JSA FOR DISMANTLING OF STRUCTURE

S.NO SCOPE OF HAZARD CONTROL MEASURES REQUEST BY


ACTIVITY
1) PREPARATORY 1) Collapse of Structure 1) The Competent Person shall survey the integrity of the SITE INCHARGE/
OPERATIONS 2) Collapse of a Portion of the structure prior to the start of demolition operations. EHS
Structure 2) All required permits shall be obtained.
3) Asbestos/Lead Exposure 3) Prior to the start of the demolition, abatement of all
4) Electrical, Gas, Water, asbestos or lead, by a licensed removal company, will be
Sewer, Cable Damage completed.
5) Glass Fragmentation 4) Locate, shut off, cap, or otherwise control all utilities.
6) Fire Hazards 5) All glass shall be broken out and removed to the proper
7) Exposure of the Public to disposal container.
Falling Debris 6) Fire extinguishers shall be available on site and
8) Rodents Emergency Services numbers shall be posted.
7) Work zone must be completely fenced in and of a
sufficient distance away from sidewalks to remove any
hazard to the public.
8) A certified exterminator will treat the entire building in
accordance with governing health regulations

2) PERSONAL 1) Falling and flying debris 1) All workers on site shall wear hard hats. SITE INCHARGE/
PROTECTIVE 2) Dust Inhalation 2) A supply of dust masks shall be kept on hand to fill worker EHS
EQUIPMENT 3) Eye Injuries requests.
4) Cuts/Scrapes/Abrasions 3) All workers shall wear safety glasses.
5) Struck By 4) Workers handling debris from the demolition will wear
6) Caught Between work gloves.
5) All workers on site shall wear approved, hi-visibility safety
vests, to make them visible to the equipment operators

3) DISMANTLING 1) Structure Collapse 1) Proceed with demolition in a systematic manner, working SITE INCHARGE/
OF STRUCTURE 2) Falling Debris from the top of the structure downwards. EHS
3) Pollution 2) Any worker signalling the operator shall be in plain sight of
JSA FOR DISMANTLING OF STRUCTURE
4) Housekeeping the operator at all times.
5) Fire 3) All workers shall remain at least 8-10 feet from the
6) Slipping hazard equipment used to perform the demolition.
7) Tripping hazard 4) Only workers necessary to the operation shall be
8) Falling hazard permitted in the work zone during this operation.
5) Barrels and caution tape will be used to demarcate the
demolition zone.
6) Debris removal will not begin until the removal can be
safely performed without exposure to structural collapse or
falling debris.
7) Water will be sprayed to keep down the dust from the
demolition.
8) Water will not be allowed to accumulate and cause a
hazardous condition.
9) Drainage for temporary water use will be provided.
10) Structural framing members shall not be removed until all
stories above them have been demolished and removed.
11) Framing members will be removed to a separate container.
12) Concrete and masonry debris will be removed to a
separate container.
13) Workers shall be instructed to posses heightened
awareness of their surroundings both during the
demolition and removal of debris.