HIGH RISE BUILDING

SCHEDULE

ID Task Name Duration Start Finish 01 January 01 May 01 September 01 January 01 May 01 September 01 Jan
18/12 12/02 09/04 04/06 30/07 24/09 19/11 14/01 11/03 06/05 01/07 26/08 21/10 16/12
1 LUXURY APARTMENT CONSTRUCTION  702 days 01/03/17 31/01/19
PACKAGE NO: LAC‐02 ‐ CONSTRUCTION OF 
ZONE‐9, CLUSTER 3 TOWERS OF 2 BED 
APARTMENTS
2 NTP and Mobilization  21 days 01/03/17 21/03/17
3 Notice to Proceed 1 day 01/03/17 01/03/17
4 Deployment of Manpower 15 days 02/03/17 16/03/17
5 Deployment of Machinery  15 days 02/03/17 16/03/17
6 Temporary Office Setup 20 days 02/03/17 21/03/17
7 High Rise Towers 1, 2, 3 & 4 691 days 12/03/17 31/01/19
8 Excavation 30 days 12/03/17 10/04/17
9 Stone Soling 30 days 11/04/17 10/05/17
10 Lean Concrete 20 days 11/05/17 30/05/17
11 Raft Foundations 30 days 31/05/17 29/06/17
12 Basement ‐ 1 44 days 30/06/17 12/08/17
13 Walls & Columns 20 days 30/06/17 19/07/17
14 Roof Slab & Beams 24 days 20/07/17 12/08/17
15 Tower (18 Storeys) 537 days 13/08/17 31/01/19
16 Structural Works 454 days 13/08/17 09/11/18
17 Ground Level 17 days 13/08/17 29/08/17
18 Column and Shear Walls 6 days 13/08/17 18/08/17
19 Beam and Slab 17 days 13/08/17 29/08/17
20 1st Floor 23 days 30/08/17 21/09/17
21 Column and Shear Walls 6 days 30/08/17 04/09/17
22 Beam and Slab 17 days 05/09/17 21/09/17
23 2nd Floor 23 days 22/09/17 14/10/17
24 Column and Shear Walls 6 days 22/09/17 27/09/17
25 Beam and Slab 17 days 28/09/17 14/10/17
26 3rd Floor 23 days 15/10/17 06/11/17
27 Column and Shear Walls 6 days 15/10/17 20/10/17
Echo West International Pvt. Limited
HIGH RISE BUILDING
SCHEDULE

ID Task Name Duration Start Finish 01 January 01 May 01 September 01 January 01 May 01 September 01 Jan
18/12 12/02 09/04 04/06 30/07 24/09 19/11 14/01 11/03 06/05 01/07 26/08 21/10 16/12
28 Beam and Slab 17 days 21/10/17 06/11/17
29 4th Floor 23 days 07/11/17 29/11/17
30 Column and Shear Walls 6 days 07/11/17 12/11/17
31 Beam and Slab 17 days 13/11/17 29/11/17
32 5th Floor 23 days 30/11/17 22/12/17
33 Column and Shear Walls 6 days 30/11/17 05/12/17
34 Beam and Slab 17 days 06/12/17 22/12/17
35 6th Floor 23 days 23/12/17 14/01/18
36 Column and Shear Walls 6 days 23/12/17 28/12/17
37 Beam and Slab 17 days 29/12/17 14/01/18
38 7th Floor 23 days 15/01/18 06/02/18
39 Column and Shear Walls 6 days 15/01/18 20/01/18
40 Beam and Slab 17 days 21/01/18 06/02/18
41 8th Floor 23 days 07/02/18 01/03/18
42 Column and Shear Walls 6 days 07/02/18 12/02/18
43 Beam and Slab 17 days 13/02/18 01/03/18
44 9th Floor 23 days 02/03/18 24/03/18
45 Column and Shear Walls 6 days 02/03/18 07/03/18
46 Beam and Slab 17 days 08/03/18 24/03/18
47 10th Floor 23 days 25/03/18 16/04/18
48 Column and Shear Walls 6 days 25/03/18 30/03/18
49 Beam and Slab 17 days 31/03/18 16/04/18
50 11th Floor 23 days 17/04/18 09/05/18
51 2nd Floor 6 days 17/04/18 22/04/18
52 Beam and Slab 17 days 23/04/18 09/05/18
53 12th Floor 23 days 10/05/18 01/06/18
54 Col umn and Shear Walls 6 days 10/05/18 15/05/18
55 Beam and Slab 17 days 16/05/18 01/06/18
56 13th Floor 23 days 02/06/18 24/06/18
57 Column and Shear Walls 6 days 02/06/18 07/06/18

Echo West International Pvt. Limited


HIGH RISE BUILDING
SCHEDULE

ID Task Name Duration Start Finish 01 January 01 May 01 September 01 January 01 May 01 September 01 Jan
18/12 12/02 09/04 04/06 30/07 24/09 19/11 14/01 11/03 06/05 01/07 26/08 21/10 16/12
58 Beam and Slab 17 days 08/06/18 24/06/18
59 14th Floor 23 days 25/06/18 17/07/18
60 Column and Shear Walls 6 days 25/06/18 30/06/18
61 Beam and Slab 17 days 01/07/18 17/07/18
62 15th Floor 23 days 18/07/18 09/08/18
63 Column and Shear Walls 6 days 18/07/18 23/07/18
64 Beam and Slab 17 days 24/07/18 09/08/18
65 16th Floor 23 days 10/08/18 01/09/18
66 Column and Shear Walls 6 days 10/08/18 15/08/18
67 Beam and Slab 17 days 16/08/18 01/09/18
68 17th Floor 23 days 02/09/18 24/09/18
69 Column and Shear Walls 6 days 02/09/18 07/09/18
70 Beam and Slab 17 days 08/09/18 24/09/18
71 18th Floor 23 days 25/09/18 17/10/18
72 Column and Shear Walls 6 days 25/09/18 30/09/18
73 Beam and Slab 17 days 01/10/18 17/10/18
74 Roof Top 23 days 18/10/18 09/11/18
75 Column and Shear Walls 10 days 18/10/18 27/10/18
76 Beam and Slab 13 days 28/10/18 09/11/18
77 Architectural Works 418 days 10/12/17 31/01/19
78 Block Work 300 days 10/12/17 05/10/18
79 Plumbing Rough In 240 days 17/12/17 13/08/18
80 Electrical Rough In 240 days 17/12/17 13/08/18
81 Plaster Internal Walls 380 days 11/01/18 25/01/19
82 External Plaster 300 days 12/03/18 05/01/19
83 External Facing Works 300 days 07/04/18 31/01/19

Echo West International Pvt. Limited