No.

C6-C5 R - ALPHAKIT 1 Days Start Finish


1 Alphakit Installation Completed
2 Slab Formwork Completed
3 Slab+Wall Reinforcement Completed
4 Outer Wall Formwork + Spiral Pipe Installation Completed
5 Slab Concrete Completed
6 Lateral Wall Reinforcement + Inner Wall Formwork Started 9/4/2019
7 RS1-RS5 Cabling - Freyssinet 4 8/31/2019 9/4/2019
8 Wall Concrete 1 9/5/2019 9/5/2019
9 Wall Formwork Dismantling 2 9/6/2019 9/8/2019
10 Top Slab Formwork 7 9/9/2019 9/16/2019
11 Top Slab Reinforcement 7 9/12/2019 9/19/2019
12 Top Slab Concrete 1 9/20/2019 9/20/2019
13 Top Slab support and Formwork Dismantling 5 9/27/2019 10/2/2019
14 Open Section Slab Concrete 1 10/1/2019 10/1/2019
15 Open Section Wall Concrete 1 10/2/2019 10/2/2019
16 Open Section Top Slab Concrete 3 10/3/2019 10/6/2019
17 RS3-SA Cable Stressing - Freyssinet 3 10/13/2019 10/16/2019
18 RS3-SA Injection - Freyssinet 3 10/17/2019 10/20/2019
19 Alphakit Dismantling 10 10/17/2019 10/27/2019

C5-C4 R - ALPHAKIT 2 Days Start Finish


1 Alphakit Installation Completed
2 Slab Formwork Completed
3 Slab+Wall Reinforcement 9/7/2019
4 Outer Wall Formwork + Spiral Pipe Installation 3 9/7/2019 9/10/2019
5 Slab Concrete 1 9/11/2019 9/11/2019
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 9/12/2019 9/14/2019
7 RS3-RS7 Cabling - Freyssinet 4 9/10/2019 9/14/2019
8 Wall Concrete 1 9/15/2019 9/15/2019
9 Wall Formwork Dismantling 2 9/16/2019 9/18/2019
10 Top Slab Formwork 7 9/19/2019 9/26/2019
11 Top Slab Reinforcement 7 9/22/2019 9/29/2019
12 Top Slab Concrete 1 9/30/2019 9/30/2019
13 Top Slab support and Formwork Dismantling 5 10/7/2019 10/12/2019
14 Open Section Slab Concrete 1 10/17/2019 10/17/2019
15 Open Section Wall Concrete 1 10/18/2019 10/18/2019
16 Open Section Top Slab Concrete 3 10/19/2019 10/22/2019
17 RS1-RS5 Cable Stressing - Freyssinet 3 10/29/2019 11/1/2019
18 RS1-RS5 Injection - Freyssinet 3 11/2/2019 11/5/2019
19 Alphakit Dismantling 10 11/2/2019 11/12/2019

C4-C3 R - ALPHAKIT 3 Days Start Finish


1 Alphakit Installation Started 9/7/2019
2 Slab Formwork 4 9/8/2019 9/12/2019
3 Slab+Wall Reinforcement 12 9/10/2019 9/22/2019
4 Outer Wall Formwork + Spiral Pipe Installation 3 9/19/2019 9/22/2019
5 Slab Concrete 1 9/23/2019 9/23/2019
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 9/24/2019 9/26/2019
7 RS5-RS9 Cabling - Freyssinet 4 9/22/2019 9/26/2019
8 Wall Concrete 1 9/27/2019 9/27/2019
9 Wall Formwork Dismantling 2 9/28/2019 9/30/2019
10 Top Slab Formwork 7 10/1/2019 10/8/2019
11 Top Slab Reinforcement 7 10/4/2019 10/11/2019
12 Top Slab Concrete 1 10/12/2019 10/12/2019
13 Top Slab support and Formwork Dismantling 5 10/19/2019 10/24/2019
14 Open Section Slab Concrete 1 11/2/2019 11/2/2019
15 Open Section Wall Concrete 1 11/3/2019 11/3/2019
16 Open Section Top Slab Concrete 3 11/4/2019 11/7/2019
17 RS3-RS7 Cable Stressing - Freyssinet 3 11/14/2019 11/17/2019
18 RS3-RS7 Injection - Freyssinet 3 11/18/2019 11/21/2019
19 Alphakit Dismantling 10 11/18/2019 11/28/2019

C3-C2 R - ALPHAKIT 1 Days Start Finish


1 Alphakit Installation 12 10/27/2019 11/8/2019
2 Slab Formwork 4 11/9/2019 11/13/2019
3 Slab+Wall Reinforcement 12 11/11/2019 11/23/2019
4 Outer Wall Formwork + Spiral Pipe Installation 3 11/20/2019 11/23/2019
5 Slab Concrete 1 11/24/2019 11/24/2019
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 11/25/2019 11/27/2019
7 RS7-S1 Cabling - Freyssinet 4 11/23/2019 11/27/2019
8 Wall Concrete 1 11/28/2019 11/28/2019
9 Wall Formwork Dismantling 2 11/29/2019 12/1/2019
10 Top Slab Formwork 7 12/2/2019 12/9/2019
11 Top Slab Reinforcement 7 12/5/2019 12/12/2019
12 Top Slab Concrete 1 12/13/2019 12/13/2019
13 Top Slab support and Formwork Dismantling 5 12/20/2019 12/25/2019
14 Open Section Slab Concrete 1 11/18/2019 11/18/2019
15 Open Section Wall Concrete 1 11/19/2019 11/19/2019
16 Open Section Top Slab Concrete 3 11/20/2019 11/23/2019
17 RS9-RS5 Cable Stressing - Freyssinet 3 11/30/2019 12/3/2019
18 RS9-RS5 Injection - Freyssinet 3 12/4/2019 12/7/2019
19 Alphakit Dismantling 10 12/4/2019 12/14/2019

C2-C1 R - ALPHAKIT 2 Days Start Finish


1 Alphakit Installation 12 11/12/2019 11/24/2019
2 Slab Formwork 4 11/25/2019 11/29/2019
3 Slab+Wall Reinforcement 12 11/27/2019 12/9/2019
4 Outer Wall Formwork + Spiral Pipe Installation 3 12/6/2019 12/9/2019
5 Slab Concrete 1 12/10/2019 12/10/2019
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 12/11/2019 12/13/2019
7 RS9-S1 Cabling - Freyssinet 4 12/9/2019 12/13/2019
8 Wall Concrete 1 12/14/2019 12/14/2019
9 Wall Formwork Dismantling 2 12/15/2019 12/17/2019
10 Top Slab Formwork 7 12/18/2019 12/25/2019
11 Top Slab Reinforcement 7 12/21/2019 12/28/2019
12 Top Slab Concrete 1 12/29/2019 12/29/2019
13 Top Slab support and Formwork Dismantling 5 1/5/2020 1/10/2020
14 Open Section Slab Concrete 1 12/4/2019 12/4/2019
15 Open Section Wall Concrete 1 12/5/2019 12/5/2019
16 Open Section Top Slab Concrete 3 12/6/2019 12/9/2019
17 RS7-S1/RS9-S1 Cable Stressing - Freyssinet 3 12/16/2019 12/19/2019
18 RS7-S1/RS9-S1 Injection - Freyssinet 3 12/20/2019 12/23/2019
19 Alphakit Dismantling 10 12/20/2019 12/30/2019

C6-C5 L - ALPHAKIT 3 Days Start Finish


1 Alphakit Installation 12 11/28/2019 12/10/2019
2 Slab Formwork 4 12/11/2019 12/15/2019
3 Slab+Wall Reinforcement 12 12/13/2019 12/25/2019
4 Outer Wall Formwork + Spiral Pipe Installation 3 12/22/2019 12/25/2019
5 Slab Concrete 1 12/26/2019 12/26/2019
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 12/27/2019 12/29/2019
7 RS8-RS11 Cabling - Freyssinet 4 12/25/2019 12/29/2019
8 Wall Concrete 1 12/30/2019 12/30/2019
9 Wall Formwork Dismantling 2 12/31/2019 1/2/2020
10 Top Slab Formwork 7 1/3/2020 1/10/2020
11 Top Slab Reinforcement 7 1/6/2020 1/13/2020
12 Top Slab Concrete 1 1/14/2020 1/14/2020
13 Top Slab support and Formwork Dismantling 5 1/21/2020 1/26/2020
14 Open Section Slab Concrete 1 12/20/2019 12/20/2019
15 Open Section Wall Concrete 1 12/21/2019 12/21/2019
16 Open Section Top Slab Concrete 3 12/22/2019 12/25/2019
17 RS6-S11 Cable Stressing - Freyssinet 3 1/1/2020 1/4/2020
18 RS6-S11 Injection - Freyssinet 3 1/5/2020 1/8/2020
19 Alphakit Dismantling 10 1/5/2020 1/15/2020

C5-C4 L - ALPHAKIT 1 Days Start Finish


1 Alphakit Installation 12 12/14/2019 12/26/2019
2 Slab Formwork 4 12/27/2019 12/31/2019
3 Slab+Wall Reinforcement 12 12/29/2019 1/10/2020
4 Outer Wall Formwork + Spiral Pipe Installation 3 1/7/2020 1/10/2020
5 Slab Concrete 1 1/11/2020 1/11/2020
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 1/12/2020 1/14/2020
7 RS3-RS7 Cabling - Freyssinet 4 1/10/2020 1/14/2020
8 Wall Concrete 1 1/15/2020 1/15/2020
9 Wall Formwork Dismantling 2 1/16/2020 1/18/2020
10 Top Slab Formwork 7 1/19/2020 1/26/2020
11 Top Slab Reinforcement 7 1/22/2020 1/29/2020
12 Top Slab Concrete 1 1/30/2020 1/30/2020
13 Top Slab support and Formwork Dismantling 5 2/6/2020 2/11/2020
14 Open Section Slab Concrete 1 1/5/2020 1/5/2020
15 Open Section Wall Concrete 1 1/6/2020 1/6/2020
16 Open Section Top Slab Concrete 3 1/7/2020 1/10/2020
17 RS.. Cable Stressing - Freyssinet 3 1/17/2020 1/20/2020
18 RS.. Injection - Freyssinet 3 1/21/2020 1/24/2020
19 Alphakit Dismantling 10 1/21/2020 1/31/2020

C4-C3 L - ALPHAKIT 2 Days Start Finish


1 Alphakit Installation 12 12/30/2019 1/11/2020
2 Slab Formwork 4 1/12/2020 1/16/2020
3 Slab+Wall Reinforcement 12 1/14/2020 1/26/2020
4 Outer Wall Formwork + Spiral Pipe Installation 3 1/23/2020 1/26/2020
5 Slab Concrete 1 1/27/2020 1/27/2020
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 1/28/2020 1/30/2020
7 RS8-S11 Cabling - Freyssinet 4 1/26/2020 1/30/2020
8 Wall Concrete 1 1/31/2020 1/31/2020
9 Wall Formwork Dismantling 2 2/1/2020 2/3/2020
10 Top Slab Formwork 7 2/4/2020 2/11/2020
11 Top Slab Reinforcement 7 2/7/2020 2/14/2020
12 Top Slab Concrete 1 2/15/2020 2/15/2020
13 Top Slab support and Formwork Dismantling 5 2/22/2020 2/27/2020
14 Open Section Slab Concrete 1 1/21/2020 1/21/2020
15 Open Section Wall Concrete 1 1/22/2020 1/22/2020
16 Open Section Top Slab Concrete 3 1/23/2020 1/26/2020
17 RS6-S11 Cable Stressing - Freyssinet 3 2/2/2020 2/5/2020
18 RS2-RS6 Injection - Freyssinet 3 2/6/2020 2/9/2020
19 Alphakit Dismantling 10 2/6/2020 2/16/2020

C3-C2 L - ALPHAKIT 3 Days Start Finish


1 Alphakit Installation 12 1/15/2020 1/27/2020
2 Slab Formwork 4 1/28/2020 2/1/2020
3 Slab+Wall Reinforcement 12 1/30/2020 2/11/2020
4 Outer Wall Formwork + Spiral Pipe Installation 3 2/8/2020 2/11/2020
5 Slab Concrete 1 2/12/2020 2/12/2020
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 2/13/2020 2/15/2020
7 RS8-S11 Cabling - Freyssinet 4 2/11/2020 2/15/2020
8 Wall Concrete 1 2/16/2020 2/16/2020
9 Wall Formwork Dismantling 2 2/17/2020 2/19/2020
10 Top Slab Formwork 7 2/20/2020 2/27/2020
11 Top Slab Reinforcement 7 2/23/2020 3/1/2020
12 Top Slab Concrete 1 3/2/2020 3/2/2020
13 Top Slab support and Formwork Dismantling 5 3/9/2020 3/14/2020
14 Open Section Slab Concrete 1 2/6/2020 2/6/2020
15 Open Section Wall Concrete 1 2/7/2020 2/7/2020
16 Open Section Top Slab Concrete 3 2/8/2020 2/11/2020
17 RS6-S11 Cable Stressing - Freyssinet 3 2/18/2020 2/21/2020
18 RS8-S11 Injection - Freyssinet 3 2/22/2020 2/25/2020
19 Alphakit Dismantling 10 2/22/2020 3/3/2020

C2-C1 L - ALPHAKIT 1 Days Start Finish


1 Alphakit Installation 12 1/31/2020 2/12/2020
2 Slab Formwork 4 2/13/2020 2/17/2020
3 Slab+Wall Reinforcement 12 2/15/2020 2/27/2020
4 Outer Wall Formwork + Spiral Pipe Installation 3 2/24/2020 2/27/2020
5 Slab Concrete 1 2/28/2020 2/28/2020
6 Lateral Wall Reinforcement + Inner Wall Formwork 2 2/29/2020 3/2/2020
7 RS8-RS11 Cabling - Freyssinet 4 2/27/2020 3/2/2020
8 Wall Concrete 1 3/3/2020 3/3/2020
9 Wall Formwork Dismantling 2 3/4/2020 3/6/2020
10 Top Slab Formwork 7 3/7/2020 3/14/2020
11 Top Slab Reinforcement 7 3/10/2020 3/17/2020
12 Top Slab Concrete 1 3/18/2020 3/18/2020
13 Top Slab support and Formwork Dismantling 5 3/25/2020 3/30/2020
14 Open Section Slab Concrete 1 2/22/2020 2/22/2020
15 Open Section Wall Concrete 1 2/23/2020 2/23/2020
16 Open Section Top Slab Concrete 3 2/24/2020 2/27/2020
17 RS6-S11 Cable Stressing - Freyssinet 3 3/5/2020 3/8/2020
18 RS2-RS6 Injection - Freyssinet 3 3/9/2020 3/12/2020
19 Alphakit Dismantling 10 3/9/2020 3/19/2020
Comments

Starts after Freyssinet completes Stressing of C7-C6 R on 30.09.19

Tower Crane #2 must be operational by 7/09!!!