SPGCL CPU Deatails

Sr.No. Name Type and Specification M.O.C


1 Resin Seperation Tower 2120x10/1316x8 MSRL
2 Anion resin regeneration tower 1220x10 MSRL
3 cation resin regeneration tower 1520x10 MSRL
4 Waste resin trap 1212 MSRL
5 Resin injector V=.15M3 OCr18Ni9
6 DM storage tank 200 M3 Steel
7 Flushing water pump Q=100M3,Head=50 mtr Over flow partOCr18Ni9
8 Air Blower Q=6.8 M3/min , P=80Kpa
9 Compressed air storage tank V=7 M3, 1520x10, P= 10 kg/cm2 16MnR
10 Thermostatic heater tank V=6 M3,1516x8 OCr18Ni9

11 Acid unloading pump Q=15 M3/hr,H=15 mtr


12 Acid storage tank V= 20M3 MSRL

13 Acid day tank V=2M3 MSRL


14 Acid metering pump Q=1994 L/hr, P= 6.2 kg/cm2
15 Acid mist obsorber 500 UPVC
16 Alkali unloading pump Q=15 M3/hr,H=15 mtr
17 Alkali storage tank V= 20M3 MSRL

18 Alkali day tank V=2M3 MSRL


19 Alkali metering pump Q=1617 L/hr, P= 6.9 kg/cm2
20 Carbon dioxide obsorber 300
21 Alkali preparation tank V=2M3 MSRL
22 Alkali transfer pump Q= 5 M3, H=25 mtr
23 Activated carbon filter 812x6 , Height=1000mm MSRL
24 Waste water Pond V=120 M3 RCC

25 Waste water pump Q=80 TPH, H=4 kg/cm2


26 Safety shower
27 Caustic dosing tank V= 1 M3 MSRL
28 Caustic dosing pump Q= 310 LPH
ails
Unit Amount Status
Set 1 Completed
Set 1 Completed
Set 1 Completed
Set 1 Completed
Set 1 Incompleted
Set 1 Completed
Set 1w+1s Completed
Set 1w+1s Mechanical problem
Set 1 Completed
Set 1 Erection completed/Heater
charging pending
Set 1w+1s Discharge piping work u/p
Set 1 Erection completed/level
indicator fitting pending
Set 1 Completed
Set 1w+1s Completed
Set 1 Completed
Set 1w+1s Work u/p
Set 1 Erection completed/level
indicator fitting pending
Set 1 Completed
Set 1w+1s Completed
Set 1 Completed
Set 1 Completed
Set 1 Incompleted
Set 1 Completed
Set 1 tank ready/pump commissioning
pending
Set 1w+1s pump commissioning pending
Set 1 Incompleted
Set 1 Completed
Set 1w+1s Completed