Site Update Report

Reverie Power & Automation Engineering Ltd.

Name of the project: Desh Energy 200MW Power Plant Client: Desh Energy Date: 3.7.2018

Work plan
Scope of work Progress Over all site in picture
Transformer Supply, installation, Testing, Commissioning
55%
GIS Supply, installation, Testing, Commissioning
70%
Substation Structure Supply,Installation 85%
LA, CP Supply, Installation, Testing, Commissioning 0%
Cable ladder installation at cable cellar under MV room 95%
MV Switchgear Supply, Installation, Testing, Commissioning
10%
CRP Supply, Installation, Testing, Commissioning 50%
DC system Supply, Installation, Testing, Commissioning 20%
Installation of cable tray for substation Cable trench 85%
Substation Control cable termination 0%
132 KV power cable Supply and laying 58%
133 KV power cable termination 5%
Cable trench for 132 KV power cable 98%
Supply, installation of Cable tray for MV cable 60%
MV Power cable Supply, laying and testing 0%
Auxiliary transformer Supply, Installation, Testing and
commissioning 20%
LV room cable tray installation 90%
LV panel supply, installation, Testing and Commissioning 0%
Cable ladder installation at compressor room 0%
Cable ladder installation at engine hall 0%
Cable ladder installation for radiator 0%
Control cable Laying for all power plant equipment 0%
Earthing System 45%
Bus Duct and bus bar installation 0%
Wartsila control Panel installation 25%
Lighting System 0%
0%
Work progress
Power transformer GIS Substation Structure Bus Duct Installation Substation Cable trench Earthing System
No progress today SF6 filling and operation test in progress No progress today Transformer 4 Bus duct installation completed Angel installation in transformer trench in progress. 75% of work finished No progress today.
All 4 transformer installation completed 1 Gantry beam and 4 set LA structure installation pending Bus duct for TR 1,2,3 remaining Fabrication is in progress at workshop boring completed except boring for transformer neutral bushing.
Testing in progress All cable trench except Tr trench angel installation finished. Painting and finishing work
remaining.

AC, DC & Control cable for substation equipment MV switchgear & CRP LV room DC for substation 132 KV Power Cable
No progress today MV panel installation in progress Cable ladder installation 90% finished Battery rack fabrication Cable termination in progress
CRP wiring in progress Panels not reached at site yet panel installed 8 cable out of 14 completed

Cable ladder installation for tank Cable ladder installation at cable


DC System for Wartsila Cable ladder at engine hall Cable ladder for radiator MV Cable Auxiliary Transformer
and fuel pump area cellar under MV room
Panel shifting completed Ladder installation for MV cable Not started Ladder installation 2 of 4 auxiliary transformers are placed on pad 95% work completed
completed No progress

Power plant Control panel installation Control cable laying for Wartsila panel Lighting System Power plant equipment Cable termination LV cable
Panel shifted inside room No trench Not started Structure not ready No trench
Site Manpower detail
Designation Number of persons
Project Manager
Site incharge
Site Engineer
Site Commercial
Site Supervisor
Technician
Foreman
Fitter
Line man
Welder
Helper
Centrifuge machine operator
Others ( Cook, Office assistant, etc )
Total

Tools, Equipment & Vehicle List

Sl.No
Tools, Equipment & Vehicle Name Arrival date Quantity Condition Remarks
1 Crane
2 Hydra
3 Welding machine
4 Grinding machine
5 Drill machine
6 Mechanical Tools
7 Electrical Tools
8 Hydraulic jack
9 Pillar Drill Machine
10 Vacuum Machine
11 Oil centrifuge machine
12 Dilo machine
13 CRT Kit
14 BDV test kit
15 IRT Kit
16 ERT Kit
17 PPM kit
18 Ferule printer
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41