You are on page 1of 1

Doc No:SSGC/P&D/FRM-09

Rev: 00
WELDER PERFORMANCE QUALIFICATION RECORD Date of Issue: 14/03/2018
Page:1 of 1

CLIENT : SUI SOUTHERN GAS COMPANY - P&D Report No.: Date:


PROJECT : 08" x 26.5 Kms Ayesha Gas Field Pipeline Project Using WPS No. :
CONTRACTOR : SUI SOUTHERN GAS COMPANY - P&C Revision :
Welder's Name: Record Actual values used in Qualification
Stamp No. qualification: Range:

Variable
Welding Process :
Process Type :
Direct / Remote Visual Control :
Automatic Voltage Control :
Automatic Joint Tracking :
Backing (Metal , Weld Metal, Flux, etc.) :
Base Metal ASME P-No. :
Thickness :
Diameter groove :
fillet :
Filler Metal SFA Specification :
Classification :
F-No. :
Consumable :
Weld Deposit Thickness Groove :
Fillet :
Welding Position :
Progression (Uphill/Downhill) :
Backing Gas :
Elect. Charac. Current :
Polarity :
Transfer mode :

Visual Examination
Radiographic Test Results
(for alternative qualification of groove welds by Radiography)
Guided Bend Tests
Type Number Result

Fillet Weld Test :


Welding Test Conduction by :
Mechanical Tests Conducted by :
Laboratory Test No. :
We certify that the statements in this record are correct and that the test welds were prepared,
welded and tested in accordance with the requirements of section IX or API-1104.

COMPANY PREPARED BY SSGC-P&C WITNESSED BY TPI WI CHECKED BY SSGC-P&D

NAME:

SIGNATURE:

DATRE:

You might also like