Consider the following network (P6)

(times are in weeks)

2 C 5
7
A F
D H
5 3
6 8
1 G
4 6
B 10
E
3
3 7

a. Identify the critical path.


b. How long will it take to complete this project?
c. Can activity D be delayed without delaying the entire project?
How about activity C? If so, how many weeks?
d. What is the schedule for activity E?