 05-Feb-15 A 24-Aug-15 197 17.65% 6.29% -4 24-Aug-15, Special Items
Method of Statements & Pre-qualifications 21-Dec-14 A 24-Nov-15 381 12.33% 29.58% 151 24-Nov-15, Method of Statements & Pre-qualifications
Delivery Lead
Le Time 24-Jan-15 A 11-Feb-16 337 0% 0.51% 55 11-Feb-16, Delivery Lead Time
Final Deliv
Delivery Milestones 27-Jun-15 11-Feb-16 229 0% 0% 55 11-Feb-16, Final Delivery Milestones
Civil Works 20-Jun-14 A 01-Sep-15 325 70.28% 72.84% 46 01-Sep-15, Civil Works
Part 1 20-Jun-14 A 31-Aug-15 317 95% 92.55% -3 31-Aug-15, Part 1
Part 2 16-Aug-14 A 29-Jul-15 274 64.95% 88.05% 32 29-Jul-15, Part 2
Part 3 16-Aug-14 A 01-Sep-15 295 66.41% 76.23% 36 01-Sep-15, Part 3
Part 4 21-Dec-14 A 20-Aug-15 312 54.78% 34.53% 59 20-Aug-15, Part 4
Finishing Works
W 21-Mar-15 A 17-Mar-16 244 0% 0.86% 0 17-Mar-16, Finishing Works
Basement Floor 14-Jul-15 25-Feb-16 232 0% 0% -6 25-Feb-16, Basement Floor
Ground Floor
Flo 21-Mar-15 A 23-Feb-16 248 0% 0.99% 2 23-Feb-16, Ground Floor
Mezzanine Floor 05-Apr-15 A 29-Feb-16 233 0% 1.12% -10 29-Feb-16, Mezzanine Floor
First Floor 05-Apr-15 A 01-Mar-16 229 0% 3.34% -6 01-Mar-16, First Floor
Second Floor
Flo 21-Apr-15 A 24-Jan-16 214 0% 1.67% 22 24-Jan-16, Second Floor
Third Floor 13-Aug-15 08-Feb-16 186 0% 0% 17 08-Feb-16, Third Floor
Fourth Floor
Flo 23-Aug-15 01-Mar-16 198 0% 0% -6 01-Mar-16, Fourth Floor
Roof Floor 01-Sep-15 31-Dec-15 125 0% 0% 6 31-Dec-15, Roof Floor
Upper Roof
Roo Floor 22-Oct-15 15-Nov-15 25 0% 0% 75 15-Nov-15, Upper Roof Floor
Facades 01-Aug-15 17-Mar-16 240 0% 0% 0 17-Mar-16, Facades
3/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)
Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
MEP Works 11-Apr-15 A 24-Mar-16 350 0% 0.18% 22 24-Mar-16, MEP Works
Basement Floor 17-May-15 24-Mar-16 313 0% 0% 12 24-Mar-16, Basement Floor
Ground Floor
Flo 03-Aug-15 10-Dec-15 126 0% 0% 83 10-Dec-15, Ground Floor
Mezzanine Floor 19-Aug-15 12-Jan-16 152 0% 0% 63 12-Jan-16, Mezzanine Floor
First Floor 11-Apr-15 A 14-Feb-16 306 0% 1.76% 66 14-Feb-16, First Floor
Second Floor
Flo 03-Aug-15 24-Dec-15 150 0% 0% 119 24-Dec-15, Second Floor
Third Floor 18-Aug-15 02-Jan-16 141 0% 0% 75 02-Jan-16, Third Floor
Fourth Floor
Flo 27-Aug-15 07-Jan-16 139 0% 0% 69 07-Jan-16, Fourth Floor
Roof Floor 09-Nov-15 15-Mar-16 135 0% 0% -2 15-Mar-16, Roof Floor
Access to MEP Installations
Upper Roof
Roo Floor 16-Nov-15 14-Dec-15 30 0% 0% 75 14-Dec-15, Upper Roof Floor
Access to MEP Installations
Utility Rooms
Roo 19-Sep-15 05-Jan-16 89 0% 0% 29 05-Jan-16, Utility Rooms
Elevators 10-Sep-15 22-Feb-16 170 0% 0% 2 22-Feb-16, Elevators
Book Store 15-Dec-14 A 06-Feb-16 424 13.21% 20.07% -5 06-Feb-16, Book Store
Civil Works 15-Dec-14 A 03-Sep-15 263 37.35% 55.89% 78 03-Sep-15, Civil Works
Civil Works BF 15-Dec-14 A 01-Jun-15 170 80.57% 66.67% 50 01-Jun-15, Civil Works BF
Civil Works GF 08-Feb-15 A 27-May-15 92 57.81% 83.33% 167 27-May-15, Civil Works GF
Civil Works MF 14-Feb-15 A 25-Mar-15 A 32 78.41% 100% 25-Mar-15 A, Civil Works MF
Civil Works FF 01-Apr-15 A 22-Jul-15 55 0% 72.5% -10 22-Jul-15, Civil Works FF
Civil Works SF 22-Apr-15 A 11-Aug-15 55 0% 5% -10 11-Aug-15, Civil Works SF
Civil Works URF 11-Aug-15 03-Sep-15 25 0% 0% -10 03-Sep-15, Civil Works URF
Finishing Works
W 11-Apr-15 A 19-Jan-16 283 0% 0.81% -11 19-Jan-16, Finishing Works
Basement Floor 11-Apr-15 A 21-Dec-15 252 0% 3.96% -5 21-Dec-15, Basement Floor
Ground Floor
Flo 07-May-15 03-Jan-16 237 0% 0% -9 03-Jan-16, Ground Floor
Mezzanine Floor 14-Jul-15 07-Jan-16 180 0% 0% -9 07-Jan-16, Mezzanine Floor
First Floor 02-Aug-15 07-Jan-16 165 0% 0% -9 07-Jan-16, First Floor
Second Floor
Flo 20-Aug-15 19-Jan-16 157 0% 0% -11 19-Jan-16, Second Floor
Upper Roof
Roo Floor 03-Sep-15 03-Nov-15 60 0% 0% -10 03-Nov-15, Upper Roof Floor
Facades 04-Oct-15 17-Jan-16 113 0% 0% -9 17-Jan-16, Facades
MEP Works 08-Apr-15 A 17-Jan-16 222 0% 0.25% 16 17-Jan-16, MEP Works
Basement Floor 08-Apr-15 A 29-Dec-15 182 0% 1.23% 56 29-Dec-15, Basement Floor
Ground Floor
Flo 28-Jun-15 27-Dec-15 176 0% 0% 38 27-Dec-15, Ground Floor
Mezzanine Floor 21-Jul-15 24-Dec-15 163 0% 0% 3 24-Dec-15, Mezzanine Floor
First Floor 28-Jun-15 28-Dec-15 177 0% 0% 2 28-Dec-15, First Floor
Second Floor
Flo 24-Aug-15 17-Jan-16 152 0% 0% -10 17-Jan-16, Second Floor
Upper Roof
Roo Floor 03-Nov-15 05-Jan-16 68 0% 0% 3 05-Jan-16,
Access to MEP Upper Roof Floor
Utility Rooms
Roo 08-Sep-15 30-Dec-15 116 0% 0% 35 30-Dec-15, Utility Rooms
Elevator Works
W 17-Oct-15 06-Feb-16 120 0% 0% -5 06-Feb-16, Elevator Works
Multi Purpose
Purp Hall 11-Aug-15 24-Jan-16 169 0% 0% 12 Access to24-Jan-16,
MEP Multi Purpose Hall
Ground Floor
Flo Level 20-Dec-14 A 07-Feb-16 422 39.37% 25.25% -12 07-Feb-16, Ground Floor Level
Mezzanine Floor Level 02-Jun-15 21-Jan-16 228 0% 0% 6 21-Jan-16, Mezzanine Floor Level
Hallways 22-Nov-15 03-Feb-16 78 0% 0% 2 03-Feb-16, Hallways
Admin Building
Bui 03-Jan-15 A 15-Mar-16 402 7.61% 10.13% -7 15-Mar-16, Admin Building
Ground Floor
Flo Level 03-Jan-15 A 07-Jan-16 330 19.26% 18.95% 11 07-Jan-16, Ground Floor Level
Upper Floo
Floor Level 07-Mar-15 A 13-Dec-15 85 0% 7.5% -7 13-Dec-15, Upper Floor Level
External W
Works 19-Oct-15 31-Dec-15 80 0% 0% -7 31-Dec-15, External Works
Facades 02-Jan-16 15-Mar-16 78 0% 0% -7 15-Mar-16, Facades
4/5
Hotel & Complex of AL Najada Souq(Detailed
Baseline)
Activity ID Activity Name Start Finish Original Schedule % Performance % Total 2014 2015 2016 7
Duration Complete Complete Float J Jul A S Oct N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 2
Old Souq Area
A 30-Dec-14 A 30-Dec-15 351 7.66% 8.54% 15 30-Dec-15, Old Souq Area
Ground Floor
Flo level 30-Dec-14 A 23-Dec-15 344 24.7% 18.76% 23 23-Dec-15, Ground Floor level
Mezzanine Floor Level 21-Apr-15 A 06-Dec-15 135 0% 0.4% 41 06-Dec-15, Mezzanine Floor Level
Hallways 11-Apr-15 A 30-Dec-15 231 0% 13.02% 15 30-Dec-15, Hallways
Roof Floor 12-Sep-15 19-Dec-15 101 0% 0% 27 Access to19-Dec-15,
MEP Roof Floor
Ground Floor
Flo 24-Dec-14 A 18-Oct-15 358 0% 0% 88 18-Oct-15, Ground Floor
Mezzanine Floor 22-Jul-15 10-Sep-15 55 0% 0% 69 10-Sep-15, Mezzanine Floor
Hallway Floor
Fl 10-Aug-15 16-Nov-15 101 0% 0% 60 16-Nov-15, Hallway Floor
Facades 15-Oct-15 12-Nov-15 30 0% 0% 76 12-Nov-15, Facades
Specialities 07-Sep-15 03-Dec-15 90 0% 0% 59 03-Dec-15, Specialities
External W
Works 25-Aug-15 05-Mar-16 200 0% 0% 2 05-Mar-16, External Works
Undergrou Services/Utilities
Underground 25-Aug-15 05-Mar-16 200 0% 0% 2 05-Mar-16, Underground Services/Utilitie
Plaza 22-Sep-15 17-Jan-16 120 0% 0% 5 17-Jan-16, Plaza
19-Nov-15 25-Apr-16 169 0% 0% -12 25-Apr-16, Commissioning & Hand
Commissioning & Handing Over
Commissi
5/5
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS
WEATHER REPORT
MANPOWER REPORT
2,000 25,000
1,800
1,800
1,800
1,750
1,700
1,800
1,500
1,500
1,600 20,000
1,300
1,300
1,400
1296
1,150
1133
1,100
1,200 15,000
1101
1100
1,000
980
1,000
890
890
720
800 10,000
700
700
600
600
600
500
500
350
320
400 5,000
320
290
290
150
200
57
57
‐ ‐
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 Aug‐15 Sep‐15 Oct‐15 Nov‐15 Dec‐15 Jan‐16 Feb‐16 Mar‐16 Apr‐16
Plan Incr 57 290 320 500 600 700 890 980 1,100 1,150 1,300 1,500 1,750 1,800 1,800 1,800 1,700 1,500 1,300 1,000 720 350 150
Actual Incr 57 290 320 500 600 700 890 1100 1133 1101 1296
Plan Cum 57 346 666 1,166 1,766 2,466 3,356 4,336 5,436 6,586 7,886 9,386 11,136 12,936 14,736 16,536 18,236 19,736 21,036 22,036 22,756 23,106 23,256
Actual Cum 57 347 667 1167 1767 2467 3357 4457 5590 6691 7987
CONTRACTOR’S EQUIPMENT
Bob Cat 5
TeleHandler 1
Small pickup 1
Forklift 1
Backhoe loader 1
JCB 0
Pickup 3 Ton 1
Mobile Crane 50Ton 0
Wheel Loader 0
Tower Crane 2
Hiab 10Ton 1
Bus 13
TOTAL 26
Inspection Requests
a b c d e f g h
Submittals (Materials, Technical and Method of Statements)
a b c d e f g h
Total Submitted Status Percentage
DESCRIPTION Cumulative Number of Cumulative Number of
Submittals Pending with Submittals received back Total Approved Total Not Approved
% Approved on First % Not Approved on First Submittal
This Month Up to Date Consultant from Consultant
This Month Up to Date This Month Up to Date Submittal (e/c) (g/c)
Non‐Conformance Reports
Cumulative Number NCR's Cumulative Number NCR's Pending with Cumulative Number of NCR's Closed
Outstanding NCR's
% Outstanding NCR's Up to Date
This Month Up to Date This Month Up to Date This Month Previously Issued NCR's Up to Date Up to Date
1 11 0 0 0 0 9 2 81.82%
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-HCNS
SUBMITTAL LOGS
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
HCNS-IR-ARCH- Inspection Request for setting out layout of block work. See Grid C-G / 7-9 , B-D / 12,14-16 , J-L / 18,
N/A 1 ARCH B L UCC 7-Apr-15 8-Apr-15 Done
0020 attached lay-out. G-I / 17 Old Souq
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
N/A 1 ARCH B L Grid M-K / 16 Hotel Ground floor UCC 5-Apr-15 7-Apr-15 Done
0021 ground floor. As per highlighted in attached key plan.
Grid H-M / 10-11 , H-M / 11-12 , H-M /
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
34 N/A 0 ARCH B L 12-13 , H-M / 13-14 , H-M / 14-15 , H-M / UCC 1-Apr-15 4-Apr-15 Done
0033 first floor. As per highlighted in attached key plan.
15 - 16 , J-K / 18 Hotel 1st Floor
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
35 N/A 0 ARCH D NL Grid N / 7-10 Hotel Ground floor UCC 1-Apr-15 4-Apr-15 Done
0034 ground floor. As per highlighted in attached key plan.
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
35 N/A 1 ARCH B L Grid N / 7-10 Hotel Ground floor UCC 5-Apr-15 6-Apr-15 Done
0034 ground floor. As per highlighted in attached key plan.
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
37 N/A 0 ARCH B L Grid N-R / 10-14 Hotel First floor UCC 4-Apr-15 6-Apr-15 Done
0036 first floor. As per highlighted in attached key plan.
HCNS-IR-ARCH- Inspection request for complete block work at ground floor. As Grid N-Q / 15-17 & M / 17-18 Hotel
39 N/A 0 ARCH B L UCC 5-Apr-15 7-Apr-15 Done
0038 per highlighted in attached key plan. Ground floor
HCNS-IR-ARCH- Inspection request for complete block work for mock-up room.
41 N/A 0 ARCH B L Grid N-R / 14-17 Hotel First floor UCC 8-Apr-15 9-Apr-15 Done
0040 As Per Highlighted in attached key plan.
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at
42 N/A 0 ARCH B L Grid J-M / 16-19 Hotel second floor UCC 8-Apr-15 8-Apr-15 Done
0041 second floor. As per highlighted in attached key plan.
HCNS-IR-ARCH- Inspection request for 1st course laying of light weight block at Grid H-M / 5-10 & 19 / M-N & 20 / M - N
44 N/A 0 ARCH B L UCC 14-Apr-15 19-Apr-15 Done
0043 second floor. As per highlighted in attached key plan. Hotel Second Floor
HCNS-IR-ARCH- Inspection request for installation of block full height prior for Grid C-G / 7-9 , B-D / 12,14-16 , J-L / 18,
46 N/A 0 ARCH B L UCC 15-Apr-15 19-Apr-15 Done
0045 rush coat. See attached lay-out G-I / 17 Old Souq
ARCH Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
47 N/A 0 ARCH B L Grid N-R / 5-10 Hotel Second Floor. UCC 15-Apr-15 19-Apr-15 Done
0046 as per highlighted attached key plan.
HCNS-IR-ARCH- Inspection Request for application of vetonit base & finish Grid I-J / 10-19 , H-K / 12-15 , K-M / 13-
48 N/A 0 ARCH D NL UCC 18-Apr-15 20-Apr-15
0047 coat. See attached lay-out. 14 Old Souq
HCNS-IR-ARCH- Inspection request for application of Vetonit. See attached lay- Grid I-J / 10-19 , H-K / 12-15 , K-M / 13-
N/A 1 ARCH U/R L UCC 28-Apr-15
0047 out. 14 Old Souq
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
49 N/A 0 ARCH B L Grid N-R / 10-13 Hotel Second floor UCC 20-Apr-15 22-Apr-15 Done
0048 as per highlighted attached key plan.
HCNS-IR-ARCH- New Door opening at ground floor refer to new approved shop
50 N/A 0 ARCH D L Grid M / 16-17 Hotel Ground floor UCC 20-Apr-15 20-Apr-15
0049 drawing as per the attached key plan.
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
51 N/A 0 ARCH B L Grid K-L / 19 Hotel Ground floor UCC 20-Apr-15 22-Apr-15 Done
0050 as per highlighted attached key plan.
HCNS-IR-ARCH- Mock-Up as explained in the meeting with PEO regards the Room.01 Beside Main Entrance as per
52 N/A 0 ARCH D L UCC 20-Apr-15 20-Apr-15
0051 Heritage Building. attached plan.
Inspection request for setting out of block wall ( first layer )
HCNS-IR-ARCH-
53 N/A prior to block work from basement to ground floor as per 0 ARCH B L Grid 6-14 / J-T Bookstore UCC 23-Apr-15 26-Apr-15 Done
0052
attached drawing and grid lines.
HCNS-IR-ARCH- Inspection request for 1st laying course of light weight block ,
54 N/A 0 ARCH D L Grid H-M / 10-13 Hotel Second floor. UCC 23-Apr-15 25-Apr-15
0053 as per highlighted attached key plan
HCNS-IR-ARCH- 1st Course laying of light weight block at first floor as per
55 N/A 0 ARCH B L Grid N-R / 2-5 Hotel first floor UCC 26-Apr-15 27-Apr-15 Done
0054 highlighted attached plan.
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block,
56 N/A 0 ARCH B L Grid H-M / 13-16 Hotel second floor UCC 26-Apr-15 27-Apr-15 Done
0055 as per highlighted attached key plan.
HCNS-IR-ARCH- Complete block work at first floor as per highlighted attached Grid N-R / 5-14 & H-M / 5-18 Hotel First
58 N/A 0 ARCH B L UCC 26-Apr-15 28-Apr-15 Done
0057 plan floor
Grid Ground J-L / 11, G-I / 18,E-F,C-D /
HCNS-IR-ARCH- Inpspection request for surface preparation prior for plastering.
59 N/A 0 ARCH B L 19 , M EZ J-L / 18, G-I / 17-18 , B-D / UCC 26-Apr-15 28-Apr-15 Done
0058 See attached lay out.
12,14-16 , D ,F / 7-8 Old Souq.
HCNS-IR-ARCH- Inspection Request for 1st laying course of light weight block.
60 N/A 0 ARCH U/R L Grid N-R /15-17 Hotel Second floor UCC 29-Apr-15
0059 As per highlighted attached key plan.
HCNS-IR-ARCH- 1st Course laying of light weight block at first floor as per
61 N/A 0 ARCH U/R L Grid N-R / 1-2 Hotel first floor UCC 29-Apr-15
0060 highlighted attached plan.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request for column formwork from mezzanine level to
HCNS-IR-CIVIL-0537 N/A 0 C A Ok L Grid 11‐13 / I ‐ T Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
first floor slab as per drawings and grid lines.
Inspection request for corewall formwork from mezzanine level to
HCNS-IR-CIVIL-0538 N/A 0 C B Ok L Grid 11‐13 / I ‐ L , R Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
first floor slab as per attached drawing and grid lines.
Inspection request for column, wall concrete from mezzanine level
HCNS-IR-CIVIL-0539 N/A 1 C B Ok L Grid 11‐13 / I ‐ T Bookstore UCC 4‐Apr‐15 4‐Apr‐15 Done
to first floor slab as per attached drawing and grid lines.
Inspection request of rebar 2nd floor slab. Please refer to the
HCNS-IR-CIVIL-0540 N/A 1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
attached key plan for your reference.
Inspection request of form work for 2nd floor slab to proceed with
HCNS-IR-CIVIL-0541 N/A concrete casting. Please refer to the attached key plan for your 1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for 2nd floor slab. Please
HCNS-IR-CIVIL-0542 N/A 1 C B Ok L Gird R‐G / 1‐4 Hotel 2nd Floor UCC 1‐Apr‐15 2‐Apr‐15 Done
refer to the attached key plan for your reference.
Installation of waterproofing membrane MASTERPREN.BG on raft
HCNS-IR-CIVIL-0543 N/A prior to proceed with protection board. Please refer to the attached 1 C B Ok L Grid C‐H / 6 Hotel Basement UCC 2‐Apr‐15 4‐Apr‐15 Done
key plan for your reference.
Inspection request of rebar for wall at 3rd floor to proceed with form
HCNS-IR-CIVIL-0545 N/A 1 C B Ok L Grid R‐H / 10‐14 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
work. Please refer to the attached key plan for your reference.
Inspection request of formwork for wall at 3rd floor to proceed with
HCNS-IR-CIVIL-0547 N/A concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid R‐H / 10‐14 Hotel 3rd Floor UCC 4‐Apr‐15 5‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for wall at 3rd floor.
HCNS-IR-CIVIL-0549 N/A 0 C B Ok L Grid R‐H / 4‐14 Hotel 3rd floor UCC 4‐Apr‐15 5‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request of rebar for ground floor slab around swimming
HCNS-IR-CIVIL-0552 N/A 1 C B Ok L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 2‐Apr‐15 5‐Apr‐15 Done
pool. Please refer to the attached key plan for your reference.
Inspection request of form work for 1st floor slab and swimming
HCNS-IR-CIVIL-0553 N/A pool wall to proceed with concrete casting. Please refer to the 1 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
attached key plan for your reference.
Inspection request for concrete casting C40 for swimming pool area
HCNS-IR-CIVIL-0554 N/A slab and wall. Please refer to the attached key plan for your 1 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
reference.
Inspection request for blinding concrete above top layer as per
HCNS-IR-CIVIL-0556 N/A 0 C B Ok L Grid 12‐14 / J‐T // 5‐7 / L‐S Bookstore UCC 1‐Apr‐15 4‐Apr‐15 Done
attached drg and grid lines.
Inspection request for applying antitermite before blinding concrete
HCNS-IR-CIVIL-0557 N/A 0 C B Ok L Grid 12‐14 / A‐J // 5‐7 / J‐T Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
above top layer as per attached drg and grid lines.
Inspection request for back filling and compaction ( compaction test
HCNS-IR-CIVIL-0558 N/A 0 C B Ok L Grid 13‐14 / J‐T Bookstore UCC 1‐Apr‐15 1‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request for back filling and compaction ( compaction test
HCNS-IR-CIVIL-0559 N/A 0 C B Ok L Grid 1'‐5' / S‐T // 5‐7 / L‐T Bookstore UCC 1‐Apr‐15 4‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Inspection request for primer application above blinding prior to
HCNS-IR-CIVIL-0560 N/A 0 C A Ok L Grid 13‐14 / B‐J Bookstore UCC 1‐Apr‐15 2‐Apr‐15 Done
waterproofing as per attached drawing and grid lines.
Rebar for stair ‐ 2 from 1st floor to 2nd floor. Please refer to the
HCNS-IR-CIVIL-0561 N/A 0 C B Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
attached key plan for your reference.
Form work for Stair‐2 from 1st floor to 2nd floor to proceed with
HCNS-IR-CIVIL-0562 N/A concrete casting. Please refer to the attached key plan for your 0 C A Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for stair‐2 from 1st floor
HCNS-IR-CIVIL-0563 N/A to 2nd floor. Please refer to the attached key plan for your 0 C B Ok L Grid J‐Stair‐2 Hotel 1st Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
reference.
Inspection Request of rebar for column at 3rd floor to proceed with
HCNS-IR-CIVIL-0564 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
form work. Please refer to the attached key plan for your reference.
Inspection request of form work for column at 3rd floor to proceed
HCNS-IR-CIVIL-0565 N/A with concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 5‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for column at 3rd floor.
HCNS-IR-CIVIL-0566 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request of rebar for wall at 3rd floor to proceed with form
HCNS-IR-CIVIL-0567 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
work. Please refer to the attached key plan for your reference.
Inspection request of form work for wall at 3rd floor to proceed with
HCNS-IR-CIVIL-0568 N/A concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 5‐Apr‐15 6‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for wall at 3rd floor.
HCNS-IR-CIVIL-0569 N/A 0 C B Ok L Grid R‐H / 13‐17 Hotel 3rd Floor UCC 1‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request for double layer waterproofing prior to screed as
HCNS-IR-CIVIL-0570 N/A 0 C B Ok L Grid 13‐14 / A‐J Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
per attached drawing and grid lines.
Inspection request for surface preparation and primer application
HCNS-IR-CIVIL-0571 N/A above blinding prior to water proofing as per attached drawing and 0 C B Ok L Grid 13‐14 / J‐T Bookstore UCC 2‐Apr‐15 5‐Apr‐15 Done
grid lines.
Inspection request for protection screed above double layer water
HCNS-IR-CIVIL-0572 N/A 0 C A Ok L Grid 13‐14 / A‐J Bookstore UCC 2‐Apr‐15 6‐Apr‐15 Done
proofing as per attached drawings grid lines.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request for back filling and compaction ( compaction test
HCNS-IR-CIVIL-0573 N/A 0 C B Ok L Grid 5‐7 / J‐T Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Inspection request of form work for ground floor slab to proceed
HCNS-IR-CIVIL-0574 N/A with concrete casting. Please refer to the attached key plan for your 0 C D Ok NL Grid A‐C / 2‐6 Hotel Ground floor UCC 2‐Apr‐15 6‐Apr‐15 Done
reference.
Inspection request of form work for ground floor slab to proceed
HCNS-IR-CIVIL-0574 N/A with concrete casting. Please refer to the attached key plan for your 1 C B Ok L Grid A‐C / 2‐6 Hotel Ground floor UCC 13‐Apr‐15 14‐Apr‐15 Done
reference.
Depth of drilled hole for planting rebar for stair‐3 from 3rd floor to
HCNS-IR-CIVIL-0575 N/A 0 C B Ok L Stair‐3 Hotel 3rd floor UCC 2‐Apr‐15 4‐Apr‐15 Done
4th floor. Please refer to the attached key plan for your reference.
Inspection request for raft rebar and formwork inspection prior to
HCNS-IR-CIVIL-0576 N/A 0 C B Ok L Grid 1‐7 / A‐K Bookstore UCC 2‐Apr‐15 5‐Apr‐15 Done
concrete as per attached drawing and grid lines.
Inspection request for concrete casting C40 for ground floor slab.
HCNS-IR-CIVIL-0577 N/A 0 C B Ok L Grid A‐C / 2‐6 Hotel Ground floor UCC 2‐Apr‐15 4‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request for concrete casting for raft as per attached
HCNS-IR-CIVIL-0578 N/A 0 C B Ok L Grid 1‐7 / A‐K Bookstore UCC 2‐Apr‐15 4‐Apr‐15 Done
drawing and grid lines.
Inspection request for surface preparation and primer application
HCNS-IR-CIVIL-0579 N/A above blinding prior to water proofing as per attached drawing and 0 C A Ok L Grid 5‐7 / J‐T Bookstore UCC 2‐Apr‐15 6‐Apr‐15 Done
grid lines.
Inspection request for double layer waterproofing prior to screed as
HCNS-IR-CIVIL-0580 N/A 0 C D Ok NL Grid 13‐14 / J‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
per attached drawing and grid lines.
Double layer of waterproofing membrane prior to screed as per
HCNS-IR-CIVIL-0580 N/A 1 C B Ok L Grid I‐T / 7‐13 Bookstore UCC 6‐Apr‐15 7‐Apr‐15 Done
attached drawing and grid lines.
Inspection Request for Backfilling & Compaction ( Compaction Test
HCNS-IR-CIVIL-0581 N/A 0 C B Ok L Grid ( S ‐ T / 1'‐8' ) Bookstore UCC 5‐Apr‐15 6‐Apr‐15 Done
will be done by third Party )
Rebar for column at 2nd floor to proceed with form work. Please
HCNS-IR-CIVIL-0582 N/A 0 C A Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 11‐Apr‐15 12‐Apr‐15 Done
refer to the attached key plan for your reference.
Formwork for column at 2nd floor to proceed with concrete casting.
HCNS-IR-CIVIL-0583 N/A 0 C D Ok NL Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Formwork for column at 2nd floor to proceed with concrete casting.
HCNS-IR-CIVIL-0583 N/A 1 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 13‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection reqest for concrete casting C40 column at 2nd floor.
HCNS-IR-CIVIL-0584 N/A 0 C D Ok NL Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection reqest for concrete casting C40 column at 2nd floor.
HCNS-IR-CIVIL-0584 N/A 1 C A Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 13‐Apr‐15 14‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Rebar for wall at 2nd floor to proceed with form work. Please refer
HCNS-IR-CIVIL-0585 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
to the attched key plan for your reference.
Formwork for wall at 2nd floor to proceed with concrete casting.
HCNS-IR-CIVIL-0586 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 15‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request for concrete casting C40 for wall at 2nd floor.
HCNS-IR-CIVIL-0587 N/A 0 C B Ok L Grid H‐R / 1‐4 Hotel 2nd floor UCC 15‐Apr‐15 16‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request of rebar for mezz. Floor slab. Please refer to the
HCNS-IR-CIVIL-0588 N/A 0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
attached key plan for your reference.
Inspection request of form work for mezz. Floor slab to proceed with
HCNS-IR-CIVIL-0589 N/A concrete casting . Please refer to the attached key plan for your 0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for mezz. Floor slab.
HCNS-IR-CIVIL-0590 N/A 0 C B Ok L Grid H‐A / 1‐4 Mezz. Floor UCC 21‐Apr‐15 22‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request for structural repairing for external column,
HCNS-IR-CIVIL-0591 N/A 0 C D Ok NL N/7‐19 , A‐N / 19 , A‐N / 7 Old Souq UCC 5‐Apr‐15 5‐Apr‐15 Done
Beams, Arch wall and parapet wall. See attached layout
Inspection request for structural repairing for external column,
HCNS-IR-CIVIL-0591 N/A 1 C A Ok L N/7‐19 , A‐N / 19 , A‐N / 7 Old Souq UCC 6‐Apr‐15 9‐Apr‐15 Done
Beams, Arch wall and parapet wall. See attached layout
Inspection request for back filling and compaction ( compaction test
HCNS-IR-CIVIL-0592 N/A 0 C D Ok NL 13‐15 / A‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Inspection request for back filling and compaction ( compaction test
HCNS-IR-CIVIL-0592 N/A 1 C A Ok L Grid S‐T / 1'‐8' Bookstore UCC 6‐Apr‐15 7‐Apr‐15 Done
by third party ) as per attached drawing and grid lines.
Inspection request for blinding concrete above top layer as per
HCNS-IR-CIVIL-0593 N/A 0 C B Ok L Grid 13‐15 / A‐T Bookstore UCC 4‐Apr‐15 6‐Apr‐15 Done
attached drg and grid lines.
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request of rebar for stair‐3 at 3rd to 4th floor. Please Staircase ‐ 3 3rd floor to 4th floor Hotel 3rd
HCNS-IR-CIVIL-0598 N/A 0 C A Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
refer to the attached key plan for your reference. floor
Inspection request of form work for stair‐3 at 3rd to 4th floor to
Staircase ‐ 3 3rd floor to 4th floor Hotel 3rd
HCNS-IR-CIVIL-0599 N/A proceed with concrete casting. Please refer to the attached key plan 0 C A Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
floor
for your reference.
Inspection request for concrete casting C40 for stair‐3 at 3rd to 4th Staircaise‐3 3rd floor to 4th floor Hotel 3rd
HCNS-IR-CIVIL-0600 N/A 0 C B Ok L UCC 5‐Apr‐15 7‐Apr‐15 Done
floor. Please refer to the attached key plan for your reference. floor
Inspection request for raft rebar and formwork inspection prior to
HCNS-IR-CIVIL-0601 N/A 0 C B Ok L Grid ( 13‐14 / A ‐ T ) Bookstore UCC 7‐Apr‐15 9‐Apr‐15 Done
concrete as per attached drawing and grid lines.
Double layer of waterproofing membrane prior to screed as per
HCNS-IR-CIVIL-0603 N/A 0 C A Ok L Grid P‐T / 5‐7 Bookstore UCC 7‐Apr‐15 8‐Apr‐15 Done
attached drawing and grid lines.
Inspection Request for first floor beam rebar inspection as per
HCNS-IR-CIVIL-0604 N/A 0 C A Ok L Grid 4‐13 / A‐J Bookstore UCC 7‐Apr‐15 9‐Apr‐15 Done
attached drawing and grid lines.
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Installation of waterproofing membrane MASTERPREN.BG on raft
HCNS-IR-CIVIL-0616 N/A and wall prior to proceed with protection board. Please refer to the 0 C A Ok L Grid G‐H / 6 Hotel Basement UCC 9‐Apr‐15 9‐Apr‐15 Done
attached key plan for your refrence.
Depth of drilled hole for planting rebar for stair‐3 from 4th floor to
HCNS-IR-CIVIL-0617 N/A 0 C A Ok L Stair ‐3 Hotel 4th floor UCC 9‐Apr‐15 9‐Apr‐15 Done
roof. Please refer to the attached key plan for your reference.
Depth of drilled hole for planting rebar for stair‐4 from basement to
HCNS-IR-CIVIL-0618 N/A ground floor. Please refer to the attached key plan for your 0 C A Ok L Stair‐4 Hotel Basement floor UCC 11‐Apr‐15 12‐Apr‐15 Done
reference.
Inspection request of rebar for stair‐3 at 4th floor roof. Please refer
HCNS-IR-CIVIL-0619 N/A 0 C A Ok L Staircase‐3 4th floor roof Hotel 4th floor UCC 11‐Apr‐15 12‐Apr‐15 Done
to the attached key plan for your reference.
Inspection request of formwork for stair‐3 at 4th floor to roof to
HCNS-IR-CIVIL-0620 N/A proceed with concrete casting. Please refer to the attached key plan 0 C A Ok L Staircase‐3 4th floor roof Hotel 4th floor UCC 11‐Apr‐15 12‐Apr‐15 Done
for your reference.
Inspection request concrete casting C40 for stair‐3 at 4th floor to
HCNS-IR-CIVIL-0621 N/A 0 C A Ok L Staircase ‐3 4th floor to roof Hotel 4th floor. UCC 11‐Apr‐15 13‐Apr‐15 Done
roof. Please refer to the attached key plan for your reference.
Witness inspection request for compaction test ( 1st layer ) . Please
HCNS-IR-CIVIL-0622 N/A 0 C D Ok NL Grid C‐J / 6‐7 Hotel UCC 11‐Apr‐15 12‐Apr‐15 Done
refer to the attached key plan for your reference.
Witness inspection request for compaction test ( 1st layer ) . Please
HCNS-IR-CIVIL-0622 N/A 1 C A Ok L Grid C‐J / 6‐7 Hotel UCC 12‐Apr‐15 13‐Apr‐15 Done
refer to the attached key plan for your reference.
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Witness inspection request of grouting for PT slab 2nd Floor. Please
HCNS-IR-CIVIL-0628 N/A 0 C D Ok NL Grid J‐R / 4‐15 Hotel 2nd floor UCC 12‐Apr‐15 13‐Apr‐15 Done
refer to the attached key plan for your reference.
Witness inspection request of grouting for PT slab 2nd Floor. Please
HCNS-IR-CIVIL-0628 N/A 1 C B Ok L Grid J‐R / 4‐15 Hotel 2nd floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.
Witness inspection request for compaction test ( 2nd layer ) . Please
HCNS-IR-CIVIL-0629 N/A 0 C A Ok L Grid C‐J / 6‐7 Hotel UCC 13‐Apr‐15 14‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection request for drilling & grouting for steel bars in staircase
HCNS-IR-CIVIL-0630 N/A 0 C A Ok L Grid ( I‐J / 7 ) Bookstore UCC 13‐Apr‐15 14‐Apr‐15 Done
mid landing.
Grid ground floor 8‐10 / N‐P Hotel Ground
HCNS-IR-CIVIL-0631 N/A Inspection for Drill hole Depth for ( 16mm ) rebar 0 C B Ok L UCC 13‐Apr‐15 14‐Apr‐15 Done
Floor
Inspection request of rebar for 4th floor slab. Please refer to the
HCNS-IR-CIVIL-0632 N/A 0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
attached key plan for your reference.
Inspection request of form work for 4th floor slab to proceed with
HCNS-IR-CIVIL-0633 N/A concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for 4th floor slab. Please
HCNS-IR-CIVIL-0634 N/A 0 C B Ok L Grid R‐J / 14‐17 Hotel 4th floor UCC 13‐Apr‐15 14‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection Request of rebar for pour strip at 3rd floor. Please refer
HCNS-IR-CIVIL-0636 N/A 0 C B Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
to the attached key plan for your reference.
Inspection request of form work for pour strip at 3rd floor to
HCNS-IR-CIVIL-0637 N/A proceed with concrete casting. Please refer to the attached key plan 0 C A Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
for your reference.
Inspection Request for concrete Casting C40 for pour strip at 3rd
HCNS-IR-CIVIL-0638 N/A 0 C B Ok L Grid J‐R / 14‐15 Hotel 3rd Floor UCC 14‐Apr‐15 15‐Apr‐15 Done
floor. Please refer to the attached key plan for your reference.
Inspection request of Rebar for column at ground floor to proceed
HCNS-IR-CIVIL-0639 N/A with formwork. Please refer to the attached key plan for your 0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
reference.
Inspection request of rebar for column at 4th floor to proceed with
HCNS-IR-CIVIL-0640 N/A 0 C A Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 15‐Apr‐15 16‐Apr‐15 Done
formwork. Please refer to the attached key plan for your reference.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request for rebar and shutter at ground floor as per Grid Ground floor 8‐10 / N , 10/ N‐P Hotel
HCNS-IR-CIVIL-0643 N/A 0 C B Ok L UCC 14‐Apr‐15 23‐Apr‐15 Done
highlighted key plan Ground floor
Inspection request of rebar for wall at ground floor to proceed with
HCNS-IR-CIVIL-0644 N/A 0 C U/R U/R L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15
formwork. Please refer to the attached key plan for your reference.
Inspection request of formwork for column at ground floor C1 ‐ 02
HCNS-IR-CIVIL-0648 N/A No, C2 ‐ 04 No, C15 ‐ 01 No, to proceed with concrete casting. Please 0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection request for concrete casting C40 for column C1‐02 No, C2‐
HCNS-IR-CIVIL-0649 N/A 04 No, C15 ‐ 01 No , at Ground floor. Please refer to the attached 0 C D Ok NL Grid A‐B / 2‐5 Hotel Ground floor UCC 15‐Apr‐15 16‐Apr‐15 Done
Key plan for your reference.
Inspection request for concrete casting C40 for column C1‐02 No, C2‐
HCNS-IR-CIVIL-0649 N/A 04 No, C15 ‐ 01 No , at Ground floor. Please refer to the attached 1 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
Key plan for your reference.
Inspection request of formwork for column at 4th floor C11‐03 No ,
HCNS-IR-CIVIL-0650 N/A C33‐01 no, C34 ‐ 01 No, to proceed with concrete casting. Please 0 C B Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection request for concrete casting C40 for column at 4th floor
HCNS-IR-CIVIL-0651 N/A C11‐03 No , C33‐01 No , C3A ‐ 01 No . Please refer to the attached 0 C B Ok L Grid K‐Q / 15‐17 Hotel 4th floor UCC 16‐Apr‐15 23‐Apr‐15 Done
key plan for your reference.
Inspection request of formwork for wall at ground floor to proceed
HCNS-IR-CIVIL-0652 N/A with concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
reference.
Inspection request for concrete C40 for wall at ground floor. Please
HCNS-IR-CIVIL-0653 N/A 0 C D Ok NL Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 16‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection request for concrete C40 for wall at ground floor. Please
HCNS-IR-CIVIL-0653 N/A 1 C B Ok L Grid A‐B / 2‐5 Hotel Ground floor UCC 16‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request of rebar for stair‐4 at basement to ground floor.
HCNS-IR-CIVIL-0656 N/A 0 C A Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request of formwork for stair‐4 at basement to ground
HCNS-IR-CIVIL-0657 N/A floor to proceed with concrete casting. Please refer to the attached 0 C B Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
key plan for your reference.
Inspection request for concrete casting C40 for stair‐4 at basement
HCNS-IR-CIVIL-0658 N/A to ground floor. Please refer to the attached key plan for your 0 C B Ok L Staircase‐4 basement to ground floor Hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.
Inspection for columns formwork ( from Mezzanine to first floor
HCNS-IR-CIVIL-0660 N/A columns ) as per attached drawings [ 3 columns ( C16 ) and One 0 C B Ok L Grid ( 1 / A‐E ) Bookstore UCC 19‐Apr‐15 20‐Apr‐15 Done
Column ( C16A ) ]
Casting concrete for 4 Columns ( From Mezzanine to first floor ) as
HCNS-IR-CIVIL-0661 N/A 0 C B Ok L Grid ( A‐E / 1 ) Bookstore UCC 19‐Apr‐15 20‐Apr‐15 Done
per attached drawing [ 3 Columns ( C16 ) and one Column ( C16A ) ]
Inspection for first floor slab and beams formwork including
HCNS-IR-CIVIL-0663 N/A 0 C B Ok L Grid ( I‐T / 6‐14 ) Bookstore UCC 19‐Apr‐15 21‐Apr‐15 Done
staircase
Depth of Drilled hole for planting rebar at 1st floor slab. Please refer
HCNS-IR-CIVIL-0666 N/A 0 C D Ok L Grid Y2 ‐Y'2 / X1‐X5 Hotel 1st Floor UCC 19‐Apr‐15 20‐Apr‐15 Done
to the attached key plan for your reference.
Depth of Drilled hole for planting rebar at 1st floor slab. Please refer
HCNS-IR-CIVIL-0666 N/A 1 C A Ok L Grid Y2 ‐Y'2 / X1‐X5 Hotel 1st Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
to the attached key plan for your reference.
Inspection request for steel rebars for columns from mezzanine floor
HCNS-IR-CIVIL-0668 N/A to first floor columns ( as per attached drawing) ( 3 columns C18 & 1 0 C B Ok L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15 23‐Apr‐15 Done
column C17 and C108 and NC1 ( 40cm x 40cm )
Inspection request for columns from mezzanine floor to first floor
HCNS-IR-CIVIL-0669 N/A columns ( as per attached drawing ) ( 3 columns C18 & 1 column C17 0 C B Ok L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15 23‐Apr‐15 Done
and C108 and NC1 ( 40cm x 40cm )
Casting Concrete for columns from mezzanine floor to first floor
HCNS-IR-CIVIL-0670 N/A columns ( as per attached drawing ) ( 3 columns C18 & 1 column C17 0 C U/R U/R L Grid ( 2 / B‐E ) Bookstore UCC 21‐Apr‐15
and C108 and NC1 ( 40cm x 40cm )
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Installation of Waterproofing membrane MASTERPREN.BG on
HCNS-IR-CIVIL-0671 N/A external face of retaining wall prior to proceed with protection 0 C A Ok L Grid A‐C / 6 & A / 2‐6 Hotel Basement UCC 22‐Apr‐15 23‐Apr‐15 Done
board. Please refer to the attached key plan for your reference.
Inspection Request of rebar for 3rd floor slab. Please refer to the
HCNS-IR-CIVIL-0672 N/A 0 C B Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
attached key plan for your reference.
Inspection request of formwork for 3rd floor slab to proceed with
HCNS-IR-CIVIL-0673 N/A concrete casting. Please refer to the attached key plan for your 0 C A Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.
Inspection request for concrete casting C40 for 3rd floor slab. Please
HCNS-IR-CIVIL-0674 N/A 0 C B Ok L Grid R‐G / 1‐4 Hotel 3rd floor UCC 22‐Apr‐15 23‐Apr‐15 Done
refer to the attached key plan for your reference.
Inspection request for column , wall rebar from first floor level to
HCNS-IR-CIVIL-0675 N/A second floor slab as per attached drawing and grid lines ( C1B‐3, C9‐ 0 C B Ok L Grid ( I ‐ T / 6‐14 ) Bookstore UCC 23‐Apr‐15 25‐Apr‐15 Done
1 , C1‐6 , C10‐2, C6‐8 , CW5‐1 , W6‐1 , C12‐1 , C10A‐1 , C4A‐2 )
Inspection request for rebar for 4th floor PT slab. Please refer to the
HCNS-IR-CIVIL-0676 N/A 0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
attached key plan for your reference.
Inspection request for formwork for 4th floor pt slab to proceed with
HCNS-IR-CIVIL-0677 N/A concrete casting. Please refer to the attached key plan for your 0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
reference.
Inspection request for concrete casting C50 for 4th floor PT slab.
HCNS-IR-CIVIL-0678 N/A 0 C B Ok L Grid J‐R / 4‐15 4th floor hotel UCC 22‐Apr‐15 23‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Rebar for column at mezz. Floor to proceed with form work. Please
HCNS-IR-CIVIL-0679 N/A refer to the attached key plan for your reference. ( C1‐05nos , C2‐07 0 C B Ok L Grid A‐G / 2‐5 Hotel Mezz. Floor UCC 23‐Apr‐15 25‐Apr‐15 Done
nos , C16‐02nos , C15‐05 nos , C22‐01 nos )
Grid Ground floor 9/N ‐ Q & 13‐14 / L ,
HCNS-IR-CIVIL-0680 N/A Inspection request for Drill hole depth as per highlighted Key plan. 0 C D D NL second floor 6 / L & 8‐L Hotel ground floor UCC 23‐Apr‐15 25‐Apr‐15
and second floor
Grid Ground floor 9/N ‐ Q & 13‐14 / L ,
HCNS-IR-CIVIL-0680 N/A Inspection request for Drill hole depth as per highlighted Key plan. 1 C U/R U/R L second floor 6 / L & 8‐L Hotel ground floor UCC 29‐Apr‐15
and second floor
Rebar for column at mezz. Floor to proceed with form work. Please
HCNS-IR-CIVIL-0681 N/A refer to the attached key plan for your reference. ( C16‐01 no , C15‐ 0 C A Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 25‐Apr‐15 Done
02 nos )
Formwork for column at mezz. Floor to proceed with concrete
HCNS-IR-CIVIL-0682 N/A casting. Please refer to the attached key plan for your reference. ( C1‐ 0 C A Ok L Grid A‐G / 2‐4 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
05 nos , C2‐07 nos , C16‐01 nos , C15‐03 nos , C22‐01 no )
Inspection request for concrete casting C40 for column at Mezz.
HCNS-IR-CIVIL-0683 N/A Floor. Please refer to the attached key plan for your reference. ( C1‐ 0 C B Ok L Grid A‐G / 2‐4 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
05nos , C2‐07 nos , C16‐01 nos, C15‐03 nos, C22‐01 no )
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Rebar for column at 4th floor to proceed with formwork. Please
HCNS-IR-CIVIL-0684 N/A refer to the attached key plan for your reference. ( C1‐02 nos, C14‐ 0 C B Ok L Grid L‐Q / 5‐13 Hotel 4th floor UCC 25‐Apr‐15 26‐Apr‐15 Done
02 nos, C12‐05 nos , C11‐01 no , C29‐08 nos , C30‐01 no , C14‐01 no )
Inspection request for first floor rebar for slab, beam and stair. As
HCNS-IR-CIVIL-0685 N/A 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
per attached drawing and grid lines.
Inspection request for first floor formwork for slab, beam and stair
HCNS-IR-CIVIL-0686 N/A 0 C A Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
prior to concrete as per attached drawing and grid lines.
Inspection request for first floor concrete for slab, beam and stair as
HCNS-IR-CIVIL-0687 N/A 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
per attached drawing and grid lines.
Inspection for column rebar ( 1 column C1 , 2 columns C10 , 1
HCNS-IR-CIVIL-0688 N/A columns C5 , 2 columns C4A , 1 columns CW 5 , 1 columns C10A , 1 0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 28‐Apr‐15 Done
columns C10C ) From first floor to second floor level.
Inspection for formwork for the following columns ( 4 columns C1 , 3
HCNS-IR-CIVIL-0689 N/A columns C1B , 1 columns C9 , 6 column C8 ) from first floor level to 0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 26‐Apr‐15 Done
second floor level.
Concrete Casting for the following columns ( 4 columns C1 , 3
HCNS-IR-CIVIL-0690 N/A Columns C1B , 1 column C9 , 6 column C8 ) from first floor level to 0 C B Ok L Grid J‐T / 6‐14 Bookstore UCC 25‐Apr‐15 27‐Apr‐15 Done
second floor level.
Formwork for column at mezz. Floor to proceed with concrete
HCNS-IR-CIVIL-0693 N/A casting. Please refer to the attached key plan for your reference. ( 0 C A Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
C16‐01 nos , C15‐02 nos )
Inspection request for concrete casting C40 for column at Mezz.
HCNS-IR-CIVIL-0694 N/A Floor. Please refer to the attached key plan for your reference. ( C16‐ 0 C B Ok L Grid A‐C / 5 Hotel Mezz. Floor UCC 25‐Apr‐15 27‐Apr‐15 Done
01 no , C15‐02 nos )
Formwork for column at 4th floor to proceed with concrete casting.
HCNS-IR-CIVIL-0695 N/A Please refer to the attached key plan for your reference. ( C1‐02 nos, 0 C A Ok L Grid J‐Q / 5‐13 Hotel 4th. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
C12‐04 nos , C11‐01 no , C29‐05 nos )
Inspection request for concrete casting C40 for column at 4th floor.
HCNS-IR-CIVIL-0696 N/A Please refer to the attached key plan for your reference. ( C1‐02 nos 0 C B Ok L Grid J‐Q / 5‐13 Hotel 4th. Floor UCC 25‐Apr‐15 26‐Apr‐15 Done
, C12‐04 nos , C11‐01 no , C29‐05 nos )
Rebar for column at 4th floor to proceed with formwork . Please
HCNS-IR-CIVIL-0699 N/A refer to the attached key plan for your reference ( C11‐05nos, C18A ‐ 0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
01 no, C12‐01 no , C14‐03 nos , C33‐01no , C30‐10 no , PC1‐04nos )
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Rebar for wall at 4th floor to proceed with formwork . Please refer to
HCNS-IR-CIVIL-0700 N/A the attached key plan for your reference. ( SW1‐01 nos & SW2‐01 no 0 C B Ok L Grid K‐Q / 10 Hotel 4th floor UCC 26‐Apr‐15 28‐Apr‐15 Done
)
Rebar for wall at Mezz. Floor to proceed with formwork. Please refer
HCNS-IR-CIVIL-0701 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 26‐Apr‐15 28‐Apr‐15 Done
to the attached key plan for your reference. ( CW7‐01 no )
Inspection request for rebar for stair‐1 from ground to mezz.floor.
HCNS-IR-CIVIL-0702 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 28‐Apr‐15 Done
Please refer to the attached key plan for your reference.
Inspection request for formwork for stair‐1 from ground to
HCNS-IR-CIVIL-0703 N/A mezz.floor to proceed with concrete casting. Please refer to the 0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 28‐Apr‐15 Done
attached key plan for your reference.
Inspection request for concrete casting C40 for stair‐1 from ground
HCNS-IR-CIVIL-0704 N/A 0 C B Ok L Grid E‐F / 1‐3 Hotel Ground floor. UCC 26‐Apr‐15 27‐Apr‐15 Done
to mezz. Please refer to the attached key plan for your reference.
Installation of waterproofing membrane MASTERPREN.BG on raft
HCNS-IR-CIVIL-0705 N/A prior to proceed with protection board. Please refer to the attached 0 C B Ok L Grird A‐C / 6 & A / 2‐6 Hotel basement UCC 26‐Apr‐15 27‐Apr‐15 Done
key plan for your reference.
Inspection for corewall rebar ( CW4 and W6 ) , and for columns rebar
HCNS-IR-CIVIL-0706 N/A 0 C D D NL Grid I‐T / 6‐14 Bookstore UCC 27‐Apr‐15 28‐Apr‐15
( C6 and C12 )
Inspection for corewall rebar ( CW4 and W6 ) , and for columns rebar
HCNS-IR-CIVIL-0706 N/A 1 C U/R U/R L Grid I‐T / 6‐14 Bookstore UCC 28‐Apr‐15
( C6 and C12 )
Inspection request for formwork for columns ( 6 columns C6 , 2
HCNS-IR-CIVIL-0707 N/A columns C4a , 1 CW 5 , 1 C10a , 1 column C10c ) from first floor level 0 C D Ok NL Grid J‐T / 6‐13 Bookstore UCC 26‐Apr‐15 28‐Apr‐15 Done
to second floor level.
Inspection request for formwork for columns ( 6 columns C6 , 2
HCNS-IR-CIVIL-0707 N/A columns C4a , 1 CW 5 , 1 C10a , 1 column C10c ) from first floor level 1 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 28‐Apr‐15 29‐Apr‐15 Done
to second floor level.
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Concrete Casting for columns ( 6 columns C6 , 2 columns C4a , 1 CW
HCNS-IR-CIVIL-0708 N/A 0 C D Ok NL Grid J‐T / 6‐13 Bookstore UCC 26‐Apr‐15 28‐Apr‐15 Done
5 , 1 C10a , 1 column C10c ) from first floor to second floor level.
Concrete Casting for columns ( 6 columns C6 , 2 columns C4a , 1 CW
HCNS-IR-CIVIL-0708 N/A 1 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 28‐Apr‐15 29‐Apr‐15 Done
5 , 1 C10a , 1 column C10c ) from first floor to second floor level.
Formwork for column at 4th floor to proceed with concrete casting.
Please refer to the attached key plan for your reference. ( C11‐
HCNS-IR-CIVIL-0709 N/A 0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 28‐Apr‐15 Done
05nos, C12‐02nos, C14‐04nos , C29‐03nos, C18A‐01no, C30‐01no ,
C33‐01no , PC1‐04 nos )
Inspection request for concrete casting C40 for column at 4th floor.
Please refer to the attached key plan for your reference. ( C11‐05nos
HCNS-IR-CIVIL-0710 N/A 0 C B Ok L Grid K‐Q / 4‐14 Hotel 4th. Floor UCC 26‐Apr‐15 27‐Apr‐15 Done
, C12‐02nos , C14‐04nos , C29‐03nos , C18A‐01 No , C30‐01no , C33‐
01 no , PC1‐04 nos )
Rebar for wall at 4th floor to proceed with formwork . Please refer to
HCNS-IR-CIVIL-0711 N/A the attached key plan for your reference. ( CW1‐01no , CW2‐01 no , 0 C B Ok L Grid J‐Q / 13‐15 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
SW2‐01 no )
Formwork for wall at 4th floor to proceed with concrete casting.
HCNS-IR-CIVIL-0712 N/A Please refer to the attached key plan for your reference. ( SW1‐01 no 0 C A Ok L Grid K‐Q / 10 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
& SW2‐01 no )
Inspection request for concrete casting C40 for wall at 4th floor.
HCNS-IR-CIVIL-0713 N/A Please refer to the attached key plan for your reference. ( SW1‐01 no 0 C B Ok L Grid K‐Q / 10 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
& SW2‐01 no )
Inspection request for column rebar from first floor level to second
HCNS-IR-CIVIL-0714 N/A floor as per attached drawing and grid lines ( C1‐9 , C1C‐2 , C2‐2 , C3‐ 0 C B Ok L Grid 1‐14 / A ‐ J Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
1 , C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7 ‐2, C10B‐1 )
Inspection request for column shutter from first floor level to second
HCNS-IR-CIVIL-0715 N/A floor as per attached drawing and grid lines ( C1‐9, C1C‐2 , C2‐2 , C3‐ 0 C U/R U/R L Grid 1‐14 / A ‐ J Bookstore UCC 28‐Apr‐15
1 , C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7‐2 , C10B‐1 )
Inspection Request for column casting from first floor level to second
HCNS-IR-CIVIL-0716 N/A floor as per attached drawing and grid lines ( C1‐9 , C1C‐2 , C2‐2 , C3‐ 0 C U/R U/R L Grid 1‐14 / A ‐ J Bookstore UCC 28‐Apr‐15
1 ,C5‐1 , C4‐1 , C4A‐1 , C4B‐1 , C10‐3 , C1D‐1 , W7‐2 , C10B‐1 )
Inspection for formwork for columns ( 2 columns C10 , 1 column C1 ,
HCNS-IR-CIVIL-0720 N/A 1 column C5 and 1 column C6 ) from first floor level to second floor 0 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
level.
Concrete casting for columns ( 2 columns C10 , 1 column C1 , 1
HCNS-IR-CIVIL-0721 N/A column C5 and 1 column C6 ) from first floor level to second floor 0 C B Ok L Grid J‐T / 6‐13 Bookstore UCC 27‐Apr‐15 29‐Apr‐15 Done
level.
Rebar for column at 3rd floor to proceed with form work. Please
HCNS-IR-CIVIL-0722 N/A refer to the attached key plan for your reference. ( C11‐11 nos , C12‐ 0 C B Ok L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 27‐Apr‐15 29‐Apr‐15 Done
02 nos, C1‐01 no )
Formwork for wall at 4th floor to proceed with concrete casting.
HCNS-IR-CIVIL-0723 N/A Please refer to the attached key plan for your reference. ( SW2‐01no 0 C A Ok L Grid J‐M / 13 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
)
Civil Inspection Request
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 HCNS As of: 13‐May‐15
Inspection request for concrete casting C40 for wall at 4th floor.
HCNS-IR-CIVIL-0724 N/A Please refer to the attached key plan for your reference. ( SW2‐01 no 0 C B Ok L Grid J‐M / 13 Hotel 4th floor UCC 27‐Apr‐15 28‐Apr‐15 Done
)
Witness inspection request for compaction test ( 1st layer ) . Please
HCNS-IR-CIVIL-0725 N/A 0 C D D NL Grid C‐A / 3‐7 Hotel UCC 28‐Apr‐15 29‐Apr‐15
refer to the attached key plan for your reference.
Witness inspection request for compaction test ( 1st layer ) . Please
HCNS-IR-CIVIL-0725 N/A 1 C U/R U/R L Grid C‐A / 3‐7 Hotel UCC 29‐Apr‐15
refer to the attached key plan for your reference.
Formwork for column at 3rd floor to proceed with Concrete casting.
HCNS-IR-CIVIL-0726 N/A 0 C U/R U/R L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
Please refer to the attached key plan for your reference.
Inspection request for concrete casting C40 for column at 3rd floor.
HCNS-IR-CIVIL-0727 N/A Please refer to the attached key plan for your reference. ( C11‐11nos 0 C U/R U/R L Grid H‐Q / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
, C12‐02 nos , C1‐01 no )
Inspection request of rebar for wall at 3rd floor to proceed with form
HCNS-IR-CIVIL-0728 N/A work. Please refer to the attached key plan for your reference. ( CW6‐ 0 C U/R U/R L Grid K‐M / 1‐4 Hotel 3rd floor UCC 28‐Apr‐15
01no )
Inspection Request of rebar for stair‐2 from 2nd floor to 3rd floor.
HCNS-IR-CIVIL-0729 N/A 0 C D D L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15 29‐Apr‐15
Please refer to the attached key plan for your reference.
Inspection request of formwork for stair‐2 from 2nd floor to 3rd
HCNS-IR-CIVIL-0730 N/A floor to proceed with concrete casting. Please refer to the attached 0 C D D L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15 29‐Apr‐15
key plan for your reference.
Inspection request for concrete casting C40 for stair‐2 from 2nd floor
HCNS-IR-CIVIL-0731 N/A 0 C U/R U/R L Grid Stair‐2 Hotel 2nd floor UCC 28‐Apr‐15
to 3rd floor. Please refer to the attached key plan for your reference.
Inspection requet of rebar for 1st floor slab besides swimming pool.
HCNS-IR-CIVIL-0732 N/A 0 C D D L Grid Y3‐Y7 / X1‐X6 Hotel 1st Floor UCC 28‐Apr‐15 29‐Apr‐15
Please refer to the attached key plan for your reference.
Formwork for wall at 4th floor to proceed with concrete casting.
HCNS-IR-CIVIL-0733 N/A Please refer to the attached key plan for your reference. ( CW2‐01no 0 C U/R U/R L Grid Q‐N / 13‐15 Hotel 4th floor UCC 29‐Apr‐15
& CW1‐01no )
Inspection request for concrete casting C40 for wall at 4th floor.
HCNS-IR-CIVIL-0734 N/A Please refer to the attached key paln for your reference . ( CW2‐ 0 C U/R U/R L Grid Q‐N / 13‐15 Hotel 4th floor UCC 29‐Apr‐15
01no & CW1‐01 no )
Formwork for wall at mezz. Floor to proceed with concrete casting.
HCNS-IR-CIVIL-0735 N/A Please refer to the attached key plan for your reference. ( CW7‐01no 0 C U/R U/R L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 29‐Apr‐15
)
Inspection request for concrete casting C40 for wall at mezz. Floor .
HCNS-IR-CIVIL-0736 N/A Please refer to the attached key plan for your reference. ( CW7‐01 0 C U/R U/R L Grid E‐F / 1‐3 Hotel Mezz. Floor UCC 29‐Apr‐15
no )
Inspection for formwork for columns ( C6 , C12 and Shear wall W6 )
HCNS-IR-CIVIL-0740 N/A 0 C U/R U/R L Grid R‐T / 5‐7 Bookstore UCC 29‐Apr‐15
from first floor level to second floor level.
Concrete Casting for columns ( C6 , C12 and Shear wall W6 ) from
HCNS-IR-CIVIL-0741 N/A 0 C U/R U/R L Grid R‐T / 5‐7 Bookstore UCC 29‐Apr‐15
first floor leve to second floor level.
Rebar for Beam at 4th floor to proceed with formwork. Please refer
HCNS-IR-CIVIL-0742 N/A 0 C U/R U/R L Grid J / 6‐9 Hotel 4th floor UCC 29‐Apr‐15
to the attached key plan for your reference.
MEP Inspection Request (Mechanical)
Approved A
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
Installation of PVC conduits and Boxes for small power & RMS
HCNS-IR-MEP-E- Hotel fourth column ( Gridline: H-R / 15-
N/A at fourth floor column. ( Gridline H-R / 15-17 ) as per attached 0 E B L UCC 15-Apr-15 16-Apr-15 Done
0049 17 )
highlighted drawings.
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
Approved as Noted B
Not Approved C
Revise & Resubmit D
Under Review U/R U‐295‐295‐14 SNRCP As of: 13‐May‐15
Updated On :
MDIR No. Rev. Discipline Project Delivery Note No. Description Manufacture/ Supplier Sub. Date Reply. Date Status with Dar Status
Updated On :
MDIR No. Rev. Discipline Project Delivery Note No. Description Manufacture/ Supplier Sub. Date Reply. Date Status with Dar Status
13 MDIR-E-0014 N/A PVC conduit pipe 25mm 0 E A L HCNS UCC 1-Apr-15 4-Apr-15 done
14 MDIR-E-0015 N/A PVC Pipes and Fittings. 0 E B L HCNS UCC 4-Apr-15 5-Apr-15
Updated On :
Manufacture/
MDIR No. Rev. Discipline Project Delivery Note No. Description Sub. Date Reply. Date Status with Dar Status
Supplier
MDIR-MEP-0006 M HCNS Thermobreak Insulation Thermobreak Satisfactory
0 3264 15-Apr-2015 19-Apr-2015 A - Accepted
MDIR-MEP-0007 M HCNS UPVC Drainage pipes-above ground Pipes-Tech Satisfactory
0 15198 / 15176 16-Apr-2015 22-Apr-2015 A - Accepted
MDIR-MEP-0008 M HCNS Hangers and Supports Leminar / Weicco Satisfactory
0 15854 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0009 M HCNS Hilti Materials-Hangers , Supports and accessories Hilti Satisfactory
0 76321 & 76322 20-Apr-2015 22-Apr-2015 A - Accepted
MDIR-MEP-0010 M HCNS Aspen Aluminium Tapes Aspen Satisfactory
0 CR-583 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0011 M HCNS PPR Pipes and fittings. Aquatherm Satisfactory
0 CR-1201 22-Apr-2015 23-Apr-2015 A - Accepted
MDIR-MEP-0012 M HCNS GI Duct Nippon Satisfactory
0 22042015 23-Apr-2015 25-Apr-2015 A - Accepted
Under Review U/R U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
MS Submittal Ref. Document Ref L/N Area of Specialty of Date Pending Date
SN Rev Title Rev Disc Status Specialty Zone Originator Remarks
No. No. L Location Works Submitte days Commente
Internal and
Method Statement for Internal and External Internal and
27 U29529514-HCNS/MS/0022 0 MS-A-0002 0 A B L General General External UCC 4‐Apr‐15 9‐Apr‐15 Done
Plastering External Plastering
Plastering
B
Method Statement for the Installation of UPVC Drainage Pipes and Installation of UPVC Drainage Installation of UPVC
28 U29529514-HCNS/MS/0023 0 MS‐M‐0009 0 MEP‐M L General General Radiant 5‐Apr‐15 8‐Apr‐15 Done
Fittings Pipes and Fittings Drainage Pipes and Fittings
Installation of
Installation of Polypropylene
B
Method Statement for the Installation of Polypropylene (PPR) Pipes Polypropylene (PPR) Pipes
29 U29529514-HCNS/MS/0024 0 MS‐M‐0002 0 MEP‐M L (PPR) Pipes and Fittings for General General Radiant 5‐Apr‐15 8‐Apr‐15 Done
and Fittings for Water System and Fittings for Water
Water System
System
U/R
REE‐HCNS‐DT‐0079
30 U29529514‐HCNS/MS/0025 0 Method Statement ‐ Installation of Fire Pumps 0 MEP L Installation of Fire Pumps General General Installation of Fire Pumps Radiant 7‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0012
Method Statement ‐
U/R
REE‐HCNS‐DT‐0081 Method Statement ‐
31 U29529514‐HCNS/MS/0026 0 Method Statement ‐ Instalaltion of Sanitary Wares 0 MEP L General General Instalaltion of Sanitary Radiant 7‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0013 Instalaltion of Sanitary Wares
Wares
Method Statement ‐ Method Statement ‐
B
REE‐HCNS‐DT‐0089 Method Statement ‐ Installation and Testing of Fire Fighting Pipes, Installation and Testing of Fire Installation and Testing of
32 U29529514‐HCNS/MS/0027 0 0 MEP L General General Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0011 Fittings, Sprinkles and Air Vents Fighting Pipes, Fittings, Fire Fighting Pipes, Fittings,
Sprinkles and Air Vents Sprinkles and Air Vents
Method Statement ‐ Method Statement ‐
B
REE‐HCNS‐DT‐0077
33 U29529514‐HCNS/MS/0028 0 Method Statement ‐ Installation of Grills and Diffusers 0 MEP L Installation of Grills and General General Installation of Grills and Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0004
Diffusers Diffusers
B
REE‐HCNS‐DT‐0076 Method Statement ‐ Method Statement ‐
34 U29529514‐HCNS/MS/0029 0 Method Statement ‐ Installation of Fans 0 MEP L General General Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0003 Installation of Plans Installation of Plans
Method Statement ‐ Method Statement ‐
Installation of Ducts, Installation of Ducts,
B
REE‐HCNS‐DT‐0075 Method Statement ‐ Installation of Ducts, Accessories and Thermal
35 U29529514‐HCNS/MS/0030 0 0 MEP L Accessories and Thermal General General Accessories and Thermal Radiant 7‐Apr‐15 13‐Apr‐15 Done
U‐295‐295‐14‐HCS‐MS‐M‐0002 Insulation(including anchors and support)
Insulation(including anchors Insulation(including anchors
and support) and support)
B
REE‐HCNS‐DT‐0080 Method Statement ‐ Instalaltion of Refrigerant Copper Pipes and Method Statement ‐ Method Statement ‐
36 U29529514‐HCNS/MS/0031 0 0 MEP L General General Radiant 7‐Apr‐15 12‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0005 Fittings (including anchors and supports) Instalaltion of Refrigerant Instalaltion of Refrigerant
Method Statement ‐ Testing of Method Statement ‐ Testing
B
REE‐HCNS‐DT‐0078
37 U29529514‐HCNS/MS/0032 0 Method Statement ‐ Testing of UPVC Drainage Pipes and Fitting 0 MEP L UPVC Drainage Pipes and General General of UPVC Drainage Pipes and Radiant 7‐Apr‐15 12‐Apr‐15
U‐295‐295‐14‐HCS‐MS‐M‐0010
Fitting Fitting
Method Statement ‐
Method Statement ‐
U/R
Method Statement ‐ Installation of D X Spilts Units (Included anchors Installation of D X Spilts
38 U29529514‐HCNS/MS/0033 0 REE‐HCNS‐DT‐0088 0 MEP L Installation of D X Spilts Units General General Radiant 9‐Apr‐15
and suport) Units (Included anchors and
(Included anchors and suport)
suport)
Method Statement ‐
Method Statement ‐
Installation and Insulation
Installation and Insulation of
U/R
Method Statement ‐ Installation and Insulation of water supply copper of water supply copper
39 U29529514‐HCNS/MS/0034 0 REE‐HCNS‐DT‐0087 0 MEP L water supply copper pipes and General General Radiant 9‐Apr‐15
pipes and fittings ( including anchors, supports, gauges and meters) pipes and fittings ( including
fittings ( including anchors,
anchors, supports, gauges
supports, gauges and meters
and meters
B
Method Statement for Installation & Termination of LV Cables and Installation & Termination of Installation & Termination
40 U29529514‐HCNS/MS/0035 0 HCNS‐MS‐E‐0006 0 MEP‐E L General General Radiant 14‐Apr‐15 20‐Apr‐15 Done
Wires LV Cables and Wires of LV Cables and Wires
Installation of Underground Installation of Underground
C
Method Statement ‐ Installation of Underground UPVC Ducts for
41 U29529514‐HCNS/MS/0036 0 HCNS‐MS‐E‐009 REV.0 0 MEP‐E L UPVC Ducts for Electrical and General General UPVC Ducts for Electrical Radiant 15‐Apr‐15 20‐Apr‐15
Electrical and ELV Servics
ELV Servics and ELV Servics
C
Installation of LV Distribution Installation of LV
42 U29529514‐HCNS/MS/0037 0 U29529514‐HCNS‐ME‐E‐0010 Method Statement ‐ Installation of LV Distribution Boards 0 MEP‐E L General General Radiant 15‐Apr‐15 20‐Apr‐15
Boards Distribution Boards
Installation of Cable
C
Installation of Cable Trunking
43 U29529514‐HCNS/MS/0038 0 MS‐E‐0007 Method Statement ‐ Installation of Cable Trunking for Electrical Ststem 0 MEP‐E L General General Trunking for Electrical Radiant 15‐Apr‐15 20‐Apr‐15
for Electrical Ststem
Ststem
44 U29529514‐HCNS/MS/0039 0 MS‐A‐003 Method Statement for Renovation & Repairing of Heritage Building 0 A B L Renovation & Repairing Heritage Building Heritage Building Renovation & Repairing UCC 21‐Apr‐15 27‐Apr‐15 Done
B
Method Statement ‐ Coring Through Concrete Structural for MEP Coring Through Concrete Coring Through Concrete
45 U29529514‐HCNS/MS/0040 0 MS‐0018 0 C L General General UCC 23‐Apr‐15 27‐Apr‐15 Done
Services Structural Structural
Installation and Testing of Installation and Testing of
46 U29529514‐HCNS/MS/0041 0 MS‐E‐011 Method Statement ‐ Installation and Testing of MMC (Capacitor Bank) 0 MEP‐E L General General UCC ‐ MEP 28‐Apr‐15
MMC MMC
Approved - A A
Under Review U/R U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
MS Submittal Ref. Document Ref L/N Area of Specialty of Date Pending Date
SN Rev Title Rev Disc Status Specialty Zone Originator Remarks
No. No. L Location Works Submitte days Commente
B
Method Statement for Demolition of the Existing Restaurant and Old Demolition of the Existing Existing Restaurant Existing Restaurant
47 U29529514‐HCNS/MS/0042 0 MS‐C‐022 0 C L Demolition UCC 28‐Apr‐15 29‐Apr‐15 Done
Souq Restaurant and Old Souq and Old Souq and Old Souq
Approved - A A
Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Najada Souq As of: 13-May-15
Pendi
Pre-qualification Submittal Area of Date
SN Rev Document Ref No. Title Rev Disc Status L/NL Documents Specialty Originator Date Submitted: ng Remarks
Ref: Location Commented
days
6 SPQS-0005 0 FBTC-GRC-2015-DT-246 Pre-Qualification from M/S. Fibro 0 C C L Pre-qualification Pre-Qualification Documents General Fibro 7-Apr-15 11-Apr-15
8 SPQS-0007 0 Transmittal No:0916 Pre-Qualification from M/s. Doha Extraco 0 C U/R L Pre-qualification Pre-Qualification Documents General Doha Extraco 16-Apr-15
Joinery
10 SPQS-0009 0 ZWW/017/DT/506 Pre-Qualifications for M/s. Zebrano 0
Wokrs
U/R L Pre-qualification Pre-Qualification Documents Hotel & Bookstore Zebrano 29-Apr-15
Pre-Qualification of M/s JBK Controls for Fire Alarm
11 SPQS-0010 0 HCNS-REE-SCP-E-0001
System Controls
0 MEP-E U/R L Pre-qualification Pre-Qualification Documents General JBK Controls 27-Apr-15
Pre-Qualification of M/s Pacific Ocean Electrical Pacific Ocean Electrical
12 SPQS-0011 0 HCNS-REE-SCP-E-0002
Switchgear Wll for LV Panels
0 MEP-E U/R L Pre-qualification Pre-Qualification Documents Hotel & Bookstore
Switchgear
29-Apr-15
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
U29529514- UCC/295-295-14-HCNS/SD-S-RE-
83
HCNS/SDS/0013
1
H-4F-AABCO-0264
Hotel Fourth Floor- Part 1 Key Plan 1 S B L Part 1 Key Plan Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15 Done
U29529514- UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 1 AAO & Additional at Corner of Core Wall Part 1 AAO & Additional at Corner
85
HCNS/SDS/0013
1
H-4F-AABCO-0470 Reinforcement
1 S C L
of Core Wall Reinforcement
Fourth Floor Hotel AABCO 14-Apr-15 29-Apr-15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor to Roof Floor -Part 1 Columns Reinforcement and Key Part1 - Columns Reinforcement Fourth Floor to
SDS/0029 1
H-4F-AABCO-0265 Plan
1 S U/R L
and Key Plan Roof Floor
Hotel AABCO 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Basement
SDS/0031 1
BS-BF-AABCO-0014
Book Store Basement Floor Level Columns Starter Reinforcement 1 S U/R L Columns Starter Reinforcement
Floor Level
Book Store AABCO 28-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Basement
SDS/0031 1
BS-BF-AABCO-0015
Book Store Basement Floor Level Columns Starter Reinforcement 1 S U/R L Columns Starter Reinforcement
Floor Level
Book Store AABCO 28-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
181 SDS/0034 1
H-4F-AABCO-0349
Hotel Fourth Floor - Part 2 Keyplan 1 S C L Part 2 Keyplan Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 2 Add. Around Opening - Chair & Section & Add at Add. Around Opening - Chair &
183 SDS/0034 1
H-4F-AABCO-0350 Corner CW
1 S C L
Section & Add at Corner CW
Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Hotel Fourth Floor - Part 2 Add. Around Opening & Add at Corner Core Wall Add. Around Opening & Add at
185 SDS/0034 1
H-4F-AABCO-0351 Reinforcement
1 S C L
Corner Core Wall Reinforcement
Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
187 SDS/0034 1
H-4F-AABCO-0352
Hotel Fourth Floor - Part 2 Punching Shear Reinforcement 1 S C L Punching Shear Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
189 SDS/0034 1
H-4F-AABCO-0353
Hotel Fourth Floor - Part 2 Bottom B1 & B2 Reinforcement 1 S C L Bottom B1 & B2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
193 SDS/0034 1
H-4F-AABCO-0355
Hotel Fourth Floor - Part 2 Top T1 & T2 Reinforcement 1 S C L Top T1 & T2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
195 SDS/0034 1
H-4F-AABCO-0356
Hotel Fourth Floor - Part 2 Add Top & Top T2 Reinforcement 1 S C L Top & Top T2 Reinforcement Fourth Floor Hotel AABCO 15-Apr-15 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
210 SDS/0037 1
H-RF-AABCO-0327
Hotel Roof Floor - Part 1 Key Plan 1 S B L Key Plan Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15 Done
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS/SD-S-RE-
218 SDS/0037 1
H-RF-AABCO-0331
Hotel Roof Floor - Part 1 Top T1 & T2 Reinforcement 1 S B L Part 1 Top T1 & T2 Reinforcement Roof Floor Hotel AABCO 19-Apr-15 29-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL-
229 SDS/0039 5
H-GF-UCC-0105
Hotel Ground Floor Blockwork Master Plan 5 A C NL Blockwork Master Plan Ground Floor Hotel UCC 5-Apr-15 6-Apr-15
UCC/295-295-14-HCNS/SD-A-BL-
230 SDS/0039 6
H-GF-UCC-0105
Hotel Ground Floor Blockwork Master Plan 6 A B L Blockwork Master Plan Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL-
241 SDS/0039 4
H-GF-UCC-0106
Hotel Ground Floor Blockwork Plan Partial -2 Light Weight Blocks 4 A C NL Blockwork Plan Partial - 2 Ground Floor Hotel UCC 4-Apr-15 4-Apr-15
UCC/295-295-14-HCNS/SD-A-BL-
248 SDS/0039 5
H-GF-UCC-0108
Hotel Ground Floor Blockwork Plan Partial - 3 Light Weight Blocks 4 A C NL Blockwork Plan Partial - 3 Ground Floor Hotel UCC 5-Apr-15 6-Apr-15
UCC/295-295-14-HCNS/SD-A-BL-
249 SDS/0039 6
H-GF-UCC-0108
Hotel Ground Floor Blockwork Plan Partial - 3 Light Weight Blocks 6 A B L Blockwork Plan Partial - 3 Ground Floor Hotel UCC 12-Apr-15 19-Apr-15 Done
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
268 SDS/0043 2
H-MZ-UCC-0109
Hotel Mezzanine Floor Master Plan Light Weight Blocks 2 A B L Master Plan Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
271 SDS/0043 2
H-MZ-UCC-0110
Hotel Mezzanine Floor Plan Partial -1 Light Weight Blocks 2 A B L Plan Partial 1 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
274 SDS/0043 2
H-MZ-UCC-0111
Hotel Mezzanine Floor Plan Partial -2 Light Weight Blocks 2 A B L Plan Partial 2 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
277 SDS/0043 2
H-MZ-UCC-0112
Hotel Mezzanine Floor Plan Partial -3 Light Weight Blocks 2 A B L Plan Partial 3 Light Weight Blocks
Floor
Hotel UCC 13-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-S-RE-
353 SDS/0062 0
BS-FF-UCC-0002
Book Store First Floor Level ARC Reinforcement Detail 0 S B L ARC Reinforcement Detail First Floor Book Store UCC 21-Apr-15 27-Apr-15 Done
UCC/295-295-14-HCNS/SD-E-EL- Basement
377 SDS/0065 0
BS-BF-REE-0001
Book Store Basement Floor plan Lighting Layout 0 MEP-E D L Plan Lighting Layout
Floor
Book Store Radiant 5-Apr-15 9-Apr-15
UCC/295-295-14-HCNS/SD-E-EP--
378 SDS/0066 0
BS-FF-REE-0004
Book Store First Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout First Floor Book Store Radiant 5-Apr-15 9-Apr-15
UCC/295-295-14-HCNS/SD-A-BL-
379 SDS/0067 0
SSC-GF-UCC-0100
Souq Building Ground Floor Plan Concrete Blockwork 0 A B L Plan Light Weight Blocks Ground Floor Souq Building UCC 5-Apr-15 7-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Mezzanine
380 SDS/0067 0
SSC-MZ-UCC-0101
Souq Building Mezzanine Floor Concrete Blockwork 0 A B L Light Weight Blocks
Floor
Souq Building UCC 5-Apr-15 7-Apr-15 Done
UCC/295-295-14-HCNS-SD-E-EP-
382 SDS/0068 0
H-2F-REE-0019
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-E-EP-
383 SDS/0068 0
H-2F-REE-0020
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-E-EP-
384 SDS/0068 0
H-2F-REE-0021
Hotel Second Floor Plan Small Power Layout 0 MEP-E D L Plan Small Power Layout Second Floor Hotel Radiant 6-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-M- Basement
385 SDS/0069 0
HVAC-BS-BF-REE-0010
Book Store Ventilation Ducting Layout Basement Floor Plan 0 MEP-M D L Ventilation Ducting Layout
Floor
Book Store Radiant 6-Apr-15 13-Apr-15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS-SD-FA-H-
388 SDS/0070 0
FF-REE-0015
Hotel First Floor Plan Fire Alaram Layout 0 MEP-M D L Plan Fire Alarm Layout First Floor Hotel Radiant 6-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
389 SDS/0070 0
FF-REE-0016
Hotel First Floor Plan Fire Alaram Layout 0 MEP-M D L Plan Fire Alarm Layout First Floor Hotel Radiant 6-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
390 SDS/0071 0
3F-REE-0021
Hotel Master Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
391 SDS/0071 0
3F-REE-0022
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
392 SDS/0071 0
3F-REE-0023
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
393 SDS/0071 0
3F-REE-0024
Hotel Third Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Third Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
394 SDS/0072 0
2F-REE-0017
Hotel Master Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
395 SDS/0072 0
2F-REE-0018
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
396 SDS/0072 0
2F-REE-0019
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
397 SDS/0072 0
2F-REE-0020
Hotel Second Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Second Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
398 SDS/0073 0
GF-REE-0005
Hotel Master Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
399 SDS/0073 0
GF-REE-0006 -1/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
400 SDS/0073 0
GF-REE-0007 -2/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
401 SDS/0073 0
GF-REE-0008 -3/3
Hotel Ground Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Ground Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
403 SDS/0074 0
RF-REE-0030 - 1/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
404 SDS/0074 0
BF-REE-0031 -2/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
405 SDS/0074 0
BF-REE-0032 - 3/3
Hotel Roof Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Roof Floor Hotel Radiant 7-Apr-15 9-Apr-15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS-SD-E-EP-
408 SDS/0075 0
H-FF-REE-0015 -1/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-E-EP-
409 SDS/0075 0
H-FF-REE-0016 -2/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-E-EP-
410 SDS/0075 0
H-FF-REE-0017 -3/3
Hotel First Floor Plan Small Power Layout 0 MEP‐E D L Plan Small Power Layout First Floor Hotel Radiant 7-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-E-EP-
412 SDS/0076 0
H-GEN-REE-0055 - 1/1
Najadah Hotel Twin Type Connecting -02 0 MEP‐E D L Connecting -2 Twin Type Hotel Radiant 7-Apr-15 11-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
414 SDS/0077 0
4F-REE-0026 -1/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
415 SDS/0077 0
BF-REE-0027 -2/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H-
416 SDS/0077 0
BF-REE-0028 -3/3
Hotel Fourth Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Fourth Floor Hotel Radiant 7-Apr-15 9-Apr-15
Master
UCC/295-295-14-HCNS-SD-FA-H-
417 SDS/0078 0
MZ-REE-0009
Hotel Master Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Mezzanine Hotel Radiant 7-Apr-15 9-Apr-15
Floor
UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
418 SDS/0078 0
MZ-REE-0010
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
419 SDS/0078 0
MZ-REE-0011
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H- Mezzanine
420 SDS/0078 0
MZ-REE-0012
Hotel Mezzanine Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
Master
UCC/295-295-14-HCNS-SD-FA-H-
421 SDS/0079 0
BF-REE-0001
Hotel Master Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout Basement Hotel Radiant 7-Apr-15 9-Apr-15
Floor
UCC/295-295-14-HCNS-SD-FA-H- Basement
422 SDS/0079 0
BF-REE-0002 -1/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H- Basement
423 SDS/0079 0
BF-REE-0003 -2/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-FA-H- Basement
424 SDS/0079 0
BF-REE-0004 -3/3
Hotel Basement Floor Plan Fire Alarm Layout 0 MEP‐M D L Plan Fire Alarm Layout
Floor
Hotel Radiant 7-Apr-15 9-Apr-15
UCC/295-295-14-HCNS-SD-M-
426 SDS/0080 0
HVAC-H-FF-REE-0014 -1/3
Hotel First Floor Plan -HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15
UCC/295-295-14-HCNS-SD-M-
427 SDS/0080 0
HVAC-H-FF-REE-0015 - 2/3
Hotel First Floor Plan HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS-SD-M-
428 SDS/0080 0
HVAC-H-FF-REE-0016 - 3/3
Hotel First Floor Plan HVAC System Layout 0 MEP‐M C L Plan HVAC System Layout First Floor Hotel Radiant 8-Apr-15 14-Apr-15
Basement
UCC/295-295-14-HCNS/SD-S-RE- Book Store Basement Floor to Ground Floor - Part 1 Keyplan -Columns Part 1 -Keyplan Columns
429 SDS/0081 0
BS-BF-AABCO-0047 Reinforcement
0 S C L
Reinforcement
Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor
Basement
UCC/295-295-14-HCNS/SD-S-RE-
430 SDS/0081 0
BS-BF-AABCO-0126
Book Store Basement Floor to Ground Floor - Part 1 Columns Reinforcement 0 S C L Part 1- Columns Reinforcement Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor
Basement
UCC/295-295-14-HCNS/SD-S-RE-
431 SDS/0081 0
BS-BF-AABCO-0127
Book Store Basement Floor to Ground Floor - Part 1 Columns Reinforcement 0 S C L Part 1 - Columns Reinforcement Floor to Book Store AABCO 9-Apr-15 12-Apr-15
Ground Floor
Room Twin
UCC/295-295-14-HCNS/SD-E-EL-
437 SDS/0083 0
H-GEN-REE-0075
Najadah Hotel Room Twin Type -02 Connecting Electrical Lighting Layout 0 MEP-E U/R L Electrical Lighting Layout Type -02 Hotel Radiant 9-Apr-15
Connecting
UCC/295-295-14-HCNS/SD-M-
438 SDS/0084 0
HVAC-BS-BF-REE-0011
Book Store Ventilation Ducting Layout Ground Floor Plan 0 MEP-M C L Ventilation Ducting Layout Ground Floor Book Store Radiant 15-Apr-15 19-Apr-15
UCC/295-295-14-HCNS/SD-M-
439 SDS/0085 0
HVAC-BS-FF-REE-0004
Book Store AC Ducting Layout First Floor Plan 0 MEP-M C L AC Ducting Layout First Floor Book Store Radiant 11-Apr-15 14-Apr-15
UCC/295-295-14-HCNS/SD-M-
440 SDS/0086 0
HVAC-BS-GF-REE-0002
Book Store AC Ducting Layout Ground Floor Plan 0 MEP-M C L AC Ducting Layout Ground Floor Book Store Radiant 12-Apr-15 14-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Mezzanine
441 SDS/0087 0
H-MZ-UCC-0001
Hotel Mezzanine Floor Level Construction Joint Detail 0 S B L Construction Joint Detail
Floor
Hotel UCC 22-Apr-15 27-Apr-15 Done
UCC/295-295-14-HCNS/SD-P-DR- Basement
442 SDS/0088 0
BS-BF-REE-0001
Book Store Basement Floor Plan Drainage Layout 0 MEP-M B L Drainage Layout
Floor
Book Store Radiant 13-Apr-15 18-Apr-15 Done
UCC/295-295-14-HCNS/SD-M-
443 SDS/0089 0
HVAC-BS-SF-REE-0005
Book Store AC Ducting Layout Second Floor Plan 0 MEP-M C L AC Ducting Layout Second Floor Book Store Radiant 14-Apr-15 19-Apr-15
UCC/295-295-14-HCNS/SD-A-BL-
444 SDS/0090 0
BS-GEN-UCC-0001
Book Store General Details Blockworks 0 A B L General Details Blockworks General Book Store UCC 14-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Basement
445 SDS/0090 0
BS-BF-UCC-0100
Book Store Basement Floor Master Plan Blockworks 0 A B L Master Plan Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295-295-14-HCNS/SD-A-BL- Basement
447 SDS/0090 0
BS-BF-UCC-0102
Book Store Basement Floor Partial -2 Blockworks 0 A B L Partial - 2 Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done
UCC/295-295-14-HCNS/SD-A-BL- Basement
448 SDS/0090 0
BS-BF-UCC-0103
Book Store Basement Floor Partial -3 Blockworks 0 A B L Partial - 3 Blockworks
Floor
Book Store UCC 14-Apr-15 19-Apr-15 Done
Foundation to
UCC/295-295-14-HCNS/SD-S-RE-
450 SDS/0092 0
BS-BF-AABCO-0128
Book Store Foundation to Ground Floor Level Columns Reinforcement 0 S C L Columns Reinforcement Ground Floor Book Store AABCO 15-Apr-15 27-Apr-15
Level
Foundation to
UCC/295-295-14-HCNS/SD-S-RE-
451 SDS/0092 0
BS-BF-AABCO-0129
Book Store Foundation to Ground Floor Level Columns Reinforcement 0 S C L Columns Reinforcement Ground Floor Book Store AABCO 15-Apr-15 27-Apr-15
Level
UCC/295-295-14-HCNS/SD-S-RE-
452 SDS/0093 0
BS-FT-AABCO-0130
Book Store Foundation at (+2.500 B.O.F.) Bottom Bars Reinforcement ‐ B1 0 S C L Bottom Bars Reinforcement ‐ B1 Foundation Book Store AABCO 16-Apr-15 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
453 SDS/0093 0
BS-FT-AABCO-0131
Book Store Foundation at (+2.500 B.O.F.) Bottom Bars Reinforcement - B2 0 S C L Bottom Bars Reinforcement - B2 Foundation Book Store AABCO 16-Apr-15 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
454 SDS/0093 0
BS-FT-AABCO-0132
Book Store Foundation at (+2.500 B.O.F.) Top Bars Reinforcement - T2 0 S C L Top Bars Reinforcement - T2 Foundation Book Store AABCO 16-Apr-15 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
455 SDS/0093 0
BS-FT-AABCO-0133
Book Store Foundation at (+2.500 B.O.F.) Top Bars Reinforcement - T1 0 S C L Top Bars Reinforcement - T1 Foundation Book Store AABCO 16-Apr-15 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Book Store Foundation at (+2.500 B.O.F.) Additional Bottom Bars Additional Bottom Bars
456 SDS/0093 0
BS-FT-AABCO-0134 Reinforcement
0 S C L
Reinforcement
Foundation Book Store AABCO 16-Apr-15 26-Apr-15
UCC/295-295-14-HCNS/SD-S-RE- Part 1 Bottom B1 & B2 & Add Top AAO
457 SDS/0094 0
H-URF-AABCO-0418
Hotel Upper Roof Floor ‐ Part 1 Bottom B1 & B2 & Add Top AAO Reinforcement 0 S B L
Reinforcement
Upper Roof Floor Hotel AABCO 19‐Apr‐15 29‐Apr‐15 Done
UCC/295-295-14-HCNS/SD-S-RE- Part 2 Bottom B1 & B2 & Add Top & AAO
458 SDS/0095 0
H-URF-AABCO-0426
Hotel Upper Roof Floor ‐Part 2 Bottom B1 & B2 & Add Top & AAO Reinforcement 0 S B L
Reinforcement
Upper Roof Floor Hotel AABCO 19‐Apr‐15 29‐Apr‐15 Done
UCC/295-295-14-HCNS/SD-M-BW-
459 SDS/0096 0
BS-BF-REE-0006
Book Store Basement Floor Plan MEP Builders Work in Walls 0 MEP‐M C L Plan MEP Builders Work in Walls Basement Floor Book Store Radiant 19‐Apr‐15 25‐Apr‐15
UCC/295-295-14-HCNS/SD-P-WS-
460 SDS/0097 0
H-FF-REE-0013
Hotel Master First Floor Water Supply Layout 0 MEP‐M C L Water Supply Layout Master First Floor Hotel Radiant 22‐Apr‐15 29‐Apr‐15
UCC/295-295-14-HCNS/SD-P-WS-
461 SDS/0097 0
H-FF-REE-0014
Hotel First Floor Plan Water Supply Layout - Sheet 1/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant 22‐Apr‐15 29‐Apr‐15
UCC/295-295-14-HCNS/SD-P-WS-
462 SDS/0097 0
H-FF-REE-0015
Hotel First Floor Plan Water Supply Layout - Sheet 2/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant 22‐Apr‐15 29‐Apr‐15
UCC/295-295-14-HCNS/SD-P-WS-
463 SDS/0097 0
H-FF-REE-0016
Hotel First Floor Plan Water Supply Layout - Sheet 3/3 0 MEP‐M C L Water Supply Layout First Floor Hotel Radiant 22‐Apr‐15 29‐Apr‐15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved A
Approved as Noted B
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of: 13-May-15
UCC/295‐295‐14‐HCNS/SD‐P‐WS‐BS‐GF‐
464 SDS/0098 0
REE‐0008
Book Store Ground Floor Plan Water Supply Layout 0 MEP‐M C L Water Supply Layout Ground Floor Book Store Radiant 23‐Apr‐15 29‐Apr‐15
UCC/295-295-14-HCNS/SD-S-RE-
488 SDS/0100 0
H-4F-AABCO-0257
Hotel Fourth Floor ‐Part 1 Keyplan and Beams Reinforcement 0 S U/R L Part 1 Keyplan and Beams Reinforcement Fourth Floor Hotel AABCO 25-Apr-15
UCC/295-295-14-HCNS/SD-S-RE-
489 SDS/0101 0
H-4F-AABCO-0344
Hotel Fourth Floor- Part 2 Beams Reinforcement 0 S U/R L Part 2 Beams Reinforcement Fourth Floor Hotel AABCO 25-Apr-15
UCC/295-295-14-HCNS/SD-M- Basement
494 SDS/0103 0
HVAC-BS-BF-REE-0001
Book Store AC Ducting Layout Basement Floor Plan 0 MEP-M U/R L AC Ducting Layout
Floor
Book Store UCC-MEP 28-Apr-15
U295/00QA/PQP/008 Rev. 00 February 2015
Approved - A A
Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Najada Souq As of: 2-Mar-15
REE-SNCP-DT-072/TS-SNCP- MEP-
1 SPQS-0001 0
PQ-004
Pre-qualification ELV System 0
ELV
C L Pre-qualification ELV System Pre-qualification Car Park Radiant 29-Jan-15 4-Feb-15
Landsca
3 SPQS-0003 0 PAB-DC-BD-0215-116 Palmera Company Profile 0
ping
C L Company Profile Landscaping Company Profile General Palmera 4-Feb-15 8-Feb-15
4 \
6
7
9
10
11
12
13
14
Approved - A A
Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Material Submittal ‐ Copper Pipes and Fittings for Refrigerant Pipes(HVAC)
97 MAS‐0078 1 UCC/MEP/MS/ME/0078
+ Sample
1 MEP-M B L Copper Pipes & Fittings Hotel & Bookstore Radiant 15‐Apr‐15 29-Apr-15 Done
130 MAS-0101 1 UCC/MEP/MS/EL/018 Material Submittal for LV Cable & Single Core Wires 1 MEP-E B L LV Cables General Doha Cables 20-Apr-15 22-Apr-15
MAS‐0114 1 UCC/MEP/MS/EL/0024 Material Submittal for GI Conduits and Accessories 0 MEP‐E A L GI Conduits and Accessories General Al Hathboor Enterprises 28‐Apr‐15 29‐Apr‐15 Done
UCC / Khalid Manufacturing
152 MAS‐0116 1 UCC/MEP/MS/ME/027 Material Submittal for Curtain Fire Damper (Sample Only) 1 MEP‐M B L Curtain Fire Damper General
Company
4‐Apr‐15 8‐Apr‐15 Done
UCC/ Khalid Manufacturing
154 MAS‐0117 1 UCC/MEP/MS/M/029 Material Submittal for Access Door (Sample Only) 1 MEP‐M B L Access Door General
Company
4‐Apr‐15 6‐Apr‐15 Done
Hotel and
162 MAS‐0123 0 UCC/MEP/MS/ME/0036 Material Submittal for Hangers & Support for HVAC Duct 0 MEP‐M B L Hangers & Support for HVAC Duct
Bookstore
Radiant / Hilti 4‐Apr‐15 8‐Apr‐15 Done
Hotel and
163 MAS‐0124 0 UCC/MEP/MS/EL/0037 Material Submittal for Electrical Supporting System (Alterante Submission) 0 MEP‐E D L Electrical Supporting System
Bookstore
Radiant / Hilti 4‐Apr‐15 5‐Apr‐15
Hotel and
164 MAS‐0125 0 UCC/MEP/MS//EL/0038 Material Submittal for Disconnect Switches / Isolationg Switch + Sample 0 MEP‐E B L Switches
Bookstore
ABB 11‐Apr‐15 13‐Apr‐15 Done
Radiant / Equipment
Hotel and
166 MAS‐0127 0 UCC/MEP/MS/ME/042 Material Suibmittal ‐ Acoustic ‐ Liner 0 MEP-M D NL Acoustic ‐ Liner
Bookstore
Trading & Contrating Co. 11‐Apr‐15 14‐Apr‐15 Rejected
WLL
Approved - A A
Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Radiant / Equipment
Hotel and
MAS‐0127 1 UCC/MEP/MS/ME/0042 Material Submittal ‐ Duct Acoustic Liner 1 MEP-M U/R L Acoustic ‐ Liner
Bookstore
Trading & Contrating Co. 25‐Apr‐15
WLL
RADIANT / Qatar
Hotel and
169 MAS‐0130 0 UCC/MEP/MS/ME/0041 Material Submittal for AC Condensate Drain Pipes & Fittings + Sample 0 MEP-M C L AC Condensate Drain Pipes & Fittings
Bookstore
Pipeline & Fittings 13‐Apr‐15 16‐Apr‐15
Company
Hotel and
172 MAS‐0133 0 REE‐HCNS‐DT‐0172 Material Submittal ‐ GRP Sectional Water Tanks 0 MEP-M C L GRP Sectional Water Tanks
Bookstore
Radiant / Bijan Groups 14‐Apr‐15 29‐Apr‐15
179 MAS‐0140 0 N/A Material Submittal ‐ Plaster Gypsum 0 ARCH B L Plaster Gypsum Hotel Saudi Vetonit Company Ltd 20‐Apr‐15 22‐Apr‐15 Done
Under Review - U/R U/R U-295-295-14 HCNS Hotel & Complex of Al Nadaja Souq As of: 13-May-15
Material Date Date
Area of Pendin
SN Submittal Ref. Rev Document Ref No. Title Rev Disc Status L/NL Specialty Originator Submitt Comment Remarks
Location g days
No. ed: ed
Hotel and
181 MAS‐0142 0 UCC/MEP/MS/ME/0056 Material Submittal ‐ UPVC Pipes and Fittings 0 MEP-M U/R L UPVC Pipes and Fittings
Bookstore
Al Madadd Al Qatariah 25‐Apr‐15
Hotel and Al Riyadh Trading &
182 MAS‐0143 0 UCC/MEP/MS/ME/0057 Material Submittal ‐ Water Hammer Arrester + Sample Board 0 MEP-M C L Water Hammer Arrester
Bookstore Contracting Company
25‐Apr‐15 27‐Apr‐15
Hotel and
183 MAS‐0144 0 UCC/MEP/MS/ME/0060 Material Submittal ‐ Fire Fighting Seamless Pipe 0 MEP-M U/R L Fire Fighting Seamless Pipe
Bookstore
CESCO 25‐Apr‐15
Hotel and
184 MAS‐0145 0 UCC/MEP/MS/EL/0059 Material Submittal ‐ Uninterruptible Power System 0 MEP-E D L Uninterruptible Power System
Bookstore
Snap Power Solution 26‐Apr‐15 28‐Apr‐15
Hotel and
185 MAS‐0146 0 UCC/MEP/MS/ME/0061 Material Submittal ‐ Mechanical Identification Labels & Tags + Sample 0 MEP-M U/R L Mechanical Identification Labels & Tags
Bookstore
Alianza Trading & Advertising 28‐Apr‐15
Hotel and
188 MAS‐0149 0 UCC/MEP/MS/ME/0062 Material Submittal ‐ Sprinklers 0 MEP-M U/R L Sprinklers
Bookstore
CESCO 28‐Apr‐15
Hotel and
189 MAS‐0150 0 UCC/MEP/MS/ME/0084 Material Submittal ‐ Insulation for Plumbing Pipes + Sample 0 MEP‐M U/R L Insulation for Plumbing Pipes
Bookstore
Qatar Insulation Company 28‐Apr‐15
Approved A
Approved as Noted B
Revise & Resubmit C HCNS Design Drawing LOG
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received
Previous comment of
the submittals /
workshop meetings /
U29529514-HCNS-DS- Design Architectural Book discussion are not
12 1 2459-DT038-15 1 Revised Architectural Design Detail Drawings A C NL General ERGA 08-Apr-15 09-Apr-15
DD-0009 Drawings Drawings Store implemented
comments should be
revised before
submitting.
Revised Architectural Design Detail Drawings for Book Store - Draft IFC,
U29529514-HCNS-DS- List of Deliverables, Design Architectural Book
13
DD-0009
2 2459-DT045-15
Reply on the Commented Drawings received from DAR Drawings
A D L
Drawings
General
Store
ERGA 16-Apr-15 19-Apr-15
and Compliance Statement on the Arch. Comments received from DAR
14-132-JCP-ST-TN-0117 -
Drawings
Drawing SR No. 1-5
14-132-JCP-ST-TN-0119- Design
U29529514-HCNS-DS- Structural Drawings for Hotel & James Revise and Resubmit
22 1 Drawings 2 Drawings - S B NL Structural Drawings General Hotel 19-Apr-15 22-Apr-15
DD-0015 Structural Design Calculation Cubitt Drawing SR No. 6-12
14-132-JCP-ST-TN-0118 - Draft IFC
AAN
Design Calculation
Design
Drawings -
Structural
U29529514-HCNS-DS- 14-132-JCP-ST-TN-0126 & Structural Drawings for Hotel & Draft IFC, James
DD-0015
2
14-132-JCP-ST-TN-0127
3
Structural Design Calculation Report Design
S U/R L Drawings& General Hotel
Cubitt
26-Apr-15
Calculations
Calculation
Report
Interior
Design
Drawings & Interior Design
FFE for Mock Drawings & FFE for
U29529514-HCNS-DS- HAI-DEN-IDD-100-NAJ-044- Interior Design Drawings & FFE for Mock up Rooms 129 & 132 (Suite
25
DD-0017
1
2015
1
Type 04 & Twin Type 02)
up Rooms A B L Mock up Rooms 129 General Hotel Highness 20-Apr-15 23-Apr-15 Done
129 & 132 & 132 (Suite Type 04
(Suite Type & Twin Type 02)
04 & Twin
Type 02)
Approved A
Approved as Noted B
Revise & Resubmit C HCNS Design Drawing LOG
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received
B7 Souq Building Architectural Drawings
General Cover Sheet
14-132-JCP-AR-TN-0115 Drawing List
GN-001 Ground Floor Plan
B7-GN-001 Mezzanine Floor Plan
Roof Floor Plan Previous Submittal
U29529514-HCNS-DS- B7-A-101 Architectural Architectural B7 Souq B7 Souq James
27 0 1 Elevations A C NL 05-Apr-15 07-Apr-15 Submitted through Ts-
DD-0019 B7-A-102 Drawings Drawings Building Building Cubitt
Sections 0058 Rev. 0
B7-A-103
B7-A-201
B7-A-202
Done
*Foundation
Structural
Retrofitting revised to
Design,
Structural Design, resubmit
U29529514-HCNS-DS- Structural Design Calculation Report, Structural Analysis Models and Analysis James
28 0 14-132-JCP-ST-TN-0102 0 S B L Analysis Models & General Hotel 08-Apr-15 12-Apr-15 *water tanks on roof
DD-0020 Structural Design Report Models & Cubitt
Design Report should be considered
Design
for P.T slob design
Report
*refer to comment
attached
Revised
Revised Design
U29529514-HCNS-DS- 2459-DT041-15 & Design Detail- MEP- Book
29
DD-0021
0
2459-DT042-15
0 Revised Design Detail - Electrical for Book Store - Draft IFC
Electrical - E
C L Detail - Electrical for General
Store
ERGA 15-Apr-15 29-Apr-15
Book Store
Draft IFC
Revised
Revised Design
Design Detail -
U29529514-HCNS-DS- MEP- Detail - Mechanical, Book
30 0 2459-DT039-15 0 Revised Design Detail - Mechanical, Fire Fighting & Plumbing Mechanical, U/R L General ERGA 11-Apr-15
DD-0022 M Fire Fighting & Store
Fire Fighting
Plumbing
& Plumbing
855.CCL.DTN PTD-AI/MA-
0015
1. UCC/295-295-14-HCNS/SD-
S-GA-H-L4-CCL-0001 Rev. 0 1. Hotel Level 4 -General Arrangement & Load Key Plan
Design 1st Drawing (General
2. UCC/295-295-14-HCNS/SD- 2. Hotel Level 4- Tendon Layout - Sheet 1/2
Drawings Arrangement) Revise &
U29529514-HCNS-DS- S-TL-H-L4-CCL-0002 P1/2 3. Hotel Level 4 - Tendon Layout - Sheet 2/2
31 0 0 and S B NL Structural Drawings Level 4 Hotel CCL 18-Apr-15 21-Apr-15 Resubmit. Remaining
DD-0023 Rev. 0 4. Hotel Level 4 - Reinforcement Layout - Sheet 1/2
Calculations - Drawings Approved as
3. UCC/295-295-14-HCNS/SD- 5. Hotel Level 4 - Reinforcement Details - Sheet 2/2
Draft IFC Noted.
S-TL-H-L4-CCL-0002 P2/2 6. Level 4 - PT Calculation
Rev. 0
4. UCC/295-295-14-HCNS/SD-
S-RC-H-L4-CCL-0003 P1/2
Design
U29529514-HCNS-DS- UCC/295-295-14-HCNS/SD-S-
32
DD-0023
1
GA-H-L4-CCL-0001
1 Hotel Level 4-General Arrangement & Load Key Plan Drawings S B L Structural Drawings Level 4 Hotel CCL 23-Apr-15 27-Apr-15 Done
- Draft IFC
Approved A
Approved as Noted B
Revise & Resubmit C HCNS Design Drawing LOG
Not Approved D
Under Review U/R U-295-295-14 HNCS Hotel & Complex of Al Najada Souq As of:
Drawing Submitttal Date Pending Date
SR No. Rev Drawing Numbers Rev. Title Type Disc Status L/NL Activity Zone location Originator Remarks
Number Submitted: days received
Design
U29529514-HCNS-DS- Design Drawings - James
35
DD-0026
0 14-132-JCP-ST-TN-0124 2 B2 Hotel Architectural Drawings Drawings - A U/R L
Draft IFC
General Hotel
Cubitt
22-Apr-15
Draft IFC
Design
Drawings - Hotel -
Design Drawings - Hotel -B2
U29529514-HCNS-DS- 14-132-JCP-ST-TN-0123 & Draft IFC, B2 James
36
DD-0027
0
14-132-JCP-ST-TN-0125
0 Structural Drawings & Design Report for B2 Hotel Extension
Design
S U/R L Draft IFC, Design Extensio
Extensio Cubitt
26-Apr-15
Report n
Calculation n
Report
UCC/295-295-14-HCNS/SD-E-
EP-H-GEN-REE-0045(Sheet Hotel Room Suite Type -04 (Mockup Room) Electrical & ELV Combined Layout (Sheet Mockup
1/2) 1/2) Design
U29529514-HCNS-DS- MEP- Design Drawings - Room-
37
DD-0028
0 & 0 & Drawings -
E
C NL
Draft IFC Suite
Hotel UCC-MEP 27-Apr-15 28-Apr-15
UCC/295-295-14-HCNS/SD-E- Hotel Room Suite Type ‐04 (Mockup Room) Electrical & ELV Combined Layout (Sheet 2/2) Draft IFC
Type 4
EP-H-GEN-REE-0045(Sheet
2/2)
Mockup
Design
U29529514-HCNS-DS- UCC/295-295-14-HCNS/SD-E- MEP- Design Drawings - Room-
38
DD-0029
0
EP-H-GEN-REE-0043
0 Hotel Room Twin Type -02 (Mockup Room) Electrical & ELV Combined Layout Drawings -
E
C L
Draft IFC Twin
Hotel UCC-MEP 27-Apr-15 29-Apr-15
Draft IFC
Type 2
HOTEL & COMPLEX OF AL NAJADAH SOUQ
Project no. U-295-295-15-CHNS
PROGRESS PHOTO
● Hotel Building – Slab Form & Rebar works in Progress at First floor level.
● Book Store- Column Form & Concrete works in progress at first level
● Book Store –External slab Concrete Works in Progress at First floor level.
● Book Store – Column Form & Concrete works in progress at first level