Professional Documents
Culture Documents
PROJECT NAME :
PROJECT NUMBER :
PLANT
CONTRACTOR :
Permission to proceed does not constitute acceptance or approval of design calculations, analysis, test
methods or materials developed or selected by supplier and does not relieve supplier from full
compliance with contractual obligations
1. Approved
2a. Revise and Resubmit - Work may proceed subject to incorporation of changes indicated
2b. Revise – Work may proceed. Do not resubmit until it is final
3. Review not required
4. Rejected
PAGE : : 2
OF 21
DATE 07/11/2018
INDEX
1. REFERENCE DOCUMENTS/PARTIES ............................................................ 3
1.1. Documents ......................................................................................................... 3
1.2. Definitions ....................................................................................................... 3
2. SCOPE ................................................................................................................. 3
3. APPLICATION AND RESPONSIBILITIES ............................................................ 3
3.1 Application ..................................................................................................... 3
3.2 Responsibilities .............................................................................................. 4
4. DESCRIPTION ..................................................................................................... 4
4.1 General Requirements ..................................................................................... 4
4.2 Surface Preparation ......................................................................................... 5
4.3 Coating Materials ............................................................................................. 6
4.4 Paint Application .............................................................................................. 6
4.5 Safety Requirements ....................................................................................... 7
4.6 Testing – Inspection ......................................................................................... 8
Table 1. ................................................................................................................. 8
5. PAINTING SYSTEM.............................................................................................. 9
Table 2 .................................................................................................................. 9
Table 3 .................................................................................................................. 9
6. REPAIR OF DEFECTS ................................................................................. 10
7. HANDLING AND TRANSPORTATION................................................................ 10
8. DOCUMENTATION............................................................................................. 10
Attachment A* ......................................................................................................... 11
Attachment B........................................................................................................... 12
Attachment C .......................................................................................................... 19
PROJECT TITLE: - Project no:
PAGE : : 3
OF 21
DATE 07/11/2018
1. REFERENCE DOCUMENTS/PARTIES
1.1. Documents
S-000-13A0-001_R2_0001: General specification for painting
NACE RP-0188: Discontinuity (Holiday) Testing of New Protective Coatings on Conductive
Substrates
1.2. Definitions
EMPLOYER ORPIC
Project EPCC for SR-AP Firewater Integration Project
CONTRACTOR
Works Subcontractor a Construction company to which the CONTRACTOR has
subcontracted part of the field works.
Project Number 0.17.006
2. SCOPE
The procedure is indented to give the appropriate instructions for surface preparation and
painting against atmospheric corrosion. The instructions apply to the following items:
1. Newly purchased piping materials (pipes, valves, fittings and flanges)
2. Prefabricated items (vessels, piping spools)
3. Structural material and prefabricated structural items
4. Painting of existing facility modifications works (includes TIE-ins)
PAGE : : 4
OF 21
DATE 07/11/2018
3.2 Responsibilities
QA Dept. of the CONTRACTOR shall submit this procedure once approved by EMPLOYER to
Production Dept.
The applicable painting system shall conform to the specifications of the project.
The appointed Production Engineer is responsible for the receipt, check of quality and storage
of the paints. In his responsibilities are also to ensure that all requirements of this instruction
are implemented during sandblasting and painting works.
In case subcontractors perform sandblasting and painting works, the inspection described
herein shall be followed in full by an appointed Quality Engineer or Production Engineer of
CONTRACTOR. Manufacturer’s recommendation shall be followed for storage of coating
material at site. Expired material shall not be used at all and shall be removed from site, if any.
4. DESCRIPTION
4.1 General Requirements
Surface preparation and painting shall be performed in accordance with the herein mentioned
instructions.
The painting material shall be stored in a location that is protected from deleterious weather
conditions, well ventilated and free from excessive heat, open flame or other sources of
ignition. Conditions of storage shall also conform to paint manufacturer recommendations.
Paint shall be mixed and thinned in accordance with manufacturer’s instructions immediately
prior to application. Only thinners of a type recommended by the paint manufacturer shall be
used.
Thin-film coating are normally not acceptable for use on equipment on the project, with
exception in non-corrosive environment. Examples of unacceptable thin-film coatings are
electroplating, thin paint coating, ‘’cold-galvanizing’’, etc.
The surfaces listed below shall be shielded to prevent damage during sandblasting or/and
painting operations. After completion of operations all materials used for shielding and sealing
applications shall be removed.
Lining surfaces
Non-ferrous metal surfaces
Galvanized steel surfaces except for color identification
Aluminized steel surfaces
Stainless steel surfaces except insulated surfaces with operating temperature
between 50 – 120 °C
Internal surfaces of equipment and pipes
Bolts/nuts of flanged connections
Insulation jacketing metal sheet
PROJECT TITLE: - Project no:
PAGE : : 5
OF 21
DATE 07/11/2018
Interior wall surfaces, heating tubes and portions with heat resistant treatment of
furnaces, boilers, etc.
Screwed items of valves, gasket surfaces, finished machine parts of equipment and
piping components.
Bevels of open spools subject to welding at later stage (including 50mm of metal
adjacent to the bevel)
PAGE : : 6
OF 21
DATE 07/11/2018
When coating is carried out or the coating is left for drying and curing in adjacent
areas
When the surface temperature is not 3 oC above dew point temperature
All prefabricated surface preparation works are subject to SA 21/2, areas which deliberately
will remain uncoated (areas adjacent to bevel), surface preparation will be commenced again
at site to St2 or St3, whichever practical. Welds performed at site, prior coating, shall be
subject of surface preparation to St2 or St3. Primer shall be applied within 4 hours after the
preparation is finished
PAGE : : 7
OF 21
DATE 07/11/2018
7. Following weld defects: spatter, rough capping, slags, arc strikes and undercuts (which
dimensions are not accepted by ASME B31.3 code), sharp rough edges and burrs.
8. When the previous coat has not been allowed to fully cure
9. Under high wind conditions which can cause excessive over spray and other defects.
10. If rains showers are expected before the coating can completely dry and painted
surfaces will be exposed to the rain.
11. Painting shall be applied after post weld heat treatment
12. If a period of 4 hours after surface preparation is exceeded, coating is not allowed
unless the surface is prepared again. At least primer coating shall be completed before
the period of 4 hours has passed
Paint manufacturer’s recommendations shall be consulted in each case for possible special
temperature requirements.
Surfaces shall not be recoated until the previous coat has properly dried or cured, as per
coating material manufacturer’s recommendations. The surface may be considered ready for
recoating when the next coat can be applied without the development of paint film
irregularities, such as lifting or loss of adhesion of the undercoat.
Welds performed at site may be primed before hydrotest.
Where the required thickness is not achieved, additional coats shall be applied until the proper
thickness is obtained. Application shall be such, that the film thickness will not affect
appearance or service life of the paint.
For steel structures, piping and pressure vessels fabricated in shop or site the applicable
system is that of table 2. (system no. 1)
PAGE : : 8
OF 21
DATE 07/11/2018
Table 1.
Area/length of inspection Minimum number of Maximum number of
(m2 or m) measurements measurements allowed to
be repeated
Up to 1 5 1
Above 1 to 3 10 2
Above 3 to 10 15 3
Above 10 to 13 20 4
Above 30 to 100 30 6
Above 100 Add 10 every additional 20% of the minimum
100m2 or 100m number of measurements
Area above 1000 m2 or m, should be divided into smaller areas
PROJECT TITLE: - Project no:
PAGE : : 9
OF 21
DATE 07/11/2018
5. PAINTING SYSTEM
The coating and the color code (RAL) which will be applied on each item should be that of
table 2 below. Final DFT may be varies depending on the manufacturer’s recommendations.
For underground piping, the system of table 3 will be applied.
Table 2
Coating System no. 1 (Piping above ground <120°)
Surface preparation SSPC-SP10(SA 21/2): Near white blast cleaning
(shop):
Surface preparation SSPC-SP2(St2) or SSPC-SP3(St3): Hand tool or Power tool cleaning
(site):
Layer Type Commercial name DFT(μm)-Minimum
Hempel’s Hempadur 17360
1st layer Zinc rich epoxy 75
(Avantguard 750)
Hempel’s Hempadur Mastic
2rd layer High Solid build epoxy 150
MIO 45881
Hempel’s Hempathane Topcoat
3th layer Acrylic polyurethane 50
55210/55610
Total DFT 275
ITEM RAL
Steel Structures, platforms frames, ladders 7035
Nearest to Munsell 5R 4/14 (Code of
Firefighting piping materials (including valves)
Hempel 53320)
Notes: Datasheets in attachment B
Table 3
Coating System no. 2
Surface preparation (shop): SSPC-SP10(SA 21/2): Near white blast cleaning
Surface preparation (site): SSPC-SP2(St2) or SSPC-SP3(St3): Hand tool or Power tool cleaning
Layer Type Commercial name DFT(μm)
As per manufacturer’s
High Solid Build Hempel’s Hempadur
recommendation to achieve the 125-200 per layer
Epoxy Mastic MIO 45881
required thickness
Total DFT 500-600μm
Color designation as per RAL system will be chosen the nearest to Munsell
ITEM RAL
Nearest to Munsell 5R 4/14
Firefighting piping materials underground
(Code of Hempel 53320)
Notes: DFT is as per manufacturer’s recommendation, datasheet in attachment C.
PROJECT TITLE: - Project no:
PAGE : : 10
OF 21
DATE 07/11/2018
6. REPAIR OF DEFECTS
Wherever damaged painting is observed, but primer is not exposed, surface shall be cleaned
with appropriate thinner and rinsed with water dumped in a clean cloth. Subsequent mid-coat
and final coat will be applied by a roller. In case primer or metal is exposed, the defected area,
along with an adjacent 25mm around it, shall be prepared by a hand tool or power tool.
Subsequently the full system will be applied to the required DFT. An alternative primer may
be used to accommodate the change in surface preparation from SA21/2 to St2 or St3, as per
manufacturer’s recommendations. For galvanized surfaces if any, the repair shall be done by
a hand or power tool for surface preparation and apply a Zinc rich epoxy layer (for example
Hempadur Zinc 17360) by brush, roller, spraying from aerosol can or spraying by an agitated
pot.
8. DOCUMENTATION
The package of quality records for painting works, shall consist of the following documents:
▪ Surface preparation and Painting Inspection Reports
▪ Product Datasheets of coating materials to be applied at the final manufacturer’s data
book.
PROJECT TITLE: - Project no:
PAGE : : 11
OF 21
DATE 07/11/2018
Attachment A*
Contractor:
INSPECTION FORM No: REVISION :
Client:
Project:
Ambient Condition
Item Operator Painted Item Surface Relative
Week
No: I.D Description(S.N.) Temp. Humidity
(ºC) (%)
Inspection equipment:
Blasting: SA 2 ½:
Check of Roughness(μm) :
For Metron
PAGE : : 12
OF 21
DATE 07 1/2018
Attachment B
PROJECT TITLE: - Project no:
PAGE : : 13
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 14
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 15
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 16
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 17
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 18
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 19
OF 21
DATE 07/11/2018
Attachment C
PROJECT TITLE: - Project no:
PAGE : : 20
OF 21
DATE 07/11/2018
PROJECT TITLE: - Project no:
PAGE : : 21
OF 21
DATE 07/11/2018