Silicon Valley Rapid Transit
Program Update
VTA Board of Directors Meeting
December 9, 2010
AE, BART,
TTA, STAGON VAULEYRequest for Qualifications for the Berryessa Extension Design
Build Line, Track, Stations and Systems (LTSS)
+ Released October 19, 2010
* Received sets of qualifications from four proposers on
November 19, 2010
* Notify qualified teams nextweek 9 70 0AY thy
+ Draft Request for Proposals for industry review anticipated
December 17, 2010
+ Request for Proposals for bid issued late-February 2011.
Ai BART,Vehicle Procurement
VTA and BART working through a set of financial principles
BART fleet replacement program for 775 vehicles
60 vehicles required for the Berryessa Extension included
In January, VTA staff will bring forward a recommendation to execute
necessary agreements with BART.
Ai BARTDraft document released on November 1, 2010
Addresses proposed project changes for Berryessa Extension and
phasing of project
Public comment period until December 17, 2010
Release of Final SEIR expected in February 2011
Board adoption in March 2011.