lide 2:

Project Location Azadpur

Key Map :
Grade Separator at Ring Road - GTK RoadIntersection Key Map LAYOUT PLAN length of flyover
780 m length of underpass 393 m

Slide 4:
Prospective view of Grade Separator at Ring Road, G. T. Karnal Road Intersection, Azadpur
New Delhi

Slide 5:
General Layout Drawing

SALIENT FEATURES :
780 m long Main flyover along the Ring Road (334 m viaduct, 50m+2X40m+6X34 m, Dual
carriageway of 9 m in each direction). 532 m long Underpass along the GTK Road - Mall Road
with Diaphragm wall (covered portion of 50m at the intersection, Dual carriageway of 9 m in
each direction, 5m wide central verge to accommodate Metro track) Road in embankment-
23340 sqm Surface level road & Service Road- 75627 sqm Service road on all sides for the
pedestrian and cyclist. 2 no’s Foot Over Bridge 1 no. on Road no.51 & 1 no. on Mall Road with
third leg connecting to DMRC Station at Azadpur. 1 no. Box Pushing for Pedestrians & 1 no. Box
pushing for Vehicular traffic approaching to Subji mandi Azadpur. Drainage Scheme,Electrical
and lighting Horticulture and Landscaping Traffic Booth,Traffic signage and temporary traffic
signals SALIENT FEATURES Name of Work : Construction of Grade Separator at Azadpur at G. T.
Karnal Road –Ring Road Intersection, Delhi.

Contract Information :
Contract Information CONTRACTOR : NAVAYUGA ENGINEERING CO. LTD. ORIGINAL CONTRACT
VALUE: 87.37 CRORE CONTRACTUAL PERIOD : 18 MONTHS DATE OF START : 12TH MAY,2007
DATE OF COMPLETION : 11TH NOVEMBER,2008

Slide 8:
Executive Engineer, Flyover Project Division, F-132, PWD. Structural, Electrical, Landscaping &
Soil Investigation consultants-M/s L & T Ramboll Pvt. Ltd Feasibility Study- M/s Crafts
Consultants (I) Pvt. Ltd. Proof Consultants- M/s Stup Consultants Pvt. Ltd Third Party Quality
Assurance- Engineers India Ltd. Construction- Navayuga Engineering Co. Project Team

Slide 9:
WORK PROGRESS STATUS AS ON 15.01.2009

Slide 13:
Present status on Inspection dated 24.07.08

Slide 17:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Slide 18:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Slide 19:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Slide 20:
BOX GIRDER FROM A1L TO P3L RETAINING WALL & CRASH BARRIER TOWARDS POLICE
STATION SIDE BOX GIRDER FROM A2R TO P6R REINFORCEMENT OF VOIDED SLAB
Slide 21:
RETAINING WALL AT PEER BABA SIDE ERECTION OF FOB RETAINING WALL AT POLICE STATION
SIDE ERECTION OF FOB

Slide 22:
PEDISTRIAN UNDERPASS THRUST BED & PROTECT WORK FOR VUP

Slide 23:
RE WALL WORK AT ROAD NO. 51 DRAIN WORK AT ROAD NO. 51 DLC AT AZADPUR VILLAGE
SIDE

RETAINING WALL & CRASH BARRIER TOWARDS PEER BABA SIDE :


RETAINING WALL & CRASH BARRIER TOWARDS PEER BABA SIDE REINFORCEMENT OF
RETAINING WALL AT PEER BABA SIDE

Slide 25:
MOBILIZATION OF EQUIPMENTS

{MANPOWER AT AZADPUR} :
{MANPOWER AT AZADPUR} Chief manager projects - 01 Project Manager - 01 PLANT &
EQUIPMENT:- Mechanical Manager - 01 Dy. Project Manager - 03 Project Engineer - 01 Sr. Site
Engineer - 02 Site Engineer - 08 Jr.Engineer (Mech.,) - 02 Sr. Surveyor - 02 Supervisors - 14
Foreman - 04 Bore Master - 03 Store officer - 02 Store Asst. - 04 Admt. - 04 Crane operators -
08 Accounts - 02 Safety staff - 03 Electrician - 02 Computer operator - 02 Mechanical
Supervisor - 02 Manager (Q.A./Q.C) - 01 Sr. Site Engineer - 01 Site Engineer - 02 Supervisors -
04 Store officer - 01 Store Asst. - 02 Admt. - 01 Laboratory - 04 Safety staff - 02 {MANPOWER
AT WAJIRPUR}

Slide 27:
MAN POWER

Slide 29:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Slide 30:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Slide 31:
PLANNED PROGRAMME UPTO Aug 09 except Vehicular Underpass by DECEMBER - 2009

Special Design Features :


Grade Separator at Ring Road - GTK RoadIntersection Special Design Features FIG. - SHOWING
SECTION OF UNDERPASS WITH DIAPHRAGM WALLS

Special Design Features :


Two level Ramps Grade Separator at Ring Road - GTK RoadIntersection Special Design
Features

Section of the Underpass and flyover :


Grade Separator at Ring Road - GTK RoadIntersection Section of the Underpass and flyover
FIG. - SHOWING SECTION OF UNDERPASS WITH FLYOVER OVER IT FIG. - SHOWING SECTION OF
FLYOVER

Slide 35:
Hindrances at Site

Slide 36:
HINDRANCES IN THE WORK DUE TO WHICH WORK DELAYED (i) DJB WATER SUPPLY LINE is
located under the pile caps (P5) of the obligatory span on Road No. 51 side. DJB services 1100
mm pipe lines are also falling in the thrust bed for 11 m width box pushing and passing under
Azadpur crossing interfering with the underpass Diaphragm walls. The work of shifting of Delhi
Jal Board lines has been started and will be completed by 20.01.2009. Shifting of NDPL cables
is coming in Underpass at Shastri Market. 3. Land Acquisition: The MCD shops coming in layout
towards Mall Road side. For acquiring the same letter written to the MCD officials. SDM, Model
Town has been requested to identify the properties / land coming in the project in towards
Road No. 51. These hindrances were overlapping and net delayed 13 months in execution of
the project. Programme of project has been rescheduled and complete it by stipulated date of
31.12.2009.