: Site report
: Sailendra Site
: As per Wednesday, 27 March 2019
: 14:30 – 15:30 pm.
1
No Description Status
I PHASE I
TANDOORI
Needs to add wood panel on the corner window column CGN As per
in reference to HBA’s 3D design concept. Since it’s on Comment
the corner area, no need to demolish the existing ACP. 14 March 2019
Installing a timber cladding panel will suffice.
Change downlights matching the ones earlier supplied ENG To check light
by Lelco, current pin lights are dim and does not give output at site
enough lighting.
The back framing does not align with the graphic. CGN Done
2
The light source not strong enough. HBA suggested LED CGN As per
type 10 watts or stronger, and should have cover so the Comment
LED bulbs would not be seen. 14 March 2019
- Fix already, but still not strong enough (See updated CGN Outstanding
photo 27 March 2019)
- HBA suggest to change the LED strip with the type CGN
included with the diffuser.
The indirect lights on the rack not installed yet. CGN As per
Comment
14 March 2019
3
- Please see drawing intent details CGN As per
Comment
14 March 2019
- Raised Metal for Switches are still Outstanding (See CGN Outstanding
updated photo 27 March 2019)
4
CGN
This service station inlay ending is looking unfinished. / As per
Discussion was to extend the stone finish, enough to Ham Comment
cover the metal ends. Please make it flushed… para 14 March 2019
n
5
II PHASE II
6
Wooden Panel beside Beverage counter supposed to be
full and one big square panel. Not separated 2 panels.
- Still Outstanding (as per site visit 27 March 2019) CGN Outstanding
7
SALAD BAR
Old service counter needs to refurbish into the new forms CGN Done
similar with sushi counter & salad bar.
- Needs to fix the damaged existing stone as shown Ham 27 March 2019
on the red mark below. para
n
As per
Needs also plate rack on Sushi Counter requested by CGN
Comment
Chefs.
14 March 2019
Outstanding
8
MAIN BUFFET
9
The Light Source above Main Buffet hanging rack aren’t CGN Outstanding
instaled yet refer to HBA drawings.
The metal accent bars under round Main Buffet aren’t CGN Outstanding
installed yet refer to HBA drawings.
10
Need to add metal edging on the top of Pizza oven cover. CGN Outstanding
ENTRANCE AREA
11
Entrance Area still outstanding. CGN Outstanding
Entrance Area front display top has a gap. HBA suggest CGN 27 March 2019
to fill the gap with Wooden box fit to the space.
12
Need to Add Wooden box behind the sofa between the CGN Outstanding
metal frame structure refer to HBA drawings.
13
Some metal on the curve rack display are not align with CGN Outstanding
the curve shape.
Indirect lights inside entrance curve display still not CGN Done
installed yet.
FOYER CAFE
14
Some of the shelf divider aren’t installed yet. Also the
indirects & expanded metal still outstanding. Should CGN Outstanding
refer to HBA drawings.
15
Need to add additional steel structure to support existing CGN Outstanding
wall as it’s not possible to demolish because of structural
considerations.
The Contractor need to look carefully with the quality of CGN 27 March 2019
end joint and gap finishes.
16
Since the reduction will made, HBA suggest to lower CGN 27 March 2019
down the sweet kitchen table on 1100 m
PDR
17
3 sides of the back of the existing wall should covered CGN Outstanding
with wooden panels.
18
Wood finishes colour looks inconsistent. And the joint CGN 27 March 2019
looks rough.
Need to add wooden frame to this Column cover of PDR CGN 27 March 2019
3 to make it similar style with the others. And the same
problems on wood finishes colour looks inconsistent.
And the joint looks rough.
19
Wine rack needs alignment, current installed on site is CGN Outstanding
note straight.
These minutes is written by Hydri Andromeda of HBA, based on the recollection of issues raised at the
meeting, should any of those have different recollection please notify for necessary corrections.
20