You are on page 1of 3

CORPORACION MINERA VIRGEN DE LA MERCED S.A.

C
UNIDAD EL "OCROS 11"
PROGRAMA DE AVANCES - NIVEL 200
MES DE MARZO - 2019

SECCION GEOLOGIA RATIOS DE VOLADURA AVANCES PROGRAMADOS PRODUCCION PROGRAMADA PERSONAL COSTO SUB TOTAL
NIVEL VETA FASE LABOR LEY AVANCE PROM X N° DE AVANCE M3 M3 TM DE UNITARIO (US$)
ANCHO (A) ALTO (H) PROMEDIO POT. VETA DISPARO DISPAROS PROG. (Mts) DESMONTE MINERAL M3 TOTAL MINERAL % CU H - H/GURDIA H - H/MES (US$/ml)
200 DORADO PREPARACION 10° SN E 1.00 1.80 3.30% 0.20 1.10 4.00 4.40 4.75 3.17 7.92 11.40 3.30% 29.00 116.00 147.47 $ 648.87
200 DORADO PREPARACION 10° SN W 1.00 1.80 4.20% 0.11 1.10 6.00 6.60 5.94 5.94 11.88 21.38 4.70% 27.00 162.00 147.47 $ 973.30
200 DORADO PREPARACION 9° SN E 1.00 1.80 3.50% 0.22 1.10 4.00 4.40 3.96 3.96 7.92 14.26 3.50% 33.00 132.00 147.47 $ 648.87
200 DORADO PREPARACION SN 220 E 1.00 1.80 3.00% 0.20 1.10 5.00 5.50 4.95 4.95 9.90 17.82 3.00% 37.00 185.00 147.47 $ 811.09
200 DORADO PREPARACION SN 220 W 1.00 1.80 3.00% 0.05 1.10 5.00 5.50 9.90 0.00 9.90 0.00 2.40% 27.00 135.00 147.47 $ 811.09
200 DORADO PREPARACION CH ACCESO 1.50 1.00 3.90% 0.25 1.00 5.00 5.00 3.00 4.50 7.50 16.20 2.40% 31.00 155.00 195.45 $ 977.25
200 DORADO PREPARACION CH 2 E 1.50 1.00 3.85% 0.22 1.00 4.00 4.00 0.00 6.00 6.00 21.60 4.00% 31.00 124.00 195.45 $ 781.80

TOTAL 33.00 35.40 32.50 28.52 61.02 102.67 3.57% 215.00 1009.00 $ 5,652.26

ING. LEON CERNA JHERY JONATHAN Ing. JHONI GAMARRA BEDON ING. FELIX BAYGORREA TINEO
JEFE DE MINA UNIDAD OCROS 11 SUPERVISOR DE MINA OCROS 11 - NIVEL 200 RESINDENTE C.M.V.M S.A.C

V.B. AREA DE PLANEAMIENTO E INGENIERIA


UNIDAD OCROS 11
CORPORACION MINERA VIRGEN DE LA MERCED S.A.C
UNIDAD EL "OCROS 11"
PROGRAMA DE EXPLOTACION - NIVEL 200
MES DE MARZO - 2019

ANCHOS TRAMOS LONG. ALTURA N° EXPLOTACION PERSONAL N° N° Costo SUB TOTAL


NIVEL VETA FASE LABOR
A.MINADO A. VETA DILUCION MINABLES CORTE CORTE CORTES TMS ROTAS % CU H - H/GURDIA H - H/MES PERF. WINCHES (US$/Ton) US$
200 DORADO EXPLOTACION TJ 8 E 0.59 0.45 0.14 6.00 1.25 2.50 2.00 31.59 5.40% 50.00 100.00 1.0 - 20.45 $ 646.02
200 DORADO EXPLOTACION TJ 8 W 0.61 0.47 0.14 7.00 1.25 2.50 2.00 38.49 5.20% 50.00 100.00 0.0 - 20.45 $ 787.18

TOTAL 0.60 0.46 0.14 13.00 2.50 5.00 4.00 70.08 5.29% 100.00 200.00 1.0 0.0 $ 1,433.20

ING. LEON CERNA JHERY JONATHAN Ing. JHONI GAMARRA BEDON ING. FELIX BAYGORREA TINEO
JEFE DE MINA UNIDAD OCROS 11 SUPERVISOR DE MINA OCROS 11 - NIVEL 200 RESINDENTE C.M.V.M S.A.C

V.B. AREA DE PLANEAMIENTO E INGENIERIA


UNIDAD OCROS 11
CORPORACION MINERA VIRGEN DE LA MERCED
UNIDAD OCROS 11 - NIVEL 200
RESUMEN GENERAL: PROGRAMA GENERAL DE MINA

1. AVANCES (PREPARACION, DESARROLLO Y EXPLORACION)


SECCION AVANCES MINERAL DE AVANCES P.U
NIVEL ESTRUCTURA LABOR DE MINA LEY (%) (US$/ml) SUB TOTAL US$
ANCHO (A) ALTO (H) (ml)
200 DORADO 10° SN E 1.00 1.80 4.40 11.40 3.30% $ 147.47 $ 648.87
200 DORADO 10° SN W 1.00 1.80 6.60 21.38 4.70% $ 147.47 $ 973.30
200 DORADO 9° SN E 1.00 1.80 4.40 14.26 3.50% $ 147.47 $ 648.87
200 DORADO SN 220 E 1.00 1.80 5.50 17.82 3.00% $ 147.47 $ 811.09
200 DORADO SN 220 W 1.00 1.80 5.50 0.00 2.40% $ 147.47 $ 811.09
200 DORADO CH ACCESO 1.50 1.00 5.00 16.20 2.40% $ 195.45 $ 977.25
200 DORADO CH 2 E 1.50 1.00 4.00 21.60 4.00% $ 195.45 $ 781.80
RESUMEN AVANCE DE MINA 35.40 102.67 3.57% $ 5,652.26

2. EXPLOTACION: (ROTURA)
ANCHO DE TRAMOS
NIVEL ESTRUCTURA LABOR VETA MINABLES TONELAJE (TMS) LEY (%) P.U (US$/Ton) COSTO US$

200 DORADO TJ 8 E 0.48 6.0 31.10 5.40% 20.45 636.0768


200 DORADO TJ 8 W 0.52 7.0 39.31 5.20% 20.45 803.9304
RESUMEN DE EXPLOTACION DE TAJOS 13.0 70.42 5.29% $ 1,440.01

RESUMEN GENERAL NIVEL 200 - DORADO. 173.08 4.27% $ 7,092.27

ING. LEON CERNA JHERY JONATHAN


JEFE DE MINA UNIDAD OCROS 11