CH G TEST REPORT FOR BREAKER BACKUP RELAY

O LTE

R O U
P
DOC. NO. : VEPL/T&CF/BBR/006/Rev : 0
VOLTECH ENGINEERS PVT. JOB REF NO : VEPL/TR/ /
V

LTD. DATE : Page No.


Excellent Electrical Service

CLIENT : M/s.
PROJECT : Sheet No 1 of 2

1. Date of Erection : Date of Energization (or) :


Last Calibration :

2. Equipment Details :

LOA No :
Make :
Type :
Sl. No. :
CT. Sec. :
Aux. Volts :
Setting Range :
Current Setting :
Current Multiplier Setting :
Mfg Year :

3. Location & Feeder Name :

4. General Inspection :

5. Pick up / Drop Off Test : (Using Equipment Details) Date :

Make : Range : Sl. No. Calib due Date :

Relay Setting Pick up Current Drop Off Current

Test Performed by Witnessed by Witnessed by


Name : Name Name
Designation : Designation Designation
Signature & Signature & Signature &
Date Date Date
CH G TEST REPORT FOR BREAKER BACKUP RELAY

O LTE

R O U
P
DOC. NO. : VEPL/T&CF/BBR/006/Rev : 0
VOLTECH ENGINEERS PVT. JOB REF NO : VEPL/TR/ /
V

LTD. DATE : Page No.


Excellent Electrical Service

CLIENT : M/s.
PROJECT : Sheet No 2 of 2

6. Functional checks : (Whether Operational Checks OK / Not OK / Not Available)

1 Wiring checks
2 Correct operation of appropriate indicator / aux. relay
3 Correct initiation of alarm contacts
4 Correct circuit breaker tripping contacts
5 Relay cover properly fixing
6 Correct operating reset switch
7 Relay Draw out conditions CT shorting link should be short

7. Service settings :

Current Setting
Current Multiplier Setting

8. Remarks :