CRONOGRAMA DE AVANCE DE OBRA

PROYECTO: MEJORAMIENTO DE LA OFERTA DE LOS SERVICIOS EDUCATIVOS DE LA I.E. N° 86330 AMPAS, DISTRITO DE HUARI, PROVINCIA DE HUARI - ANCASH
Id Descripción Partida Duración
mes 1 mes 2 mes 3 mes 4 mes 5
semana 1 semana 2 semana 3 semana 4 semana 5 semana 6 semana 7 semana 8 semana 9 semana 10 semana 11 semana 12 semana 13 semana 14 semana 15 semana 16 semana 17 semana 18 semana 19 semana 20 semana 21
S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D
0 MEJORAMIENTO DE LA OFERTA DE LOS SERVICIOS EDUCATIVOS DE LA 90 días
I.E. N° 86330 AMPAS, DISTRITO DE HUARI - ANCASH
1 1 ESTRUCTURAS 51 días
2 1.1 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD & 6 días
MITIGACION DE IMPACTO AMBIENTAL
3 1.1.1 OBRAS PROVISIONALES 2 días
4 1.1.1.1 OFICINA, ALMACEN Y GUARDIANIA 1 día
5 1.1.1.2 CARTEL DE OBRA 1 día
6 1.1.1.3 MOVILIZACION DE EQUIPO Y HERRAMIENTAS 1 día
7 1.1.1.4 CERCO PROVISIONAL DE OBRA 1 día
8 1.1.1.5 INSTALACION PROVISIONAL DE AGUA 1 día
9 1.1.1.6 INSTALACION PROVISIONAL DE ENERGIA ELECTRICA 1 día
10 1.1.2 TRABAJOS PRELIMINARES 3 días
11 1.1.2.1 LIMPIEZA MANUAL DE TERRENO 3 días
12 1.1.2.2 TRAZO, NIVELACION Y REPLANTEO 3 días
13 1.1.2.3 DEMOLICION DE ESTRUCTURAS DE MATERIAL RUSTICO EXISTENTE 3 días
14 1.1.3 SEGURIDAD Y SALUD 1 día
15 1.1.3.1 EQUIPOS DE PROTECCIÓN INDIVIDUAL 1 día
16 1.1.3.2 EQUIPOS DE PROTECCION COLECTIVA 1 día
17 1.1.3.3 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD 1 día
18 1.1.4 MITIGACION DE IMPACTO AMBIENTAL 1 día
19 1.1.4.1 MITIGACION DE IMPACTO AMBIENTAL 1 día
20 1.2 MODULO DE AULAS 35 días
21 1.2.1 MOVIMIENTO DE TIERRAS 5 días
22 1.2.1.1 EXCAVACION PARA CIMIENTOS HASTA 1.00m. TERRENO NORMAL 2 días
23 1.2.1.2 EXCAVACION PARA ZAPATAS DE 1.40 MT A 1.70 MT DE PROFUNDIDAD 2 días
24 1.2.1.3 NIVELACION Y APISONADO INTERIOR MANUAL 2 días
25 1.2.1.4 ACARREO DE MATERIAL EXCEDENTE 2 días
26 1.2.1.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día
27 1.2.2 CONCRETO SIMPLE 8 días
28 1.2.2.1 SOLADO PARA ZAPATAS 1:12 E=2" 1 día
29 1.2.2.2 CONCRETO P/SUB ZAPATA O FALSA ZAPATA 1 día
30 1.2.2.3 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% PG 2 días
31 1.2.2.4 CONCRETO SOBRECIMIENTOS MEZCLA 1:8+25% P.M 3 días
32 1.2.2.5 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS 3 días
33 1.2.2.6 CONCRETO EN FALSO PISO MEZCLA1:10 CEMENTO-HORMIGON E=4" 1 día
34 1.2.3 CONCRETO ARMADO 23 días
35 1.2.3.1 ZAPATAS 7 días
36 1.2.3.1.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 2 días
37 1.2.3.1.2 CONCRETO F'C=210 KG/CM2 (zapatas) 2 días
38 1.2.3.1.3 CURADO DE CONCRETO 5 días
39 1.2.3.2 VIGAS DE CIMENTACION 12 días
40 1.2.3.2.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 3 días
41 1.2.3.2.2 ENCOFRADO Y DESENCOFRADO (Vigas de cimentacion) 3 días
42 1.2.3.2.3 CONCRETO F'C= 210 KG/CM2 (Vigas de cimentacion) 2 días
43 1.2.3.2.4 CURADO DE CONCRETO 7 días
44 1.2.3.3 COLUMNAS 11 días
45 1.2.3.3.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 4 días
46 1.2.3.3.2 ENCOFRADO Y DESENCOFRADO (Columnas) 4 días
47 1.2.3.3.3 CONCRETO F'C=210 KG/CM2 (Columnas) 2 días
48 1.2.3.3.4 CURADO DE CONCRETO 7 días
49 1.2.3.4 VIGAS 12 días
50 1.2.3.4.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 3 días
51 1.2.3.4.2 ENCOFRADO Y DESENCOFRADO (Vigas) 3 días
52 1.2.3.4.3 CONCRETO F'C=210 KG/CM2 (Vigas) 2 días
53 1.2.3.4.4 CURADO DE CONCRETO 7 días
54 1.2.4 ESTRUCTURAS DE MADERA Y COBERTURA 7 días
55 1.2.4.1 TIJERALES DE MADERA 2 días
56 1.2.4.2 CORREAS DE MADERA TORNILLO DE 2"x2" 2 días
57 1.2.4.3 COBERTURA DE TEJA ANDINA 3 días
58 1.2.4.4 CUMBRERA DE TEJA ANDINA 3 días
59 1.3 SERVICIOS HIGIENICOS 19 días
60 1.3.1 MOVIMIENTO DE TIERRAS 3 días
61 1.3.1.1 EXCAVACION PARA CIMIENTOS HASTA 1.00m. TERRENO NORMAL 1 día
62 1.3.1.2 RELLENO CON MATERIAL PROPIO 1 día
63 1.3.1.3 NIVELACION Y APISONADO INTERIOR MANUAL 1 día
64 1.3.1.4 ELIMINACION DE MATERIAL EXCEDENTE 1 día
65 1.3.2 CONCRETO SIMPLE 10 días
66 1.3.2.1 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% PG 1 día
67 1.3.2.2 ENCOFRADO Y DEDESENCOFRADO NORMAL EN SOBRECIMIENTOS 2 días
68 1.3.2.3 CONCRETO SOBRECIMIENTOS MEZCLA 1:8+25% P.M 2 días
69 1.3.2.4 CURADO DE CONCRETO 7 días
70 1.3.3 CONCRETO ARMADO 13 días
71 1.3.3.1 COLUMNAS 10 días
72 1.3.3.1.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 2 días
73 1.3.3.1.2 ENCOFRADO Y DESENCOFRADO (Columnas) 2 días
74 1.3.3.1.3 CONCRETO F'C=210 KG/CM2 (Columnas) 1 día
75 1.3.3.1.4 CURADO DE CONCRETO 7 días
76 1.3.3.2 VIGAS 10 días
77 1.3.3.2.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 2 días
78 1.3.3.2.2 ENCOFRADO Y DESENCOFRADO (Vigas) 2 días
79 1.3.3.2.3 CONCRETO F'C=210 KG/CM2 (Vigas) 1 día
80 1.3.3.2.4 CURADO DE CONCRETO 7 días
81 1.3.4 ESTRUCTURAS DE MADERA Y COBERTURA 3 días
82 1.3.4.1 TIJERALES DE MADERA 1 día
83 1.3.4.2 CORREAS DE MADERA TORNILLO DE 2"x2" 1 día
84 1.3.4.3 COBERTURA DE TEJA ANDINA 1 día
85 1.3.4.4 CUMBRERA DE TEJA ANDINA 1 día
86 1.4 CERCO PERIMETRICO 37 días
87 1.4.1 MOVIMIENTO DE TIERRAS 6 días
88 1.4.1.1 EXCAVACION PARA CIMIENTOS HASTA 1.00m. TERRENO NORMAL 4 días
89 1.4.1.2 ACARREO DE MATERIAL EXCEDENTE D=50 m. 2 días
90 1.4.1.3 ELIMINACION DE MATERIAL EXCEDENTE 1 día
91 1.4.2 CONCRETO SIMPLE 16 días
92 1.4.2.1 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% PG 2 días
93 1.4.2.2 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS 7 días
94 1.4.2.3 CONCRETO SOBRECIMIENTOS MEZCLA 1:8+25% P.M 7 días
95 1.4.2.4 CURADO DE CONCRETO 7 días
96 1.4.3 CONCRETO ARMADO 22 días
97 1.4.3.1 COLUMNETAS 16 días
98 1.4.3.1.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 5 días
99 1.4.3.1.2 ENCOFRADO Y DESENCOFRADO (Columnetas) 5 días
100 1.4.3.1.3 CONCRETO F'C=175 KG/CM2 P/COLUMNETAS 4 días
101 1.4.3.1.4 CURADO DE CONCRETO 7 días
102 1.4.3.2 VIGA COLLARIN 13 días
103 1.4.3.2.1 ACERO DE REFUERZO F'Y=4200 KG/CM2 4 días
104 1.4.3.2.2 ENCOFRADO Y DESENCOFRADO (Viga Collarin) 4 días
105 1.4.3.2.3 CONCRETO F'C=175 KG/CM2 P/VIGA COLLARIN 2 días
106 1.4.3.2.4 CURADO DE CONCRETO 7 días
107 1.5 CONTROL DE CALIDAD 1 día
108 1.5.1 PRUEBA DE CALIDAD DEL CONCRETO 1 día
109 1.5.2 DISEÑO DE MEZCLA 1 día
110 1.6 FLETE 1 día
111 1.6.1 FLETE TERRESTRE 1 día
112 2 ARQUITECTURA 62 días
113 2.1 MODULO DE AULAS 42 días
114 2.1.1 MUROS Y TABIQUES 14 días
115 2.1.1.1 MURO DE LADRILLO KK DE ARCILLA DE CABEZA CM 1:4x1.5 CM 5 días
116 2.1.1.2 MURO DE LADRILLO KK DE ARCILLA DE SOGA CM 1:4x1.5 CM 2 días
117 2.1.1.3 CURADO DE MUROS DE ALBAÑILERIA 7 días
118 2.1.2 REVOQUES ENLUCIDOS Y MOLDURAS 9 días
119 2.1.2.1 TARRAJEO PRIMARIO 4 días
120 2.1.2.2 TARRAJEO DE MUROS INTERIORES 4 días
121 2.1.2.3 TARRAJEO DE MUROS EXTERIORES 4 días
122 2.1.2.4 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS, VIGAS Y COLUMNAS 4 días
123 2.1.2.5 CURADO DE REVOQUES 1 día
124 2.1.3 CIELORRASOS 16 días
125 2.1.3.1 CIELO RASO CON BALDOSAS ACUSTICAS DE 60cm x 60cm 2 días
126 2.1.3.2 CIELO RASO CON PLANCHA DE FIBROCEMENTO 4mm (EXTERIOR) 2 días
127 2.1.3.3 CONTRAPISO DE 2" 2 días
128 2.1.3.4 PISO DE CEMENTO ACABADO Y PULIDO 2 días
129 2.1.3.5 PISO CERAMICO 0.45X0.45 ALTO TRANSITO 3 días
130 2.1.3.6 AFIRMADO DE E=15CM PARA VEREDAS 1 día
131 2.1.3.7 CONCRETO F'C=140KG/CM2 (Veredas) 1 día
132 2.1.3.8 CURADO DE CONCRETO 7 días
133 2.1.4 CONTRAZOCALOS 3 días
134 2.1.4.1 CONTRAZOCALO DE CEMENTO PULIDO H=10 m. 3 días
135 2.1.5 PISOS Y VEREDAS 2 días
136 2.1.5.1 CONTRAZOCALO DE CERAMICA COLOR CLARO H=0.10 m. 2 días
137 2.1.6 CARPINTERIA DE MADERA 2 días
138 2.1.6.1 PUERTA APANELADA 35mm. INCLUYE MARCO TORNILLO 2"x3" 2 días
139 2.1.6.2 VENTANA DE MADERA TORNILLO CON SEGURO DE 1/2" 2 días
140 2.1.7 CERRAJERIA 3 días
141 2.1.7.1 REJA METALICA PARA PUERTA TIPO 1 3 días
142 2.1.7.2 REJA METALICA PARA VENTANA TIPO 1 3 días
143 2.1.8 VIDRIOS, CRISTALES Y SIMILARES 2 días
144 2.1.8.1 VIDRIO SEMIDOBLE INCOLORO CRUDO 2 días
145 2.1.9 PINTURA 5 días
146 2.1.9.1 PINTURA LATEX EN CIELO RAZO EXTERIOR 1 día
147 2.1.9.2 PINTURA LATEX EN MUROS INTERIORES 3 días
148 2.1.9.3 PINTURA LATEX EN MUROS EXTERIORES 3 días
149 2.1.9.4 BARNIZ EN VENTANAS DE MADERA 1 día
150 2.1.9.5 BARNIZ EN PUERTAS DE MADERA 1 día
151 2.2 SERVICIOS HIGIENICOS 29 días
152 2.2.1 MUROS Y TABIQUES 9 días
153 2.2.1.1 MURO DE LADRILLO KK DE ARCILLA DE SOGA CM 1:4x1.5 CM 4 días
154 2.2.1.2 CURADO DE MUROS DE ALBAÑILERIA 5 días
155 2.2.2 REVOQUES ENLUCIDOS Y MOLDURAS 11 días
156 2.2.2.1 TARRAJEO DE MUROS INTERIORES 5 días
157 2.2.2.2 TARRAJEO DE MUROS EXTERIORES 5 días
158 2.2.2.3 VESTIDURA DE DERRAMES EN PUERTAS Y VENTANAS, VIGAS Y COLUMNAS 1 día
159 2.2.2.4 CURADO DE REVOQUES 5 días
160 2.2.3 CIELORRASOS 2 días
161 2.2.3.1 CIELO RASO CON PLANCHA DE FIBROCEMENTO 4mm (EXTERIOR) 2 días
162 2.2.4 PISOS Y VEREDAS 13 días
163 2.2.4.1 FALSO PISO DE E=10 CM 1 día
164 2.2.4.2 CONTRAPISO DE 2" 1 día
165 2.2.4.3 PISO CERAMICO 0.45X0.45 ALTO TRANSITO 2 días
166 2.2.4.4 AFIRMADO DE E=15CM PARA VEREDAS 1 día
167 2.2.4.5 CONCRETO FC=175 KG/CM2 (VEREDAS) 1 día
168 2.2.4.6 CURADO DE CONCRETO 7 días
169 2.2.5 ZOCALOS & CONTRAZOCALOS 5 días
170 2.2.5.1 ZOCALO DE CERAMICA 0.20x0.30 EN BAÑO O SIMILAR 4 días
171 2.2.5.2 CONTRAZOCALO DE CEMENTO PULIDO H=10 m. 1 día
172 2.2.6 CARPINTERIA DE MADERA 1 día
173 2.2.6.1 PUERTA APANELADA 35mm. INCLUYE MARCO TORNILLO 2"x3" 1 día

Proyecto: MEJORAMIENTO DE LA O ́ Hito inactivo Resumen inactivo Tarea manual solo duración
Fecha: dom 28/04/19

Página 1
CRONOGRAMA DE AVANCE DE OBRA

PROYECTO: MEJORAMIENTO DE LA OFERTA DE LOS SERVICIOS EDUCATIVOS DE LA I.E. N° 86330 AMPAS, DISTRITO DE HUARI, PROVINCIA DE HUARI - ANCASH
Id Descripción Partida Duración
mes 1 mes 2 mes 3 mes 4 mes 5
semana 1 semana 2 semana 3 semana 4 semana 5 semana 6 semana 7 semana 8 semana 9 semana 10 semana 11 semana 12 semana 13 semana 14 semana 15 semana 16 semana 17 semana 18 semana 19 semana 20 semana 21
S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D
174 2.2.7 PINTURA 5 días
175 2.2.7.1 PINTURA LATEX EN CIELO RAZO 1 día
176 2.2.7.2 PINTURA LATEX EN MUROS INTERIORES 3 días
177 2.2.7.3 PINTURA LATEX EN MUROS EXTERIORES 3 días
178 2.2.7.4 BARNIZ EN PUERTAS DE MADERA 1 día
179 2.3 CERCO PERIMETRICO 30 días
180 2.3.1 MUROS Y TABIQUES 22 días
181 2.3.1.1 MURO DE LADRILLO KK DE ARCILLA DE SOGA CM 1:4x1.5 CM CARAVISTA 15 días
182 2.3.1.2 CURADO DE MUROS DE ALBAÑILERIA 7 días
183 2.3.2 REVOQUES ENLUCIDOS Y MOLDURAS 12 días
184 2.3.2.1 TARRAJEO EN COLUMNETAS & VIGAS COLLARIN 4 días
185 2.3.2.2 TARRAJEO EN SOBRECIMIENTOS 3 días
186 2.3.2.3 CURADO DE REVOQUES 5 días
187 2.3.3 CARPINTERIA METALICA 1 día
188 2.3.3.1 PUERTA METALICA (Acceso principal) 1 día
189 2.3.4 PINTURA 7 días
190 2.3.4.1 PINTURA BARNIZ EN MURO CARAVISTA 4 días
191 2.3.4.2 PINTURA ESMALTE EN CONTRAZOCALOS 3 días
192 2.4 VARIOS 18 días
193 2.4.1 PATIO DE HONOR Y AREA DE CIRCULACION 13 días
194 2.4.1.1 OBRAS PROVICIONALES 1 día
195 2.4.1.1.1 TRAZO, NIVELACION Y REPLANTEO 1 día
196 2.4.1.2 MOVIMIENTO DE TIERRAS 8 días
197 2.4.1.2.1 CORTE DE MATERIAL SUELTO 4 días
198 2.4.1.2.2 NIVELACION Y APISONADO INTERIOR MANUAL 2 días
199 2.4.1.2.3 AFIRMADO DE 4" EN INTERIORES, PATIOS 2 días
200 2.4.1.2.4 ELIMINACION DE MATERIAL EXCEDENTE 1 día
201 2.4.1.3 CONCRETO SIMPLE 4 días
202 2.4.1.3.1 ENCOFRADO Y DESENCOFRADO 3 días
203 2.4.1.3.2 CONCRETO F'C=175 KG/CM2 3 días
204 2.4.1.3.3 SOLADO PARA ZAPATAS 1:12 E=3" 1 día
205 2.4.1.3.4 CURADO P/ESTRUCTURAS DE CONCRETO 1 día
206 2.4.1.3.5 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" 1 día
207 2.4.2 PODIO DE IZAMIENTO 5 días
208 2.4.2.1 MOVIMIENTO DE TIERRAS 5 días
209 2.4.2.1.1 CORTE DE MATERIAL SUELTO 2 días
210 2.4.2.1.2 NIVELACION Y APISONADO INTERIOR MANUAL 2 días
211 2.4.2.1.3 ACARREO DE MATERIAL EXCEDENTE 2 días
212 2.4.2.1.4 ELIMINACION DE MATERIAL EXCEDENTE 1 día
213 2.4.2.2 PODIO 1 día
214 2.4.2.2.1 ENCOFRADO Y DESENCOFRADO 1 día
215 2.4.2.2.2 CONCRETO F'C=175 KG/CM2 1 día
216 2.4.2.2.3 POSTE DE F°G° PARA IZAMIENTO DE BANDERA 1 día
217 2.4.2.2.4 CURADO P/ESTRUCTURAS DE CONCRETO 1 día
218 2.4.3 AREA DE RECREACION INFANTIL 1 día
219 2.4.3.1 JUEGOS RECREATIVOS 1 día
220 2.5 MOBILIARIO Y EQUIPAMIENTO 1 día
221 2.5.1 MOBILIARIO PARA AULAS (02) 1 día
222 2.5.1.1 PIZARRA ACRILICA DE 3.00 x 1.40 1 día
223 2.5.1.2 MOBILIARIO BIPERSONAL PARA ALUMNOS 1 día
224 2.5.1.3 PUPITRE DE MADERA PARA DOCENTE 1 día
225 2.5.2 MOBILIARIO PARA SALA DE COMPUTO 1 día
226 2.5.2.1 MUEBLE PARA COMPUTADORA 1 día
227 2.5.2.2 PIZARRA ACRILICA DE 3.00 x 1.40 1 día
228 2.5.2.3 PUPITRE DE MADERA PARA DOCENTE 1 día
229 2.5.3 MOBILIARIO PARA BIBLIOTECA 1 día
230 2.5.3.1 MOBILIARIO BIPERSONAL PARA ALUMNOS 1 día
231 2.5.3.2 PIZARRA ACRILICA DE 3.00 x 1.40 1 día
232 2.5.3.3 MOBILIARIO PARA MODULO DE BIBLIOTECA 1 día
233 2.5.4 MOBILIARIO PARA DIRECCION 1 día
234 2.5.4.1 MOBILIARIO PARA OFICINA ADMINISTRATIVA 1 día
235 2.5.4.2 MOBILIARIO PARA USO MULTIPLES 1 día
236 2.5.5 EQUIPAMIENTO PARA SALA DE COMPUTO 1 día
237 2.5.5.1 EQUIPO DE COMPUTO DE ULTIMA GENERACION 1 día
238 2.5.5.2 IMPRESORA MULTIFUNCIONAL A4 1 día
239 2.5.6 MOBILIARIO PARA BIBLIOTECA 1 día
240 2.5.6.1 IMPRESORA MULTIFUNCIONAL A4 1 día
241 2.5.6.2 MODULO DE BIBLIOTECA DIDACTICA 1 día
242 2.5.7 EQUIPAMIENTO PARA SISTEMA DE COMUNICACION 1 día
243 2.5.7.1 EQUIPO DE SONIDO 1 día
244 2.5.7.2 EQUIPO DE PROYECCION AUDIO Y VISUAL PARA USO DEL PRONOI 1 día
245 2.6 CAPACITACION 1 día
246 2.6.1 CAPACITACIONES Y CHARLAS (DOCENTE Y PADRES DE FAMILIA) 1 día
247 2.6.2 EQUIPO DE COMPUTO DE ULTIMA GENERACION 1 día
248 3 INSTALACIONES SANITARIAS 34 días
249 3.1 MODULO DE AULAS 2 días
250 3.1.1 SISTEMA DE DRENAJE PLUVIAL 2 días
251 3.1.1.1 CANALETA DE FIERRO GALVANIZADO 2 días
252 3.1.1.2 MONTANTE - TUBO PVC SAL Ø3" 2 días
253 3.1.1.3 CONCRETO P/PEDESTALDE SOPORTE DE MONTANTE F'C=175 KG/CM2. 2 días
254 3.2 SERVICIOS HIGIENICOS 22 días
255 3.2.1 INSTALACIONES DE AGUA 8 días
256 3.2.1.1 SALIDA DE AGUA FRIA TUBERIA PVC C-10 DE 1/2" 3 días
257 3.2.1.2 VALVULA DE COMPUERTA 1/2" 1 día
258 3.2.1.3 VALVULA DE COMPUERTA 3/4" 1 día
259 3.2.1.4 TUBERIA PVC SAP 1/2" CLASE 10 1 día
260 3.2.1.5 TUBERIA PVC SAP 3/4" CLASE 10 1 día
261 3.2.1.6 ACCESORIOS PVC SAP PARA AGUA FRIA 3 días
262 3.2.1.7 CAJA DE REGISTRO DEL SISTEMA DE AGUA FRIA 3 días
263 3.2.2 INSTALACIONES DE DESAGUE 9 días
264 3.2.2.1 SALIDA DE DESAGUE DE 2" EN PVC 2 días
265 3.2.2.2 SALIDA DE DESAGUE DE 4" EN PVC 2 días
266 3.2.2.3 SALIDA PARA VENTILACION DE 2" DE PVC 1 día
267 3.2.2.4 REGISTRO DE BRONCE DE 4" 1 día
268 3.2.2.5 TUBERIA DE PVC SAL 2" 2 días
269 3.2.2.6 TUBERIA DE PVC SAL 4" 2 días
270 3.2.2.7 TUBERIA DE PVC SAL 6" 2 días
271 3.2.2.8 CAJA DE REGISTRO DE 12" X 24" 2 días
272 3.2.2.9 SUMIDERO DE BRONCE RODCADO 2" 2 días
273 3.2.2.10 CANALETA DE DRENAJE PLUVIAL Y REJILLA METALICA 2 días
274 3.2.2.11 ACCESORIOS PVC SAL PARA DESAGUE 2 días
275 3.2.3 APARATOS Y ACCESORIOS SANITARIOS 2 días
276 3.2.3.1 INODORO TANQUE BAJO BLANCO 2 días
277 3.2.3.2 LAVATORIO DE LOSA BLANCA 2 días
278 3.2.3.3 COLOCACION DE APARATOS SANITARIOS 2 días
279 3.2.4 SISTEMA DE DESAGUE PLUVIAL 3 días
280 3.2.4.1 CANALETA DE FIERRO GALVANIZADO 1 día
281 3.2.4.2 TUBERIA DE DESAGUE PVC SAL 4" 1 día
282 3.2.4.3 CAJA DE REGISTRO DE CONCRETO 175 P/EVAC. PLUVIAL 1 día
283 3.2.4.4 CANALETA DE DRENAJE PLUVIAL Y REJILLA METALICA 1 día
284 3.2.4.5 ABRAZADERA DE FIJACION DE TUBERIA DE 4" 1 día
285 3.3 CERCO PERIMETRICO 9 días
286 3.3.1 SISTEMA DE DRENAJE SUBTERRANEO - RED COLECTOR 9 días
287 3.3.1.1 TRAZO, NIVELACION Y REPLANTEO 2 días
288 3.3.1.2 CORTE DE MATERIAL SUELTO 2 días
289 3.3.1.3 NIVELACION Y APISONADO INTERIOR MANUAL 2 días
290 3.3.1.4 ACARREO DE MATERIAL EXCEDENTE 2 días
291 3.3.1.5 TUBERIA HDPE CORRUGADA PERFORADA D=110 MM 3 días
292 3.3.1.6 FILTRO DE GRAVA 3 días
293 3.3.1.7 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO 1 día
294 3.3.1.8 ELIMINACION DE MATERIAL EXCEDENTE 1 día
295 3.4 PATIOS Y CIRCULACION (REJILLA PLUVIALES) 13 días
296 3.4.1 RED DE COLETOR 7 días
297 3.4.1.1 TRAZO, NIVELACION Y REPLANTEO 2 días
298 3.4.1.2 CORTE DE MATERIAL SUELTO 2 días
299 3.4.1.3 NIVELACION Y APISONADO INTERIOR MANUAL 1 día
300 3.4.1.4 ACARREO DE MATERIAL EXCEDENTE 1 día
301 3.4.1.5 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO 3 días
302 3.4.1.6 TUBERIA C.S.N. U.FLEXIBLE DE 6" (150MM) 3 días
303 3.4.1.7 ELIMINACION DE MATERIAL EXCEDENTE 1 día
304 3.4.2 RED DE EMISORES 6 días
305 3.4.2.1 TRAZO, NIVELACION Y REPLANTEO 2 días
306 3.4.2.2 CORTE DE MATERIAL SUELTO 2 días
307 3.4.2.3 NIVELACION Y APISONADO INTERIOR MANUAL 1 día
308 3.4.2.4 ACARREO DE MATERIAL EXCEDENTE D=50 M 1 día
309 3.4.2.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día
310 3.4.2.6 ENCOFRADO Y DESENCOF MUROS DE CANAL 1 día
311 3.4.2.7 CONCRETO F'C=175KG/CM2 P/MUROS DE CANAL 1 día
312 3.4.2.8 REJILLA METALICA P/ALCANTARILLADO PLUVIAL (A=0.40 m) 1 día
313 3.4.2.9 CONCRETO F'C=175 KG/CM2 P/ CAJAS DE REUNION 1 día
314 4 INSTALACIONES ELECTRICAS 15 días
315 4.1 MODULO DE AULAS 7 días
316 4.1.1 SALIDAS PARA ALUMBRADO Y TOMACORRIENTES 2 días
317 4.1.1.1 SALIDA PARA CENTRO DE LUZ 1 día
318 4.1.1.2 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC 1 día
319 4.1.2 INSTALACION DE ARTEFACTOS Y LAMPARAS 5 días
320 4.1.2.1 INSTALACION DE ACCESORIOS LUMINARIAS 2 días
321 4.1.2.2 INSTALACION DE ACCESORIOS TOMACORRIENTES 2 días
322 4.1.2.3 POZO DE CONEXION A TIERRA EN SISTEMA, ALUMBRADO, TOMACORRIENTE 1 día
323 4.2 SERVICIOS HIGIENICOS 3 días
324 4.2.1 SALIDAS PARA ALUMBRADO Y TOMACORRIENTES 3 días
325 4.2.1.1 SALIDA PARA CENTRO DE LUZ 1 día
326 4.2.1.2 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON PVC 1 día
327 4.2.1.3 INSTALACION DE ACCESORIOS LUMINARIAS 1 día
328 4.2.1.4 ARTEFACTOS SPOT FIJO P/LAMPARA AHORRADORA 25W 1 día
329 4.3 CERCO PERIMETRICO 5 días
330 4.3.1 CONEXIÓN A LA RED EXTERNA DE MEDIDORES 5 días
331 4.3.1.1 SALIDAS PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES 4 días
DÉBILES
332 4.3.1.1.1 TRAZO, NIVELACION Y REPLANTEO 2 días
333 4.3.1.1.2 CORTE DE MATERIAL SUELTO 2 días
334 4.3.1.1.3 NIVELACION Y APISONADO INTERIOR MANUAL 1 día
335 4.3.1.1.4 ACARREO DE MATERIAL EXCEDENTE D=50 M 1 día
336 4.3.1.1.5 ELIMINACION DE MATERIAL EXCEDENTE 1 día
337 4.3.1.1.6 CABLE NYY 3-1X12MM2 TUB PVC 2". 1 día
338 4.3.1.2 TABLEROS PRINCIPAL Y DE DISTRIBUCION 1 día
339 4.3.1.2.1 TABLERO ELECTRICO GABINETE METALICO PARA DISTRIBUCION DE 1 día
6 CIRCUITOS (TABLERO GENERAL)
340 4.3.1.2.2 TABLERO ELECTRICO GABINETE METALICO PARA DISTRIBUCION DE 1 día
4 CIRCUITOS
341 4.3.1.3 ARTEFACTOS DE ILUMINACION EXTERIOR 1 día
342 4.3.1.3.1 CAJA RECTANGULAR DE FIERRO GALVANIZADO 100X100X30 MM. 1 día
343 4.3.1.3.2 SALIDA DE PARED C/CABLE AWG TW 2.5MM(14)+D PVC SEL 16MM(5/8) 1 día
344 4.3.1.3.3 REFLECTOR LED DE 20W EN EXTERIORES (Inc. Instalacion y Accesorios). 1 día

Proyecto: MEJORAMIENTO DE LA O ́ Hito inactivo Resumen inactivo Tarea manual solo duración
Fecha: dom 28/04/19

Página 2