Professional Documents
Culture Documents
17.1. The Bidding Documents shall be prepared by the Procuring Entity following the
standard forms and manuals prescribed by the GPPB. The Bidding Documents shall
ABC;
Eligibility Requirements;
the Act, and post-qualification, as well as the date, time and place of the prebid conference (where applicable),
submission of bids and opening of bids;
30.1. The BAC shall open the first bid envelopes in public to determine each bidder’s
compliance with the documents required to be submitted for eligibility and for the
technical requirements, as prescribed in this IRR. For this purpose, the BAC shall
document, it shall be rated “passed” for that particular requirement. In this regard,
bids that fail to include any requirement or are incomplete or patently insufficient
shall be considered as “failed.” Otherwise, the BAC shall rate the said first bid
envelope as “passed.”(a)
30.2. Immediately after determining compliance with the requirements in the first
envelope, the BAC shall forthwith open the second bid envelope of each remaining
eligible bidder whose first bid envelope was rated “passed.” The second envelope of
each complying bidder shall be opened within the same day, except as provided
under Section 33 of this IRR. In case any of the requirements in the second envelope
submitted total bid price exceeds the ABC, the BAC shall rate the bid concerned as
“failed.” Only bids that are determined to contain all the bid requirements for both
30.3. For the procurement of Goods where, due to the nature of the requirements of the
bids is likely to occur, a two (2)-stage bidding procedure may be employed. In these
cases, the Procuring Entity concerned shall prepare the Bidding Documents, including
the technical specification in the form of performance criteria only. Under this
procedure, prospective bidders shall be requested at the first stage to submit their
respective eligibility requirements if needed, and initial technical proposals only (no
price tenders). The concerned BAC shall then evaluate the technical merits of the
standards. A meeting/discussion shall then be held by the BAC with those eligible
bidders whose technical tenders meet the minimum required standards stipulated in
the Bidding Documents for purposes of drawing up the final revised technical
specifications are completed and duly approved by the concerned BAC, copies of the same shall be issued to all the
bidders identified in the first stage who shall then be
required to submit their revised technical tenders, including their price proposals in
two (2) separate sealed envelopes in accordance with this IRR, at a specified
deadline, after which time no more bids shall be received. The concerned BAC shall
31.1. The ABC shall be the upper limit or ceiling for acceptable bid prices. If a bid price, as
evaluated and calculated in accordance with this IRR, is higher than the ABC, the
31.2. For Foreign-funded Procurement, the ABC shall be applied as the ceiling: Provided,
The Procuring Entity has procedures in place to ensure that the ABC is based
Procuring Entity and that the estimates are based on adequate detailed
engineering (in the case of Infrastructure Projects) and reflect the quality,
supervision and risk and inflationary factors, as well as prevailing market prices,
The Procuring Entity has trained cost estimators on estimating prices and
The Procuring Entity has established a system to monitor and report bid prices
The Procuring Entity has established a monitoring and evaluation system for
10.1. In the submission of bids, the first envelope (Technical Proposal) shall contain
all the required documents for infrastructure projects under Section 25.2(b) of
10.2. The second envelope (Financial Proposal) shall contain all the required
documents for infrastructure projects under Section 25.3 of the IRR of R.A
Lump sum bid prices, which shall include the detailed engineering cost,