Railway Electrification Broad Checklist

Name of the Section: Vijaypur to Pachore Road ​RKM: 100.32 ​


1) ​Total No. of Stations:- 05

TKM: 112.30 ​

2) ​No. of TSS in the Section: - Total - 01 ; Fully Ready - 0 ; Back-Charged - 0 ; Not-Ready - 01;
3) No. of SP in the Section: - Total - 01; Not-Ready – 0;
4) No. of SSP in the Section: - Total – 03 ; Not-Ready – 01;
5) Max one side Feed Length from TSS: 129 Km
6) Voltage drop calculations attached if any of the TSS is not fully ready: Attached
7) All the loops and lines are wired :- Yes
8) EIG Sanction Available:
a) For OHE charging of complete section : - Yes
b) For TSS which are charged/back-charged :- Not Ready
c) For SP/SSP which are ready:- Not Ready
d) For AT commissioning :- Not Erected
9) Compliance of EIG sanction Conditions :- Not Ready
10) Inspection note of Joint Inspection at SAG level :- Will be done before charging
11) Compliance of Joint Inspection note of SAG level :- Will be done before charging
12) Joint SED checking with Division done for the complete section:- Will be done before charging
13) Joint Tower wagon checking done for the complete section:- Will be done before charging
14) Adjustment of all the ATDs in the section done with proper temperature marking:- Will be done before charging
15) Bonding is done as per bonding plan in complete section :- Will be done before charging
16) Loco Trial has been done in the section :- Will be done before charging
17) All the P-Way gangs have been trained and safety equipment are provided:- Yes
18) All the Gate Men have been trained for precautions in Electrified section:- Yes
19) Gate working rules includes precautions to be taken in electrified sections:- Yes

1 of
14

Name of the Section: Vijaypur to Pachore Road
Item Description ↓ Stations Name -> Kumbhraj Chachaura Sinduriya Biyavara Pachore Road
Binaganj Rajgarh
1 Appendix ‘G’ of SWR has been issued as per the current power supply Yes Yes Yes Yes Yes
scheme and assurance of the staff regarding the same had been taken?

2 Electric Traction Working Rule Diagram is provided in front of the Signal Yes Yes Yes Yes Yes
panel?
3 Power Block Register, Power Block Collars, Line Block Collars are Yes Yes Yes Yes Yes
provided?
4 OHE key Box, Hand gloves for isolator operation, Isolator Key Regis- ter with Yes Yes Yes Yes Yes
List of authorized TRD official who can withdraw key from
SM provided?
5 Electric Shock Treatment Chart in bilingual/ trilingual provided in S Yes Yes Yes Yes Yes
Room?
6 Sealed First Aid Box with prescribed medicine provided? Sealing and last Yes Yes Yes Yes Yes
replenished date?
7 No. and type of Fire Extinguishers in SM room? Available Available Available Available Available
Next due date for refilling/testing of F.E? NA NA NA NA NA
8 Competency issued to all SM/ASM for Isolator operation along with Yes Yes Yes Yes Yes
Designation of person issuing Competency certificate.
9 TPC is in place and Working TPC phone provided? Yes Yes Yes Yes Yes
10 Joint Inspection of traction bonds done in track circuited area by SSE/TRD & Yes Yes Yes Yes Yes
SSE/Sig? A register with approved bonding plan is provided at Station?

11 No.of Bonds provided in yard - (Actually provided/As per bonding plan)


(Typical numbers given, Actual shall be as per SIP and yard geometry) :

Provided as per approved bond plan.


(i) Structure Bond (64 for 4 Lines; 30 for 3 Lines):
(ii) L- Bond (250 for 4 Lines; 150 for 3 Lines):
(iii) Z-Bond (40 for 4 Lines, 30 for 3 Lines):
(iv) IT/IR Bond (30 for 4 Lines; 20 for 3 Lines):
(v) C-Bond (40 for 4 Lines; 20 for 3 Lines):
(vi) SEJ-Bond (8 for 4 Lines; 6 for 3 Lines):
(vii) Special Bonds (20 for FOB & Shed):
Platform:
12 Staff Caution notice boards(1 each for SM/ASM room, Relay room): Yes Yes Yes Yes Yes

13 Public Caution Boards (4 on each PF, 2 on Station bulding, 1 each at Yes Yes Yes Yes Yes
Station Entry, Booking Window and waiting rooms:
14 PF sheds are bonded with earth on at least two places? Yes Not Applicable Not Applicable Yes Yes
15 Separate earth pit is provided for PF shed if shed length is more than 350 NA NA NA NA NA
mtr?(EP res. Less than 10 (ind.) & 2 (comb.))
16 Caution boards are provided to prevent entry over roof of PF shelter, one Yes Yes Yes Yes Yes
on each side?
17 All the Masts/portals on PF bonded with structure bond? Yes Yes Yes Yes Yes
18 Fencing/Railing on the platform bonded on at least two places, if more than 20 Yes Yes NA Yes Yes
mtr and with separate earth pit also if more than 350 mtr?(EP res.
Less than 10 (ind.) & 2 (comb.))
19 Caution Unwired Turnout / Track ahead boards, Electric Engine Stop Yes Yes Yes Yes Yes
boards are provided?
20 Implantation of OHE Mast/portal is more than 4.75mtr on PF? Yes Yes Yes Yes Yes
Foot Over Bridge (FOB) -
1 Static Clearance from bottom of girder to top of catenary is more than NA NA NA Yes NA
250mm?
2 Insulated catenary or Contact Catenary is provided under the FOB with NA NA NA False Contact NA
minimum 2-3 M on either side from the edge of FOB. Wire will be
Provided
3 Continuous Protective screen is provided across full span of FOB? NA NA NA Yes NA
4 FOB is bonded with Rail and Separate Earth Pit?(EP res. Less than 10 NA NA NA Bonded with Rail NA
(ind.) & 2 (comb.)) and Separate
Earth Pit will be
Provided Before
Charging
5 Public Caution Board and 25 KV Danger Board are provided on the NA NA NA Yes NA
protective screen (one each for each track) and on the ascent of FOB (one on
each entry)?

Other Over Line Structure ( ROB/FLY OVER etc.)


1 Static Clearance from bottom of girder to top of catenary is more than of
NA NA NA NA NA 10
250mm? 14

2 Insulated catenary or Contact Catenary is provided under the OLS with NA NA NA NA NA


minimum 2-3 M on either side from the edge of OLS?
3 Continuous Protective screen is provided across full span? NA NA NA NA NA
4 Nearby OHE structure is located at least 10 m away from the edge of NA NA NA NA NA
OLS?
5 Separate Earth Pit with one bond between Earth Pit and Structural Column an NA NA NA NA NA
another one between Structural Column and Rail is provided?.(EP res.
Less than 10 (ind.) & 2 (comb.))
6 Public Caution Board and 25 KV Danger Board are provided on the NA NA NA NA NA
protective screen (one each for each track)?

PTFE Neutral Section: ​Location -> Loc 1148.930 Loc 1188.300


1 Two Bonds with separate earth pit are provided (EP res. Less than 10
(ind.) & 2 (comb.)):
Feeding from One Side from Guna TSS.

Remark: PTFE will be erected after commissioning of BRRG TSS.


2 Caution Boards provided at 500 M , 250 M, DJ OPEN and DJ close :
3 Conditions –
4 On tangent Track :
5 No gradient :
6 Located at least 200 mtr before stop signal or 400 mtr after stop signal :

7 Stagger of OHE is be zero :


LC No. LC No. LC LC LC LC LC No. LC No. LC No. LC No. LC No. LC LC
Sl. Manned Level Crossing Gates 77A 84C No.91C No.98C No.100C No.105C 109C 117C 118C 124C 131C No.136C No.137C
Description Km Km Km Km Km Km Km Km Km Km Km Km Km
1122.454 1129.345 1138.723 1149.137 1152.204 1160.077 1165.922 1181.683 1184.910 1196.330 1209.123 1218.177 1219.563
1 Gatemen are trained and counselled regarding precautions and working in Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Electrified section?
2 Height of Height gauge from Ground Level is not more than 4.67mtr? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
3 3.67mtr black band marking on the upright is provided? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
4 Danger Board in Bilingual/Trilingual with skull mark is provided? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
5 Height of contact wire on all the lines is not less than 5.50mtr? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
6 Cross bonds are within 5metre from transverse edge of LC? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
7 Distance of nearest OHE mast from transverse edge of LC is not more Yes Yes
than 10mtr?
10 of Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

14
8 Proper bonding of fencing and gate machine is done? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
9 Public caution notice boards are provided on the uprights of HG (1 per Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
HG)
10 Staff caution notice board is provided on the cabin: Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
11 Electric shock Treatment chart in bilingual/trilingual is provided? Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
12 Precautions to be taken in electrified section are included in Gate Working Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Rules (GWR)?
13 Insulator are provided in SS wires and Rods?, Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes

Unmanned Level Crossing Gates ULC No. ULC No. ULC No. ULC No.
Description Km Km Km Km
1 Height of Height gauge from Ground Level is not more than 4.67mtr? NA NA NA NA
2 3.67mtr black band marking on the upright is provided? NA NA NA NA
3 Danger Board in Bilingual/Trilingual with skull mark is provided? NA NA NA NA
4 Height of contact wire on all the lines is not less than 5.50mtr? NA NA NA NA
5 Cross bonds are within 5metre from transverse edge of LC? NA NA NA NA
6 Distance of nearest OHE mast from transverse edge of LC is not more NA NA NA NA
than 10mtr?
7 Public caution notice boards on uprights (1 per HG): NA NA NA NA

Switching Stations (SP/SSP) ​Name-> Kumbhraj SP Chachaura Binaganj Sinduriya SSP


SSP
1 Name board for SP/SSP is provided on the fencing facing track?
2 Caution Board for staff as well as for Public are provided (one on each
side)

10 of
14

All activity will be completed before commissioning of section


with 25KV AC.
3 25 KV AC Danger Board and protected area boards are provided on the
fencing facing track and on the entry?
4 Staff Caution Board is provided on the wall of Control Room?
5 Number of earth pits provided Typically 8 for D/L, 6 for S/L):
6 Individual earth value of each earth pit is less than 10ohms?
7 Combined earth value is less than 2 ohms?
8 Earth Pit Boxes are casted?
9 Earth pit boxes are made as per RDSO drawings?
10 Earth pit boxes are buried in the ground as per RDSO drawing? Stencilling
of all the earth resistance values are done?
11 Buried Rail is provided near SP/SSP as per RDSO SMI?
12 LAs with discharge counters and two earth bonds are provided?
13 All the Equipment are connected with two earth bonds?
14 Equipment earth bonds were made by MS flats with two coats of painting
by colour grass green?
15 Isolator are provided with locking arrangement and flexible earth?
16 Fencing Earth by at least two bonds?
17 Minimum 100mm thickness crushed rock is provided?
Control Room :
18 Panel & Battery Charger are commissioned and connected with earth ring
by 8 SWG wire?
19 Shock Treatment Chart is provided?
20 Schematic Diagram provided?
21 Hand gloves are provided?
22 OHE Key Box is provided?
23 TPC phone is provided and working?
24 Message register and PN book for operation of interrupters and Isolators
is provided?
25 Ring earth with separate earthing for RTU is provided?
Safety Equipment :
26 First Aid Box with prescribed medicine is provided? Last
10 of
14
replenished/sealed date of F.A. Box?
27 Fire Buckets ( 4 nos i.e. 2 sand filled and 2 with water near AT) are provided?

No.
​ and type of Fire Extinguishers provided with next due date?
28

All activity will be completed before commissioning of section


with 25KV AC.
29 Battery Room :
➢ All the batteries are commissioned and properly numbers?
➢ Specific gravity of the battery has been taken?
➢ Exhaust fan is provided in battery room?
➢ No sulphation is there on the battery terminal?
➢ Anti-acid tiles on floor with skirting are provided?
➢ voltmeter and hydrometer are provided in battery room?
30 Implantation meeting the minimum requirement as below?
➢ Fencing - 3.5 mtr.
➢ Main gantry – 4.3 mtr.
AT (auxiliary transformer) is commissioned?
Inner distance between 2 interrupters is not less than 3 M?
31 Numbering scheme is as per approved drawing?
32 Emergency Telephone Socket is provided and working?
33 If manned, Competency certificate for operation of interrupter and isolator
is given to manning staff?

Traction Sub Station (TSS) ​Name-> 10 of Biyavara Rajgarh TSS


14
1 Name board for TSS is provided on the fencing facing track?

Biyavara TSS is not commissioned due to 132KV incoming


transmission line is not yet erected. So the feed has been taken
from existing TSS at Guna.
2 Provided Caution Boards for staff (Minimum one on each side, near main
gate and on control room gate):
3 Provided Caution Boards for Public (Minimum one on each side of
fencing):
4 25 KV AC Danger Board and protected area boards are provided on the
fencing facing track and on the Main Entry?
Earthing:
5 Provided as per approved earthing lay out based on ACTM guide line?
6 Total number of earth pits (Typically 40):
7 Earth Pit Covers are with handle
8 Individual Earth Pit Resistance is less than 10 ohm
9 Combined earth resistance is less than 0.5 ohm.
10 Earth Pit Boxes are casted?
11 Earth pit boxes are made as per RDSO drawings?
12 Earth pit boxes are buried in the ground as per RDSO drawing? Stencilling
of all the earth resistance values are done?
13 Control Panel Room is separately earthed with 50 mm x 6 mm flat in
merry- go-round on just above the floor level. Further connected with main
earthing network. 10 of
14 All equipment - CT, PT, CT, LA, SPI, DPI, AT, BM, Power Transformer etc are 14
with double earthing. For LA – separate earthing (working of surge counter to be
confirmed for ensuring leakage current and number of surge).

15 Isolator are provided with locking arrangement and flexible earth?


16 Fencing Earth by at least two bonds?
17 Minimum 100mm thickness crushed rock is provided?
18 AT (auxiliary transformer) is commissioned?
19 Numbering scheme of equipmentsis as per approved drawing?
20 Number of Transformer provided -
21 All the protections for tranformer are commissioned:
22 Primary and Secondary injection testing of all the relays are done:

23 Buried Rail : Buried Rail of 13 M length is buried near feeding post gantry
fencing coming from secondary side of transformer. It should be
connected with all traction rail(s) by 75x8 mm MS flat.

Biyavara TSS is not commissioned due to 132KV incoming


transmission line is not yet erected. So the feed has been taken
from existing TSS at Guna.
24 Opposite to TSS/ FP all the traction railsare provided with rail bonds at
approximate distances of 300 M, 500 M, 700 M and 1000 M from the
TSS/FP.
25 Cable Trench: It is as per approved drawing based on RDSO. Depth, Width,
Depth of Trench is as per RDSO standard.. Execution of cable trench and 10 of
earthing system are done as per Approved Earthing lay out drawing available at 14
site.
Control Room :
26 Separate earthing for RTU is provided?
27 All Panels & Battery Charger are commissioned:
28 Shock Treatment Chart is provided?
29 Schematic Diagram provided?
30 Hand gloves are provided?
31 OHE Key Box is provided?
32 TPC phone is provided and working?
33 DoT/BSNL/WLL phone provided and working?
34 Message register and PN book provided?
35 Rubber Mat at the front of all control panel provided?
Safety Equipment :
36 First Aid Box with prescribed medicine is provided? Last
replenished/sealed date of F.A. Box?
37 Fire Buckets ( Min. 6 nos i.e. 3 sand filled and 3 with water) are provided?

38 No. and type of Fire Extinguishers provided with next due date?
Battery Room :
39 ➢ All the batteries(55 cells, 200AH, 2.1 volts, Total bank Voltage
110Volts) are commissioned and properly numbers?
40 ➢ Specific gravity of the battery has been taken (Typically 1220)
41 ➢ Exhaust fan is provided in battery room?
42 ➢ No sulphation is there on the battery terminal?
43 ➢ Anti-acid tiles on floor with skirting are provided?
44 ➢ voltmeter and hydrometer are provided in battery room?

45 If manned, Competency certificate for operation of interrupter and isolator


is given to manning staff?
Biyavara TSS is not commissioned due to 132KV incoming
transmission line is not yet erected. So the feed has been taken
from existing TSS at Guna.
46 Earth Fault Test (providing discharge rod on busbar between LV CB and
feeder CV) is done:
47 Earth Fault Test to be done by providing earthing at furthest end of the
sector is done:
10 of
14

Steel Girder Bridge Loc Loc Loc Loc


1 Earth pit on both ends :

All activity will be completed before commissioning of section


with 25KV AC.
2 Earth Values are within prescribed values:
3 Connection with separate earth pit, Bonding between rail and girder and
girder and earth pit provided:
4 U-Bond between traction rail and gaurd rail at both the ends:
5 Longitudnal/continuity bonds are provided in traction as well as gaurd rail:
6 Cross bonds at 100m.

Check list for Inspection of Signaling & Telecommunication


Brief description of Item
Stations Name
Station Pachore Road Biyavara Rajgarh Sinduriya Chachaura Kumbhraj
Binaganj
1 Nos of running Lines. 2 Nos 3 Nos 2 Nos 3 Nos 2 Nos
2 Sand Hump / Overrun on loop lines. Over run line-2 Nos SH-4, One SH. SH-2No SH-2 Nos, SH-2 Nos
Converted in overrun Overrunline-1 Nos
Signalling
1 Type - - - - -
2 Standard of Interlocking PI Siemens, Std. –II(R) EI Siemens, Std. – PI Siemens, Std. – EI Ansaldo, Std. – EI Ansaldo, Std. –
class-B II(R) class-B II(R) class-B II(R) class-B II(R) class-B
3 Complete Track Circuit of yard Yes Yes Yes Yes Yes
4 Type of Signal MACLS MACLS MACLS MACLS MACLS
Block working
1 Up side& DiadoTokenless DiadoTokenless DiadoTokenless DiadoTokenless DiadoTokenless
2 Down Side DiadoTokenless DiadoTokenless DiadoTokenless DiadoTokenless DiadoTokenless
3 Provision of block filter in RE area Provided Provided Provided Provided Provided
Telecommunication
1 OFC with 6 Quad cables. Already Provided Already Provided Already Provided Already Provided Already Provided
2 Dismantling of overhead Telecom Alignment Already Provided 4 ofAlready
14 Provided Already Provided Already Provided Already Provided
3 Emergency Socket at every one km. Already Provided Already Provided Already Provided Already Provided Already Provided
4 Emergency Socket at SSP, SP & TSS in RE area. Will be completed before charging 25KV AC.
Relay Room
1 Bunching& lacing of wiring Already Provided Already Provided Already Provided Already Provided Already Provided
2 Tag block covers Already Provided Already Provided Already Provided Already Provided Already Provided
3 Door Close switch proving in data logger
4 Fire fighting equipment Already Provided Already Provided Already Provided Already Provided Already Provided
5 HMU for LED Signals Already Provided Already Provided Already Provided Already Provided Already Provided
6 Painting and writing particulars Will be completed before charging 25KV AC.
7 Double Lock arrangement Already Provided Already Provided Already Provided Already Provided Already Provided
8 Earthing for EI as per RDSO guidelines NA Already Provided NA Already Provided Already Provided
9 Air Conditioning Equipment at Junction station. Not Provided Not Provided Not Provided Not Provided Not Provided
10 Flashing of relays more than 3 years old. - - - - -
11 AC immunized relays connected with outdoor circuit in RE area Already Provided Will be completed Already Provided Already Provided Already Provided
before charging 25KV
AC.

IPS & Battery Room


1 Earthing of IPS (less than 2ohm) Already Provided Already Provided Already Provided Already Provided Already Provided
2 IPS with 55+5 battery bank Already Provided Already Provided Already Provided Already Provided Already Provided
3 Exhaust fan in battery room Already Provided Already Provided Already Provided Already Provided Already Provided
4 Compliance of pre commissioning check list Already Provided Already Provided Already Provided Already Provided Already Provided
SM Panel Room
1 Simulation / Panel Test NA NA NA NA NA
2 Filling of duct at ASM office NA NA NA NA NA
3 Earthing of Block Provided Provided Provided Provided Provided
4 Crank handle wiring Already Provided Already Provided Already Provided Already Provided Already Provided
5 FAT & SAT in case of EI NA NA NA NA NA
Data logger room
1 Data logger validation & networking NA NA NA NA NA
2 Diagnostic Panel NA NA NA NA NA
3 ELD NA NA NA NA NA
4 Mineral water plant at SI/HQ NA NA NA NA NA
Power Supply (DG set / AT Supply)
1 Nos of sources 3 3 3 3 3
2 DG Set Capacity & Make 10 KVA 10 KVA 10 KVA 10 KVA 10 KVA
3 Auto start from SM Panel Room NO NO NO NO NO
4 AT Supply with Auto change over 4 ofbe
Will 14completed before charging 25KV AC.
Outdoor
1 Signal – number plates Already ProvidedAlready Provided Already Provided Already Provided Already Provided
2 Signal – X mark on back side NA NA NA NA NA
3 Glued Joints Already ProvidedAlready Provided Already Provided Already Provided Already Provided
4 Earthing of signals & location box Provided Provided Provided Provided Provided
5 Earthing Cable armours Already ProvidedAlready Provided Already Provided Already Provided Already Provided
6 Cable Route Markers Already ProvidedAlready Provided Already Provided Already Provided Already Provided
7 Painting and writing particulars Already ProvidedWill be completed Already Provided Already Provided Already Provided
before charging 25KV
AC.
8 AC immunized relays connected with outdoor circuit in RE area Already Provided Will be completed Already Provided Already Provided Already Provided
before charging 25KV
AC.
Track Circuits
1 Provision of Choke in RE Provided Provided Provided Provided Provided
2 QTA2 relays in RE area Provided Provided Provided Provided Provided

Sl. Manned Level Crossing Gates LC No.137 LC No. No LC No.118 LC No.105 LC No.91
Description Km 1219.564 Km Km1184.910 Km1160.077 Km1138.723
1 Name of Gate Keeper - - - - -
2 Competency NA NA NA NA NA
3 PME NA NA NA NA NA
4 RC NA NA NA NA NA
5 GWR in Bilingual NA NA NA NA NA
6 Interlocked / Electrical Operated NA Electrical Operated Electrical Mechanical operated
Interlock Interlock Operated Interlock Interlocked
7 NI (Manned / UM)
8 Class NA NA NA NA NA
9 TVU NA NA NA NA NA
10 Wire Rope Insulators Provided NA Provided Provided Provided
11 Rodding Insulators Provided NA Provided Provided Provided
12 Road Warning Signals & Alarming Bells NA NA NA NA NA
13 Height of Booms when lowered Less than 1 Mtr NA Less than 1 Mtr Less than 1 Mtr Less than 1 Mtr

List of Documents and Testing Report to be kept at station during CRS inspection
Stations Name
Brief description of Item
Pachore Road Biyavara Sinduriya Chachaura Kumbhraj
Rajgarh Binaganj
Documents
1 CRS sanction NA NA NA NA NA
2 ESP NA NA NA NA NA
3 SIP NA Approved NA NA NA
4 SWRD NA Approved NA NA NA
5 Selection Table NA Approved NA NA NA
6 Panel Diagram NA Approved NA NA NA
7 Track Bonding Diagram Approved Approved Approved Approved Approved
8 Cable corage plan NA Approved NA NA NA

Compliance of Pre-commissioning check list of


1 IPS NA NA NA NA NA
2 Data Logger NA NA NA NA NA
3 LED Signal NA NA NA NA NA
4 BPAC/SSDAC NA NA NA NA NA
Testing Reports:
1 Selection Table Test NA NA NA NA NA
2 Square sheet Test NA NA NA NA NA
3 SAT for EI NA NA NA NA NA
4 Bell Testing of Wiring diagram NA NA NA NA NA
5 Compliance of Joint Inspection with open line NA NA NA NA NA
6 Corresponding Test of functions NA NA NA NA NA
7 Cable meggering jointly with Open Line NA NA NA NA NA
8 As made cable route plan jointly with open line NA NA NA NA NA
9 Relay deposition chart NA NA NA NA NA
10 Signals on Right hand side and condonation from COM. NA NA NA NA NA
11 Joint Signal Sighting report NA NA NA NA NA

Documents to be given to SM on Duty commissioning of Signalling


1 SWR with Rule NA NA NA NA NA
2 Signal Failure Register NA NA NA NA NA
3 Signal History Register NA NA NA NA NA
4 Relay Room Key Register NA NA NA NA NA
5 Block Instrument Key register for Token Instruments) NA NA NA NA NA
6 Panel Counters register ( all six counters) NA NA NA NA NA
7 Disconnection / Reconnection register NA NA NA NA NA
8 Crank Handle register NA NA NA NA NA

(Chhakki Lal) (Yogesh Chaudhari) (Yogendra Baghel)


Project Head/RITES Sr.DGM(C)/RITES Sr.DEE/TRD/BPL

(Aditya Lekha) (Gaurav Singh) (Sanjeev Kumar)


Sr. DEE(TRO)/BPL Sr. DSTE/Co/BPL Sr. DEN/Co/BPL

(Anurag Pateriya) (Ajay Srivastava) (Ravindra Sharma)


Sr. DOM/BPL Sr. DME/Co./ BPL Sr. DSO/BPL

(Avanesh Kumar) (Vandana Garg) (M B Vijay)


PCEE/WCR/JBP PCSTE/WCR/JBP PCE/WCR/JBP

(Monaj Seth) (Ashutosh Gangal)


PCOM/JBP PCME/JBP

( Ajay Vijayvargiya )
General Manager
West Central Railway