ATA 05 TIME LIMIT

Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only
05.00 GENERAL Maintenance Operations

INSPECTION DEFINITIONS:
For the check of an aircraft, various types of inspections are carried out.
Line checks:
Checks and Zonal Visual Inspections.
A checks and multiple:
Zonal Visual Inspections, Lubrication, Servicing, Operational Checks.
C checks and multiple:
Zonal Visual Inspections. Operational and Functional checks on aircraft and powerplant systems.
Structural inspections:

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 2
05.00 GENERAL Maintenance Operations
General Visual Inspections (GVI).
Detailed Visual Inspections (DVI).
Special Detailed Inspections (SDI).

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 3
05.00 GENERAL Maintenance Operations

STANDARD INSPECTION INTERVALS:


These inspections are carried out with regular intervals.
- Line Check:
2 days.
- Weekly Check:
7 days.
- A check:
500 Flight Hours (FH).
- C check:

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 4
05.00 GENERAL Maintenance Operations
5,000 Flight Hours (FH).

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 5
05.00 GENERAL Maintenance Operations

STRUCTURAL INSPECTION INTERVALS:


Three structural inspection categories exist:
Fatigue damage:
Thresholds:
18,000 / 24,000 / 36,000 Flights.
Repeat Intervals:
3,000 / 6,000 / 12,000 / 18,000 / 24,000 Flights.
Environmental damage:
Thresholds: 2 / 4 / 8 Years.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 6
05.00 GENERAL Maintenance Operations
Repeat Intervals: 2 / 4 / 8 Years.
Accidental damage:
Intervals:
2 / 4 / 8 Years.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 7
05.00 GENERAL Maintenance Operations

MAINTENANCE PLANNING DOCUMENT (MPD):


- Tasks identified in the MRB Report are broken down into a comprehensive Maintenance Planning Document.
- The MPD references each task and provides details on:
Zone, Accesses, Description, Job Procedure, Manpower required, Man-hours required, Efficiency, Interval. - The program defined in MRB/MPD
documents is based on an average daily utilization of 5.5FH for 8.2FL (2,000 FH/YE and 3,000 FL/YE). In the event that operation appreciably
differs from these figures, the program should be adapted to account for A/C utilization.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 8
05.00 GENERAL Maintenance Operations

MAINTENANCE PRECAUTIONS:
BACKGROUND:
Following a series of accident involving large commercial aircraft, the influences on Fuel Tank Safety have been widely discussed in recent years,
to establish means by which fuel tank explosions can be prevented in future. The FAA and EASA issued special requirements for maintenance and
inspection, focused on prevention against fuel tank explosion risk-adjacent systems and on Fuel Tank Airworthiness Limitations.
CDCCL:
An important concept of the new regulation is the introduction of Critical Design Control Configuration Limitation (CDCCL).
As applied to fuel tank safety policy, this term covers all items of the fuel tank and adjacent systems that are considered as critical ignition source
prevention features. All precautions shall be taken to prevent unsafe conditions to develop from configuration changes caused by maintenance

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 9
05.00 GENERAL Maintenance Operations
action, repair or alteration of these critical items.
All CDCCLs are included in the time limit section of the MRB and are highlighted into AMM task cards and CMMs to provide the list of critical parts
that should not be repaired out of the scope.
CAUTION:
All along the ATA 28 (FUEL) covered in this course, the trainee will have to pay a particular attention to the safety precautions.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 10
05.00 GENERAL Maintenance Operations

ENGINE AND PROPELLER MAINTENANCE:


The engine Maintenance Hard Time are:
- Removal of the engine at the defined time limit:
- HSI (Hot Section Inspection).
- OVH (OVerHaul).
The engine Maintenance On-Condition are:
- No scheduled Hot Section Inspection (HSI) / Overhaul (OVH). (2 HSI for 1 OVH recommended by P&WC).
- Engine removal for refurbishment driven by on wing task and ECTM.
- Proven to be the most cost effective way of maintaining engines.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 11
05.00 GENERAL Maintenance Operations
The propeller maintenance Major Inspection Intervals (MII) are:
- ATR 42-300 and 42-320: 10,000 Flight Hours,
- ATR 72-200: 10,500 Flight Hours,
- ATR 42-400 ATR 42-500 and 72-500: 8,100 Flight Hours.

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 12
05.00 GENERAL Maintenance Operations

COMPONENT MAINTENANCE:
Components have scheduled overhaul. Look at following examples.
- Main and emergency batteries:
- Generators:
- Propeller brake and landing gear:

MW05.MO_.01.O1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 13
05.00 GENERAL Exercises

MW05.00_.02.E1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 14
05.00 GENERAL Exercises

MW05.00_.02.E1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 15
05.00 GENERAL Exercises

MW05.00_.02.E1L1 Copyright © 2011-2012 - ATR Training Centre - All right reserved For Training Only Page 16
Table of contents

05.00 GENERAL .............................................................................................................................................................................................................................................................


2

Maintenance Operations ..........................................................................................................................................................................................................................................


2

Exercises ................................................................................................................................................................................................................................................................
14