You are on page 1of 4

Maerz Ofenbau AG Phone +41-44-287 27 27

Richard Wagner-Strasse 28 Fax +41-44-201 36 34


CH-8027 Zurich e-mail: info@maerz.com
Switzerland www.maerz.com

NEW – Cooling of
industrial kilns and furnaces
1. Cooling of industrial kilns and furna- The temperature profile of the air-cooled wall is shown in the
ces - still unsolved in many cases following picture If the outside of the shell is water cooled, the
temperature gradient in the inner bricks is obvious steeper. This
The cooling of refractory lined kilns or furnaces for metallurgi- steeper gradient is the explanation for the lower wear rate of
cal or other industrial high temperature processes is often a the refractory: The chemical reactions between slag and refrac-
difficult technique. tory material slow down.
The cooling of the steel shell in many applications is a must for So this new cooling system is a technical solution between an
an adequate lifetime of the refractory lining but in some cases unchilled shell and a furnace with "freeze lining". On furnaces
the usual solutions do not show good results or contain hid- with "freeze lining", the liquid slag freezes onto a water cooled
den risks. (copper) wall. (fig. 1)

• Some types of kilns should be cooled, but this is difficult due But this simple spray cooling solution also had several disad-
to the geometry of the shell. vantages:
• Some kilns or furnaces are cooled with spray cooling or film • In the kiln shop there is a lot of damp, which causes
cooling. Water losses are unavoidable. Maintenance is neces- corrosion of the building and equipment
sary to remove organic and inorganic deposits which insula- • The cooling requires a certain amount of maintenance as
te between water and steel sintered carbonates cover the shell after a short while
• Critical areas like feeding ports or tapping holes are always a • Water can penetrate through cracks in the steel shell into the
problem at spray or film cooled furnaces. magnesite and hydrates it.
• Some kilns are built with walls carrying welded cooling • Some areas, e.g. neat flanges could not be sprayed with
pockets or cooling pipes. The weld seams carry the long term water.
risk of cracks and undetected water penetration into the • The part underneath was not cooled in a reproducible
refractory lining. manner.

The demands for an improved water cooling system resulted


from the following requirements:
2. A new approach of shell cooling • Defined cooling of all those shell areas with wearing
problems in the inner side, e.g. slag line, feeding ports, etc.
The new cooling system (patent applied) , developed in a co- • Direct welding to the steel shell is not acceptable (danger of
operation between BERZELIUS Germany and MAERZ Ofenbau cracks and uncontrolled water penetration)
AG in Zurich, Switzerland, is a new approach to this task. It is • The cooling system must work properly even on distorted
now an industrially approved technique and can be a solution and uneven areas of the surface.
for other industrial kilns and furnaces. • The cooling system must be a compromise between the
increased heat losses of the process and the expected
In order to reduce the wearing of the lining, BERZELIUS extension of the lifetime of the lining.
installed a very simple water spray cooling system. This results • As the steel shell is expanding and deforming under
in a higher temperature drop in the wear lining and the life of temperature and charge load, the cooling must work
the bricks lasted longer. nevertheless.
• The cooling system should not
Fig. 1: Temperature gradient in the wear lining. require maintenance.
Shell uncooled or water cooled. • In case of emergency, if cracks have to
be welded in the shell, the cooling
must not obstruct this work too much.
• The cooling system should not require
an extension of the plant’s water
supply system (pumps, pipes, cooling
capacity)
• It must also be possible to install the
cooling system during a 2-3 week
relining shutdown period.

2
Fig. 2: Group of cooling elements.
Detail of fixation.

flexible hose

disc spring heat conductive paste

welding bolt

3. This is the new solution • The cooling elements are pressed to the shell by numerous
for the old problem strong bolts. These bolts are welded semi-automatically to
the shell.
The solution, as shown on the pictures, has the following fea- • To maintain the tension, the nuts are underlayed with disk
tures (fig. 2) : springs.
• The area to be cooled is covered by many single cooling • Water in and outlets of the single elements are connected
elements. Each of those has an approximate area of 0.5 m2. with flexible hoses.
• Each of these consist of a thin base plate shaped as the shell. • Groups of 8 - 12 elements are linked together for one water
On the other side water channels made of half pipes are circuit. Each circuit has a temperature- and flow controlled
welded to these base plates. outlet.
• Between the furnace shell and base plate of the cooling ele-
ment a special heat conductive paste ensures good heat
Fig. 3: Cooling elements mounted at a kiln of transport. If the unavoidable gap would not be closed with
Berzelius, Germany
this heat conductive paste, the system could not work
properly.

4. Installation and
first operational results
The first part of a kiln at BERZELIUS was
equipped in January 2003 with
approximately 100 of these cooling
elements during a 2 weeks shut-
down. The cooling effect since
the new start is within the cal-
culated limits right from the
beginning. (fig. 3 and 4)

3
The paste, specially developed for this application, was careful-
ly tested in a large scale experiments by BERZELIUS and
MAERZ. In particular, its properties after an overheating cau-
sed by a longer interruption of the water supply was investiga-
ted.
The paste keeps its good heat conductivity and its softness in
a range of several hundred degrees Celsius.
The panels are designed in such a way that should the gap
between the shell and the panel increase, for example due to a
distortion of the shell, the gap can be refilled with heat con-
ductive paste from outside.

6. Revamping an existing furnace -


how to proceed
The experiences gained during the successful prototype pro-
ject enable MAERZ to revamp other kilns. This new technical
solution is not without technical risks. Therefore, the following
steps for a safe and smooth revamping must be taken.

6.1 Basic design study


This study must include :
• Thermal calculations of heat losses, temperature profiles,
Fig. 4: One side of the kiln with cooling elements cooling water demand.
• Outline drawing of one typical element and of the whole shell
showing the cooled parts, the amount and the variety of
The average heat transfer is app. 10 kW/m2. The calculated heat
single elements and the water circuits.
loss of the air cooled shell is approximately 6 kW/m2.
• Water flow sheet including emergency water supply and
The outside temperature of the shell is circa 60°C. The unchil-
instrumentation.
led shell showed temperatures around 300°C.

© 2003 - Maerz Ofenbau AG, Zurich, Switzerland: www.maerz.com; Dtp: aku2 kury-kugler, Seeboden, Austria: www.aku2.at; Printed in Swizzerland
• Recommendations if modifications in the refractory lining
During a longer shutdown in Summer 2003 the rest of the shell
are advisable.
will be revamped with another 140 pieces.
• FEM calculation to check the thermo-mechanical stress of
the steel structure.
It is expected that the cooling elements will prolong the shut-
down interval for relining from 18 months to at least 24
After this basic design study the benefits of a revamping can
months.
be estimated, hidden risks should show up, the costs can be
Other positive side effects are :
predicted and a time schedule for the whole project can be
• Improved working environment - less vapour, and cooler
established.
reactor shell.
• Ideal monitoring of the cooling behaviour of all cooled areas.
6.2 Detail Design and project execution
This allows conclusions to be drawn to the extent of the
If the results of the basic design study show technically good
wearing of the lining.
results then a revamping would be worth doing assuming of
course that the payback of the investment is acceptable.
5. The heat conductive paste For an industrial kiln it is usually important to make the revam-
ping modifications during a scheduled shutdown period of a
The heat conductive paste is one key element for this new coo- few weeks . Normally this will be carried out during the relining
ling system. It is a product developed for improving the coo- of the kiln. Therefore the modification has to be designed to
ling of semiconductor elements for high current loads. be carried out during this short shut down period.
The gap between the outside of the shell and the cooling
panels is due to imperfections of the shell of an average 2 - 3 The control system of the plant also has to be supplemented in
mm. This air gap would insulate quite a lot and the heat trans- a way that the signals of the cooling water outlet are monito-
fer would be low, uneven and unpredictable. The heat conduc- red and registered. A trend analysis can give reliable informa-
tive paste closes the gap and a steady and even heat transport tion of the wear of the lining. This makes the operation of the
is guaranteed. The panels are designed in a way that during furnaces more predictable and safe.
erection a closed film of paste can easily be achieved. June 2003

You might also like