Riverhead CSD Topics to Explore
Part One
Enrollment Trends & Current Building Capacity
Overall Grade Level Configuration
Pre-Kindergarten
Remaining Modular Classrooms @ Phillips
Two (5-8) Middle Schools or Current (5-6) + (7-8)
[ (9-12) HS ] or [ (10-12) HS + Grade 9 Center ]
Additional Indoor P.E. Space/ Field House
District Office/ PPS Consolidation & Improvements
The Fairgrounds at Pulaski Master Plan (PUL/ MS/ HS)
District-Wide Security Upgrades
District-Wide Capital Projects
Part Two
Potential Impact of McGann-Mercy Property & Buildings

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Long Range Planning Study (2018 – 2019)
Overall Potential Timeline
Changes in Market Escalation Since 2011 Bond Vote
(9-12) Riverhead HS Current
(9-12) Riverhead HS Proposed
(5-8) Pulaski & Middle School (5-6) Pulaski
Pre-Kindergarten New Pre-K Center @ Phillips Site
Phillips Avenue School - Replace Modular Classrooms?
Phillips Avenue School – New District Pre-Kindergarten Wing?
District Office & Pupil Personnel Services
Fairgrounds at Pulaski New Field House & D.O. @ Fairgrounds
District-Wide Security District-Wide Capital Projects/ LED Lighting
(10-12) Riverhead High School Grade 9 Center New Building
McGann-Mercy High School
McGann-Mercy Grade 9 Center
McGann-Mercy Convent Convent as New District Office

bbs
McGann-Mercy Former Convent as Pre-Kindergarten Center (& Potential PPS)
Riverhead Central School District September 10, 2019
MATRIX: Broad
2019 FACILITIES Options
ANALYSIS MATRIX: Focused
UpdateOptions & Preferred
Riverhead CSD
Base Information

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
Long Range
Planning Study
Western Suffolk BOCES 2018-19 Update

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Overall Potential
Timeline

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD

A Winter 2020 Vote


Means Starting
Occupancy Fall 2023
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Potential Time Line
Summer 2019 Admin Committee Gathers & Discusses Overall
District Information About Multiple Possibilities

Sept-Nov 2019 Committee & BOE Public Discussion

Late Nov 2019 BOE SEQRA/ Bond Resolution (45 Days to Vote)

Nov/Dec 2019 Public Relations Campaign

Jan 2020 Referendum Vote


Documents, Applications & Approvals
Bidding, Award of Contracts & Construction
Sep 2023 Begin Occupancy

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Changes Since 2011
Market Escalation

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
2011 $50.00 $ 78.33
2012 $51.11 + 2.2% $ 80.07
2013 $53.21 + 4.1% $ 83.35
2014 $55.55 + 4.4% $ 87.02
2015 $58.07 + 4.5% $ 90.98
2016 $60.91 + 4.9% $ 95.42
2017 $63.92 + 5.0% $ 100.14
2018 $67.50 + 5.6% $ 105.74
2019 $69.90 + 3.6% $ 109.50
+ 39.8% Overall Escalation since 2011

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
Part One

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Today’s Snapshot
Riverhead High School

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead High School (9-12)

2011 Enrollment 1,525


2018 Enrollment 1,922 + (397) Students

Current Capacity @ 100% 1,955


Current Enrollment 99.0%

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead HS
Short Term Solutions
(+4 CR Internally)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead High School (9-12)

2011 Enrollment 1,525


2018 Enrollment 1,922 + (397) Students
Current Capacity @ 100% 1,955
Current Enrollment 99.0%

Short Term Measures @ 100% 2,067


Short Term Measures 93.7%

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead HS
Long Term Solutions
& Closed Campus

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead High School (9-12)
2011 Enrollment 1,525
2018 Enrollment 1,922 + (397) Students
Current Capacity @ 100% 1,955
Current Enrollment 99.0%
Short Term Measures @ 100% 2,067
Short Term Measures 93.7%
(9-12) Projected Peak (LRPS) 2,120 (85% of 2,494)
(9-12) Design Load (100%) 2,494
(9-12) Delta (2,494 – 2,067) = (427) Students
(427) Students @ 25/CR = + 18 CR’s Needed
Reverse Short Term Measures + 4 CR’s Needed
Connect to 2-Story Wing + 2 CR’s Needed
Total New Addition Required + 24 CR’s

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead HS
Long Term Solution
(PPS Leaves = 2-Story CR Addition)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski (5-6)
Current Space

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski (5-6)
Pulaski (5-6) had (841) Students in (2018-2019),
with current utilization yielding a
100% capacity figure of (737) Students.

Pulaski is at 114% Capacity.

By taking over Health, Music, Art, Science & Support,


97% Capacity could be achieved at Pulaski.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
MS (7-8)
Current Space

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Middle School (7-8)
The Middle School (7-8) had (855) Students in
(2018-2019), with current utilization yielding a
100% capacity figure of (1,220) Students.

The Middle School is at 70% Capacity.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski & Middle School
Grades (5-8)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Two (2) (5-8) Buildings
Pulaski (5-6) has (841) Students now, with current
utilization yielding a 100% capacity figure of (737)
Students.
Pulaski is at 114% Capacity.
By taking over Health, Music, Art, Science & Support,
97% Capacity could be achieved at Pulaski.

The Middle School (7-8) has (855) Students now, with


current utilization yielding a 100% capacity figure of
(1,220) Students.
The Middle School is at 70% Capacity.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Two (2) (5-8) Buildings
By reconfiguring each building as a (5-8) school,
we can shift the enrollment proportionately with
the potential capacity of each building.
Pulaski as a (5-8) could have 100% Capacity @ ( 827)
The MS as a (5-8) could have 100% Capacity @ (1,150)
Combined (5-8) Potential @ 100% Capacity = (1,977)
Pulaski = (827/ 1,977) = 42%
MS = (1,150/ 1,977) = 58%
Target Enrollment is 85% of 100%

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Two (2) (5-8) Buildings
The Peak Projected (5-8) Enrollment is (1,695) in 2027.

58% = 983 = Middle School


42% = 712 = Pulaski

MS @ 100% = 1,150 (983/ 1,150) = 85.5%


Pulaski @ 100% = 827 (712/ 827) = 86.1%

Based upon the following proposed plan diagrams.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski (5-8)

Accommodate 42% of the (5-8) Population


Convert two (2) CR’s to (7-8) Science
Convert two (2) CR’s back to P.E. Lockers
Overlay FCS onto an Existing CR
Provide (376) Hall Lockers for Grades (7 & 8)
(Add 230 to existing 146)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Middle School (5-8)
Accommodate 58% of the (5-8) Population
Convert two (2) Computer Rooms to (5-6) CR’s
Convert FCS to (5-6) Science
Convert one (1) Classroom to (5-6) Art

(+1 P.E. Station may not be necessary to meet


SED Guidelines so is not included within cost estimate.)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski
Proposed (5-6)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Pulaski (5-6)
Pulaski (5-6) Current Utilization yields a
100% Capacity Figure of (737) Students.
The Projected Peak (5-6) Enrollment is (831) Students
in 2025. That yields an Over-Capacity of nearly 113%.
If Pulaski is to remain a (5-6) Building, a 10 -
classroom addition would need to be added, plus
support, etc.
(831)/ 85% = (977) – (737) = (240)/ 25/CR = 9.6 = 10 CR
(10) CR @ 1,550 GSF = +/- 15,500 GSF.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
District Wide
Pre-Kindergarten

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Current Riverhead CSD
Pre-Kindergarten Program
There are currently (251) children in Pre-Kindergarten
located in six (6) locations in nine (9) classrooms:

Phillips Elementary (6) Half-Day Sections


St. David’s (3) Half-Day Sections
Alternatives (1) Half-Day Section
Head Start (4) Half-Day Sections
Southampton Head Start (2) Half-Day Sections
Riverhead Head Start (2) Half Day Sections
Total Available Sections (18) Half-Day Sections
Maximum @ 18 per Section (324) Students

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
What About One (1) Centralized
Pre-Kindergarten Center?
There are currently (251) children in Pre-K.
Maximum class size is eighteen (18).
(251/ 18) = (14) sections required.
For half-day classes that equates to the need for
seven (7) classrooms in lieu of nine (9) currently used.

SED Guidelines for space suggest 900 SF for both


Kindergarten (27) and Pre-Kindergarten (18).

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Phillips School
New Pre-K Center?

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Phillips School
Replace Modular CR’s

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Phillips School
New Pre-K Wing

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
District Office & PPS

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Main Campus
Fairgrounds @ Pulaski

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
New Field House &
District Office/ PPS

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Main Campus
Fairgrounds @ Pulaski

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
District Security
Program Upgrades
$400K per School
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
District LED Lighting
Replacements

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
LED Lighting Replacement (EPC)
Aquebogue $ 310,625
Phillips $ 293,125
Riley $ 271,250
Roanoke $ 284,375
Pulaski $ 516,250
Middle School $ 538,125
High School $ 987,000
HS Observatory $ 1,000
PPS $ 36,750
B&G completed
District Office $ 43,750
Transportation completed Total EPC $ 3,285,625

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Power Purchase Agreement
Perhaps the Riverhead CSD could lease space on the new
roofing areas, as well as on the ground at the Phillips site for
Solar Power. The District could request proposals from ESCO’s
independently of any Bond/EPC projects. There would be zero
Building Aid; no involvement with BBS. The direct benefit
would either be a lease payment, or a reduction in electric rates
from the ESCO.

If the District uses the EPC for solar, it would receive Building
Aid. This building aid may reduce the payback period from
about eighteen (18) years to eight (8) years.

The District would have to weigh its options and decide which
scenario would be most beneficial.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
Capital Projects $18.8M
Roofing, Boilers, Toilets, Etc.

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update
$18.8M
bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update
$18.8M
bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update
$18.8M
bbs
Riverhead Central School District $18.8M
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update
$18.8M
bbs
Riverhead Central School District $18.8M
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead CSD
Part Two

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead HS
Grades (10-12)

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
High School (10-12)

100% Capacity is (1,955) Students


Projected Peak (10-12) is (1,488) Students in 2024
(1,488/ 1,955) = 76.1%
76.1% > 85% Target

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Creating a Separate
Grade 9 Center

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Grade 9 Center

How Large A New Building for Grade 9?


Projected Peak is (638) Students in 2028
(638/ 85%) = (750) Target @ 100%
(750) Students @ 175 SF/ Student = 131,250 GSF

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
McGann-Mercy
High School

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
McGann-Mercy HS
Grade 9 Center

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
McGann-Mercy High School

What would capacity be as a Grade 9 Center?


(871) Students @ 100%
(728) Students @ 85% Target

What is the Peak Grade 9 Enrollment Projection?


(638) Grade 9 Students in 2028
(638/ 871) = 73.2% < 85% Target

Leaves growth for ninety (90) students

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
McGann-Mercy
Former Convent

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Former Convent
As New District Office

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Former Convent
As Pre-Kindergarten

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
BROAD MATRIX:
Overall Potential Costs

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Riverhead Central School District
2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
FOCUSED MATRIX:
For Consideration

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Major Differences
Between Options

Identical Scope
Except for
Former Convent
Building

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Option “A” Option “B”
Improve Purchase & Improve
Current Assets McGann-Mercy Property
Keep Grades (9-12) Separate 9th Grade
Together From Grades (10-12)
Existing Building Conditions are Existing Building Conditions are
Known and Less Known & Could Result in
More Predictable Unexpected Costs
Maintains District’s Current Land Expands District’s Current Land
Ownership Ownership
Less Expensive More Expensive
Less Staffing Required More Staffing Required
Less to Maintain More to Maintain
Less Impact on Greater Impact on
Transportation Needs Transportation Needs

Riverhead Central School District


2019 FACILITIES ANALYSIS
September 10, 2019
Update bbs
Option A - Preferred
Improve Current Assets