You are on page 1of 3

ELPIDIO S.

UY, doing business under the name and  The PEA-PMO evaluated the EDC’s claim
style EDISON DEVELOPMENT & CONSTRUCTION, and arrived at a lesser amount of
vs. ₱146,484,910.
PUBLIC ESTATES AUTHORITY and the  The Performance Audit Committee (PAC)
HONORABLE COURT OF APPEALS, reviewed the progress report and noted that
the EDC’s landscaping works were behind
 Respondent Public Estates Authority (PEA) schedule by twenty percent (20%). The PAC
was designated as project manager by the considered this delay unreasonable and
Bases Conversion Development Authority intolerable, and immediately recommended to
(BCDA), primarily tasked to develop its 105- BCDA the termination of the landscaping
hectare demilitarized lot in Fort Bonifacio, contract.
Taguig City into a first-class memorial park to  The BCDA adopted PAC’s recommendation
be known as Heritage Park. and demanded from PEA the termination of
 PEA then engaged the services of Makati the contract with EDC. In compliance, PEA
Development Corporation (MDC) to terminated the agreement.
undertake the horizontal works on the project;  PEA fully paid all the progress billings but it
and Uy, doing business under the name and did not heed EDC’s additional claims.
style Edison Development and Construction Consequently, Uy filed a Complaint with the
(EDC), to do the landscaping. Construction Industry Arbitration Commission
 For a contract price of ₱355,080,141.15, PEA (CIAC).
and EDC signed the Landscaping and
Construction Agreement  the CIAC rendered a Decision in favor of the
 EDC undertook to complete the landscaping Contractor ELPIDIO S. UY and Award is
works in four hundred fifty (450) days hereby made on its monetary claims as
commencing on the date of receipt of the follows:
notice to proceed.
 EDC received the notice to proceed on --- for the cost of idle
December 3, 1996; and three (3) days after, ₱19,604,132.06
time of equipment.
or on December 6, 1996, it commenced the
mobilization of the equipment and manpower --- for the cost of idled
needed for the project. 2,275,721.00
manpower.
 PEA, however, could not deliver any work
area to EDC because the horizontal works of --- for the construction of
MDC were still ongoing. EDC commenced the 6,050,165.05 the nursery shade net
landscaping works only on January 7, 1997 area.
when PEA finally made an initial delivery of a
work area. --- for attorney’s fees
605,016.50
 PEA continuously incurred delay in the
turnover of work areas. Resultantly, the  Uy received the CIAC decision on June 7,
contract period of 450 days was extended to 2000. On June 16, 2000, Uy filed a motion for
693 days. correction of computation.
 In view of the delay in the delivery of work  The CIAC, however, failed to resolve Uy’s
area, EDC claimed additional cost from the motion within the 30-day period as provided in
PEA-PMO amounting to ₱181,338,056.30. its rules, and Uy considered it as denial of the
 Specifically, Uy alleged that he incurred motion.
additional rental costs for the equipment,  Hence, on July 24, 2000, Uy filed a petition for
which were kept on standby, and labor costs review with the CA. Uy’s petition was
for the idle manpower. He added that the consolidated with the earlier petition filed by
delay by PEA caused the topsoil at the PEA, assailing the same CIAC decision.
original supplier to be depleted; thus, he was  But on August 1, 2000, the CIAC issued an
compelled to obtain the topsoil from a farther Order denying Uy’s motion for correction of
source, thereby incurring extra costs. He also computation.
claims that he had to mobilize water trucks for
 the CA rendered decision dismissing both
the plants and trees which had already been
petitions on both technical and substantive
delivered to the site. Furthermore, it became
grounds. PEA’s petition was dismissed
necessary to construct a nursery shade to
because the verification thereof was
protect and preserve the young plants and
defective. Uy’s petition, on the other hand,
trees prior to actual transplanting to the
was dismissed upon a finding that it was
landscaped area.
belatedly filed..
 PEA and Uy filed motions for reconsideration.
Subsequently, PEA filed with the CA an
Urgent Motion for Issuance of a Temporary August 1, 2000, the CIAC issued an Order denying the
Restraining Order and/or Writ of Preliminary motion for correction of computation.
Injunction, seeking to enjoin the CIAC from
proceeding with CIAC Case No. 03-2001, Obviously, when Uy filed his petition for review
which Uy had subsequently filed. PEA alleged with the CA, the period to appeal had not yet
that the case involved claims arising from the lapsed; it was interrupted by the pendency of his
same Landscaping and Construction motion for computation. There is no basis,
Agreement, subject of the cases pending with therefore, to conclude that the petition was
the CA. belatedly filed.
 the CA denied both MRs but issued an
injunction permanently enjoining the
Construction Industry Arbitration Commission 2) W/N THE CA ACTED WITHOUT OR IN EXCESS
from proceeding with CIAC CASE NO. 03- OF ITS JURISDICTION OR WITH GRAVE ABUSE OF
2001, DISCRETION AMOUNTING TO LACK OR EXCESS
 PEA and Uy then came to us with their OF JURISDICTION WHEN IT ENJOINED THE
respective petitions for review assailing the PROCEEDINGS IN CIAC CASE NO. 03-2001
CA ruling. PEA’s petition was docketed as
G.R. Nos. 147933-34, while that of Uy was NO.
docketed as G.R. Nos. 147925-26.
 PEAs petition was denied. Thus, what Indeed, the assailed resolution shows no patent or
remains to be resolved is Uy’s petition. gross error amounting to grave abuse of discretion.
Neither does it show an arbitrary or despotic exercise
ISSUES: of power arising from passion or hostility.

1) W/N THE CA ERRED IN DISMISSING At this point, it should be stated that the Court is not
PETITIONER UY’S PETITION ON THE ALLEGED convinced by Uy’s argument that the claims under
GROUND OF NON-COMPLIANCE WITH THE CIAC Case No. 03-2001 are different from his claims in
REGLEMENTARY PERIOD IN FILING AN APPEAL. CIAC Case No. 02-2000. There is only one cause of
action running through Uy’s litigious undertakings – his
alleged right under the Landscaping and Construction
YES.
Agreement. Therefore, the landscaping agreement is
indispensable in prosecuting his claims in both CIAC
Appeals from judgment of the CIAC shall be taken Cases Nos. 02-2000 and 03-2001.
to the CA by filing a petition for review within fifteen
(15) days from the receipt of the notice of award,
2) W/N THE CA ERRED IN AFFIRMING THE
judgment, final order or resolution, or from the date
AWARDS OF CIAC
of its last publication if publication is required by
law for its effectivity, or of the denial of petitioner’s
motion for new trial or reconsideration duly filed in Uy cries foul on the award granted by CIAC, and
accordance with the governing law of the court or affirmed by the CA. He posits that PEA already
agency a quo. admitted its liability, pegged at ₱146,484,910.10, in its
memorandum. Thus, he faults the CA for awarding a
lesser amount.
Admittedly, Uy received the CIAC decision on June 7,
2000; that instead of filing a verified petition for review
with the CA, Uy filed a motion for correction of We meticulously reviewed the records before us and
computation on June 16, 2000, pursuant to Section 9, failed to discern any admission of liability on the part of
Article XV of the Rules of Procedure Governing PEA.
Construction Arbitration.
By no stretch of the imagination can we consider the
With the filing of the motion for correction, the memorandum an admission of liability on the part of
running of the period to appeal was effectively PEA. First, nowhere in the memorandum does it say
interrupted as provided in Sec 9. that PEA is admitting its liability. The evaluation
contained in the memorandum is merely a verification
of the accuracy of EDC’s claims. As a matter of fact,
CIAC was supposed to resolve the motion for
the evaluation is still subject for review by the project
correction of computation within 30 days from the time
manager, whose decision on the matter requires the
the comment or opposition thereto was submitted. In
approval of the Heritage Park ExCom. Second,
Uy’s case, no resolution was issued despite the lapse
Messrs. Ignacio and Urcia had no legal authority to
of the 30-day period, and Uy considered it as a denial
make admissions on behalf of PEA. Thus, even
of his motion. Accordingly, he elevated his case to the
assuming that the evaluation contained in the
CA on July 24, 2000. But not long thereafter, or on
memorandum was in the nature of an admission, the
same cannot bind PEA. Third, Uy filed his complaint 20% as statedin the agreement to 10% of the total
with the CIAC because PEA did not act on EDC’s amount due.
various claims.
But the agreement is about the stipulated attorney’s
This supports our conclusion that PEA never fees applicable only in complaints filed by PEA against
admitted, but on the contrary denied, whatever the contractor. The provision is silent on the amount of
additional liabilities were claimed by Uy under the attorney’s fees that can be recovered from PEA.
landscaping contract.
Articles 1229 and 2227 of the Civil Code empower the
Neither do we find any admission of liability on the part courts to reduce the penalty if it is iniquitous or
of PEA during the proceedings before the CIAC. What unconscionable. The determination of whether the
was admitted by PEA was that PMO evaluated the penalty is iniquitous or unconscionable is addressed to
claim at the lesser amount of ₱146,484,910. The the sound discretion of the court
admission of the evaluation made by PEA cannot
translate to an admission of liability. There is simply no The Court finds Uy’s claim for attorney's fees
basis for Uy to claim that PEA had admitted its liability. equivalent to 20% of whatever amount is due and
payable to be exorbitant. The CIAC and the CA,
As to the monetary award: therefore, correctly awarded 10% of the total amount
due and payable as reasonable attorney’s fees.
Uy claims ₱95,740,834.30 as the standby equipment
cost. CIAC, however, did not agree and granted only Respondent Public Estates Authority is ordered to pay
₱19,604,132.06 as the cost of standby equipment Elpidio S. Uy, doing business under the name and style
using its so-called equitable method. Edison Development and Construction,
₱55,680,492.38 for equipment rentals on standby;
Upon review of the records before us, we find a need ₱2,275,721.00 for the cost of idle manpower; and
to modify, by increasing, the award for standby ₱6,050,165.05 for the construction of the nursery
equipment cost. shade net area; plus interest at 6% per annum to be
computed from the date of the filing of the complaint
until finality of this Decision and 12% per annum
CIAC found that PEA incurred delays in the turnover of thereafter until full payment. Respondent PEA is further
work areas. The several periods of delayed turn-over ordered to pay petitioner Uy 10% of the total award
of work areas total one year and six months or 546 as attorney’s fees.
days.Surely, on the days that EDC was waiting for the
turn over of additional work areas, it was paying rentals
for the equipment on standby. Yet, CIAC completely
ignored these delays in determining the cost of
equipment on standby,

Uy is entitled to the cost of idle time for equipment


by reason of the delay incurred in the delivery of
work areas.

As to Uy’s claims for costs for additional hauling


distance of topsoil and for mobilization of water truck:

Indisputably, Uy mobilized water trucks for the


landscaping projects and, certainly, incurred additional
costs. But like his claim for additional cost of topsoil,
such additional expenses were incurred without
prior written approval of PEA’s general manager.
Thus, he cannot claim payment for such cost from
PEA.

Uy cannot, therefore, claim from PEA the costs of


the additional hauling distance of topsoil, and of
the mobilization of water trucks.

As to attorneys’s fee,he ascribes error to the CIAC and


the CA for reducing the stipulated attorney’s fees from

You might also like