SP SINGLA CONSTRUCTIONS PVT. LTD.

BAILEY ROAD PROJECT


CONSTRUCTION PROGRAMME FOR R04 DRAIN
SL. NO. ACTIVITY DURATION START FINISH HINDRANCE STATUS
1 R04 DRAIN
CH 410-470
EXCAVATION
410-420 COMPLETED
420-430 COMPLETED
430-440 COMPLETED
440-450 COMPLETED
450-460 COMPLETED
460-470 SLUM ROAD COMPLETED
PCC
410-420 COMPLETED
420-430 COMPLETED
430-440 COMPLETED
440-450 COMPLETED
450-460 COMPLETED
460-470 SLUM ROAD COMPLETED
DRAIN
410-420 3 14-04-19 16-04-19 COMPLETED
420-430 3 17-04-19 19-04-19 BOTTOM SLAB COMPLETED
430-440 3 20-04-19 22-04-19
440-450 3 23-04-19 25-04-19
450-460 3 26-04-19 28-04-19
460-470 3 29-04-19 01-05-19
TOP SLAB
410-420 1 17-04-19 17-04-19
420-430 1 20-04-19 20-04-19
430-440 1 23-04-19 23-04-19
440-450 1 26-04-19 26-04-19
450-460 1 29-04-19 29-04-19
460-470 1 02-05-19 02-05-19

Page 1 of 3
SP SINGLA CONSTRUCTIONS PVT. LTD.
BAILEY ROAD PROJECT
CONSTRUCTION PROGRAMME FOR R04 DRAIN
SL. NO. ACTIVITY DURATION START FINISH HINDRANCE STATUS
CH 470-540
EXCAVATION
470-480 SLUM ROAD COMPLETED
480-490 BOUNDARY WALL COMPLETED
490-500 POST OFFICE COMPLETED
500-510 POST OFFICE COMPLETED
510-520 DRAIN COMPLETED
520-530 COMPLETED
530-540 COMPLETED
540-550 BPSC GATE COMPLETED
550-560 BPSC GATE COMPLETED
560-570 BPSC GATE COMPLETED
570-580 COMPLETED
580-590 COMPLETED
590-600 COMPLETED
600-610 1 17-04-19 17-04-19 COMPLETED
610-620 1 17-04-19 17-04-19
620-630 1 18-04-19 18-04-19
630-640
PCC
470-480 SLUM ROAD COMPLETED
480-490 BOUNDARY WALL COMPLETED
490-500 POST OFFICE COMPLETED
500-510 POST OFFICE COMPLETED
510-520 COMPLETED
520-530 COMPLETED
530-540 COMPLETED
540-550 BPSC GATE COMPLETED
550-560 BPSC GATE COMPLETED
560-570 BPSC GATE COMPLETED
570-580 1 16-04-19 16-04-19 COMPLETED
580-590 1 16-04-19 16-04-19 COMPLETED
590-600 COMPLETED
600-610 COMPLETED
610-620
620-630
630-640

Page 2 of 3
SP SINGLA CONSTRUCTIONS PVT. LTD.
BAILEY ROAD PROJECT
CONSTRUCTION PROGRAMME FOR R04 DRAIN
SL. NO. ACTIVITY DURATION START FINISH HINDRANCE STATUS
DRAIN
470-480 SLUM ROAD COMPLETED
480-490 BOUNDARY WALL COMPLETED
490-500 12-04-19 12-04-19 POST OFFICE COMPLETED
500-510 12-04-19 12-04-19 POST OFFICE COMPLETED
510-520 3 12-04-19 12-04-19 COMPLETED
520-530 3 12-04-19 12-04-19 COMPLETED
530-540 3 13-04-19 13-04-19 COMPLETED
540-550 COMPLETED
550-560
560-570
570-580
580-590
590-600
600-610
610-620
620-630
630-640
TOP SLAB
470-480 1 17-04-19 17-04-19 SLUM ROAD SLABS TO BE SHIFTED
480-490 18-04-19 18-04-19 BOUNDARY WALL SLABS TO BE SHIFTED
490-500 19-04-19 19-04-19 POST OFFICE SLABS TO BE SHIFTED
500-510 20-04-19 20-04-19 POST OFFICE SLABS TO BE SHIFTED
510-520 1 21-04-19 21-04-19 SLABS TO BE SHIFTED
520-530 1 22-04-19 22-04-19 SLABS TO BE SHIFTED
530-540 1 23-04-19 23-04-19 SLABS TO BE SHIFTED
540-550 COMPLETED
550-560
560-570
570-580
580-590
590-600
600-610
610-620
620-630
630-640

Page 3 of 3