ERC Refinery Project

Mostorod, Cairo, Arab Republic of Egypt


Project Number EPROM Engineering Department (Projects Division) Weekly Report (1) Revision: (01)
(7T04) Date Submitted: 11/11/2018
From: 04/11/2018 To: 08/11/2018
Date Activity Description Discipline
Submit EPROM (Project Division) engineering comments on drawings of the new supplied internal floating Roof
11/4/2018 Mechanical
for (Tank 112) at Petroleum Pipelines Company
Submit EPROM (Project Division) engineering comments for the following Mechanical punch items:
11/5/2018 37645, 80492, 82120, 82128, 82111, 82116, 82536, 82129, 63746, 29301, 37753, 49714, 38100, 49706, 49821, Mechanical
49861 & 49897

Submit EPROM (Project Division) engineering comments for the following Civil punch items:
• Cover of the Oily water sump at (unit 51) Civil
• Requirements of construction of new handrail for the stairs of (unit 31) chemical injection tanks area

11/6/2018
EPROM (Project Division) senior engineer attended meeting at Petroleum Pipelines Company to discuss burring
the newly constructed VR insulated pipeline that caused accessibility problems for some manual valves installed
on another pipeline at Petroleum Pipelines Company which was rejected by EPROM and another proposal Mechanical
(installing fixed scaffolding) was suggested as alternative solution because the new line can’t be buried due to
steam tracing lines and insulation

Eprom (Project Division) Civil team attended meeting with CORC civil team at CORC office to discuss the
following items:
11/7/2018 • Rehibition of all roads around the geographical area Civil
• Concept design of the foreseen new proposed road form ERC gate (g) to the Ring road
• Construction of new ramp at GASCO gate

11/8/2018